SlideShare una empresa de Scribd logo
1 de 26
Descargar para leer sin conexión
Prepared By
Prof. Ashish Makwana
Civil Engg. Dept.
Prof. Ashish Makwana 1
PRESENTATION
OUTLINE…
• Introduction
• Object of Resource Planning
• Methods of Resource Planning
• Resource Smoothing
• Resource Levelling
• Steps in Resource Levelling
• Scheduling
• Advantages: Project Scheduling
• Steps to Prepare Project Schedule
• Other Schedules Derived from Project Schedule
Prof. Ashish Makwana 2
INTRODUCTION
Resource is a physical variable such as –
• Men
• Material
• Machines
• Space
• Money
• Time
Prof. Ashish Makwana 3
OBJECT OF RESOURCE PLANNING
• At the time of preparing the network of any
project, usually it is assumed that all
resources needed for its execution are
available in plenty and no consideration of
resource constraints is taken into account.
• In such situations the duration of the project
may increase escalating the cost of the
project.
Prof. Ashish Makwana 4
• The planning of resources should be done in
such a manner that no increase or decrease
in resource demand may occur.
• As the engagement of skilled labour all a
sudden is difficult, similarly the lay off of the
labour suddenly is more difficult than their
employment. Thus for a good resource plan,
it is essential that the project may be
completed during the stipulated period.
• To achieve this objective some times it
becomes essential to make changes in the
earliest start time of some critical activities
or the execution of some activities may be
postponed for the time being.Prof. Ashish Makwana 5
• While taking decision for postponing the
execution of any activity or effective changes
in the earliest time of critical activities
following points should be kept in mind.
• Such activities should be started first, whose
completion duration is minimum.
• The activity having maximum time of
completion should be postponed.
• The activity having maximum float time
should be chosen for postponement first.
Prof. Ashish Makwana 6
METHODS OF
RESOURCE PLANNING
• Depending upon the situation, the resource
allocation can be done by the following two
methods.
1. Resource smoothing
2. Resource levelling
Prof. Ashish Makwana 7
RESOURCE SMOOTHING
• Resource smoothing is done when there is
restriction on the duration of project
completion time.
• The resource smoothing is applied in such a
way that the total project duration remains
the same. i.e. there is no change in the total
duration of the project.
Prof. Ashish Makwana 8
• First the periods of minimum demand,
resources are determined and the activities
are shifted according to the availability of
float and requirement of resources.
• Thus the intelligent use of floats can
smoothen the demand to the maximum
possible extent. This type of resource
allocation is known as resource smoothing.
Prof. Ashish Makwana 9
STEPS IN RESOURCE SMOOTHING
1. The list of resources required for the
execution of different activities is prepared
and the important activities are identified.
2. The resource profiles are prepared by
resource aggregation and cumulative
resource requirements for each unit are
plotted in the form of histogram.
3. The time periods of peak and low demand
are identified and the peaks are lowered
and the troughs are filled up.
Prof. Ashish Makwana 10
4. If there is no restraint on the availability of
resources, the demand of resources should be
made as uniform as possible. This can be done
by changing the time of start and finish of
non-critical activities in the first instance.
These activities have some float. Hence the
available float can be used for doing
adjustment in the start or finish of the
concerned activities. Thus the peak demand
may be lowered by staggering the resource
requirements with out delaying the project
duration.
Prof. Ashish Makwana 11
RESOURCE LEVELLING
• In a project, there are many activities which
need varying resources.
• The demand on specific resource should not
increase beyond the prescribed limit.
• If the demand of a resource increases more
than its availability, then the only alternative
is to delay the activity having maximum
float. This process is called resource levelling.
Prof. Ashish Makwana 12
• If there are more than one activities
requiring the same amount of resources, in
that case activity having minimum duration
is chosen for resource reallocation.
• Resource levelling if adopted in case, there is
restriction on the availability of resources.
Prof. Ashish Makwana 13
STEPS IN RESOURCE LEVELLING
1. The peak requirement of the resources is
