SlideShare una empresa de Scribd logo
1 de 38
Descargar para leer sin conexión
1
CONSTRUCTION & ERECTION PHASE PLAN FOR MW SCALE
WIND POWER PROJECT
300 MW WIND FARM PROJECT AT WESTERN REGION
Methodology – Execution of Wind Power Projects
2
Wind Resource Assessment
Site Feasibility Studies (SFS)
Technical Due Diligence (TDD)
Statutory Permits and Approvals
Erection &
Commissioning
Wind Resource Assessment
3
 WRA is the quantification of wind resources to compute parameters such as average wind speed, Wind energy density and
average annual energy production.
Figure: Stages of Wind Resource Assessment
*AEP=Annual Energy Production, CFD = Computational Fluid Dynamics
Stage I:
Prospecting
Stage II:
Wind
Measurement
Stage III:
Linear Wind
Flow Model
Based
Estimation of
AEP
Stage IV:
CFD Model
Based
Estimation of
AEP
Stage V:
Loss &
Uncertainty
Estimation
Bankable WRA
Pre-Feasibility & Prospecting
4
Mandatory during the pre
feasibility of project site
 Anecdotal evidences
 Wind speed observation from
wind deformation on objects
and tress
 Topology
Siting Consideration
1. Transmission Capability
 Substation Requirement
 Existing Infrastructure
 Compatibility
 Point of Use
Prospecting Process
 Climatological study
 Prospecting survey
 Rating & Ranking the sites
 Wind map & Upper Air Data
2. Wind Resource
 Desirable Wind Speed (>7 m/s)
 Long Term Average
 Wind Profile
3. Permitting
 Local/ State Authorities
Clearance
 Environmental Impact Study
 Avian Impact Study
4. Land Use and Terrain
 Agricultural Compatibility
 Habitat Preservation
 Road Access
 Terrain Complexity, Roughness
& Offshore
Erection & Commissioning (Civil)
5
 Location should be obstacles free and have large space
 Accessible for transportation of heavy machineries.
 Co-ordinate verification should be done at site.
Site Inspection
 Witnessing of soil testing and samples collection at various depth during
construction should be done.
 Scrutiny of soil test reports to be done to check soil bearing capacity to
rest the WTG foundation.
Soil Testing
Erection & Commissioning (Civil)
6
 Excavation is ensured within the provided bench mark & marked area.
 Ensure earth work is done to the exact dimensions mentioned in the
foundation drawing of the OEM.
 Ensure bottom of excavation is leveled and shall be free of loose
unconsolidated material
Excavation Pre-stressed Cement Concrete
 Ensure bottom of excavated surface lightly watered, thoroughly
rammed, compacted & levels should be ensured before and after PCC .
 Ensure PCC is laid as per the given specification & curing work for PCC
 Ensure materials used for PCC (Cement, Sand, Aggregate & Water)
comply with IS456 and other required standards.
Erection & Commissioning (Civil)
7
 Ensure TMT bars of grade Fe-500 conforming to IS: 1786 is used.
 Ensure test certificates from the manufacturers received and complies with
the relevant IS specification .
 Visual inspection on bars to be done.
 Ensure lapping of rods are ok.
 Ensure all steel reinforcement been accurately placed in position as shown in
the drawing tied with 2 strands of 18 gauge GI annealed steel wire.
 Ensure reinforcement is having cover as shown on the structural drawings.
 Ensure electrical conductivity of reinforcement is ensured with welding in the
indicated points in the relevant drawing.
Reinforcement
Quality Inspection Of Concrete Ingredients
8
 Ensure cement used are in sealed bag and compiles with Indian Standards.
 Cement bags shall be stacked as per Standards.
 It shall be stored in such a way as to allow the removal and use of cement in
chronological order of receipt, i.e. FIFO (First in First Out).
 Test certificates from the manufacturers should be obtained.
 Cement stored in plant should be used before 3 months’ time from tests conducted.
Cement
 Ensure test certificate from registered laboratory or Government colleges and the source of
coarse aggregate submitted for design mix is not changed during the concrete pour.
 Ensure coarse aggregate conforms to IS : 383
 Ensure the nominal maximum size as large as possible & within the limits specified in the
design mix.
 Conducting sieve test once every month to confirm the sand stocked in site
Coarse Aggregate
Quality Inspection Of Concrete Ingredients
9
Fine Aggregate Sieve Designation as per IS 383
 Ensure test certificate for sand from registered laboratory or
Government colleges available and reviewed.
 Ensure fine aggregate conform to IS: 383.
 Ensure fine aggregate stacked carefully on a clean hard dry surface .
 Ensure source of sand which has been submitted for design mix not
been changed during the concrete pour.
Fine Aggregate
Quality Inspection Of Concrete Ingredients
10
 Ensure availability of water test report for water from
registered laboratory or Government colleges and reviewed
to confirm water compiles as per IS 456.
 Ensure water used for mixing and curing is clean and free
from materials deleterious to concrete or steel.
Water
Admixture
 Ensure admixtures used comply with IS 9103.
 Ensure admixture used is not stored in direct sun light and
kept in sheds.
 Ensure admixtures used before 1 year or as per
manufacture specifications.
Verification Of Mix Design Report
11
 Ensure detailed design mix report is obtained.
