SlideShare una empresa de Scribd logo
1 de 4
Descargar para leer sin conexión
Generation Assessment and Loss Justification
The generation was estimated considering 315Wp modules of a reputed
make and 1MW solar inverter of a reputed make as initial design inputs for
conducting the simulations.
The project uses a seasonal tilt system for with 7.5m pitch.
The DC to AC overloading that has been decided as a design parameter is
25%.
The typical loss breakdown is as shown below with relevant justifications
Table 1: Justification of PVSyst Losses
S.No. Parameter Measure Justification
1. PV Syst Version 6.41
Latest version of PVSyst simulation tool has
been used
2. Tilt Angle/Tracking Angle 5 o and 30 o
For seasonal tilt, the aforementioned tilt angles
for summer and winter have been assumed.
3. Pitch(m) 7.5
Considering the overloading of 25%, and
corresponding land usage and generation
optimization, the pitch values given here came
out to be optimal
4. Shading
-0.2% (5 o)
Near shading is caused by inter row distance
and due to tall objects like control rooms and
lightening arrestors. For shading from tall
objects, sufficient spaces are left by conducting a
shadow estimation study so as to keep the PV
array shadow free during generation hours. The
near shading loss due to inter row spacing is
however determined by PVSyst as per the
design pitch considered. In the case of seasonal
tilt, the shading losses are low for summer tilt
and is higher for winter tilt. However, the
average shading loss will fall somewhere in
between the two values.
-3.7% (30 o)
5. Incidence Angle Modifier
-2.2% (5 o)
IAM loss accounts for losses in radiation
penetrating the front glass of the PV
modules due to angles of incidence other than
perpendicular. The loss figures is a module
dependent parameter and is calculated by the
PVSyst as per the module chosen.
-3.3% (30 o)
6. Soiling Loss -1.5%
This is the loss due to dust and bird droppings
on the PV modules depending on the
environmental conditions, rainfall frequency
and on the plant’s O&M module cleaning
strategy.
To assure the maintenance of soiling losses
below 1.5%, a novel soilingestimation setup will
be setup at plant during O&M consisting of two
PV strings. One of the PV strings will be cleaned
on a daily basis, while the other one will not be
cleaned. Once, the difference between
performance of the two strings will start
touching 1.25%, a module cleaning cycle of the
entire plant will be initiated, thus ensuring
soiling loss in line with the design assumption.
7. Module Temperature Loss -9.5% (Seasonal)
The characteristics of a PV module are
determined at standard temperature conditions
of 25˚C. Considering the temperature coefficient
of the 315Wp modules selected, the module
performance decreases by -0.40% for every oC
rise in cell temperature.
Module temperature loss is computed by the
PVSyst by considering the temperature profile
of the location as per the meteo database. Since,
the site is located in Rajasthan, a desert region
with high temperatures, and the high
temperature losses calculated are representative
of the high temperature profile.
8. Module Quality Loss +0.4%
PV modules generally deviate from the
manufacturer’s technical specifications. The
315W modules considered here are supplied
with a positive Power tolerance of 0 to 3%. The
developer has thus considered a quality gain of
0.4%, although on a conservative side so as to
account for other contingencies in generation
estimation.
9.
First Year Module
Degradation (under Light
Induced Degradation(LID))
-1.5%
The performance of PV modules degrades over
the time. The degradation is most significant
during few hours of first exposure of PV
modules to light. This phenomenon is known as
Light Induced Degradation (LID). Factors
affecting the degree of degradation include the
quality of materials used in manufacture, the
manufacturing process and the quality of
assembly and packaging of cells into the
modules.
The first year degradation considering LID and
annual degradation is guaranteed to be less than
2.5% in the datasheet. However, as per the
general industry experience, the first year
degradation for Tier-1 modules has typically
been observed between 0.8% to 1.5%. Hence, the
first year module performance degradation has
been considered as 1.5% here.
