CONTENTS
 Introduction.
 Construction of Fluidized Bed Dryer (FBD).
 Working of FBD.
 Validation of FBD.
 Validation protocol .
 Design Qualification (DQ).
 Installation Qualification (IQ).
 Operational Qualification (OQ).
 Performance Qualification (PQ).
 Conclusion.
 References.
2
 Fluid bed drying is most widely used technique for drying
Pharmaceutical powders , granules and slurries
 Fluid bed processing involves drying, mixing, granulation,
and coating of particulate materials.
 In fluid bed drying, heat is supplied by the fluidization gas,
but the gas flow need not be the only source. Heat may be
effectively introduced by heating surfaces (panels or tubes)
immersed in the fluidized layer.
3
contd…
 The direct contact between particles and air/gas is possible in
fluid bed system.
 Fluid bed drying is suited for powders, granules,
agglomerates, and pellets with an average particle size
normally between 50 to 5,000 microns. Very fine, light
powders or highly elongated particles may require vibration
for successful fluid bed drying.
 Materials with moisture content up to 80% such as some
polymers, dye stuffs and molecular sieve catalysts can also be
accommodated.
4
 Fluidized bed dryer requires less time to complete drying. i.e.,
20 to 40 min.
 Hot spots are not observed in the dryer, because of its
excellent mixing and drying capacities.
 The thermal efficiency is 2 to 6 times greater than tray dryer.
 It facilitates the drying of thermolabile substances , since the
contact time for drying is short.
5
 The dryer is made up of stainless steel or plastic.
 It consist of a hollow vertical chamber where dry, heated air
enters through the bottom of the chamber and exhaust air
exits through the top of the chamber.
 A detachable bowl is placed at the bottom of the dryer, which
is used for charging and discharging of material.
6
 The bowl has a perforated bottom with a wire mesh support
for placing materials to be dried and to diffuse the upward
flowing air which helps to create a stable and uniform
fluidized bed.
 A fan is mounted in the upper part for circulating hot air.
 Fresh air inlet, pre-filter and heat exchanger are connected
serially to heat the air to the required temperature.
 Bag filters are placed above the drying bowl for the recovery
of fines.
7
8
 The main principle involved in fluidized bed dryer is
“Fluidization”.
 In this state the granules are completely suspended in a
stream of hot air which is being supplied from the bottom of
the container.
 Fluidization produces full agitation of solid particles and
since each particle gets surrounded by hot air, heat transfer is
extremely high and uniform.
9
 The product is dried fast without appreciable loss of heat.
Filter bags prevent particles escaping from the dryer.
 The material is left for some time in the dryer for reaching
ambient temperature.
 The end product is free flowing.
 Warning:-
The FBD is not an explosion proof instrument and therefore
samples having volatile compounds that are flammable or
able to reach their flash point should not be used with this
dryer.
10
Drying of granules in FBD
11
12
Fixed parameters:
 Porosity of filter bags,
 Bowl sieve.
Variable ( to be monitored):
 Inlet/exhaust air temperature,
 Product temperature,
 Drying time,
 Air volume,
 Humidity of incoming air and exhaust air.
VALIDATION
“ Establishing documented evidence that provides a high
degree of assurance that a specific process will consistently
produce a product meeting its predetermined specifications
and quality attributes.”
Validation applies to processes or analytical methods.
12
 Validation provides an approach to prove quality,
functionality and performance of a
pharmaceutical/biotechnological manufacturing process.
 This approach can be applied to individual pieces of
equipment as well as the manufacturing process as a whole.
14
QUALIFICATION
“Qualification is a process of assurance that the specific system,
premises or equipment are able to achieve the predetermined
acceptance criteria to confirm the attributes what it purports to
do.’’
Qualification applies to equipment.
15
Equipment Qualification:
Studies which establish with confidence that the process
equipment and ancillary systems are capable of consistently operating
within established limits and tolerances. The studies must include
equipment specifications, installation qualification (IQ), operational
qualification (OQ) and performance qualification all major equipment to
be used in the manufacture of commercial scale batches. Equipment
qualification should simulate actual production conditions, including
"worst case"/ stressed conditions.
Worst Case Condition: The highest and /or lowest value of a given
parameter actually evaluated in the validation exercise.
16
• A Validation Protocol is an approved document which outlines
the program to be employed, the tests that will be made and
the acceptance criteria for those tests.
Validation Phases:
 DQ- Design Qualification
 IQ- Installation Qualification
 OQ-Operational Qualification
 PQ- Performance Qualification