 Ensure mix design report complies with IS10262.
 Ensure design mix report includes detailed specifications of ingredients
used.
 Ensure compressive strength values of 7th and 28th day is mentioned in
report.
Trial Mix Verification
 Ensure trail mix is made at site as per design ratio.
 Ensure trial mixes prepared using coarse aggregates, sand, water and
cement actually available at site.
 Ensure adequate number of cube samples collected during trial mix.
 Based on the trial mix cube reports results, The mix proportion of
concrete shall be followed during the execution of castings.
Mix Design Report
Site Observations
12
Concrete Pouring
Foundation CompletedSlump Test
Temperature Test Concrete Specimen Sampling
Post Concreting
13
De-shuttering
 Ensure shuttering is removed after 24hrs from the finishing time of concrete
 After de-shuttering, honeycombs in the concrete, if any, should be rectified
 Ensure curing is done as per Standards.
 Ensure curing is done using curing compound as per manufacture
specifications or by wet gunny bags.
Curing
Concrete Acceptance
14
 Ensure number of samples tested comply with Indian Standards or as per
OEM Standards.
 Ensure test results of samples compiles with Indian standards for 28th day &
OEM Specifications on intermediate date .
 Witnessing the compressive test conducted .
 Witnessing the Core test Or Non-Destructive Test.
Acceptance as per IS 456 Clause 16.1
Core Test
15
Back Filling & Levelling of Location
16
 Ensure backfilling is done as per specifications.
 Ensure sides of the foundation is cleared .
 Ensure backfilling is done in layers, thickness not exceeding 300mm.
 Each layer should be properly consolidated / watered and compacted.
 Minimum field dry density should be 1.8 g/cm3 for each layer.
 Witnessing stone pitching or PCC laying over foundation backfilling as per
OEM specification.
 Witnessing demarcation and boundary stones laying .
 Ensure proper drain facility to be done.
 Ensure location is clean and levelled.
Back Filling & Levelling of locations
17
 Number of Tangent, Cut point poles, Span Length, River
crossings, road crossings , Rail way crossings , Span
Length are being appropriately reviewed for the size of
the poles as per IE rules & the size of the conductor.
 Ensure proper design calculation is done in selecting the
conductors.
 Ensure Sag – Tension for all lines and sizes of poles used
are designed by taking proper calculation.
 Ensure Line poles are as per the IS Code no: 802 (Code of
practice for use of structural steel in overhead
transmission line towers)
33 kV Line Works
Erection & Commissioning (Electrical)
33 kV Line Works
Incoming Material Inspection
18
Incoming Material Inspection
19
Material & Documentation
 Visual inspection of materials during delivery.
 Verifying the test certificates for the materials received
and check its compliances.
 Ensure components certificates complies with the
following standards.
Pole
 RSJ pole : IS2062
 Pre-stressed Concrete poles : IS78-1978 & IS2905- 1966
 Tubular Pole should confirm to IS2713
Insulators
 Polymer Insulators : IEC61109
 Porcelain Insulators : IS731/71
Conductor
 Al59 : IS398 PT.4
 All ACSR : IS398 PT.2
Route Survey
 Ensure shortest route is chosen.
 Ensure minimum number of line crossings & road
crossings.
 Ensure all the line work and all the installations
comply with the IE rules .
Safe Clearances In Consideration For The Line Crossing As Per IE Rule 1956
Sl.
No
Nominal System
Voltage
11-66 KV
(m)
110-132 KV
(m)
220 KV
(m)
400 KV
(m)
800 KV
(m)
1 Low & Medium 2.44 3.05 4.58 5.49 7.94
2 11- 66kV 2.44 3.05 4.58 5.49 7.94
3 110-132kV 3.05 3.05 4.58 5.49 7.94
4 220 Kv 4.58 4.58 4.58 5.49 7.94
5 400 kV 5.49 5.49 5.49 5.49 7.94
6 800 kV 7.94 7.94 7.94 7.94 7.94
Incoming Material Inspection
20
Pole Marking
 Ensure marking of the pole pits are in proper alignment.
 Ensure cut point locations are marked after each 7 spans for other
conductors and 6 spans for panther conductor.
 Span length between maintained as per standards.
Pole Pit Excavation
 Ensure pole pit excavation depth is 1/6th of the pole height.
 Ensure size of the pit dimension is as per Specifications.
 Ensure excavation depth for stay pits are 4.5feet.
Incoming Material Inspection
21
Pole Selection & Erection
 Ensure pole length, pole size and pole shifting should be done
properly without any damages
 Proper concerting, sufficient support should be provided during
erection.
 Ensure PCC is to be done in the bottom of the excavated pit .
Pole Earthing, Coping & Identification
 Ensure earthing done to all poles and insulators as per standards &
earth resistance for poles are within 20 Ohms
 Pole coping & muffing should be done as per specifications.
 Ensure pole identification with proper standard like pole number,
feeder details , SS details mentioned.
Incoming Material Inspection
22
Stay Rods
 Ensure stay rod arrangements are as per standards and quality of
stay rods are ok.
 Ensure concrete for stay rods done as per specifications.
Channel Fixing
 Ensure stay provided at each cut point, angle points.
 Ensure fabrication channel fixed with proper clamps.
 Ensure all the hardware's and fasteners are provided and tighten properly.
Incoming Material Inspection
23
