SlideShare una empresa de Scribd logo
1 de 30
UNIT – IV REPLACEMENT AND
MAINTENANCE ANALYSIS
BY
Dr. A. Asha
Professor/Mechanical Engineering
Kamaraj College of Engineering & Technology
Virudhunagar
December 2016
MAINTENANCE
• Definition : Maintenance is defined
as the action taken by the user to
maintain an existing facility in
operating condition.
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/
Dr. A. Asha 2
OBJECTIVES OF MAINTENANCE
• To achieve minimum break down
• To keep a plant in good working condition at
the lowest possible cost.
• To keep machines at their optimum cost
without any hindrance.
• To ensure the availability of machineries,
buildings and services.
• To achieve efficient functioning of machines.
• To reduce operation and maintenance cost.
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha
3
TYPES OF MAINTENANCE
• Corrective (or) Break down
Maintenance
• Scheduled Maintenance
• Preventive Maintenance
• Predictive Maintenance
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 4
CORRECTIVE (OR) BREAK DOWN
MAINTENANCE
• This implies that repairs are made after the
equipment is out of order and it can not perform
its normal functions any longer.
• Production Dept Maintenance Dept to
rectify the fault.
• Maintenance Dept checks into the difficulty
and makes the necessary repairs
• After removing the fault the maintenance
engineers do not attend the equipment until
another failure occurs
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 5
CAUSES FOR EQUIPMENT
BREAK DOWN
• Failure to replace the worn out parts.
• Lack of lubrication
• Neglected cooling system.
• Not attending minor faults.
• External factors such as low or high
voltage, wrong fuel
• Not attending unusual sounds,
vibrations etc.
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 6
SCHEDULED MAINTENANCE
• Scheduled maintenance is concerned
with the time schedule to avoid
breakdown.
• This maintenance includes inspection,
repair, overhaul etc which if neglected
can result in serious issues.
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 7
PREVENTIVE MAINTENANCE
• It is defined as an action performed in an
attempt to keep the machine in a specified
operating condition by means of systematic
inspection, detection and prevention of
failures.
• It works on the principle of “Prevention is
better than cure”
• It locates weak spots in all equipments
provides them with regular inspection and
minor repairs and thereby reduces the danger
of unanticipated breakdown
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 8
OBJECTIVES OF PREVENTIVE MAINTENANCE
• To keep the equipment always available.
• To maintain the value of the equipment by
periodic inspection, repairs and overhauls.
• To maintain optimum production ᶯ of the
equipment.
• To ensure safety of the workers
• To reduce the work content of maintenance
jobs.
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 9
Preparation for maintenance
Repair over
Preventivemaintenance
FF==Fault Detection
LoLLocalisation and isolation of
fault
Disassembly
Remove fault
item
Reinstallation and Reassembly
Repair
Ffinal adjustments
CChecking
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 10
PROCEDURE OF PREVENTIVE
MAINTENANCE
• Inspection or checkups
• Lubrication
• Planning and scheduling
• Record keeping and analysis
• Training of maintenance personnel
• Storage of spare parts
• Control and evaluation of preventive
maintenance.
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 11
ADVANTAGES OF PREVENTIVE
MAINTENANCE
• Reduction in production down time.
• Less overtime pay for maintenance
personnel
• Lesser expenditure on repairs
• Fewer repetitive repairs
• Better product quality and fewer
rejections.
• Lesser number of standby equipments
are needed
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 12
PREDICTIVE MAINTENANCE
• Newer maintenance technique
• It uses human sense organs or some
sensitive instruments such as audio gauges,
vibration analysers, amplitude meters etc to
predict troubles before the equipment fails.
• Equipment conditions are monitored
periodically and thus enables the
maintenance men to take timely action such
as repairs and overhauls.
• Extends the service life of an equipment
without the fear of failure
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 13
REPLACEMENT
• Replacement can be defined as the
decision problems involving the
replacement of existing obsolete or
worn out assets
• Causes of replacement :
1. Deterioration
2. Obsolescence
3. Inadequacy
4. Working conditions
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 14
TYPES OF REPLACEMENT
PROBLEM
• Replacement of assets with deteriorate
with time
(a) Economic Life of an asset
(b) Replacement of an existing
asset with a new asset
• Simple probabilistic model for assets
which fail completely.(replacement due
to sudden failure)
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 15
PROBLEM
• The following table gives the operation
and maintenance cost and salvage
value at the end of the every year of a
machine whose purchase price is Rs
20,000. Find the economic service life
of the machine assuming interest rate
i = 15%
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 16
PROBLEM
END OF
YEAR
OPERATING
COST (RS)
MAINTENANCE
COST (RS)
SALVAGE
VALUE (RS)
1 3000 300 9000
2 4000 400 8000