lowered by staggering the resource input
on non-critical activities. If needed sub-
critical and critical activities may also be
rescheduled to bring down demand than
specified limits. Thus the completion of
project work may be delayed due to
resource constraints.
Prof. Ashish Makwana 14
2. Either some of the concurrent activities may
be placed in series or the duration of critical
activities may be increased to reduce the peak
demands below the specified limits. This will
increase the duration of the project.
3. Rearrange the activities having larger
magnitude of positive float as resources can
be diverted conveniently from the activities
having large amount of float.
Prof. Ashish Makwana 15
Following procedures may be adopted –
• First the high peak of resource demand
should be lowered utilizing the free floats of
the activities.
• Non-critical activities may be rescheduled to
the required extent utilizing the floats,
starting with the activity having larger float.
If necessary critical activities may also be
tackled.
Prof. Ashish Makwana 16
SCHEDULING
• After the project is properly planned, it is
scheduled.
• Scheduling is a mechanical process for
setting in order the various planned activities
by fixing the starting and finishing dates to
each part of the work in such a manner that
the whole work should be done in an orderly
and systematic way.
Prof. Ashish Makwana 17
• As every attempt is made to stick to the
schedule but some variation is bound to take
place on account of some factors which
cannot be foreseen at the time of making
schedule, so this necessitates rescheduling of
the project during the progress of the work.
• Planning department will have to frame a
time schedule for a project which will assign
definite timings for individual constructional
operations leading to finished product.
Prof. Ashish Makwana 18
ADVANTAGES:
PROJECT SCHEDULING
• It will give clear idea about the type,
quantity of the materials required at
different stages of execution of work and the
duration of supply of materials.
• It will also show the quantities and duration
of various operations for which plant or
equipment (if needed) can be arranged well
in time, so as to avoid unnecessary
expenditure for keeping the plant idle for
dates on which it may not be required.
Prof. Ashish Makwana 19
• It will help in arranging labour, both skilled
and unskilled, as regards quantity and period
for which it may be needed.
• The money required at different stages will
also be known from the different data.
• The total time to complete the project is
known.
• From the actual progress charts, it can be
known whether the work is lagging behind
or not if the progress is slow, speeding up of
the activities can be arranges.
Prof. Ashish Makwana 20
• Project schedule is the basis of extracting a
number of other schedules and information.
• The project schedule act as reference for
completion with actual progress, cost of
construction, and profit margin at any given
time during the course of monitoring.
Prof. Ashish Makwana 21
STEPS TO PREPARE
PROJECT SCHEDULE
1. Identify and study the scope of work from
the contract documents like tender
drawings, bill of quantities, terms and
conditions of contract etc. Contractors
normally do not have access to all the
details needed to prepare an exhaustive
schedule at the beginning. Contractor
should try to extract as much information
as possible, even by unofficially meeting
the owner’s representative and architects
for the project. Prof. Ashish Makwana 22
• Decide on the construction methodology for
completing the project within the given time
schedule.
• The total project scope is finally brought
down into work packages and activities. This
breakdown into smaller activities helps the
planner in estimating resources required and
duration for completing the activities.
• Using relationships existing among different
activities a CPM or PERT network is
prepared.
• From the network a week-wise or month
wise schedule is derived.
Prof. Ashish Makwana 23
• In large project involving a number of sub
projects, a master project schedule is
prepared in addition to preparing schedules
for each of the sub projects.
• These activities need to be revised as and
when any new information is available or at
a fixed interval such as fortnightly or
monthly.
Prof. Ashish Makwana 24
OTHER SCHEDULES DERIVED
FROM PROJECT SCHEDULE
1. Construction schedule
2. Material schedule
3. Labour schedule
4. Equipment schedule
5. Financial schedule
6. Invoice schedule
Prof. Ashish Makwana 25
THANK YOU
Prof. Ashish Makwana 26

