SlideShare una empresa de Scribd logo
1 de 58
ANBARASU B
ENGINEER- Electrical
220KV SWITCHYARD
AMNEPL
Generatedpowertobeevacuatedtoloadcentersfor
consumption.
Generating stationsarefarfromloadcenters.
Theprocessof
Generation Transmission Consumption
(in11’skV) (in220’skV) (in230’sV)
PURPOSE & NECESSITY OF SWITCHYARD
DESIGN OF SWITCHYARD
Factors to note before design of switchyard
 Soil Resistivity and Earthing system
 Structure selection
 Bus Bar
 Clearance
 Insulators
 Conductor and its fittings
 Equipment selection
OVERVIEW
6 BAYS CORRESPONDS TO MSETCL PORTION
12 BAYS CORRESPONDS TO ABHIJEET PORTION
FULLY AUTOMATED SUBSTATION
1. In this scheme there are two main buses, called as BUS-1 & BUS-2
2. One more bus is available, its called as TRANSFER BUS
3. This is useful, when any one of the breaker in trouble or maintenance
4. Most of the time transfer bus in dead condition
ADVANTAGE:
1. Possible to take one bay CB and one BUS under maintenance
DISADVANTAGES:
1. If second(one more) circuit breaker in trouble, then this scheme is not
useful
2. There is no possible to take CT ,CVT and other equipments under
maintenance
• The tentative layout of the scheme shown in the next slide
DOUBLE MAIN BUS WITH TRANSFER BUS SCHEME
DOUBLE MAIN BUS WITH TRANSFER BUS
BUS-2
BUS-1
TRANSFER BUS
CHANGE OVER OF BUS-1 TO BUS-2 FOR BUS-1 MAINTENANCE
1. Normally each GT or feeder is to be connected to either bus-1 or bus-2
2. The concept behind is when either of the bus bar protection operates at
least 50% circuits will be in service
3.For maintenance point of view it is happy that all circuits kept on one bus
and another bus can be taken in to maintenance.
4. Normally bus-1 or bus-2 selection is to be done before charging circuit.
5. For example GT-1 & GT-2 transformers are available, GT-1 connected on
Bus-1 and GT-2 connected on bus-2.
6. The bus coupler breaker is should be in service.
7. During service, change over of bus is not a practice, however this is
possible
when bus coupler is charged condition.
8. During service the change over of BUS-1 to BUS-2 procedure is as follows: If
the circuit is connected on bus-1, close bus-2 isolator and open bus-1
isolator. This is purely for emergency
CHANGE OVER OF MAIN BUS TO TRANSFER BUS
1. When any one of the CB in trouble that will be transferred to transfer bus.
2. The operation sequence of transfer bus will be explained in next slides.
3. Bus coupler CB & isolators are in service.
4. During this change over to transfer bus, the tripping circuits are Transferred to transfer
bus coupler CB.
5. At the time, if fault occurs on circuit, the protective relays will give trip signal to
concerned CB and Transfer bus CB.
6. This can be avoided by using some more logic.
7. In TBC panel, auto reclose is available. This is useful when any Line feeder is
connected to TBC
8. In TBC panel, TBC LBB is also available.
9. Normal conventional system we are providing TTS switch. In normal mode tripping is
done for particular circuit Breaker, if it is transfer mode the trip circuit is parallel and
extended to TBC circuit breaker bay.
CHANGE OVER OPERATION OF GT-1 TO TRANSFER BUS
The sequence of operation for Normal to Transfer:
GT-1 on BUS-1 at Normal
1. Close TBC bay bus-1 89A isolator.
2. Close TBC bay transfer bus 89TB isolator.
3. Close GT-1 bay, transfer bus 89TB isolator.
4. So the TBC CB both sides having voltage.
5. Put NIT switch in ‘I’ inter mode of GT-1 C&R panel.
6. Close the TBC CB.
7. Then, the GT-1 is parallel with TBC CB and feeding two parallel paths.
8. Path1:GT-1 circuit : GT-1 89L line isolator, GT-1 CB, GT-1 89A bus-1 isolator to GT-1.
9. Path2:TBC circuit : GT-1 transfer bus 89TB isolator, TBC transfer bus 89TB isolator, TBC CB,
and TBC bus-1 89A isolator
10. Then open GT-1 CB.
11. Put NIT switch in ‘T’ transfer position
12. Open the GT-1 isolators i.e. Bus-1 89A isolator, 89L line isolator.
13. Now the GT-1 is feeding to bus-1 through TBC CB.
14. After maintenance work is over, the reverse procedure to be followed
OPERATION FOR TRANSFER TO NORMAL
• Put NIT switch in ‘I’ inter position.
• Close GT-1 89A bus-1 isolator.
• Close GT-1 89L line isolator.
• Close GT-1 circuit breaker.
• Open TBC CB.
• Open TBC bay 89A bus-1 isolator.
• Open TBC bay 89TB transfer bus isolator.
• Open GT-1 bus-3 isolator.
• Put NIT switch in ‘N’ normal position.
EQUIPMENTS
Circuit breaker
Current transformer
Capacitor voltage
transformer
Isolator
Lightning arrester
Coupling capacitor
Wave trap
Insulators and
Conductors
AC Distribution board
DC Distribution board
Battery & Battery Charger
MAIN EQUIPMENTS & COMPONENTS.
CIRCUIT BREAKER
 A circuit breaker is an automatically-operated electrical switch
under fault condition i.e on fault.
 To open and close the electric circuit.
TECHNICAL SPECIFICATION
1. MAKE - AREVA T&D
2. TYPE - SF6 CB GL314MGO
3. RATED CURRENT - 2500 A
4. RATED VOLTAGE - 245 KV
5. SHORT CIRCUIT CURRENT - 40KA for 3sec
6. OPERATING SEQUENCE - O-0.3s-CO-3min-CO
7. SF6 GAS PRESSURE AT 20⁰C - 0.85 Mpa
ISOLATOR
 Isolators or Disconnector are no-load switch.
 Earth Switch is used to discharge the voltage on the circuit to earth
for safety at the time of maintenance.
TECHNICAL SPECIFICATION
ISOLATOR
1. MAKE - SIEMENS LTD
2. TYPE - DBR
3. RATED CURRENT - 1600 A
4. RATED VOLTAGE - 245 KV
5. SHORT CIRCUIT CURRENT - 40KA for 3sec
6. TYPE OF DRIVE - MOTOR/MANUAL
7. MOTOR VOLTAGE (AC) - 415V
8. CONTROL VOLTAGE (DC) - 220V
9. CREEPAGE DISTANCE - 7812 mm
EARTH SWITCH
TYPE OF DRIVE - MANUAL
CURRENT TRANSFORMER
 CT merely reduces a high current flowing through its primary to a low
current on secondary.
 The secondary of a CT should never be kept open circuited because
very high flux will be developed in the secondary and hence it may be
damaged.
TECHNICAL SPECIFICATION
CAPACITOR VOLTAGE TRANSFORMER
 CVT is a transformer used to step down the high voltage to low
voltage. For metering and protection.
 Also useful in communication system, to block the power frequency
entering into PLCC terminal.
TECHNICAL SPECIFICATION
LIGHTNING ARRESTER
 Lightning arrester or Surge arrester are used to protect
other equipments from over-voltage due to lightning and
switching.
 This is the first equipment in all feeders and transformer
bay.
TECHNICAL SPECIFICATION
1. MAKE - OBLUM ELECTRICAL
2. TYPE - Gapless Type, METOVAR
3. NO. OF UNITS PER ARRESTOR - Three units of 66kV each
4. RATED VOLTAGE - 198 KV
5. NOMINAL DISCHARGE CURRENT - 10 KA
6. HIGHEST SYSTEM VOLTAGE - 245 KV
7. NOMINAL SYSTEM VOLTAGE - 220 KV
8. SYSTEM EARTHING - Solidly Earthed system
COUPLING CAPACITOR
 Coupling Capacitors are used in communication system, to block