3 5000 500 7000
4 6000 600 6000
5 7000 700 5000
6 8000 800 4000
7 9000 900 3000
8 10000 1000 2000
9 11000 1100 1000
10 12000 1200 0
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 17
SOLUTION
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 18
PROBLEM
• A firm is considering replacement of an
machine whose cost price is Rs
1,20,000 and the scrap value is Rs
10,000 at the end of the first year and
declines each year by rs 1000 from the
previous years scrap value. The
operating cost is as follows
Year 1 2 3 4 5 6 7 8
Operating cost 2000 5000 8000 12000 18000 25000 32000 40000
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 19
SOLUTION
End of
year
Operating
cost
Cumulative
operating
cost
Scrap
value
Total cost
FC + COC-S
Average
cost =
TC/n
1 2000 2000 10000 112000 112000
2 5000 7000 9000 118000 59000
3 8000 15000 8000 127000 42333.33
4 12000 27000 7000 140000 35000
5 18000 45000 6000 159000 31800
6 25000 70000 5000 185000 30833.33
7 32000 102000 4000 218000 31142.85
8 40000 142000 3000 259000 32375
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 20
REPALCEMENT OF EXISTING ASSET
WITH NEW ASSET
• Annual equivalent cost of existing
asset and the new asset is calculated.
• The alternative which gives the least
value is considered as the best
alternative.
• The formula to calculate the annual
equivalent cost is
AE = (P-F)(A/P , i, n) + F x i +A
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 21
PROBLEM
Two years ago a machine was purchased at
a cost of Rs 2,00,000 to be useful for eight
years. Its salvage value at the end of the life
is Rs 25,000. The annual maintenance cost
is Rs 25,000. The market value of the
present machine is Rs 1,20,000. Now a new
machine to cater to the need of the present
machine is Rs 1,50,000 to be useful for six
years. The annual maintenance cost is Rs
14,000. The salvage value of the new
machine is Rs 20,000. Using the rate of 12%
find whether it is worth replacing the present
machine with the new machine
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 22
SIMPLE PROBABILISTIC MODEL FOR
ASSETS WHICH FAIL COMPLETELY
• A system usually consists of a large no
of low cost items that are increasing
liable to failure with age.
• The cost of failure is > the cost of item
itself.
• Two types of replacement policies are
considered
a. Individual replacement policy
b. Group replacement policy
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 23
SIMPLE PROBABILISTIC MODEL FOR
ASSETS WHICH FAIL COMPLETELY
• For a given problem the individual &
group replacement policies are
evaluated and the most economical
policy is selected for implementation.
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 24
PROBLEM
• The failure rates of transistors in a
computer are summarized in the
following table. The cost of replacing
an individual failed transistor is Rs 8/-.
If all the transistors are replaced
simultaneously it would cost Rs 4 per
transistor. Find the optimum
replacement policy
End of
week
1 2 3 4 5 6 7
Probability
of failure
0.09 0.17 0.27 0.50 0.65 0.90 1.00
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 25
SOLUTION
• Let Ni = The number of transistors
replaced at the end of the ith week.
• N0 = Number of transistors replaced at
the end of the week 0.
N1 = N0 x P1 = 100 x 0.09 = 9
N2 = N0 x P2 + N1 x P1
= 100 x 0.08 + 9 x 0.09 = 8.81
N3 = N0 x P3 + N1 x P2 + N2 x P1
= 100 x 0.1 + 9 x 0.08 + 8.81 x 0.09
= 11.51
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 26
SOLUTION
N4 = N0 x P4 + N1 x P3 + N2 x P2 + N3 x P1
= 100 x 0.23 + 9 x 0.1 + 8.81 x 0.08 + 11.51 x 0.09
= 25.63
N5 = N0 x P5 + N1 x P4 + N2 x P3+ N3 x P2 + N4 x P1
= 100 x 0.15 + 9 x 0.23 + 8.81 x 0.1 + 11.51 x 0.23 +
25.63 x 0.09
= 21.17
N6 = N0 x P6 + N1 x P5 + N2 x P4+ N3 x P3 + N4 x P2 + N5 x P1
= 100 x 0.25 + 9 x 0.15 + 8.81 x 0.23 + 11.51 x 0.1 + 25.63 x
0.08 + 21.17 x 0.09
= 33.47
N7 = N0 x P7 + N1 x P6 + N2 x P5+ N3 x P4 + N4 x P3 + N5 x P2 +
N6 x P1
= 100 x 0.1 + 9 x 0.25 + 8.81 x 0.15 + 11.51 x 0.23 + 25.63 x
0.1 + 21.17 x 0.08 + 33.47 x 0.09
= 23.47
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 27
SOLUTION
• Expected life of the transistor =
= 1 x 0.09 + 2x 0.08 + 3 x0.1+ 4 x 0.23 + 5 x 0.15 + 6x
0.25 + 7x 0.1
= 4.42 weeks
• Average number of failure per week = 100/4.42
= 23
• Cost of individual replacement
= Number of failures/week x Individual replacement cost/transistor
= 23 x 8
= Rs 184
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 28
SOLUTION
• GROUP REPLACEMENT COST
End
of
Week
Group
replacement
cost
Cost of individual replacement Total
Cost
(Rs)
Average
Cost
(Rs)
1 4 x 100 = 400 9 x 8 = 72 472 472
2 400 (9 + 8.81) x 8 = 142.48 542.48 271.24
3 400 (9 + 8.81+11.51) x 8 = 234.56 634.56 211.52
4 400 (9 + 8.81+11.51+25.63) x 8 = 439.60 839.60 209.90
5 400 (9 + 8.81+11.51+25.63+21.17) x 8
= 608.96
1008.96 201.79
6 400 (9 + 8.81+11.51+25.63+21.17+
33.47) x 8 = 876.72
1276.72 212.78
7 400 (9 + 8.81+11.51+25.63+21.17+
33.47+ 23.47) x 8 = 1064.48
1464.48 209.21
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 29
SOLUTION
• Individual replacement cost /week = Rs. 184/-
• Group replacement cost /week = Rs. 201.79/-
Since the individual cost/week is < group
replacement cost the individual replacement
cost is adopted
KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A.
Asha 30