Insulator Fixing
 Visual inspection done before insulator is fixed to observe any damages found
 Ensure insulators are cleaned properly.
 Ensure insulators installed as per standard procedures.
Stringing
 Ensure conductors used complies with Indian standards (IS 398)
 Ensure quality of the components are as per standard & no damages found.
 Ensure during stringing the conductor unrolled from the cable drum and laid
as per procedures.
 Ensure conductors tightened properly.
 Ensure the sag is not more than 450mm in mid span area.
DP Yard Works
24
Double Pole Erection Activity
Boundary Works
DP Yard Works
25
Yard Equipment Erection
Earth Resistance Check
Earthing Check
Transformer & Other Accessories Erection
EHV Line Tower Works
26
EHV Tower Foundation & Member Erection
Pooling SS Works
27
Activities During Construction Of Pooling Substation
 Land Purchasing.
 Soil Resistivity Test.
 Land or Zero level, FGL(Filled Ground Level) Marking By surveyor.
 Structure & Transformer Foundations
 Compound wall.
 Earth mat-Grid
 Structures & Transformers Erection
 Equipment, Control & Relay Panel Erection,
 Equipment, Control & Relay Panel Testing.
 Battery Erection, AC,DCDB, PLCC, SAS Panel erection.
 CIG Inspection for charging clearance.
 Commissioning for Line & Transformer bay.
 Control Room Constructions
 Cable Trench
Pooling SS Works
28
Location Marking, Excavation & PCC
Steel Binding & Raft Casting Column Casting & Curing
Earth Mat Excavation for Laying Rod, Earth Mat
Compacting & Core Test for Moisture Value
Pooling SS Works
29
Equipment Erection – CT/PT & Transformer
Transformer Bushing Test Before Erection Cable Tray Fixing And Tack Welding
Main Bus Stringing & Cable Tray Supporting Angle Welding
Pooling SS Works
30
Panel Erection At Control Room & Transformer Oil Filtration
Power Evacuation Infrastructure
Battery Erection & Control Room Building
WTG Incoming Material Inspection/Verification
Damage Rectification At Site
31
Nacelle FRP Damaged Nacelle FRP Rectification Nacelle FRP after Rectification
Tower Preparation
32
 Ensure proper cleaning of tower on both inside & outside.
 Ensure sufficient cranes used for loading and unloading of segments from trailers during erection.
Tower Installation
33
 Ensure all the erection activities are in progress according to OEM’s procedure
 Ensure the presence of mechanical engineer of OEM .
 Ensure proper orientation of Tower door of the T1 Tower Shell.
 Ensure the safe torquing of bolts for every Tower to Tower Shell joints.
Nacelle Erection & Rotor Blade Assembly
34
Nacelle Erection Rotor Blade Assembly
Post Erection & Monitoring
35
 Proper cable terminations & final torqueing
 Proper routing and termination of control cables
 Functional checks and DG commissioning should be ensured
 Blade calibration for both pitching in and pitching out
 Mechanical equipment's and grid parameters in the lCS of WTG will be
ensured
 Proper monitoring of WTG for few days after post commissioning
The following points will be ensured post erection & monitoring:
Testing & Quality
36
 Ensuring the quality standards of all project materials according to the applicable
standards before dispatch clearances.
 Witnessing the factory tests/type tests/functional tests of all project materials at
their manufacturing facility to ascertain the materials quality.
 HDG thickness should be checked for all hot dipped materials at the time of
production as well as pre-installation time at site.
 Site team shall make ensure the quality of all incoming materials as per the
procedure/QAP before usage.
 Testing & Quality inspection all project materials should be ensured during &
after installation time.
 Tightness of all machine parts like tower, nacelle ,hub and rotor should be
checked twice by calibrated torque wrenches/other tightening tools & tackles.
Temperature Test
WTG materials for inspection
Plant Commissioning
37
 Pre-commissioning checks should be carried out as per approved
procedures.
 Site team should ratify the quality of all project activities before
commissioning.
 Project manager & site team should concentrate on the safety practices
and standards during works execution.
 Plant handover to O&M team for lifetime of the project shall be done
along with punch points and document handover.
Gensol is one of the leading consultants and system integrators for Solar Power Plants. We boast of a portfolio of over 6000 MW of Solar Photovoltaic Plants. Gensol is also a channel
partner to Ministry of New & Renewable Energy and installs kW scale Solar Rooftop systems on a turnkey basis with more than 42 MW of cumulative installations across the country.
The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavor to provide
accurate and timely information, there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one
should act on such information without appropriate professional advice after a thorough examination of the particular situation.
Email: solar@gensol.in | Web: www.gensol.in | Phone: +91 79 40068235 | Twitter: gensol_tweets
Gensol Engineering Ltd | Gensol Consultants Pvt Ltd | Solarig Gensol Utilities Pvt Ltd
Corporate Office
A2, 12th Floor Palladium, Opp. to Vodafone House , Corporate Road, Prahladnagar, Ahmedabad, Gujarat. India - 380015