the power frequency entering into PLCC terminal.
TECHNICAL SPECIFICATION
1. MAKE - AREVA T&D INDIA LTD.
2. TYPE - CCV-245
3. RATED FREQUENCY - 50HZ
4. VOLTAGE CLASS - 245KV
5. 1-MINUTE 50 HZ WITHSTAND - 460 KV
6. TYPE - Porcelain-Oil
7. MAX. TEMP. RISE OVER 50 ⁰C AMBIENT -55 ⁰C
8. TOTAL EQUIVALENT CAPACITANCE -6600 pF + 10%, -5%
9. CVT SUITABLE FOR FREQUENCY RANGE -40-500 kHz
10. TYPE OF LA -Non-linear resistive type Gapped LA
11. Rated voltage of LA - 9 KV
12. Nominal Discharge Current -10 KA
WAVE TRAP
 Line trap OR Wave trap used to trap the high frequency
communication signals entering into switchyard equipments and
diverting them to the telecom panel in the switchyard control room
(through coupling capacitor and LMU).
TECHNICAL SPECIFICATION
1. MAKE - AREVA
2. TYPE OUTDOOR -Air cored
3. INDUCTANCE OF THE MAIN COIL -0.5 mH
4. BLOCKING RANGE -100-175 &150-500kHz
5. TYPE OF TUNING -Variable Broad Band Tuning
6. MATERIAL OF MAIN COIL -Aluminium Alloy
7. MATERIAL OF TERMINAL CONNECTOR -Aluminium Alloy
8. SYSTEM VOLTAGE - 220KV
9. CONTINUOUS CURRENT RATING 40 ⁰C - 1250A Max.
10. SHORT CIRCUIT CURRENT -40 KA for 1 sec
CONDUCTOR
 Conductor is the material allowing the flow of electric current
ACSR Aluminum Conductor Steel Reinforced.
INSULATOR
 Insulator is the material to support a conductor physically and to
separate it electrically from another conductor or object.
1. Long Rod Insulator(Tension & Suspension Stringing)
2. Post Insulators
BATTERY BANK AND BATTERY CHARGER
1. 220 VOLT BATTERY BANK- For Protection & Controlling
 Total No. of cell- 173
 Volt. Rating of each cell- 1.2 Volt
 Capacity - 148 Ah
2. 48 VOLT BATTERY- For SCADA RTU & SIC Panel.
 Total No. of cell- 24.
 Volt. Rating of each cell- 2 Volt.
 Capacity- 50 Ah
3. TWO 12 VOLT BATTERY BANK – For Inverter
 Total No. of cell- 12(For MPP 6KVA Inverter)
 Total No. of cell- 12(For MSETCL 3KVA Inverter)
 Volt. Rating of each cell- 12 Volt
 Capacity- 26 Ah.
BATTERY BANK
BATTERY CHARGER
1. Type- Float Cum Boost Charger.
 Float mode( Simultaneously Charge & Discharge the Battery Bank )
 Boost mode( This is the Charging mode)
 Auto mode(Its Play the role according to the system requirements)
2. Rating-
1. MPP FCBC- 135A/220V
2. MSETCL FCBC- 50A/48V
3. Make-
1. MPP FCBC- Amar Raj
2. MSETCL FCBC- Panva
TESTING OF CURRENT TRANSFORMER
1. Insulation resistance test (IR test)
2. Polarity test
3. Excitation test (Knee point voltage test).
4. Ratio test
5. Winding resistance test
6. Tan delta and Capacitance Measurement test.
IR TESTING
To measure the insulation resistance of the
equipments.
a) Primary to earth by 5 KV
b) Secondary each core to earth by 500 V
c) Primary to secondary by 5 KV
d) Secondary core to core by 500 V
MAKE - MEGGER
POLARITY TEST
Polarity test of current transformer is to be carried out check the
correctness of the primary and secondary polarity
 For carrying out this test, we require one 1.5 V cell, DC analogue
ammeter.
 By making below connection, if there is positive deflection of
ammeter , then polarity is confirmed.
EXCITATION TEST
Excitation test will be carried out to measure the knee point voltage of
different cores of the current transformer
Knee point check for PS class core - Inject 230 V variable AC voltage in
secondary core with ammeter in series.
At certain point, with 10% increase in voltage, current shoots up almost 50%. This is
the Knee point voltage. After performing this test, Voltage is gradually reduced to Zero
to demagnetize the CT.
RATIO TEST
Inject current in primary winding & measure induced secondary
current for different current readings and verify with CT Ratio.
WINDING RESISTANCE TEST
Measure secondary winding resistance by micro ohm meter.
value should be .
TAN DELTA MEASUREMENT
Consider the insulation of equipment as Capacitor. If the capacitor is
good or perfect, it will pass only capacitive or charging current on
application of voltage. Ideal capacitive current Ic leads voltage by 90°.
But in practice, insulation has impurities & actual charging current
vector departs from the ideal Ic vector by a small angle (δ) called the
loss angle.
The loss angle (δ) = 90 – Power factor angle (φ)
Higher tan δ produces high dielectric loss that causes increase in
temperature of paper insulation. Increased value of Tan δ can be due to
any of the following: -
a) Moisture in the insulation.
b) Contamination of oil.
c) Internal partial discharge.
TESTING OF POTENTIAL TRANSFORMER
 Insulation resistance test (IR test)
 Winding resistance measurement
 Ratio test
 Tan Delta and Capacitance measurement test
TESTING OF LIGHTNING ARRESTER
IR Testing between Stack to stack & between each Stack to earth by
megger.
 Surge Counter Test - Apply 230V AC supply across the counter &
check pointer movement in clockwise direction.
TESTING OF CIRCUIT BREAKER
 Insulation Resistance Test
 Timing Test
 Contact Resistance Measurement Test
INSULATION RESISTANCE TEST
To measure the insulation healthiness of circuit breaker.
Open condition:
1. Top- Earth
2. Bottom- Earth
3. Top- Bottom
Close condition:
1. Top- Earth
2. Bottom- Earth
3. Top- Bottom
CONTACT RESISTANCE MEASUREMENT
 To measuring the contact resistance measurement of circuit
breaker main contacts.
 The value of the contact resistance for a new circuit breaker should
be around 50 micro-ohms.
 If the value of the contact resistance exceeds the permissible limits
this could lead to over heating of contacts.
TIMING TEST
To check the operation timing of circuit breaker.
 Trip circuit 1
O->open
C->close
C-O->close-open
 Trip circuit 2
O->open
C->close
C-O->close-open
 Kit used- Circuit Breaker Analyzer (EGIL BM19090)- Megger
 Tripolar Unipolar
O-> 23- 25 18-20
C-> 60-65 100-110
C-O-> 35-40 35-40
TESTING OF ISOLATORS
 Insulation Resistance Measurement
 Contact Resistance Measurement
 Motor Insulation Resistance Measurement
 Motor Winding Resistance Measurement
 Contact Resistance Measurement of Earth Switch
Insulation Resistance Measurement
 To measure the insulation resistance of Isolators.
 Measuring of insulation resistance against following condition.
1. Phase to Earth
2. Phase to Phase
CONTACT RESISTANCE MEASUREMENT
 To measuring the contact resistance measurement of Isolator
contacts.
 The value of the contact resistance for a new isolator should be
around (100-120)micro-ohms.
 If the value of the contact resistance exceeds the permissible limits
this could lead to over heating and arcing in contacts.
 Kit used- Contact Resistance Measurement (PE-20R)- Prestige
Motor Insulation Resistance Measurement
 To measure the insulation resistance of motor by 500V.
 Measuring of IR against Winding to Earth.
Motor Winding Resistance Measurement