Más contenido relacionado

La actualidad más candente

Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenancePankaj Singh
 
Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Dhanesh S
 
Replacement and Maintenance Analysis
Replacement and Maintenance AnalysisReplacement and Maintenance Analysis
Replacement and Maintenance AnalysisPrabu U
 
System reliability and types of systems in machine design
System reliability and types of systems in machine designSystem reliability and types of systems in machine design
System reliability and types of systems in machine designVikasSuroshe
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive MaintenanceMahendra K SHUKLA
 
UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.pptAsha A
 
09 shop floor control
09 shop floor control09 shop floor control
09 shop floor controlArif Rahman
 
Life cycle costing (sqm)
Life cycle costing (sqm)Life cycle costing (sqm)
Life cycle costing (sqm)Adil Shaikh
 
Tpm introduction-ame
Tpm introduction-ameTpm introduction-ame
Tpm introduction-amefarades
 
Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy Fhatiha Atika
 
Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...
Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...
Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...Flevy.com Best Practices
 
COMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEP
COMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEPCOMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEP
COMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEPMANI KRISHNA
 

La actualidad más candente (20)

Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenance
 
Tpm
TpmTpm
Tpm
 
Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Maintenance module1 ppt number 3
Maintenance module1 ppt number 3
 
Replacement and Maintenance Analysis
Replacement and Maintenance AnalysisReplacement and Maintenance Analysis
Replacement and Maintenance Analysis
 
Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenance
 
TPM: Planned Maintenance
TPM: Planned MaintenanceTPM: Planned Maintenance
TPM: Planned Maintenance
 
System reliability and types of systems in machine design
System reliability and types of systems in machine designSystem reliability and types of systems in machine design
System reliability and types of systems in machine design
 
The MTBF - Day1_v2
The MTBF - Day1_v2The MTBF - Day1_v2
The MTBF - Day1_v2
 
Automotive mechatronics
Automotive mechatronicsAutomotive mechatronics
Automotive mechatronics
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.ppt
 
09 shop floor control
09 shop floor control09 shop floor control
09 shop floor control
 
Life cycle costing (sqm)
Life cycle costing (sqm)Life cycle costing (sqm)
Life cycle costing (sqm)
 
Tpm introduction-ame
Tpm introduction-ameTpm introduction-ame
Tpm introduction-ame
 
overview of reliability engineering
overview of reliability engineeringoverview of reliability engineering
overview of reliability engineering
 
Engineering economics (1)
Engineering economics (1)Engineering economics (1)
Engineering economics (1)
 
Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy Chapter 1 introduction to engineering economy
Chapter 1 introduction to engineering economy
 
Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...
Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...
Reliability Centered Maintenance (RCM) and Total Productive Maintenance (TPM)...
 