10.
Module Array Mismatch
Loss
-0.8%
Mismatch losses represent the mismatch in
current/voltage of modules in a string due to
statistical variations. Typically, the mismatch
losses are considered as 1%. However, the loss
can be reduced by sorting the modules as per
current before factory dispatch. The modules
supplied at site with a 3-bin current sorting will
effectively reduce the mismatch losses. Hence,
we have considered the module mismatch losses
as 0.8%.
11. DC Ohmic Wiring Loss -1.5% (STC)
Electrical resistance in the wires between the
power available at the modules and at the
terminals of the array gives rise to ohmic losses
(I²R).
For well-designed plants, DC cabling losses at
STC vary from 1.2% to 1.5% at STC. We have
considered 1.5% as the DC Ohmic losses at STC.
The losses are at full load, and the PVsyst
computed the overall losses considering the
solar plant operates at partial loads most of the
times. The final loss then computed by PVSyst
corresponding to 1.5% loss at STC considering
the partial load profile of plant is 1.1%
12.
Inverter Loss during
Operation (Efficiency)
-1.7%
Inverters convert power from DC into AC at a
certain efficiency. This results in a loss of power
during conversion from AC to DC. The
efficiency curves are inverter dependent. In our
case, the inverters considered are 1000kW of a
reputed make. The efficiency loss has been
calculated by the PVSyst as per the
manufacturer provided efficiency curves of the
inverter and stands at around 1.7%.
13. Auxiliary Losses -0.6%
Various components of plants like inverters,
PLC, module cleaning system, plant lighting,
security systems etc and amenities like Air
conditioning, plumbing and others consume
electricity for their operation. This is known as
auxiliary loss. The auxiliary losses vary from
0.5% to 1% depending upon the size, design and
structure of the plant. Typically, small plants
require a higher percentage of auxiliary
consumption than bigger plants on relative
terms. Various measures such as night
disconnect, self-powered trackers, LED lighting,
have been considered in the design for reducing
auxiliary consumption. The auxiliary losses
have thus been reasonably considered at 0.6%
with sufficient margin.
14. AC Ohmic Losses -0.5% (Full Load)
This includes ohmic losses in the cable from
inverter leading to the substation, and depends
on the sizingof cables during the design. During
the design of the plants, the AC cable sizing has
been done in such a way that the losses do not
exceed 0.5% in the AC side. Full load AC ohmic
losses of 0.5% have been considered,
corresponding to which PVsyst computes the
overall losses considering the solar plant
operates at partial loads most of the times. The
final loss then computed by PVSyst
corresponding to 0.5% loss at STC considering
the partial load profile of plant is 0.3%.
15. System Unavailability -0.5%
Downtime depends on the diagnostic response
time and stock of spare equipment. Further, loss
in generation due to unavailability of plant and
grid are also accounted for in downtime losses.
Typically, the unavailability is higher for smaller
plants, as compared to larger plants due to
relative impact of failure of a single component
on the entire plant availability. The O&M
scheme thought out also considers stocking of
inverter transformer, breaker, inverter IGBT
stacks, and modules, cables of all sizes,
consumables and on site deployment of service
persons of critical components like
transformers, inverters on site along with
regular manufacturer training of O&M
personnel. Large solar plants in solar parks are
now connected at 132kV to the grid which is
ultimately connected at 400kV to green corridor
grid network, which will be extremely stable
with very less downtime. Considering the
above, the system unavailability has been
considered as 0.5%
16. External Transformer Loss -1.6%
Large losses may rise in the transformer but are
generally less than 1% for each transformation
level. Given the fact that the plant will be
evacuating at 132kV, two levels of losses have
been considered; 1.0% for the intermediate
transformation at 33/11kV, and 0.6% (following
the GTP of the transformer to be used on-site)
for the second level of transformation at 132kV
in line with standard design practices.