 To measure the motor winding resistance by ohm meter.
 Measuring of winding resistance against phase to phase
Contact Resistance Measurement of Earth Switch
 To measuring the contact resistance measurement of Earth Switch
contacts.
 The value of the E/S contact resistance should be around (50-
100)micro-ohms.
NEED OF SYSTEM PROTECTION
 Detect the fault
 Isolate the faulty component
 Restore the faulted component
Aim: To provide continuous supply
Relay
It detects the fault and initiate the operation of CB to isolate the
defective system from the rest of the system
ANSI REFERENCE CODE
21 -Distance
24 -Over Fluxing
27 –Under Voltage
30- Auxiliary Relay
50- Instantaneous over current
50N- Instantaneous Earth Fault
50Z- Local Breaker Back-up
51- Time delay over current
51N- Time delay Earth Fault
64- Restricted Earth Fault
67- Directional over current
67N- Directional Earth Fault
74-DC fail alarm accept relay
75- Bus PT selection
78- Vector surge Relay
79- Auto reclose Relay
80- Supply Supervision
86- Master trip Relay
87- Differential
95- Trip circuit supervision
97- Fuse failure Relay
Over Current
It operate when the current exceeds a specified/set value.
O/C relays are employed for external fault conditions.
A Differential relay compares the currents on both sides of the transformer.
As long as there is no fault within the protected equipment (Transformer), the
current circulates between the two CTs and no current flows through the differential
element. But for internal faults the sum of the CTs secondary currents will flow
through the differential relay making it to operate.
Distance relay
The relay operates when the ratio of the voltage and current change beyond
the specified limit
Z r= Vr / Ir
VECTOR SURGE RELAY
The vector surge relay is used to decouple the synchronous
generator from grid in case of grid failure
1. Fast acting relay < 300ms
2. Relay operate when angle 0 to 20 deg
Restricted Earth Fault protection
It means an earth fault from a restricted zone of a circuit.
Auto reclose protection
Automatically close the CB after it has been opened due to a fault
• 90% fault in transmission line is transient faults
ANTI PUMPING
It blocks the repeat closing pulse when breaker is already in closed
condition.
LOCAL BREAKER BACKUP PROTECTION
A protection which is designed to clear a system faulty by initiating
tripping other circuit breaker(s) in the case of failure to trip of the
appropriate circuit breaker.
BREAKER BACK-UP
Because of the high cost of high voltage Circuit breakers, it is not
feasible to duplicate them.
In case of a breaker failure the other circuit breakers connected to the
same bus as the faulted breaker must there fore be tripped.
TYPES OF MAINTENANCE
i) Breakdown maintenance
ii) Preventive maintenance
iii) Condition based monitoring
Breakdown maintenance
 Breakdown maintenance is carried out when the equipment fails.
This type of maintenance may be appropriate for low cost equipments.
 However for costly switchyard equipments, it is not desirable to wait
till the breakdown of the equipment.
 The revenue loss due to non-availability of the system shall be much
more than the cost of the failed equipment.
 Therefore identifying the defect before failure, is more appropriate
to plan repair / replacement.
PREVENTIVE MAINTENANCE
 The preventive maintenance of equipment is being mostly adopted
by almost all the utilities. In this type of maintenance, the
equipments are inspected at a predetermined period.
 The frequency determined based on the past experience and also
guidance from the manufacturer of the equipment.
 This type of maintenance would require specific period of shut-
down.
CONDITION BASED MONITORING
 This type of maintenance technique is adopted to assess the
condition of the equipment.
 However, this type of maintenance would need sophisticated testing
equipments and skills for analyzing the test results.
Maintenance of Lighting Arrester
1) Insulator cleaning
2) Connections tightness
3) Checking of Earthing connections
4) Reading of leakage current on daily basis to be taken. If current
shoots in red zone, then that particular LA is to be replaced as early as
possible.
Maintenance of CT and CVT
1. Check oil level and leakage if any.
2. Cleaning of insulator and check any cracks.
3. Check HV connections, earthing and wiring in the marshalling box.
4. Measurement of IR values for comparison with earlier values.
5. Measurement of capacitors and tan-delta for windings and
bushings.
MAINTENANCE OF ISOLATORS
1. Check linkages for simultaneous operation and stopper bolts etc.
2. Check earth switch flexible.
3. Check earth connection and earth blade for proper closing
4. Clean and check any cracks in insulators.
5. Check jumper connections
6. Check auxiliary switch operation
7. Linkages including gears, Stopper bolts
8. Cleaning of auxiliary switch contact & greasing with silicon grease
9. Lubrication of operating mechanism
10. Checking of all mounting bolts for tightness
MAIN CONTACTS
1. Cleaning and lubrication of main contacts and alignment
2. Main contact resistance measurement
MAINTENANCE OF CIRCUIT BREAKER
 Check for gas pressure and leakages.
 Check operation of counters.
 Cleaning and lubricating the mechanism.
 Checking breaker status indicator, auxiliary switch linkages.
 Check operation of breaker for close and trip through local/remote
switch and protective relays.
 Check operation of anti-pumping relay and pole discrepancy.
 Check tightness of control wiring.
 Measuring of IR and CRM
 Checking of C.B timing.
 Detailed checkup of breaker operating mechanism and lubrication of
drive mechanism.
POWER SYSTEM AUTOMATION
It means switching, regulating, controlling, logging, protection etc….
SCADA
A SCADA system is one which facilitates an operator to control a
remote system and acquire real time information from remote
location.
Control and Data acquisition can be from a single point or from
multiple point.
Basic component
1. RTU
2. Communication media
3. Master control
RTU Communication
media
Master
control
The Breaker Failure Protection (LBB/BFR) can operate single-stage/twostage.
When used as single-stage protection, the Bus trip command is given to
the adjacent Circuit Breakers if the protected feeder Breaker fails.
When used as two-stage protection, the first stage can be used to
repeat the trip command to the relevant feeder Breaker, normally on a
different trip coil, if the initial trip command from the feeder protection
not successful. The second stage will result in a Bus trip to the
adjacent Breakers, if the command of the first stage is not successful.
AND
YES
YES
RETRIP
YES
NO