10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
 
COMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEP
COMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEPCOMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEP
COMPUTERIZED LAYOUT METHODS ,CRAFT , ALDEP
 

Destacado

MG 6863 UNIT II MAKE OR BUY DECISION
MG 6863 UNIT II MAKE OR BUY DECISIONMG 6863 UNIT II MAKE OR BUY DECISION
MG 6863 UNIT II MAKE OR BUY DECISIONAsha A
 
Make or Buy IT Decision
Make or Buy IT DecisionMake or Buy IT Decision
Make or Buy IT DecisionUmesh Bajaj
 
MG 6863 Unit III cash flow
MG 6863 Unit III cash flowMG 6863 Unit III cash flow
MG 6863 Unit III cash flowAsha A
 
UNIT V DEPRECIATION
UNIT V DEPRECIATIONUNIT V DEPRECIATION
UNIT V DEPRECIATIONAsha A
 
Value Engineering And Value Analysis
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysisthombremahesh
 
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERING
 MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERINGAsha A
 
Build vs Buy Strategy
Build vs Buy StrategyBuild vs Buy Strategy
Build vs Buy StrategyChris Halton
 
Make or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcingMake or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcingAnkit
 
Maintainance & replacement fluid therapy pediatrics AG
Maintainance & replacement fluid therapy pediatrics AGMaintainance & replacement fluid therapy pediatrics AG
Maintainance & replacement fluid therapy pediatrics AGAkshay Golwalkar
 
Engineering economics and cost analysis
Engineering economics and cost analysisEngineering economics and cost analysis
Engineering economics and cost analysissriamrish
 
2016.10.19 subsidiary strategies for local knowledge creation and protection ...
2016.10.19 subsidiary strategies for local knowledge creation and protection ...2016.10.19 subsidiary strategies for local knowledge creation and protection ...
2016.10.19 subsidiary strategies for local knowledge creation and protection ...NUI Galway
 
AN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRY
AN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRYAN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRY
AN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRYIAEME Publication
 
Software Development Outsourcing - Total Cost Of Engagement Tce
Software Development Outsourcing - Total Cost Of Engagement TceSoftware Development Outsourcing - Total Cost Of Engagement Tce
Software Development Outsourcing - Total Cost Of Engagement TceScioSales
 
Knowing When to Build Versus Buy a Mobile Backend
Knowing When to Build Versus Buy a Mobile BackendKnowing When to Build Versus Buy a Mobile Backend
Knowing When to Build Versus Buy a Mobile BackendInMobi
 
InMobi inDecode - All About Location on Mobile : Ian Anderson
InMobi inDecode -  All About Location on Mobile : Ian AndersonInMobi inDecode -  All About Location on Mobile : Ian Anderson
InMobi inDecode - All About Location on Mobile : Ian AndersonInMobi
 

Destacado (20)

MG 6863 UNIT II MAKE OR BUY DECISION
MG 6863 UNIT II MAKE OR BUY DECISIONMG 6863 UNIT II MAKE OR BUY DECISION
MG 6863 UNIT II MAKE OR BUY DECISION
 
Make or Buy IT Decision
Make or Buy IT DecisionMake or Buy IT Decision
Make or Buy IT Decision
 
Make or buy diagram
Make or buy diagramMake or buy diagram
Make or buy diagram
 
MG 6863 Unit III cash flow
MG 6863 Unit III cash flowMG 6863 Unit III cash flow
MG 6863 Unit III cash flow
 
UNIT V DEPRECIATION
UNIT V DEPRECIATIONUNIT V DEPRECIATION
UNIT V DEPRECIATION
 
Value Engineering And Value Analysis
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysis
 
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERING
 MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERING
 
Slide Make or buy
Slide Make or buySlide Make or buy
Slide Make or buy
 
COST MAkE OR BUY
COST MAkE OR BUY COST MAkE OR BUY
COST MAkE OR BUY
 
Build vs Buy Strategy
Build vs Buy StrategyBuild vs Buy Strategy
Build vs Buy Strategy
 
Make or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcingMake or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcing
 
Maintainance & replacement fluid therapy pediatrics AG
Maintainance & replacement fluid therapy pediatrics AGMaintainance & replacement fluid therapy pediatrics AG
Maintainance & replacement fluid therapy pediatrics AG
 
Depreciation
DepreciationDepreciation
Depreciation
 
Softwareproject planning
Softwareproject planningSoftwareproject planning
Softwareproject planning
 
Engineering economics and cost analysis
Engineering economics and cost analysisEngineering economics and cost analysis
Engineering economics and cost analysis
 
2016.10.19 subsidiary strategies for local knowledge creation and protection ...
2016.10.19 subsidiary strategies for local knowledge creation and protection ...2016.10.19 subsidiary strategies for local knowledge creation and protection ...
2016.10.19 subsidiary strategies for local knowledge creation and protection ...
 