Más contenido relacionado

La actualidad más candente

SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
Murugappa Group
 
PV solar Design and Installtion
PV solar Design and InstalltionPV solar Design and Installtion
PV solar Design and Installtion
Eli Israeli
 

La actualidad más candente (20)

Grid connected pv solar power plant
Grid connected pv solar power plantGrid connected pv solar power plant
Grid connected pv solar power plant
 
Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
 
Solar PV System
Solar PV SystemSolar PV System
Solar PV System
 
Solar plant
Solar plantSolar plant
Solar plant
 
Solar system design
Solar system designSolar system design
Solar system design
 
A quick guide to off grid solar power systems design
A quick guide to off grid solar power systems designA quick guide to off grid solar power systems design
A quick guide to off grid solar power systems design
 
CUF vs PR
CUF vs PRCUF vs PR
CUF vs PR
 
PV solar Design and Installtion
PV solar Design and InstalltionPV solar Design and Installtion
PV solar Design and Installtion
 
PVsysts new framework to simulate bifacial systems
PVsysts new framework to simulate bifacial systemsPVsysts new framework to simulate bifacial systems
PVsysts new framework to simulate bifacial systems
 
Grid-connected PV system
Grid-connected PV systemGrid-connected PV system
Grid-connected PV system
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV system
 
Solar on grid application ppt
Solar on grid application pptSolar on grid application ppt
Solar on grid application ppt
 
How solar rooftop system works
How solar rooftop system worksHow solar rooftop system works
How solar rooftop system works
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
 
Solar Training 20100208
Solar Training 20100208Solar Training 20100208
Solar Training 20100208
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plant
 
Erection Checklist for Solar Inverters, Solar Transformers & Solar String Com...
Erection Checklist for Solar Inverters, Solar Transformers & Solar String Com...Erection Checklist for Solar Inverters, Solar Transformers & Solar String Com...
Erection Checklist for Solar Inverters, Solar Transformers & Solar String Com...
 
Optimizing Operation & Maintenance Practices for Solar Power Plant
Optimizing Operation & Maintenance Practices for Solar Power PlantOptimizing Operation & Maintenance Practices for Solar Power Plant
Optimizing Operation & Maintenance Practices for Solar Power Plant
 

Destacado

Destacado (20)

10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design
 
Pre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantPre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power Plant
 
Steps to simulate grid connected solar pv project through PVSyst Software
 Steps to simulate grid connected solar pv project through PVSyst Software Steps to simulate grid connected solar pv project through PVSyst Software
Steps to simulate grid connected solar pv project through PVSyst Software
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
 
Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in India
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power Plant
 
Guide to Solar Project Implementation
Guide to Solar Project ImplementationGuide to Solar Project Implementation
Guide to Solar Project Implementation
 
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power PlantTransmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
 
Phases of Construction - Solar Project
Phases of Construction - Solar ProjectPhases of Construction - Solar Project
Phases of Construction - Solar Project
 
Economics of Solar Park
Economics of Solar ParkEconomics of Solar Park
Economics of Solar Park
 
Comparison between different Li Ion Cells Type
Comparison between different Li Ion Cells TypeComparison between different Li Ion Cells Type
Comparison between different Li Ion Cells Type
 
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
 
Solar Roof top Project proposal delhi
Solar Roof top Project proposal delhiSolar Roof top Project proposal delhi
Solar Roof top Project proposal delhi
 
Solar mango corporate presentation
Solar mango   corporate presentationSolar mango   corporate presentation
Solar mango corporate presentation
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Gensol Lender's Engineer Services
Gensol Lender's Engineer ServicesGensol Lender's Engineer Services
Gensol Lender's Engineer Services
 
Market Outlook for Energy Storage in India
Market Outlook for Energy Storage in IndiaMarket Outlook for Energy Storage in India
Market Outlook for Energy Storage in India
 
Gensol's EPC Credentials (Engineering, Procurement & Construction)
Gensol's EPC Credentials (Engineering, Procurement & Construction)Gensol's EPC Credentials (Engineering, Procurement & Construction)
Gensol's EPC Credentials (Engineering, Procurement & Construction)
 
Optimisation of Balance of System (BOS) for Solar Projects
Optimisation of Balance of System (BOS) for Solar ProjectsOptimisation of Balance of System (BOS) for Solar Projects
Optimisation of Balance of System (BOS) for Solar Projects
 