Más contenido relacionado

La actualidad más candente

Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Sourabh sharma
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersSARAVANAN A
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNadir Baloch
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.Hemendra Kumar Rajput
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTCRohit Dave
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFjang041
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1Siswoyo Edo
 
220 KV Switchyard general overview
220 KV Switchyard general overview220 KV Switchyard general overview
220 KV Switchyard general overviewThien Huynh
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relaysRoberto Costa
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.Sheikh Nazmul Islam
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsPower System Operation
 

La actualidad más candente (20)

Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Busbar configuarations
Busbar configuarationsBusbar configuarations
Busbar configuarations
 
SWITCHGEAR
SWITCHGEARSWITCHGEAR
SWITCHGEAR
 
Reactors
ReactorsReactors
Reactors
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
132 kv
132 kv132 kv
132 kv
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
220 KV Switchyard general overview
220 KV Switchyard general overview220 KV Switchyard general overview
220 KV Switchyard general overview
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 

Similar a 220kv substation

C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 
Multi-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptxMulti-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptxRickMaity
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substationpk130992
 
Power Electronics 2 mark Questions
Power Electronics 2 mark Questions Power Electronics 2 mark Questions
Power Electronics 2 mark Questions BALACHANDRAN D
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
Original Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 NewOriginal Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 NewAUTHELECTRONIC
 
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 NewOriginal Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 NewAUTHELECTRONIC
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)FunExplode
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014pinki199319
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportArijit Basu
 

Similar a 220kv substation (20)