Más contenido relacionado

La actualidad más candente

Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
Nicola2903
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
saurabmi2
 

La actualidad más candente (20)

03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Bar chart
Bar chartBar chart
Bar chart
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Construction contract
Construction contract Construction contract
Construction contract
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Construction material management_Construction Management (2180611) (Semester-...
Construction material management_Construction Management (2180611) (Semester-...Construction material management_Construction Management (2180611) (Semester-...
Construction material management_Construction Management (2180611) (Semester-...
 

Similar a Project scheduling and resource levelling_Construction Management

Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
TecnicoItca
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
TecnicoItca
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx
Janak82
 

Similar a Project scheduling and resource levelling_Construction Management (20)

Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management
 
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Resource Allocation In Software Project Management
Resource Allocation In Software Project ManagementResource Allocation In Software Project Management
Resource Allocation In Software Project Management
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
module 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdfmodule 2 Lec 1 CEM Construction project planning.pdf
module 2 Lec 1 CEM Construction project planning.pdf
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx
 
L12-Project Management (2018-2019) (1).pdf
L12-Project Management (2018-2019) (1).pdfL12-Project Management (2018-2019) (1).pdf
L12-Project Management (2018-2019) (1).pdf
 

Más de A Makwana

A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
A Makwana
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
A Makwana
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
A Makwana
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
A Makwana
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
A Makwana
 

Más de A Makwana (20)

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
 
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
 

Último

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 

Último (20)