Similar a Analysis of PVSyst Loss Diagram

Reduction of mismatch and shading loss by use
Reduction of mismatch and shading loss by useReduction of mismatch and shading loss by use
Reduction of mismatch and shading loss by use
iaemedu
 
Reduction of mismatch and shading loss by use of distributed power electronics
Reduction of mismatch and shading loss by use of distributed power electronicsReduction of mismatch and shading loss by use of distributed power electronics
Reduction of mismatch and shading loss by use of distributed power electronics
IAEME Publication
 
List of solar technologies
List of solar technologiesList of solar technologies
List of solar technologies
firstgreen
 
Solar Power Plant cash flow model
Solar Power Plant cash flow model Solar Power Plant cash flow model
Solar Power Plant cash flow model
Vijay Kannan
 

Similar a Analysis of PVSyst Loss Diagram (20)

Short Commercial presentation_ROW.pptx
Short Commercial presentation_ROW.pptxShort Commercial presentation_ROW.pptx
Short Commercial presentation_ROW.pptx
 
Pv field detailed losses
Pv field detailed lossesPv field detailed losses
Pv field detailed losses
 
Reduction of mismatch and shading loss by use
Reduction of mismatch and shading loss by useReduction of mismatch and shading loss by use
Reduction of mismatch and shading loss by use
 
Reduction of mismatch and shading loss by use of distributed power electronics
Reduction of mismatch and shading loss by use of distributed power electronicsReduction of mismatch and shading loss by use of distributed power electronics
Reduction of mismatch and shading loss by use of distributed power electronics
 
Redundant Low Voltage PV System
Redundant Low Voltage PV SystemRedundant Low Voltage PV System
Redundant Low Voltage PV System
 
IRJET - MPPT based Photovoltaic System with Zeta Converter for DC Load
IRJET - MPPT based Photovoltaic System with Zeta Converter for DC LoadIRJET - MPPT based Photovoltaic System with Zeta Converter for DC Load
IRJET - MPPT based Photovoltaic System with Zeta Converter for DC Load
 
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
IRJET- Grid Integrated Single Phase PV with Shunt Active Filter based Control...
 
ATMEGA 328SOLAR TRACKING CLOSED LOOP SYSTEM FOR POWER POWER FACTOR IMPROVEMENT.
ATMEGA 328SOLAR TRACKING CLOSED LOOP SYSTEM FOR POWER POWER FACTOR IMPROVEMENT.ATMEGA 328SOLAR TRACKING CLOSED LOOP SYSTEM FOR POWER POWER FACTOR IMPROVEMENT.
ATMEGA 328SOLAR TRACKING CLOSED LOOP SYSTEM FOR POWER POWER FACTOR IMPROVEMENT.
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
IRJET- Power Quality Assessment of Photovoltaic System
IRJET- Power Quality Assessment of Photovoltaic SystemIRJET- Power Quality Assessment of Photovoltaic System
IRJET- Power Quality Assessment of Photovoltaic System
 
List Of Solar Technologies
List Of Solar TechnologiesList Of Solar Technologies
List Of Solar Technologies
 
List of solar technologies
List of solar technologiesList of solar technologies
List of solar technologies
 
Solar Power Plant cash flow model
Solar Power Plant cash flow model Solar Power Plant cash flow model
Solar Power Plant cash flow model
 
Sampling guideline for inspection
Sampling guideline for inspectionSampling guideline for inspection
Sampling guideline for inspection
 
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
 
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
Younes Sina, Jonathan Rhyne ,Sabina Ude, Huidong Zang, Mary Waddle ,A report ...
 
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
IRJET- Performance Assessment of Grid Connected 1.1 MWp Solar Photo-Voltaic P...
 