Más contenido relacionado

La actualidad más candente

Solar Project Management
Solar Project ManagementSolar Project Management
Solar Project Managementfirstgreen
 
Developing Solar Projects
Developing Solar ProjectsDeveloping Solar Projects
Developing Solar Projectsalejolop
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
Electrical machines for renewable energy converters keynote
Electrical machines for renewable energy converters keynoteElectrical machines for renewable energy converters keynote
Electrical machines for renewable energy converters keynoteozikeysan
 
1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and TrackingATUL RAJ
 
Construction site supervision aalecture one.
Construction site supervision aalecture one.Construction site supervision aalecture one.
Construction site supervision aalecture one.Gebeyehu Worku
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)Sunrator Technologies LLP
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignLeonardo ENERGY
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Gensol Engineering Limited
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Quality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildingsQuality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildingsmbphenix
 
Hydro Power Project Management
Hydro Power Project ManagementHydro Power Project Management
Hydro Power Project ManagementJPSMADA
 
final CEA ppt 230221.pptx
final CEA ppt 230221.pptxfinal CEA ppt 230221.pptx
final CEA ppt 230221.pptxankanwal1
 
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Gensol Engineering Limited
 

La actualidad más candente (20)

Solar Project Management
Solar Project ManagementSolar Project Management
Solar Project Management
 
Quality management
Quality managementQuality management
Quality management
 
Developing Solar Projects
Developing Solar ProjectsDeveloping Solar Projects
Developing Solar Projects
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
Electrical machines for renewable energy converters keynote
Electrical machines for renewable energy converters keynoteElectrical machines for renewable energy converters keynote
Electrical machines for renewable energy converters keynote
 
1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking
 
Construction site supervision aalecture one.
Construction site supervision aalecture one.Construction site supervision aalecture one.
Construction site supervision aalecture one.
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
107 quality control
107 quality control107 quality control
107 quality control
 
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
 
Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
 
Solar shading and its effects
Solar shading and its effectsSolar shading and its effects
Solar shading and its effects
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Quality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildingsQuality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildings
 
Hydro Power Project Management
Hydro Power Project ManagementHydro Power Project Management
Hydro Power Project Management
 
final CEA ppt 230221.pptx
final CEA ppt 230221.pptxfinal CEA ppt 230221.pptx
final CEA ppt 230221.pptx
 