C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Multi-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptxMulti-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptx
 
Executive summary
Executive summaryExecutive summary
Executive summary
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
INTERFACING.ppt
INTERFACING.pptINTERFACING.ppt
INTERFACING.ppt
 
Power Electronics 2 mark Questions
Power Electronics 2 mark Questions Power Electronics 2 mark Questions
Power Electronics 2 mark Questions
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
Original Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 NewOriginal Power Supply IC LNK632DG LNK632 632 SOP-7 New
Original Power Supply IC LNK632DG LNK632 632 SOP-7 New
 
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 NewOriginal Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
 
Mcbelcb
McbelcbMcbelcb
Mcbelcb
 
400 kv nelmangala
400 kv nelmangala400 kv nelmangala
400 kv nelmangala
 
Heavy maintenance
Heavy maintenanceHeavy maintenance
Heavy maintenance
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
Wapda Engineering Acadmy Report
Wapda Engineering Acadmy ReportWapda Engineering Acadmy Report
Wapda Engineering Acadmy Report
 
Presentation (2).pptx
Presentation (2).pptxPresentation (2).pptx
Presentation (2).pptx
 
Ee6503(r 13) qb-2013_regulation
Ee6503(r 13) qb-2013_regulationEe6503(r 13) qb-2013_regulation
Ee6503(r 13) qb-2013_regulation
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)
 
[IJET V2I5P12] Authors: Mr. Harikrishnan U, Dr. Bos Mathew Jos, Mr.Thomas P R...
[IJET V2I5P12] Authors: Mr. Harikrishnan U, Dr. Bos Mathew Jos, Mr.Thomas P R...[IJET V2I5P12] Authors: Mr. Harikrishnan U, Dr. Bos Mathew Jos, Mr.Thomas P R...
[IJET V2I5P12] Authors: Mr. Harikrishnan U, Dr. Bos Mathew Jos, Mr.Thomas P R...
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 

Último

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Último (20)