Modeling and Analysis of Hybrid Ac Micro-Grid
Modeling and Analysis of Hybrid Ac Micro-GridModeling and Analysis of Hybrid Ac Micro-Grid
Modeling and Analysis of Hybrid Ac Micro-Grid
 
Solar mill vs solar panel by kevin woodbridge
Solar mill vs solar panel by kevin woodbridgeSolar mill vs solar panel by kevin woodbridge
Solar mill vs solar panel by kevin woodbridge
 

Más de Gensol Engineering Limited

Más de Gensol Engineering Limited (20)

Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019
 
List of successful bidders 11.03.2019
List of successful bidders 11.03.2019List of successful bidders 11.03.2019
List of successful bidders 11.03.2019
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Module Price Trend Analysis
Module Price Trend AnalysisModule Price Trend Analysis
Module Price Trend Analysis
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
 
Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18
 

Último

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
Renandantas16
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 

Último (20)

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

Analysis of PVSyst Loss Diagram

  • 1. Generation Assessment and Loss Justification The generation was estimated considering 315Wp modules of a reputed make and 1MW solar inverter of a reputed make as initial design inputs for conducting the simulations. The project uses a seasonal tilt system for with 7.5m pitch. The DC to AC overloading that has been decided as a design parameter is 25%. The typical loss breakdown is as shown below with relevant justifications Table 1: Justification of PVSyst Losses S.No. Parameter Measure Justification 1. PV Syst Version 6.41 Latest version of PVSyst simulation tool has been used 2. Tilt Angle/Tracking Angle 5 o and 30 o For seasonal tilt, the aforementioned tilt angles for summer and winter have been assumed. 3. Pitch(m) 7.5 Considering the overloading of 25%, and corresponding land usage and generation optimization, the pitch values given here came out to be optimal 4. Shading -0.2% (5 o) Near shading is caused by inter row distance and due to tall objects like control rooms and lightening arrestors. For shading from tall objects, sufficient spaces are left by conducting a shadow estimation study so as to keep the PV array shadow free during generation hours. The near shading loss due to inter row spacing is however determined by PVSyst as per the design pitch considered. In the case of seasonal tilt, the shading losses are low for summer tilt and is higher for winter tilt. However, the average shading loss will fall somewhere in between the two values. -3.7% (30 o) 5. Incidence Angle Modifier -2.2% (5 o) IAM loss accounts for losses in radiation penetrating the front glass of the PV modules due to angles of incidence other than perpendicular. The loss figures is a module dependent parameter and is calculated by the PVSyst as per the module chosen. -3.3% (30 o)
  • 2. 6. Soiling Loss -1.5% This is the loss due to dust and bird droppings on the PV modules depending on the environmental conditions, rainfall frequency and on the plant’s O&M module cleaning strategy. To assure the maintenance of soiling losses below 1.5%, a novel soilingestimation setup will be setup at plant during O&M consisting of two PV strings. One of the PV strings will be cleaned on a daily basis, while the other one will not be cleaned. Once, the difference between performance of the two strings will start touching 1.25%, a module cleaning cycle of the entire plant will be initiated, thus ensuring soiling loss in line with the design assumption. 7. Module Temperature Loss -9.5% (Seasonal) The characteristics of a PV module are determined at standard temperature conditions of 25˚C. Considering the temperature coefficient of the 315Wp modules selected, the module performance decreases by -0.40% for every oC rise in cell temperature. Module temperature loss is computed by the PVSyst by considering the temperature profile of the location as per the meteo database. Since, the site is located in Rajasthan, a desert region with high temperatures, and the high temperature losses calculated are representative of the high temperature profile. 8. Module Quality Loss +0.4% PV modules generally deviate from the manufacturer’s technical specifications. The 315W modules considered here are supplied with a positive Power tolerance of 0 to 3%. The developer has thus considered a quality gain of 0.4%, although on a conservative side so as to account for other contingencies in generation estimation. 9. First Year Module Degradation (under Light Induced Degradation(LID)) -1.5% The performance of PV modules degrades over the time. The degradation is most significant during few hours of first exposure of PV modules to light. This phenomenon is known as Light Induced Degradation (LID). Factors affecting the degree of degradation include the quality of materials used in manufacture, the manufacturing process and the quality of assembly and packaging of cells into the modules. The first year degradation considering LID and annual degradation is guaranteed to be less than 2.5% in the datasheet. However, as per the general industry experience, the first year degradation for Tier-1 modules has typically been observed between 0.8% to 1.5%. Hence, the first year module performance degradation has been considered as 1.5% here.