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
 
Energy audit
Energy auditEnergy audit
Energy audit
 

Similar a Phases of Construction & Erection for Wind Power Project_03 09 2019

6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concretethamand7
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Construction practices and quality control
Construction practices and quality controlConstruction practices and quality control
Construction practices and quality controlSIBENDU SURAJEET JENA
 
61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-studyhomeworkping4
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
QA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorQA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorAsad Ahsan
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.pptMuhammed Sulfeek
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfParmeshworVetwal1
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)Yousef Riad
 
PPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptxPPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptxgthpmc
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 
Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...
Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...
Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...IRJET Journal
 
Pilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesPilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesLaura Anderson
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestationYousef Riad
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 

Similar a Phases of Construction & Erection for Wind Power Project_03 09 2019 (20)

Husam CV updated (1)
Husam CV updated (1)Husam CV updated (1)
Husam CV updated (1)
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
Construction practices and quality control
Construction practices and quality controlConstruction practices and quality control
Construction practices and quality control
 
61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-study
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
QA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding InspectorQA/QC Mechanical and Welding Inspector
QA/QC Mechanical and Welding Inspector
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
 
03 Mohamed_fathi
03 Mohamed_fathi03 Mohamed_fathi
03 Mohamed_fathi
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)
 
PPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptxPPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptx
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...
Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...
Material Characterization of Buried GFRP Pipeline Failed during Hydrostatic T...
 
Pilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesPilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project Challenges
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestation
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Mohammed Asif Hassan-cv
Mohammed Asif Hassan-cvMohammed Asif Hassan-cv
Mohammed Asif Hassan-cv
 
MANAGER.QAQC(MECHANICAL)
MANAGER.QAQC(MECHANICAL)MANAGER.QAQC(MECHANICAL)
MANAGER.QAQC(MECHANICAL)
 

Más de Gensol Engineering Limited

Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Gensol Engineering Limited
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Gensol Engineering Limited
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Gensol Engineering Limited
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Gensol Engineering Limited
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019Gensol Engineering Limited
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Gensol Engineering Limited
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Gensol Engineering Limited
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Gensol Engineering Limited
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Gensol Engineering Limited
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Gensol Engineering Limited
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Gensol Engineering Limited
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol Engineering Limited
 

Más de Gensol Engineering Limited (20)

Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019
 
List of successful bidders 11.03.2019
List of successful bidders 11.03.2019List of successful bidders 11.03.2019
List of successful bidders 11.03.2019
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Module Price Trend Analysis
Module Price Trend AnalysisModule Price Trend Analysis
Module Price Trend Analysis
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
 
Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18
 
Floating Solar PV - An Introduction
Floating Solar PV -  An Introduction Floating Solar PV -  An Introduction
Floating Solar PV - An Introduction
 

Último

MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...Suhani Kapoor
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 

Último (20)

MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 

Phases of Construction & Erection for Wind Power Project_03 09 2019

  • 1. 1 CONSTRUCTION & ERECTION PHASE PLAN FOR MW SCALE WIND POWER PROJECT 300 MW WIND FARM PROJECT AT WESTERN REGION
  • 2. Methodology – Execution of Wind Power Projects 2 Wind Resource Assessment Site Feasibility Studies (SFS) Technical Due Diligence (TDD) Statutory Permits and Approvals Erection & Commissioning
  • 3. Wind Resource Assessment 3  WRA is the quantification of wind resources to compute parameters such as average wind speed, Wind energy density and average annual energy production. Figure: Stages of Wind Resource Assessment *AEP=Annual Energy Production, CFD = Computational Fluid Dynamics Stage I: Prospecting Stage II: Wind Measurement Stage III: Linear Wind Flow Model Based Estimation of AEP Stage IV: CFD Model Based Estimation of AEP Stage V: Loss & Uncertainty Estimation Bankable WRA
  • 4. Pre-Feasibility & Prospecting 4 Mandatory during the pre feasibility of project site  Anecdotal evidences  Wind speed observation from wind deformation on objects and tress  Topology Siting Consideration 1. Transmission Capability  Substation Requirement  Existing Infrastructure  Compatibility  Point of Use Prospecting Process  Climatological study  Prospecting survey  Rating & Ranking the sites  Wind map & Upper Air Data 2. Wind Resource  Desirable Wind Speed (>7 m/s)  Long Term Average  Wind Profile 3. Permitting  Local/ State Authorities Clearance  Environmental Impact Study  Avian Impact Study 4. Land Use and Terrain  Agricultural Compatibility  Habitat Preservation  Road Access  Terrain Complexity, Roughness & Offshore
  • 5. Erection & Commissioning (Civil) 5  Location should be obstacles free and have large space  Accessible for transportation of heavy machineries.  Co-ordinate verification should be done at site. Site Inspection  Witnessing of soil testing and samples collection at various depth during construction should be done.  Scrutiny of soil test reports to be done to check soil bearing capacity to rest the WTG foundation. Soil Testing
  • 6. Erection & Commissioning (Civil) 6  Excavation is ensured within the provided bench mark & marked area.  Ensure earth work is done to the exact dimensions mentioned in the foundation drawing of the OEM.  Ensure bottom of excavation is leveled and shall be free of loose unconsolidated material Excavation Pre-stressed Cement Concrete  Ensure bottom of excavated surface lightly watered, thoroughly rammed, compacted & levels should be ensured before and after PCC .  Ensure PCC is laid as per the given specification & curing work for PCC  Ensure materials used for PCC (Cement, Sand, Aggregate & Water) comply with IS456 and other required standards.
  • 7. Erection & Commissioning (Civil) 7  Ensure TMT bars of grade Fe-500 conforming to IS: 1786 is used.  Ensure test certificates from the manufacturers received and complies with the relevant IS specification .  Visual inspection on bars to be done.  Ensure lapping of rods are ok.  Ensure all steel reinforcement been accurately placed in position as shown in the drawing tied with 2 strands of 18 gauge GI annealed steel wire.  Ensure reinforcement is having cover as shown on the structural drawings.  Ensure electrical conductivity of reinforcement is ensured with welding in the indicated points in the relevant drawing. Reinforcement
  • 8. Quality Inspection Of Concrete Ingredients 8  Ensure cement used are in sealed bag and compiles with Indian Standards.  Cement bags shall be stacked as per Standards.  It shall be stored in such a way as to allow the removal and use of cement in chronological order of receipt, i.e. FIFO (First in First Out).  Test certificates from the manufacturers should be obtained.  Cement stored in plant should be used before 3 months’ time from tests conducted. Cement  Ensure test certificate from registered laboratory or Government colleges and the source of coarse aggregate submitted for design mix is not changed during the concrete pour.  Ensure coarse aggregate conforms to IS : 383  Ensure the nominal maximum size as large as possible & within the limits specified in the design mix.  Conducting sieve test once every month to confirm the sand stocked in site Coarse Aggregate
  • 9. Quality Inspection Of Concrete Ingredients 9 Fine Aggregate Sieve Designation as per IS 383  Ensure test certificate for sand from registered laboratory or Government colleges available and reviewed.  Ensure fine aggregate conform to IS: 383.  Ensure fine aggregate stacked carefully on a clean hard dry surface .  Ensure source of sand which has been submitted for design mix not been changed during the concrete pour. Fine Aggregate
  • 10. Quality Inspection Of Concrete Ingredients 10  Ensure availability of water test report for water from registered laboratory or Government colleges and reviewed to confirm water compiles as per IS 456.  Ensure water used for mixing and curing is clean and free from materials deleterious to concrete or steel. Water Admixture  Ensure admixtures used comply with IS 9103.  Ensure admixture used is not stored in direct sun light and kept in sheds.  Ensure admixtures used before 1 year or as per manufacture specifications.