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 

220kv substation

  • 2.
  • 4. DESIGN OF SWITCHYARD Factors to note before design of switchyard  Soil Resistivity and Earthing system  Structure selection  Bus Bar  Clearance  Insulators  Conductor and its fittings  Equipment selection
  • 5. OVERVIEW 6 BAYS CORRESPONDS TO MSETCL PORTION 12 BAYS CORRESPONDS TO ABHIJEET PORTION FULLY AUTOMATED SUBSTATION
  • 6.
  • 7. 1. In this scheme there are two main buses, called as BUS-1 & BUS-2 2. One more bus is available, its called as TRANSFER BUS 3. This is useful, when any one of the breaker in trouble or maintenance 4. Most of the time transfer bus in dead condition ADVANTAGE: 1. Possible to take one bay CB and one BUS under maintenance DISADVANTAGES: 1. If second(one more) circuit breaker in trouble, then this scheme is not useful 2. There is no possible to take CT ,CVT and other equipments under maintenance • The tentative layout of the scheme shown in the next slide DOUBLE MAIN BUS WITH TRANSFER BUS SCHEME
  • 8. DOUBLE MAIN BUS WITH TRANSFER BUS BUS-2 BUS-1 TRANSFER BUS
  • 9. CHANGE OVER OF BUS-1 TO BUS-2 FOR BUS-1 MAINTENANCE 1. Normally each GT or feeder is to be connected to either bus-1 or bus-2 2. The concept behind is when either of the bus bar protection operates at least 50% circuits will be in service 3.For maintenance point of view it is happy that all circuits kept on one bus and another bus can be taken in to maintenance. 4. Normally bus-1 or bus-2 selection is to be done before charging circuit. 5. For example GT-1 & GT-2 transformers are available, GT-1 connected on Bus-1 and GT-2 connected on bus-2. 6. The bus coupler breaker is should be in service. 7. During service, change over of bus is not a practice, however this is possible when bus coupler is charged condition. 8. During service the change over of BUS-1 to BUS-2 procedure is as follows: If the circuit is connected on bus-1, close bus-2 isolator and open bus-1 isolator. This is purely for emergency
  • 10. CHANGE OVER OF MAIN BUS TO TRANSFER BUS 1. When any one of the CB in trouble that will be transferred to transfer bus. 2. The operation sequence of transfer bus will be explained in next slides. 3. Bus coupler CB & isolators are in service. 4. During this change over to transfer bus, the tripping circuits are Transferred to transfer bus coupler CB. 5. At the time, if fault occurs on circuit, the protective relays will give trip signal to concerned CB and Transfer bus CB. 6. This can be avoided by using some more logic. 7. In TBC panel, auto reclose is available. This is useful when any Line feeder is connected to TBC 8. In TBC panel, TBC LBB is also available. 9. Normal conventional system we are providing TTS switch. In normal mode tripping is done for particular circuit Breaker, if it is transfer mode the trip circuit is parallel and extended to TBC circuit breaker bay.
  • 11. CHANGE OVER OPERATION OF GT-1 TO TRANSFER BUS The sequence of operation for Normal to Transfer: GT-1 on BUS-1 at Normal 1. Close TBC bay bus-1 89A isolator. 2. Close TBC bay transfer bus 89TB isolator. 3. Close GT-1 bay, transfer bus 89TB isolator. 4. So the TBC CB both sides having voltage. 5. Put NIT switch in ‘I’ inter mode of GT-1 C&R panel. 6. Close the TBC CB. 7. Then, the GT-1 is parallel with TBC CB and feeding two parallel paths. 8. Path1:GT-1 circuit : GT-1 89L line isolator, GT-1 CB, GT-1 89A bus-1 isolator to GT-1. 9. Path2:TBC circuit : GT-1 transfer bus 89TB isolator, TBC transfer bus 89TB isolator, TBC CB, and TBC bus-1 89A isolator 10. Then open GT-1 CB. 11. Put NIT switch in ‘T’ transfer position 12. Open the GT-1 isolators i.e. Bus-1 89A isolator, 89L line isolator. 13. Now the GT-1 is feeding to bus-1 through TBC CB. 14. After maintenance work is over, the reverse procedure to be followed
  • 12. OPERATION FOR TRANSFER TO NORMAL • Put NIT switch in ‘I’ inter position. • Close GT-1 89A bus-1 isolator. • Close GT-1 89L line isolator. • Close GT-1 circuit breaker. • Open TBC CB. • Open TBC bay 89A bus-1 isolator. • Open TBC bay 89TB transfer bus isolator. • Open GT-1 bus-3 isolator. • Put NIT switch in ‘N’ normal position.
  • 13.
  • 14. EQUIPMENTS Circuit breaker Current transformer Capacitor voltage transformer Isolator Lightning arrester Coupling capacitor Wave trap Insulators and Conductors AC Distribution board DC Distribution board Battery & Battery Charger MAIN EQUIPMENTS & COMPONENTS.
  • 15. CIRCUIT BREAKER  A circuit breaker is an automatically-operated electrical switch under fault condition i.e on fault.  To open and close the electric circuit. TECHNICAL SPECIFICATION 1. MAKE - AREVA T&D 2. TYPE - SF6 CB GL314MGO 3. RATED CURRENT - 2500 A 4. RATED VOLTAGE - 245 KV 5. SHORT CIRCUIT CURRENT - 40KA for 3sec 6. OPERATING SEQUENCE - O-0.3s-CO-3min-CO 7. SF6 GAS PRESSURE AT 20⁰C - 0.85 Mpa
  • 16. ISOLATOR  Isolators or Disconnector are no-load switch.  Earth Switch is used to discharge the voltage on the circuit to earth for safety at the time of maintenance. TECHNICAL SPECIFICATION ISOLATOR 1. MAKE - SIEMENS LTD 2. TYPE - DBR 3. RATED CURRENT - 1600 A 4. RATED VOLTAGE - 245 KV 5. SHORT CIRCUIT CURRENT - 40KA for 3sec 6. TYPE OF DRIVE - MOTOR/MANUAL 7. MOTOR VOLTAGE (AC) - 415V 8. CONTROL VOLTAGE (DC) - 220V 9. CREEPAGE DISTANCE - 7812 mm EARTH SWITCH TYPE OF DRIVE - MANUAL
  • 17. CURRENT TRANSFORMER  CT merely reduces a high current flowing through its primary to a low current on secondary.  The secondary of a CT should never be kept open circuited because very high flux will be developed in the secondary and hence it may be damaged. TECHNICAL SPECIFICATION
  • 18. CAPACITOR VOLTAGE TRANSFORMER  CVT is a transformer used to step down the high voltage to low voltage. For metering and protection.  Also useful in communication system, to block the power frequency entering into PLCC terminal. TECHNICAL SPECIFICATION
  • 19. LIGHTNING ARRESTER  Lightning arrester or Surge arrester are used to protect other equipments from over-voltage due to lightning and switching.  This is the first equipment in all feeders and transformer bay. TECHNICAL SPECIFICATION 1. MAKE - OBLUM ELECTRICAL 2. TYPE - Gapless Type, METOVAR 3. NO. OF UNITS PER ARRESTOR - Three units of 66kV each 4. RATED VOLTAGE - 198 KV 5. NOMINAL DISCHARGE CURRENT - 10 KA 6. HIGHEST SYSTEM VOLTAGE - 245 KV 7. NOMINAL SYSTEM VOLTAGE - 220 KV 8. SYSTEM EARTHING - Solidly Earthed system