  • 3. 10. Module Array Mismatch Loss -0.8% Mismatch losses represent the mismatch in current/voltage of modules in a string due to statistical variations. Typically, the mismatch losses are considered as 1%. However, the loss can be reduced by sorting the modules as per current before factory dispatch. The modules supplied at site with a 3-bin current sorting will effectively reduce the mismatch losses. Hence, we have considered the module mismatch losses as 0.8%. 11. DC Ohmic Wiring Loss -1.5% (STC) Electrical resistance in the wires between the power available at the modules and at the terminals of the array gives rise to ohmic losses (I²R). For well-designed plants, DC cabling losses at STC vary from 1.2% to 1.5% at STC. We have considered 1.5% as the DC Ohmic losses at STC. The losses are at full load, and the PVsyst computed the overall losses considering the solar plant operates at partial loads most of the times. The final loss then computed by PVSyst corresponding to 1.5% loss at STC considering the partial load profile of plant is 1.1% 12. Inverter Loss during Operation (Efficiency) -1.7% Inverters convert power from DC into AC at a certain efficiency. This results in a loss of power during conversion from AC to DC. The efficiency curves are inverter dependent. In our case, the inverters considered are 1000kW of a reputed make. The efficiency loss has been calculated by the PVSyst as per the manufacturer provided efficiency curves of the inverter and stands at around 1.7%. 13. Auxiliary Losses -0.6% Various components of plants like inverters, PLC, module cleaning system, plant lighting, security systems etc and amenities like Air conditioning, plumbing and others consume electricity for their operation. This is known as auxiliary loss. The auxiliary losses vary from 0.5% to 1% depending upon the size, design and structure of the plant. Typically, small plants require a higher percentage of auxiliary consumption than bigger plants on relative terms. Various measures such as night disconnect, self-powered trackers, LED lighting, have been considered in the design for reducing auxiliary consumption. The auxiliary losses have thus been reasonably considered at 0.6% with sufficient margin.
  • 4. 14. AC Ohmic Losses -0.5% (Full Load) This includes ohmic losses in the cable from inverter leading to the substation, and depends on the sizingof cables during the design. During the design of the plants, the AC cable sizing has been done in such a way that the losses do not exceed 0.5% in the AC side. Full load AC ohmic losses of 0.5% have been considered, corresponding to which PVsyst computes the overall losses considering the solar plant operates at partial loads most of the times. The final loss then computed by PVSyst corresponding to 0.5% loss at STC considering the partial load profile of plant is 0.3%. 15. System Unavailability -0.5% Downtime depends on the diagnostic response time and stock of spare equipment. Further, loss in generation due to unavailability of plant and grid are also accounted for in downtime losses. Typically, the unavailability is higher for smaller plants, as compared to larger plants due to relative impact of failure of a single component on the entire plant availability. The O&M scheme thought out also considers stocking of inverter transformer, breaker, inverter IGBT stacks, and modules, cables of all sizes, consumables and on site deployment of service persons of critical components like transformers, inverters on site along with regular manufacturer training of O&M personnel. Large solar plants in solar parks are now connected at 132kV to the grid which is ultimately connected at 400kV to green corridor grid network, which will be extremely stable with very less downtime. Considering the above, the system unavailability has been considered as 0.5% 16. External Transformer Loss -1.6% Large losses may rise in the transformer but are generally less than 1% for each transformation level. Given the fact that the plant will be evacuating at 132kV, two levels of losses have been considered; 1.0% for the intermediate transformation at 33/11kV, and 0.6% (following the GTP of the transformer to be used on-site) for the second level of transformation at 132kV in line with standard design practices.