  • 11. Verification Of Mix Design Report 11  Ensure detailed design mix report is obtained.  Ensure mix design report complies with IS10262.  Ensure design mix report includes detailed specifications of ingredients used.  Ensure compressive strength values of 7th and 28th day is mentioned in report. Trial Mix Verification  Ensure trail mix is made at site as per design ratio.  Ensure trial mixes prepared using coarse aggregates, sand, water and cement actually available at site.  Ensure adequate number of cube samples collected during trial mix.  Based on the trial mix cube reports results, The mix proportion of concrete shall be followed during the execution of castings. Mix Design Report
  • 12. Site Observations 12 Concrete Pouring Foundation CompletedSlump Test Temperature Test Concrete Specimen Sampling
  • 13. Post Concreting 13 De-shuttering  Ensure shuttering is removed after 24hrs from the finishing time of concrete  After de-shuttering, honeycombs in the concrete, if any, should be rectified  Ensure curing is done as per Standards.  Ensure curing is done using curing compound as per manufacture specifications or by wet gunny bags. Curing
  • 14. Concrete Acceptance 14  Ensure number of samples tested comply with Indian Standards or as per OEM Standards.  Ensure test results of samples compiles with Indian standards for 28th day & OEM Specifications on intermediate date .  Witnessing the compressive test conducted .  Witnessing the Core test Or Non-Destructive Test. Acceptance as per IS 456 Clause 16.1
  • 16. Back Filling & Levelling of Location 16  Ensure backfilling is done as per specifications.  Ensure sides of the foundation is cleared .  Ensure backfilling is done in layers, thickness not exceeding 300mm.  Each layer should be properly consolidated / watered and compacted.  Minimum field dry density should be 1.8 g/cm3 for each layer.  Witnessing stone pitching or PCC laying over foundation backfilling as per OEM specification.  Witnessing demarcation and boundary stones laying .  Ensure proper drain facility to be done.  Ensure location is clean and levelled. Back Filling & Levelling of locations
  • 17. 17  Number of Tangent, Cut point poles, Span Length, River crossings, road crossings , Rail way crossings , Span Length are being appropriately reviewed for the size of the poles as per IE rules & the size of the conductor.  Ensure proper design calculation is done in selecting the conductors.  Ensure Sag – Tension for all lines and sizes of poles used are designed by taking proper calculation.  Ensure Line poles are as per the IS Code no: 802 (Code of practice for use of structural steel in overhead transmission line towers) 33 kV Line Works Erection & Commissioning (Electrical) 33 kV Line Works
  • 19. Incoming Material Inspection 19 Material & Documentation  Visual inspection of materials during delivery.  Verifying the test certificates for the materials received and check its compliances.  Ensure components certificates complies with the following standards. Pole  RSJ pole : IS2062  Pre-stressed Concrete poles : IS78-1978 & IS2905- 1966  Tubular Pole should confirm to IS2713 Insulators  Polymer Insulators : IEC61109  Porcelain Insulators : IS731/71 Conductor  Al59 : IS398 PT.4  All ACSR : IS398 PT.2 Route Survey  Ensure shortest route is chosen.  Ensure minimum number of line crossings & road crossings.  Ensure all the line work and all the installations comply with the IE rules . Safe Clearances In Consideration For The Line Crossing As Per IE Rule 1956 Sl. No Nominal System Voltage 11-66 KV (m) 110-132 KV (m) 220 KV (m) 400 KV (m) 800 KV (m) 1 Low & Medium 2.44 3.05 4.58 5.49 7.94 2 11- 66kV 2.44 3.05 4.58 5.49 7.94 3 110-132kV 3.05 3.05 4.58 5.49 7.94 4 220 Kv 4.58 4.58 4.58 5.49 7.94 5 400 kV 5.49 5.49 5.49 5.49 7.94 6 800 kV 7.94 7.94 7.94 7.94 7.94
  • 20. Incoming Material Inspection 20 Pole Marking  Ensure marking of the pole pits are in proper alignment.  Ensure cut point locations are marked after each 7 spans for other conductors and 6 spans for panther conductor.  Span length between maintained as per standards. Pole Pit Excavation  Ensure pole pit excavation depth is 1/6th of the pole height.  Ensure size of the pit dimension is as per Specifications.  Ensure excavation depth for stay pits are 4.5feet.
  • 21. Incoming Material Inspection 21 Pole Selection & Erection  Ensure pole length, pole size and pole shifting should be done properly without any damages  Proper concerting, sufficient support should be provided during erection.  Ensure PCC is to be done in the bottom of the excavated pit . Pole Earthing, Coping & Identification  Ensure earthing done to all poles and insulators as per standards & earth resistance for poles are within 20 Ohms  Pole coping & muffing should be done as per specifications.  Ensure pole identification with proper standard like pole number, feeder details , SS details mentioned.
  • 22. Incoming Material Inspection 22 Stay Rods  Ensure stay rod arrangements are as per standards and quality of stay rods are ok.  Ensure concrete for stay rods done as per specifications. Channel Fixing  Ensure stay provided at each cut point, angle points.  Ensure fabrication channel fixed with proper clamps.  Ensure all the hardware's and fasteners are provided and tighten properly.