AN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRY
AN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRYAN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRY
AN EXPERT SYSTEM FOR MAKE OR BUY DECISION IN MANUFACTURING INDUSTRY
 
Software Development Outsourcing - Total Cost Of Engagement Tce
Software Development Outsourcing - Total Cost Of Engagement TceSoftware Development Outsourcing - Total Cost Of Engagement Tce
Software Development Outsourcing - Total Cost Of Engagement Tce
 
Knowing When to Build Versus Buy a Mobile Backend
Knowing When to Build Versus Buy a Mobile BackendKnowing When to Build Versus Buy a Mobile Backend
Knowing When to Build Versus Buy a Mobile Backend
 
InMobi inDecode - All About Location on Mobile : Ian Anderson
InMobi inDecode -  All About Location on Mobile : Ian AndersonInMobi inDecode -  All About Location on Mobile : Ian Anderson
InMobi inDecode - All About Location on Mobile : Ian Anderson
 

Similar a MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS

Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisChandra Kumar S
 
Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisDevalakshmanperumal1991
 
Design and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineDesign and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineIRJET Journal
 
Design improvements and costing analysis
Design improvements and costing analysisDesign improvements and costing analysis
Design improvements and costing analysisASHISH MENKUDALE
 
Replacement models and maintenance analysis
Replacement models and maintenance analysisReplacement models and maintenance analysis
Replacement models and maintenance analysisAhsanKhan837024
 
Design and Performance Analysis of Mechanical Hydro Pneumatic Suspension System
Design and Performance Analysis of Mechanical Hydro Pneumatic Suspension SystemDesign and Performance Analysis of Mechanical Hydro Pneumatic Suspension System
Design and Performance Analysis of Mechanical Hydro Pneumatic Suspension SystemIRJET Journal
 
Basic Maintenance
Basic MaintenanceBasic Maintenance
Basic MaintenanceRAHMAT EIE
 
Design and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnDesign and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnHariKirant29
 
Structural weight optimization of a bracket using
Structural weight optimization of a bracket usingStructural weight optimization of a bracket using
Structural weight optimization of a bracket usingeSAT Publishing House
 
Maintenance planning and replacement
Maintenance  planning and replacementMaintenance  planning and replacement
Maintenance planning and replacementAmit Singh
 
Design and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal MachineDesign and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal MachineIRJET Journal
 
Design and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal MachineDesign and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal MachineIRJET Journal
 
Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...MECandPMV
 
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...IRJET Journal
 
Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...
Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...
Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...Eylül Ceren Altın
 

Similar a MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS (20)

Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysis
 
Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysis
 
My Project
My ProjectMy Project
My Project
 
Design and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineDesign and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing Machine
 
Design improvements and costing analysis
Design improvements and costing analysisDesign improvements and costing analysis
Design improvements and costing analysis
 
Replacement models and maintenance analysis
Replacement models and maintenance analysisReplacement models and maintenance analysis
Replacement models and maintenance analysis
 
Design and Performance Analysis of Mechanical Hydro Pneumatic Suspension System
Design and Performance Analysis of Mechanical Hydro Pneumatic Suspension SystemDesign and Performance Analysis of Mechanical Hydro Pneumatic Suspension System
Design and Performance Analysis of Mechanical Hydro Pneumatic Suspension System
 
Basic Maintenance
Basic MaintenanceBasic Maintenance
Basic Maintenance
 
Design and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the ColumnDesign and Simulation of Divided Wall Column - Design of the Column
Design and Simulation of Divided Wall Column - Design of the Column
 
Chap5 engeco
Chap5 engecoChap5 engeco
Chap5 engeco
 
Structural weight optimization of a bracket using
Structural weight optimization of a bracket usingStructural weight optimization of a bracket using
Structural weight optimization of a bracket using
 
Maintenance planning and replacement
Maintenance  planning and replacementMaintenance  planning and replacement
Maintenance planning and replacement
 
Design and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal MachineDesign and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal Machine
 
Design and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal MachineDesign and Fabrication of Tamarind Seed Removal Machine
Design and Fabrication of Tamarind Seed Removal Machine
 
Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...Optimization of preventive maintenance to reduce maintenance costs and increa...
Optimization of preventive maintenance to reduce maintenance costs and increa...
 
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
 
Seminar _5.pptx
Seminar _5.pptxSeminar _5.pptx
Seminar _5.pptx
 
Operations REsearch
Operations REsearchOperations REsearch
Operations REsearch
 
Maintenance
MaintenanceMaintenance
Maintenance
 
Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...
Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...
Performance and Efficiency Analysis with Value Stream Mapping for Increasing ...
 