DESIGN QUALIFICATION
 Documented verification that the proposed design of
equipment/systems is suitable for the intended purpose.
 Requirements are best created before “shopping” is
undertaken.
 Requirements are created by the needs of the system/process
of which the equipment/system will be a part.
18
INSTALLATION QUALIFICATION
 “Assurance that the intended equipment is received as
designed and specified”.
 Verifying proper installation of utilities; water, steam,
electrical, compressed air, ventilation, etc.
 Instruments for measuring temperature, humidity, time, air
volume , pressure as well as recording devices for these
variables should be calibrated.
19
OPERATIONAL QUALIFICATION
 The documented evidence that the system or equipment
performs as intended throughout all anticipated operating
ranges.
 “Confirmation that the equipment functions as specified and
operates correctly”.
 Verifies correct operation of critical components and
operating ranges as defined by the specification and required
performance.
 Operational Tests: Empty Chamber Mapping
20
PERFORMANCE QUALIFICATION
 The documented evidence that the system, equipment or
process is capable of consistently producing a safe product of
high quality.
 Tests to demonstrate that the equipment/system performs in
an actual as-used scenario.
› Heat Distribution Studies
› Heat Penetration Studies
21
 Design qualification is the documentation of the planning phase,
including the decision making for the equipment.
 The goal is to perform something similar to a risk analysis and to
check the design documents of a technical system to ensure that it
fulfils the user requirements.
 Design qualification takes place before the equipment is
constructed. The risk analysis is often part of the design
qualification. The earlier risks can be recorded and evaluated, the
sooner their minimisation can be taken into consideration in the
equipment construction phase.
22
 In fluidized bed dryer the design of the instrument should be:
 Should occupy the small place.
 Based on our requirement we can go for horizontal or
vertical.
 All technical considerations should be kept in mind while
doing the design.
 Every fluid bed dryer must have explosion relief device of
required size
23
Installation Qualification for fluidized bed dryer include the
following steps:
 Verifying the approved purchase order.
 Verify model number, serial number.
 Ensure that all relevant documentation is received:
User manual,
Maintenance manual,
List of change parts,
Electrical drawings.
24
 Check the manufacturer and supplier.
 Check for any physical damage.
 Confirm location and installation requirements per
recommendation of manufacturer.
 Verify that the utilities required are available.
 Dust free area and moisture free air should be provided.
 Installation shall be conducted per instructions provided in
the manual.
25
 Verify alarm control.
 Operate the equipment at low, medium, and high speed per
operations manual to verify the operating control.
 Verify that all switches and push buttons are functioning
properly.
 Establish procedures for operation, maintenance, and
calibration.
 Establish training program for relevant staff.
 All the electrical fittings in the room must conform to ISI
specifications of Flameproof Electrical fittings.
 Do the tests for uniform distribution of air.
26
Run three batches of each product and analyze for:
 Active ingredients homogeneity.
 Moisture content.
 Particle size distribution.
 Percentage fines.
Based on this data we can fix drying end points for
each process.
27
Specially for FBD:
i. Air temperature distribution: Using thermocouples.
ii. Inlet air installation:
a) Delay time for achieving constant air conditions: Using
thermocouple and hygrometer.
b) Microbiological quality of the inlet air: Using centrifugal
air sampler.
28
It is check up of what we want actually for that particular
process from the equipment.
i. Inlet air speed.
ii. Quality of air.
iii. Uniform distribution of air.
iv. Mixing of air with temperature.
Run the trial batch during operation and there should not be any
change in the:
1. Size, 2. Shape , 3.Surface characteristics of the material
which we kept for drying.
29
 Validation provides an approach to prove quality,
functionality and performance of a
pharmaceutical/biotechnological manufacturing process.
 Each time before use of the equipment it should be calibrated
and maintained and proper precautions should be taken to
increase the life span of the equipment.
30
 C.V.S. Subrahmanyam et al, page no. 396-398,Pharmaceutical
Engineering.
 Development Pharmaceutics and Process Validation, CPMP,
1988.
 Guidelines on the Validation of Manufacturing Process,
WHO, 1996.
 Principles of Qualification and Validation in Pharmaceutical
Manufacture, PIC, 1996.
 www.google.co.in
31
 www.pharmainfo.net
 www.ikev.org/haber/bozzonejune1.pdf
 www.pharmweb.net
 en.wikipedia.org/wiki/Validation
 www.ikev.org/haber/inspection/.../ Turkey
Qualification_Validation.pdf
 http://www.qclabequipment.com/Sherwood_Digital___Analo
gue.pdf
32
33