  • 20. COUPLING CAPACITOR  Coupling Capacitors are used in communication system, to block the power frequency entering into PLCC terminal. TECHNICAL SPECIFICATION 1. MAKE - AREVA T&D INDIA LTD. 2. TYPE - CCV-245 3. RATED FREQUENCY - 50HZ 4. VOLTAGE CLASS - 245KV 5. 1-MINUTE 50 HZ WITHSTAND - 460 KV 6. TYPE - Porcelain-Oil 7. MAX. TEMP. RISE OVER 50 ⁰C AMBIENT -55 ⁰C 8. TOTAL EQUIVALENT CAPACITANCE -6600 pF + 10%, -5% 9. CVT SUITABLE FOR FREQUENCY RANGE -40-500 kHz 10. TYPE OF LA -Non-linear resistive type Gapped LA 11. Rated voltage of LA - 9 KV 12. Nominal Discharge Current -10 KA
  • 21. WAVE TRAP  Line trap OR Wave trap used to trap the high frequency communication signals entering into switchyard equipments and diverting them to the telecom panel in the switchyard control room (through coupling capacitor and LMU). TECHNICAL SPECIFICATION 1. MAKE - AREVA 2. TYPE OUTDOOR -Air cored 3. INDUCTANCE OF THE MAIN COIL -0.5 mH 4. BLOCKING RANGE -100-175 &150-500kHz 5. TYPE OF TUNING -Variable Broad Band Tuning 6. MATERIAL OF MAIN COIL -Aluminium Alloy 7. MATERIAL OF TERMINAL CONNECTOR -Aluminium Alloy 8. SYSTEM VOLTAGE - 220KV 9. CONTINUOUS CURRENT RATING 40 ⁰C - 1250A Max. 10. SHORT CIRCUIT CURRENT -40 KA for 1 sec
  • 22. CONDUCTOR  Conductor is the material allowing the flow of electric current ACSR Aluminum Conductor Steel Reinforced. INSULATOR  Insulator is the material to support a conductor physically and to separate it electrically from another conductor or object. 1. Long Rod Insulator(Tension & Suspension Stringing) 2. Post Insulators
  • 23. BATTERY BANK AND BATTERY CHARGER 1. 220 VOLT BATTERY BANK- For Protection & Controlling  Total No. of cell- 173  Volt. Rating of each cell- 1.2 Volt  Capacity - 148 Ah 2. 48 VOLT BATTERY- For SCADA RTU & SIC Panel.  Total No. of cell- 24.  Volt. Rating of each cell- 2 Volt.  Capacity- 50 Ah 3. TWO 12 VOLT BATTERY BANK – For Inverter  Total No. of cell- 12(For MPP 6KVA Inverter)  Total No. of cell- 12(For MSETCL 3KVA Inverter)  Volt. Rating of each cell- 12 Volt  Capacity- 26 Ah. BATTERY BANK
  • 24. BATTERY CHARGER 1. Type- Float Cum Boost Charger.  Float mode( Simultaneously Charge & Discharge the Battery Bank )  Boost mode( This is the Charging mode)  Auto mode(Its Play the role according to the system requirements) 2. Rating- 1. MPP FCBC- 135A/220V 2. MSETCL FCBC- 50A/48V 3. Make- 1. MPP FCBC- Amar Raj 2. MSETCL FCBC- Panva
  • 25.
  • 26. TESTING OF CURRENT TRANSFORMER 1. Insulation resistance test (IR test) 2. Polarity test 3. Excitation test (Knee point voltage test). 4. Ratio test 5. Winding resistance test 6. Tan delta and Capacitance Measurement test.
  • 27. IR TESTING To measure the insulation resistance of the equipments. a) Primary to earth by 5 KV b) Secondary each core to earth by 500 V c) Primary to secondary by 5 KV d) Secondary core to core by 500 V MAKE - MEGGER
  • 28. POLARITY TEST Polarity test of current transformer is to be carried out check the correctness of the primary and secondary polarity  For carrying out this test, we require one 1.5 V cell, DC analogue ammeter.  By making below connection, if there is positive deflection of ammeter , then polarity is confirmed.
  • 29. EXCITATION TEST Excitation test will be carried out to measure the knee point voltage of different cores of the current transformer Knee point check for PS class core - Inject 230 V variable AC voltage in secondary core with ammeter in series. At certain point, with 10% increase in voltage, current shoots up almost 50%. This is the Knee point voltage. After performing this test, Voltage is gradually reduced to Zero to demagnetize the CT.
  • 30. RATIO TEST Inject current in primary winding & measure induced secondary current for different current readings and verify with CT Ratio. WINDING RESISTANCE TEST Measure secondary winding resistance by micro ohm meter. value should be .
  • 31. TAN DELTA MEASUREMENT Consider the insulation of equipment as Capacitor. If the capacitor is good or perfect, it will pass only capacitive or charging current on application of voltage. Ideal capacitive current Ic leads voltage by 90°. But in practice, insulation has impurities & actual charging current vector departs from the ideal Ic vector by a small angle (δ) called the loss angle. The loss angle (δ) = 90 – Power factor angle (φ) Higher tan δ produces high dielectric loss that causes increase in temperature of paper insulation. Increased value of Tan δ can be due to any of the following: - a) Moisture in the insulation. b) Contamination of oil. c) Internal partial discharge.
  • 32. TESTING OF POTENTIAL TRANSFORMER  Insulation resistance test (IR test)  Winding resistance measurement  Ratio test  Tan Delta and Capacitance measurement test TESTING OF LIGHTNING ARRESTER IR Testing between Stack to stack & between each Stack to earth by megger.  Surge Counter Test - Apply 230V AC supply across the counter & check pointer movement in clockwise direction.
  • 33. TESTING OF CIRCUIT BREAKER  Insulation Resistance Test  Timing Test  Contact Resistance Measurement Test INSULATION RESISTANCE TEST To measure the insulation healthiness of circuit breaker. Open condition: 1. Top- Earth 2. Bottom- Earth 3. Top- Bottom Close condition: 1. Top- Earth 2. Bottom- Earth 3. Top- Bottom
  • 34. CONTACT RESISTANCE MEASUREMENT  To measuring the contact resistance measurement of circuit breaker main contacts.  The value of the contact resistance for a new circuit breaker should be around 50 micro-ohms.  If the value of the contact resistance exceeds the permissible limits this could lead to over heating of contacts.
  • 35. TIMING TEST To check the operation timing of circuit breaker.  Trip circuit 1 O->open C->close C-O->close-open  Trip circuit 2 O->open C->close C-O->close-open  Kit used- Circuit Breaker Analyzer (EGIL BM19090)- Megger  Tripolar Unipolar O-> 23- 25 18-20 C-> 60-65 100-110 C-O-> 35-40 35-40
  • 36. TESTING OF ISOLATORS  Insulation Resistance Measurement  Contact Resistance Measurement  Motor Insulation Resistance Measurement  Motor Winding Resistance Measurement  Contact Resistance Measurement of Earth Switch Insulation Resistance Measurement  To measure the insulation resistance of Isolators.  Measuring of insulation resistance against following condition. 1. Phase to Earth 2. Phase to Phase
  • 37. CONTACT RESISTANCE MEASUREMENT  To measuring the contact resistance measurement of Isolator contacts.  The value of the contact resistance for a new isolator should be around (100-120)micro-ohms.  If the value of the contact resistance exceeds the permissible limits this could lead to over heating and arcing in contacts.  Kit used- Contact Resistance Measurement (PE-20R)- Prestige
  • 38. Motor Insulation Resistance Measurement  To measure the insulation resistance of motor by 500V.  Measuring of IR against Winding to Earth. Motor Winding Resistance Measurement  To measure the motor winding resistance by ohm meter.  Measuring of winding resistance against phase to phase Contact Resistance Measurement of Earth Switch  To measuring the contact resistance measurement of Earth Switch contacts.  The value of the E/S contact resistance should be around (50- 100)micro-ohms.