Más de Asha A

Turbo jet engine
Turbo jet engineTurbo jet engine
Turbo jet engineAsha A
 
Unit v
Unit vUnit v
Unit vAsha A
 
Unit ii Flow through circular pipes
Unit ii Flow through circular pipesUnit ii Flow through circular pipes
Unit ii Flow through circular pipesAsha A
 
Unit IV Reciprocating pump with air vessel
Unit IV  Reciprocating pump with air vesselUnit IV  Reciprocating pump with air vessel
Unit IV Reciprocating pump with air vesselAsha A
 
Unit IV Centriufugal and reciprocating pump
Unit IV Centriufugal and reciprocating pumpUnit IV Centriufugal and reciprocating pump
Unit IV Centriufugal and reciprocating pumpAsha A
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process PlanningAsha A
 
Unit ii usm
Unit ii usm Unit ii usm
Unit ii usm Asha A
 
Chm &amp; ecm
Chm &amp; ecmChm &amp; ecm
Chm &amp; ecmAsha A
 
Electrical discharge machining
Electrical discharge machiningElectrical discharge machining
Electrical discharge machiningAsha A
 
Dielectric
DielectricDielectric
DielectricAsha A
 
Wjm unit ii
Wjm unit iiWjm unit ii
Wjm unit iiAsha A
 
Unit ii ajm
Unit ii ajm Unit ii ajm
Unit ii ajm Asha A
 
CE 6451 FMM Unit 1 Properties of fluids
CE 6451 FMM  Unit 1 Properties of fluidsCE 6451 FMM  Unit 1 Properties of fluids
CE 6451 FMM Unit 1 Properties of fluidsAsha A
 
MG 6863 FORMULA SHEET ENGINEERING ECONOMICS
MG 6863  FORMULA SHEET ENGINEERING ECONOMICSMG 6863  FORMULA SHEET ENGINEERING ECONOMICS
MG 6863 FORMULA SHEET ENGINEERING ECONOMICSAsha A
 

Más de Asha A (14)

Turbo jet engine
Turbo jet engineTurbo jet engine
Turbo jet engine
 
Unit v
Unit vUnit v
Unit v
 
Unit ii Flow through circular pipes
Unit ii Flow through circular pipesUnit ii Flow through circular pipes
Unit ii Flow through circular pipes
 
Unit IV Reciprocating pump with air vessel
Unit IV  Reciprocating pump with air vesselUnit IV  Reciprocating pump with air vessel
Unit IV Reciprocating pump with air vessel
 
Unit IV Centriufugal and reciprocating pump
Unit IV Centriufugal and reciprocating pumpUnit IV Centriufugal and reciprocating pump
Unit IV Centriufugal and reciprocating pump
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process Planning
 
Unit ii usm
Unit ii usm Unit ii usm
Unit ii usm
 
Chm &amp; ecm
Chm &amp; ecmChm &amp; ecm
Chm &amp; ecm
 
Electrical discharge machining
Electrical discharge machiningElectrical discharge machining
Electrical discharge machining
 
Dielectric
DielectricDielectric
Dielectric
 
Wjm unit ii
Wjm unit iiWjm unit ii
Wjm unit ii
 
Unit ii ajm
Unit ii ajm Unit ii ajm
Unit ii ajm
 
CE 6451 FMM Unit 1 Properties of fluids
CE 6451 FMM  Unit 1 Properties of fluidsCE 6451 FMM  Unit 1 Properties of fluids
CE 6451 FMM Unit 1 Properties of fluids
 
MG 6863 FORMULA SHEET ENGINEERING ECONOMICS
MG 6863  FORMULA SHEET ENGINEERING ECONOMICSMG 6863  FORMULA SHEET ENGINEERING ECONOMICS
MG 6863 FORMULA SHEET ENGINEERING ECONOMICS
 

MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS

  • 1. UNIT – IV REPLACEMENT AND MAINTENANCE ANALYSIS BY Dr. A. Asha Professor/Mechanical Engineering Kamaraj College of Engineering & Technology Virudhunagar December 2016
  • 2. MAINTENANCE • Definition : Maintenance is defined as the action taken by the user to maintain an existing facility in operating condition. KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 2
  • 3. OBJECTIVES OF MAINTENANCE • To achieve minimum break down • To keep a plant in good working condition at the lowest possible cost. • To keep machines at their optimum cost without any hindrance. • To ensure the availability of machineries, buildings and services. • To achieve efficient functioning of machines. • To reduce operation and maintenance cost. KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 3
  • 4. TYPES OF MAINTENANCE • Corrective (or) Break down Maintenance • Scheduled Maintenance • Preventive Maintenance • Predictive Maintenance KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 4
  • 5. CORRECTIVE (OR) BREAK DOWN MAINTENANCE • This implies that repairs are made after the equipment is out of order and it can not perform its normal functions any longer. • Production Dept Maintenance Dept to rectify the fault. • Maintenance Dept checks into the difficulty and makes the necessary repairs • After removing the fault the maintenance engineers do not attend the equipment until another failure occurs KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 5
  • 6. CAUSES FOR EQUIPMENT BREAK DOWN • Failure to replace the worn out parts. • Lack of lubrication • Neglected cooling system. • Not attending minor faults. • External factors such as low or high voltage, wrong fuel • Not attending unusual sounds, vibrations etc. KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 6
  • 7. SCHEDULED MAINTENANCE • Scheduled maintenance is concerned with the time schedule to avoid breakdown. • This maintenance includes inspection, repair, overhaul etc which if neglected can result in serious issues. KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 7
  • 8. PREVENTIVE MAINTENANCE • It is defined as an action performed in an attempt to keep the machine in a specified operating condition by means of systematic inspection, detection and prevention of failures. • It works on the principle of “Prevention is better than cure” • It locates weak spots in all equipments provides them with regular inspection and minor repairs and thereby reduces the danger of unanticipated breakdown KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 8
  • 9. OBJECTIVES OF PREVENTIVE MAINTENANCE • To keep the equipment always available. • To maintain the value of the equipment by periodic inspection, repairs and overhauls. • To maintain optimum production ᶯ of the equipment. • To ensure safety of the workers • To reduce the work content of maintenance jobs. KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 9
  • 10. Preparation for maintenance Repair over Preventivemaintenance FF==Fault Detection LoLLocalisation and isolation of fault Disassembly Remove fault item Reinstallation and Reassembly Repair Ffinal adjustments CChecking KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 10
  • 11. PROCEDURE OF PREVENTIVE MAINTENANCE • Inspection or checkups • Lubrication • Planning and scheduling • Record keeping and analysis • Training of maintenance personnel • Storage of spare parts • Control and evaluation of preventive maintenance. KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 11
  • 12. ADVANTAGES OF PREVENTIVE MAINTENANCE • Reduction in production down time. • Less overtime pay for maintenance personnel • Lesser expenditure on repairs • Fewer repetitive repairs • Better product quality and fewer rejections. • Lesser number of standby equipments are needed KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 12
  • 13. PREDICTIVE MAINTENANCE • Newer maintenance technique • It uses human sense organs or some sensitive instruments such as audio gauges, vibration analysers, amplitude meters etc to predict troubles before the equipment fails. • Equipment conditions are monitored periodically and thus enables the maintenance men to take timely action such as repairs and overhauls. • Extends the service life of an equipment without the fear of failure KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 13
  • 14. REPLACEMENT • Replacement can be defined as the decision problems involving the replacement of existing obsolete or worn out assets • Causes of replacement : 1. Deterioration 2. Obsolescence 3. Inadequacy 4. Working conditions KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 14
  • 15. TYPES OF REPLACEMENT PROBLEM • Replacement of assets with deteriorate with time (a) Economic Life of an asset (b) Replacement of an existing asset with a new asset • Simple probabilistic model for assets which fail completely.(replacement due to sudden failure) KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 15
  • 16. PROBLEM • The following table gives the operation and maintenance cost and salvage value at the end of the every year of a machine whose purchase price is Rs 20,000. Find the economic service life of the machine assuming interest rate i = 15% KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 16