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 

Project scheduling and resource levelling_Construction Management

  • 1. Prepared By Prof. Ashish Makwana Civil Engg. Dept. Prof. Ashish Makwana 1
  • 2. PRESENTATION OUTLINE… • Introduction • Object of Resource Planning • Methods of Resource Planning • Resource Smoothing • Resource Levelling • Steps in Resource Levelling • Scheduling • Advantages: Project Scheduling • Steps to Prepare Project Schedule • Other Schedules Derived from Project Schedule Prof. Ashish Makwana 2
  • 3. INTRODUCTION Resource is a physical variable such as – • Men • Material • Machines • Space • Money • Time Prof. Ashish Makwana 3
  • 4. OBJECT OF RESOURCE PLANNING • At the time of preparing the network of any project, usually it is assumed that all resources needed for its execution are available in plenty and no consideration of resource constraints is taken into account. • In such situations the duration of the project may increase escalating the cost of the project. Prof. Ashish Makwana 4
  • 5. • The planning of resources should be done in such a manner that no increase or decrease in resource demand may occur. • As the engagement of skilled labour all a sudden is difficult, similarly the lay off of the labour suddenly is more difficult than their employment. Thus for a good resource plan, it is essential that the project may be completed during the stipulated period. • To achieve this objective some times it becomes essential to make changes in the earliest start time of some critical activities or the execution of some activities may be postponed for the time being.Prof. Ashish Makwana 5
  • 6. • While taking decision for postponing the execution of any activity or effective changes in the earliest time of critical activities following points should be kept in mind. • Such activities should be started first, whose completion duration is minimum. • The activity having maximum time of completion should be postponed. • The activity having maximum float time should be chosen for postponement first. Prof. Ashish Makwana 6
  • 7. METHODS OF RESOURCE PLANNING • Depending upon the situation, the resource allocation can be done by the following two methods. 1. Resource smoothing 2. Resource levelling Prof. Ashish Makwana 7
  • 8. RESOURCE SMOOTHING • Resource smoothing is done when there is restriction on the duration of project completion time. • The resource smoothing is applied in such a way that the total project duration remains the same. i.e. there is no change in the total duration of the project. Prof. Ashish Makwana 8
  • 9. • First the periods of minimum demand, resources are determined and the activities are shifted according to the availability of float and requirement of resources. • Thus the intelligent use of floats can smoothen the demand to the maximum possible extent. This type of resource allocation is known as resource smoothing. Prof. Ashish Makwana 9
  • 10. STEPS IN RESOURCE SMOOTHING 1. The list of resources required for the execution of different activities is prepared and the important activities are identified. 2. The resource profiles are prepared by resource aggregation and cumulative resource requirements for each unit are plotted in the form of histogram. 3. The time periods of peak and low demand are identified and the peaks are lowered and the troughs are filled up. Prof. Ashish Makwana 10
  • 11. 4. If there is no restraint on the availability of resources, the demand of resources should be made as uniform as possible. This can be done by changing the time of start and finish of non-critical activities in the first instance. These activities have some float. Hence the available float can be used for doing adjustment in the start or finish of the concerned activities. Thus the peak demand may be lowered by staggering the resource requirements with out delaying the project duration. Prof. Ashish Makwana 11
  • 12. RESOURCE LEVELLING • In a project, there are many activities which need varying resources. • The demand on specific resource should not increase beyond the prescribed limit. • If the demand of a resource increases more than its availability, then the only alternative is to delay the activity having maximum float. This process is called resource levelling. Prof. Ashish Makwana 12
  • 13. • If there are more than one activities requiring the same amount of resources, in that case activity having minimum duration is chosen for resource reallocation. • Resource levelling if adopted in case, there is restriction on the availability of resources. Prof. Ashish Makwana 13
  • 14. STEPS IN RESOURCE LEVELLING 1. The peak requirement of the resources is lowered by staggering the resource input on non-critical activities. If needed sub- critical and critical activities may also be rescheduled to bring down demand than specified limits. Thus the completion of project work may be delayed due to resource constraints. Prof. Ashish Makwana 14
  • 15. 2. Either some of the concurrent activities may be placed in series or the duration of critical activities may be increased to reduce the peak demands below the specified limits. This will increase the duration of the project. 3. Rearrange the activities having larger magnitude of positive float as resources can be diverted conveniently from the activities having large amount of float. Prof. Ashish Makwana 15
  • 16. Following procedures may be adopted – • First the high peak of resource demand should be lowered utilizing the free floats of the activities. • Non-critical activities may be rescheduled to the required extent utilizing the floats, starting with the activity having larger float. If necessary critical activities may also be tackled. Prof. Ashish Makwana 16
  • 17. SCHEDULING • After the project is properly planned, it is scheduled. • Scheduling is a mechanical process for setting in order the various planned activities by fixing the starting and finishing dates to each part of the work in such a manner that the whole work should be done in an orderly and systematic way. Prof. Ashish Makwana 17
  • 18. • As every attempt is made to stick to the schedule but some variation is bound to take place on account of some factors which cannot be foreseen at the time of making schedule, so this necessitates rescheduling of the project during the progress of the work. • Planning department will have to frame a time schedule for a project which will assign definite timings for individual constructional operations leading to finished product. Prof. Ashish Makwana 18
  • 19. ADVANTAGES: PROJECT SCHEDULING • It will give clear idea about the type, quantity of the materials required at different stages of execution of work and the duration of supply of materials. • It will also show the quantities and duration of various operations for which plant or equipment (if needed) can be arranged well in time, so as to avoid unnecessary expenditure for keeping the plant idle for dates on which it may not be required. Prof. Ashish Makwana 19
  • 20. • It will help in arranging labour, both skilled and unskilled, as regards quantity and period for which it may be needed. • The money required at different stages will also be known from the different data. • The total time to complete the project is known. • From the actual progress charts, it can be known whether the work is lagging behind or not if the progress is slow, speeding up of the activities can be arranges. Prof. Ashish Makwana 20
  • 21. • Project schedule is the basis of extracting a number of other schedules and information. • The project schedule act as reference for completion with actual progress, cost of construction, and profit margin at any given time during the course of monitoring. Prof. Ashish Makwana 21
  • 22. STEPS TO PREPARE PROJECT SCHEDULE 1. Identify and study the scope of work from the contract documents like tender drawings, bill of quantities, terms and conditions of contract etc. Contractors normally do not have access to all the details needed to prepare an exhaustive schedule at the beginning. Contractor should try to extract as much information as possible, even by unofficially meeting the owner’s representative and architects for the project. Prof. Ashish Makwana 22
  • 23. • Decide on the construction methodology for completing the project within the given time schedule. • The total project scope is finally brought down into work packages and activities. This breakdown into smaller activities helps the planner in estimating resources required and duration for completing the activities. • Using relationships existing among different activities a CPM or PERT network is prepared. • From the network a week-wise or month wise schedule is derived. Prof. Ashish Makwana 23
  • 24. • In large project involving a number of sub projects, a master project schedule is prepared in addition to preparing schedules for each of the sub projects. • These activities need to be revised as and when any new information is available or at a fixed interval such as fortnightly or monthly. Prof. Ashish Makwana 24
  • 25. OTHER SCHEDULES DERIVED FROM PROJECT SCHEDULE 1. Construction schedule 2. Material schedule 3. Labour schedule 4. Equipment schedule 5. Financial schedule 6. Invoice schedule Prof. Ashish Makwana 25