Más contenido relacionado

La actualidad más candente

Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validationamol dighe
 
Process valiadtion
Process valiadtionProcess valiadtion
Process valiadtionSagar Savale
 
Processs validation
Processs validationProcesss validation
Processs validationMani Kandan
 
Validation of liquids
Validation of liquidsValidation of liquids
Validation of liquidsPriyam Patel
 
Validation of equipment copy
Validation of equipment   copyValidation of equipment   copy
Validation of equipment copysneha chavan
 
Validation Theory And Application 3
Validation   Theory And Application 3Validation   Theory And Application 3
Validation Theory And Application 3antoi alvarez
 
EQUIPMENT VALIDATION
EQUIPMENT VALIDATIONEQUIPMENT VALIDATION
EQUIPMENT VALIDATIONSagar Savale
 
Validation profile sahil
Validation profile sahilValidation profile sahil
Validation profile sahilsahilhusen
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Malla Reddy College of Pharmacy
 
QUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTSQUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTSANKUSH JADHAV
 
Validation of equipments
Validation of equipmentsValidation of equipments
Validation of equipmentssuhasini
 
Introduction to validation
Introduction to validationIntroduction to validation
Introduction to validationAshvin Bhoge
 

La actualidad más candente (20)

Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validation
 
Process valiadtion
Process valiadtionProcess valiadtion
Process valiadtion
 
Processs validation
Processs validationProcesss validation
Processs validation
 
Validation part 2
Validation part 2Validation part 2
Validation part 2
 
Validation of liquids
Validation of liquidsValidation of liquids
Validation of liquids
 
Introduction to validation
Introduction to validationIntroduction to validation
Introduction to validation
 
Ampule filling and_sealing_machine
Ampule filling and_sealing_machineAmpule filling and_sealing_machine
Ampule filling and_sealing_machine
 
Validation of equipment copy
Validation of equipment   copyValidation of equipment   copy
Validation of equipment copy
 
Validation Theory And Application 3
Validation   Theory And Application 3Validation   Theory And Application 3
Validation Theory And Application 3
 
EQUIPMENT VALIDATION
EQUIPMENT VALIDATIONEQUIPMENT VALIDATION
EQUIPMENT VALIDATION
 
Validation profile sahil
Validation profile sahilValidation profile sahil
Validation profile sahil
 
Process validation
Process validationProcess validation
Process validation
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...
 
QUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTSQUALIFICATION OF MANUFACTURING EQUIPMENTS
QUALIFICATION OF MANUFACTURING EQUIPMENTS
 
Validation of equipments
Validation of equipmentsValidation of equipments
Validation of equipments
 
Pharmaceutical validation
Pharmaceutical validation Pharmaceutical validation
Pharmaceutical validation
 
Introduction to validation
Introduction to validationIntroduction to validation
Introduction to validation
 
Equipment validation
Equipment validationEquipment validation
Equipment validation
 
Water system validation
Water system validationWater system validation
Water system validation
 
Pharmaceutical Process validation
Pharmaceutical Process validationPharmaceutical Process validation
Pharmaceutical Process validation
 

Destacado

Process Validation of API
Process Validation of APIProcess Validation of API
Process Validation of APIsrirao3462
 
Concept of URS,DQ,IQ,OQ,PQ
Concept of URS,DQ,IQ,OQ,PQConcept of URS,DQ,IQ,OQ,PQ
Concept of URS,DQ,IQ,OQ,PQdhavalrock24
 
Design and qualification approvals final2011
Design and qualification approvals final2011Design and qualification approvals final2011
Design and qualification approvals final2011wilsoncoffman
 
有肉 - 多肉植物婚禮小物客製規劃
有肉 - 多肉植物婚禮小物客製規劃有肉 - 多肉植物婚禮小物客製規劃
有肉 - 多肉植物婚禮小物客製規劃有肉 Succulent & Gift
 
Top five models of laboratory incubator
Top five models of laboratory incubatorTop five models of laboratory incubator
Top five models of laboratory incubatorMark Smith
 
Biosafety cabinets /medical microbiology Biosafety
Biosafety cabinets /medical microbiology Biosafety Biosafety cabinets /medical microbiology Biosafety
Biosafety cabinets /medical microbiology Biosafety Dr. Motas Elsadig ALHASIEN
 
Miros Design Build Approach 2 26 10
Miros Design Build Approach 2 26 10Miros Design Build Approach 2 26 10
Miros Design Build Approach 2 26 10Walter Miros
 
VALIDATION MASTER PLAN
VALIDATION MASTER PLANVALIDATION MASTER PLAN
VALIDATION MASTER PLANNarendra Edara
 
US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...
US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...
US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...GMP EDUCATION : Not for Profit Organization
 