  • 17. PROBLEM END OF YEAR OPERATING COST (RS) MAINTENANCE COST (RS) SALVAGE VALUE (RS) 1 3000 300 9000 2 4000 400 8000 3 5000 500 7000 4 6000 600 6000 5 7000 700 5000 6 8000 800 4000 7 9000 900 3000 8 10000 1000 2000 9 11000 1100 1000 10 12000 1200 0 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 17
  • 18. SOLUTION KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 18
  • 19. PROBLEM • A firm is considering replacement of an machine whose cost price is Rs 1,20,000 and the scrap value is Rs 10,000 at the end of the first year and declines each year by rs 1000 from the previous years scrap value. The operating cost is as follows Year 1 2 3 4 5 6 7 8 Operating cost 2000 5000 8000 12000 18000 25000 32000 40000 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 19
  • 20. SOLUTION End of year Operating cost Cumulative operating cost Scrap value Total cost FC + COC-S Average cost = TC/n 1 2000 2000 10000 112000 112000 2 5000 7000 9000 118000 59000 3 8000 15000 8000 127000 42333.33 4 12000 27000 7000 140000 35000 5 18000 45000 6000 159000 31800 6 25000 70000 5000 185000 30833.33 7 32000 102000 4000 218000 31142.85 8 40000 142000 3000 259000 32375 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 20
  • 21. REPALCEMENT OF EXISTING ASSET WITH NEW ASSET • Annual equivalent cost of existing asset and the new asset is calculated. • The alternative which gives the least value is considered as the best alternative. • The formula to calculate the annual equivalent cost is AE = (P-F)(A/P , i, n) + F x i +A KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 21
  • 22. PROBLEM Two years ago a machine was purchased at a cost of Rs 2,00,000 to be useful for eight years. Its salvage value at the end of the life is Rs 25,000. The annual maintenance cost is Rs 25,000. The market value of the present machine is Rs 1,20,000. Now a new machine to cater to the need of the present machine is Rs 1,50,000 to be useful for six years. The annual maintenance cost is Rs 14,000. The salvage value of the new machine is Rs 20,000. Using the rate of 12% find whether it is worth replacing the present machine with the new machine KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 22
  • 23. SIMPLE PROBABILISTIC MODEL FOR ASSETS WHICH FAIL COMPLETELY • A system usually consists of a large no of low cost items that are increasing liable to failure with age. • The cost of failure is > the cost of item itself. • Two types of replacement policies are considered a. Individual replacement policy b. Group replacement policy KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 23
  • 24. SIMPLE PROBABILISTIC MODEL FOR ASSETS WHICH FAIL COMPLETELY • For a given problem the individual & group replacement policies are evaluated and the most economical policy is selected for implementation. KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 24
  • 25. PROBLEM • The failure rates of transistors in a computer are summarized in the following table. The cost of replacing an individual failed transistor is Rs 8/-. If all the transistors are replaced simultaneously it would cost Rs 4 per transistor. Find the optimum replacement policy End of week 1 2 3 4 5 6 7 Probability of failure 0.09 0.17 0.27 0.50 0.65 0.90 1.00 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 25
  • 26. SOLUTION • Let Ni = The number of transistors replaced at the end of the ith week. • N0 = Number of transistors replaced at the end of the week 0. N1 = N0 x P1 = 100 x 0.09 = 9 N2 = N0 x P2 + N1 x P1 = 100 x 0.08 + 9 x 0.09 = 8.81 N3 = N0 x P3 + N1 x P2 + N2 x P1 = 100 x 0.1 + 9 x 0.08 + 8.81 x 0.09 = 11.51 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 26
  • 27. SOLUTION N4 = N0 x P4 + N1 x P3 + N2 x P2 + N3 x P1 = 100 x 0.23 + 9 x 0.1 + 8.81 x 0.08 + 11.51 x 0.09 = 25.63 N5 = N0 x P5 + N1 x P4 + N2 x P3+ N3 x P2 + N4 x P1 = 100 x 0.15 + 9 x 0.23 + 8.81 x 0.1 + 11.51 x 0.23 + 25.63 x 0.09 = 21.17 N6 = N0 x P6 + N1 x P5 + N2 x P4+ N3 x P3 + N4 x P2 + N5 x P1 = 100 x 0.25 + 9 x 0.15 + 8.81 x 0.23 + 11.51 x 0.1 + 25.63 x 0.08 + 21.17 x 0.09 = 33.47 N7 = N0 x P7 + N1 x P6 + N2 x P5+ N3 x P4 + N4 x P3 + N5 x P2 + N6 x P1 = 100 x 0.1 + 9 x 0.25 + 8.81 x 0.15 + 11.51 x 0.23 + 25.63 x 0.1 + 21.17 x 0.08 + 33.47 x 0.09 = 23.47 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 27
  • 28. SOLUTION • Expected life of the transistor = = 1 x 0.09 + 2x 0.08 + 3 x0.1+ 4 x 0.23 + 5 x 0.15 + 6x 0.25 + 7x 0.1 = 4.42 weeks • Average number of failure per week = 100/4.42 = 23 • Cost of individual replacement = Number of failures/week x Individual replacement cost/transistor = 23 x 8 = Rs 184 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 28
  • 29. SOLUTION • GROUP REPLACEMENT COST End of Week Group replacement cost Cost of individual replacement Total Cost (Rs) Average Cost (Rs) 1 4 x 100 = 400 9 x 8 = 72 472 472 2 400 (9 + 8.81) x 8 = 142.48 542.48 271.24 3 400 (9 + 8.81+11.51) x 8 = 234.56 634.56 211.52 4 400 (9 + 8.81+11.51+25.63) x 8 = 439.60 839.60 209.90 5 400 (9 + 8.81+11.51+25.63+21.17) x 8 = 608.96 1008.96 201.79 6 400 (9 + 8.81+11.51+25.63+21.17+ 33.47) x 8 = 876.72 1276.72 212.78 7 400 (9 + 8.81+11.51+25.63+21.17+ 33.47+ 23.47) x 8 = 1064.48 1464.48 209.21 KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 29
  • 30. SOLUTION • Individual replacement cost /week = Rs. 184/- • Group replacement cost /week = Rs. 201.79/- Since the individual cost/week is < group replacement cost the individual replacement cost is adopted KCET/DEPARTMENT OF MECHANICAL ENGINEERING/ Dr. A. Asha 30