  • 23. Incoming Material Inspection 23 Insulator Fixing  Visual inspection done before insulator is fixed to observe any damages found  Ensure insulators are cleaned properly.  Ensure insulators installed as per standard procedures. Stringing  Ensure conductors used complies with Indian standards (IS 398)  Ensure quality of the components are as per standard & no damages found.  Ensure during stringing the conductor unrolled from the cable drum and laid as per procedures.  Ensure conductors tightened properly.  Ensure the sag is not more than 450mm in mid span area.
  • 24. DP Yard Works 24 Double Pole Erection Activity Boundary Works
  • 25. DP Yard Works 25 Yard Equipment Erection Earth Resistance Check Earthing Check Transformer & Other Accessories Erection
  • 26. EHV Line Tower Works 26 EHV Tower Foundation & Member Erection
  • 27. Pooling SS Works 27 Activities During Construction Of Pooling Substation  Land Purchasing.  Soil Resistivity Test.  Land or Zero level, FGL(Filled Ground Level) Marking By surveyor.  Structure & Transformer Foundations  Compound wall.  Earth mat-Grid  Structures & Transformers Erection  Equipment, Control & Relay Panel Erection,  Equipment, Control & Relay Panel Testing.  Battery Erection, AC,DCDB, PLCC, SAS Panel erection.  CIG Inspection for charging clearance.  Commissioning for Line & Transformer bay.  Control Room Constructions  Cable Trench
  • 28. Pooling SS Works 28 Location Marking, Excavation & PCC Steel Binding & Raft Casting Column Casting & Curing Earth Mat Excavation for Laying Rod, Earth Mat Compacting & Core Test for Moisture Value
  • 29. Pooling SS Works 29 Equipment Erection – CT/PT & Transformer Transformer Bushing Test Before Erection Cable Tray Fixing And Tack Welding Main Bus Stringing & Cable Tray Supporting Angle Welding
  • 30. Pooling SS Works 30 Panel Erection At Control Room & Transformer Oil Filtration Power Evacuation Infrastructure Battery Erection & Control Room Building WTG Incoming Material Inspection/Verification
  • 31. Damage Rectification At Site 31 Nacelle FRP Damaged Nacelle FRP Rectification Nacelle FRP after Rectification
  • 32. Tower Preparation 32  Ensure proper cleaning of tower on both inside & outside.  Ensure sufficient cranes used for loading and unloading of segments from trailers during erection.
  • 33. Tower Installation 33  Ensure all the erection activities are in progress according to OEM’s procedure  Ensure the presence of mechanical engineer of OEM .  Ensure proper orientation of Tower door of the T1 Tower Shell.  Ensure the safe torquing of bolts for every Tower to Tower Shell joints.
  • 34. Nacelle Erection & Rotor Blade Assembly 34 Nacelle Erection Rotor Blade Assembly
  • 35. Post Erection & Monitoring 35  Proper cable terminations & final torqueing  Proper routing and termination of control cables  Functional checks and DG commissioning should be ensured  Blade calibration for both pitching in and pitching out  Mechanical equipment's and grid parameters in the lCS of WTG will be ensured  Proper monitoring of WTG for few days after post commissioning The following points will be ensured post erection & monitoring:
  • 36. Testing & Quality 36  Ensuring the quality standards of all project materials according to the applicable standards before dispatch clearances.  Witnessing the factory tests/type tests/functional tests of all project materials at their manufacturing facility to ascertain the materials quality.  HDG thickness should be checked for all hot dipped materials at the time of production as well as pre-installation time at site.  Site team shall make ensure the quality of all incoming materials as per the procedure/QAP before usage.  Testing & Quality inspection all project materials should be ensured during & after installation time.  Tightness of all machine parts like tower, nacelle ,hub and rotor should be checked twice by calibrated torque wrenches/other tightening tools & tackles. Temperature Test WTG materials for inspection
  • 37. Plant Commissioning 37  Pre-commissioning checks should be carried out as per approved procedures.  Site team should ratify the quality of all project activities before commissioning.  Project manager & site team should concentrate on the safety practices and standards during works execution.  Plant handover to O&M team for lifetime of the project shall be done along with punch points and document handover.
  • 38. Gensol is one of the leading consultants and system integrators for Solar Power Plants. We boast of a portfolio of over 6000 MW of Solar Photovoltaic Plants. Gensol is also a channel partner to Ministry of New & Renewable Energy and installs kW scale Solar Rooftop systems on a turnkey basis with more than 42 MW of cumulative installations across the country. The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavor to provide accurate and timely information, there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one should act on such information without appropriate professional advice after a thorough examination of the particular situation. Email: solar@gensol.in | Web: www.gensol.in | Phone: +91 79 40068235 | Twitter: gensol_tweets Gensol Engineering Ltd | Gensol Consultants Pvt Ltd | Solarig Gensol Utilities Pvt Ltd Corporate Office A2, 12th Floor Palladium, Opp. to Vodafone House , Corporate Road, Prahladnagar, Ahmedabad, Gujarat. India - 380015