  • 39. NEED OF SYSTEM PROTECTION  Detect the fault  Isolate the faulty component  Restore the faulted component Aim: To provide continuous supply Relay It detects the fault and initiate the operation of CB to isolate the defective system from the rest of the system
  • 40. ANSI REFERENCE CODE 21 -Distance 24 -Over Fluxing 27 –Under Voltage 30- Auxiliary Relay 50- Instantaneous over current 50N- Instantaneous Earth Fault 50Z- Local Breaker Back-up 51- Time delay over current 51N- Time delay Earth Fault 64- Restricted Earth Fault 67- Directional over current 67N- Directional Earth Fault 74-DC fail alarm accept relay 75- Bus PT selection 78- Vector surge Relay 79- Auto reclose Relay 80- Supply Supervision 86- Master trip Relay 87- Differential 95- Trip circuit supervision 97- Fuse failure Relay
  • 41. Over Current It operate when the current exceeds a specified/set value. O/C relays are employed for external fault conditions.
  • 42. A Differential relay compares the currents on both sides of the transformer. As long as there is no fault within the protected equipment (Transformer), the current circulates between the two CTs and no current flows through the differential element. But for internal faults the sum of the CTs secondary currents will flow through the differential relay making it to operate.
  • 43. Distance relay The relay operates when the ratio of the voltage and current change beyond the specified limit Z r= Vr / Ir
  • 44. VECTOR SURGE RELAY The vector surge relay is used to decouple the synchronous generator from grid in case of grid failure 1. Fast acting relay < 300ms 2. Relay operate when angle 0 to 20 deg Restricted Earth Fault protection It means an earth fault from a restricted zone of a circuit. Auto reclose protection Automatically close the CB after it has been opened due to a fault • 90% fault in transmission line is transient faults
  • 45. ANTI PUMPING It blocks the repeat closing pulse when breaker is already in closed condition.
  • 46. LOCAL BREAKER BACKUP PROTECTION A protection which is designed to clear a system faulty by initiating tripping other circuit breaker(s) in the case of failure to trip of the appropriate circuit breaker. BREAKER BACK-UP Because of the high cost of high voltage Circuit breakers, it is not feasible to duplicate them. In case of a breaker failure the other circuit breakers connected to the same bus as the faulted breaker must there fore be tripped.
  • 47. TYPES OF MAINTENANCE i) Breakdown maintenance ii) Preventive maintenance iii) Condition based monitoring Breakdown maintenance  Breakdown maintenance is carried out when the equipment fails. This type of maintenance may be appropriate for low cost equipments.  However for costly switchyard equipments, it is not desirable to wait till the breakdown of the equipment.  The revenue loss due to non-availability of the system shall be much more than the cost of the failed equipment.  Therefore identifying the defect before failure, is more appropriate to plan repair / replacement.
  • 48. PREVENTIVE MAINTENANCE  The preventive maintenance of equipment is being mostly adopted by almost all the utilities. In this type of maintenance, the equipments are inspected at a predetermined period.  The frequency determined based on the past experience and also guidance from the manufacturer of the equipment.  This type of maintenance would require specific period of shut- down. CONDITION BASED MONITORING  This type of maintenance technique is adopted to assess the condition of the equipment.  However, this type of maintenance would need sophisticated testing equipments and skills for analyzing the test results.
  • 49. Maintenance of Lighting Arrester 1) Insulator cleaning 2) Connections tightness 3) Checking of Earthing connections 4) Reading of leakage current on daily basis to be taken. If current shoots in red zone, then that particular LA is to be replaced as early as possible. Maintenance of CT and CVT 1. Check oil level and leakage if any. 2. Cleaning of insulator and check any cracks. 3. Check HV connections, earthing and wiring in the marshalling box. 4. Measurement of IR values for comparison with earlier values. 5. Measurement of capacitors and tan-delta for windings and bushings.
  • 50. MAINTENANCE OF ISOLATORS 1. Check linkages for simultaneous operation and stopper bolts etc. 2. Check earth switch flexible. 3. Check earth connection and earth blade for proper closing 4. Clean and check any cracks in insulators. 5. Check jumper connections 6. Check auxiliary switch operation 7. Linkages including gears, Stopper bolts 8. Cleaning of auxiliary switch contact & greasing with silicon grease 9. Lubrication of operating mechanism 10. Checking of all mounting bolts for tightness MAIN CONTACTS 1. Cleaning and lubrication of main contacts and alignment 2. Main contact resistance measurement
  • 51. MAINTENANCE OF CIRCUIT BREAKER  Check for gas pressure and leakages.  Check operation of counters.  Cleaning and lubricating the mechanism.  Checking breaker status indicator, auxiliary switch linkages.  Check operation of breaker for close and trip through local/remote switch and protective relays.  Check operation of anti-pumping relay and pole discrepancy.  Check tightness of control wiring.  Measuring of IR and CRM  Checking of C.B timing.  Detailed checkup of breaker operating mechanism and lubrication of drive mechanism.
  • 52. POWER SYSTEM AUTOMATION It means switching, regulating, controlling, logging, protection etc…. SCADA A SCADA system is one which facilitates an operator to control a remote system and acquire real time information from remote location. Control and Data acquisition can be from a single point or from multiple point.
  • 53. Basic component 1. RTU 2. Communication media 3. Master control RTU Communication media Master control
  • 54.
  • 55.
  • 56.
  • 57.
  • 58. The Breaker Failure Protection (LBB/BFR) can operate single-stage/twostage. When used as single-stage protection, the Bus trip command is given to the adjacent Circuit Breakers if the protected feeder Breaker fails. When used as two-stage protection, the first stage can be used to repeat the trip command to the relevant feeder Breaker, normally on a different trip coil, if the initial trip command from the feeder protection not successful. The second stage will result in a Bus trip to the adjacent Breakers, if the command of the first stage is not successful. AND YES YES RETRIP YES NO