Biological safety cabinets(bs cs)
Biological safety cabinets(bs cs)Biological safety cabinets(bs cs)
Biological safety cabinets(bs cs)Sudheesh Nair
 
Hvac validation protocol
Hvac validation protocolHvac validation protocol
Hvac validation protocolvivekccpr21
 

Destacado (20)

Validation of sterelization_equipment
Validation of sterelization_equipmentValidation of sterelization_equipment
Validation of sterelization_equipment
 
Process Validation of API
Process Validation of APIProcess Validation of API
Process Validation of API
 
Concept of URS,DQ,IQ,OQ,PQ
Concept of URS,DQ,IQ,OQ,PQConcept of URS,DQ,IQ,OQ,PQ
Concept of URS,DQ,IQ,OQ,PQ
 
Process Validation for Beginners - FDA - EMA Approach
Process Validation for Beginners - FDA - EMA ApproachProcess Validation for Beginners - FDA - EMA Approach
Process Validation for Beginners - FDA - EMA Approach
 
Design and qualification approvals final2011
Design and qualification approvals final2011Design and qualification approvals final2011
Design and qualification approvals final2011
 
有肉 - 多肉植物婚禮小物客製規劃
有肉 - 多肉植物婚禮小物客製規劃有肉 - 多肉植物婚禮小物客製規劃
有肉 - 多肉植物婚禮小物客製規劃
 
Top five models of laboratory incubator
Top five models of laboratory incubatorTop five models of laboratory incubator
Top five models of laboratory incubator
 
Correlation of FDA-EU-PICS-WHO Requirement for Computer System Validation
Correlation  of  FDA-EU-PICS-WHO Requirement for Computer System Validation Correlation  of  FDA-EU-PICS-WHO Requirement for Computer System Validation
Correlation of FDA-EU-PICS-WHO Requirement for Computer System Validation
 
Biosafety cabinets /medical microbiology Biosafety
Biosafety cabinets /medical microbiology Biosafety Biosafety cabinets /medical microbiology Biosafety
Biosafety cabinets /medical microbiology Biosafety
 
Miros Design Build Approach 2 26 10
Miros Design Build Approach 2 26 10Miros Design Build Approach 2 26 10
Miros Design Build Approach 2 26 10
 
Laboratory incubator
Laboratory incubatorLaboratory incubator
Laboratory incubator
 
Validation Master Plan
Validation Master PlanValidation Master Plan
Validation Master Plan
 
VALIDATION MASTER PLAN
VALIDATION MASTER PLANVALIDATION MASTER PLAN
VALIDATION MASTER PLAN
 
New EU Requirements for Qualification & Validation
New EU Requirements for Qualification & ValidationNew EU Requirements for Qualification & Validation
New EU Requirements for Qualification & Validation
 
Design qualification
Design qualificationDesign qualification
Design qualification
 
US FDA Process Validation Stage 3: Continued Process Verification
US FDA Process Validation Stage 3: Continued Process VerificationUS FDA Process Validation Stage 3: Continued Process Verification
US FDA Process Validation Stage 3: Continued Process Verification
 
US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...
US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...
US FDA Process Validation Stage 2 : No. Of Batches Required for Process Perfo...
 
New WHO Guidance on CS Validation
New WHO Guidance on CS ValidationNew WHO Guidance on CS Validation
New WHO Guidance on CS Validation
 
Biological safety cabinets(bs cs)
Biological safety cabinets(bs cs)Biological safety cabinets(bs cs)
Biological safety cabinets(bs cs)
 
Hvac validation protocol
Hvac validation protocolHvac validation protocol
Hvac validation protocol
 

Similar a Validation ppt

Equipment validation of fbd
Equipment validation of fbdEquipment validation of fbd
Equipment validation of fbdpriyanka odela
 
Qualification of Manufacturing Equipments.
Qualification of Manufacturing Equipments. Qualification of Manufacturing Equipments.
Qualification of Manufacturing Equipments. Ashish Hingnekar
 
HVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdfHVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdfBALASUNDARESAN M
 
equipmentsvalidation.pdf
equipmentsvalidation.pdfequipmentsvalidation.pdf
equipmentsvalidation.pdfpshashank0409
 
EQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVENEQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVENSagar Savale
 
Qualification of Autoclave - Dipankar.pptx
Qualification of Autoclave - Dipankar.pptxQualification of Autoclave - Dipankar.pptx
Qualification of Autoclave - Dipankar.pptxGNIPST
 
Qualification of manufacturing equipment.
Qualification of manufacturing equipment.Qualification of manufacturing equipment.
Qualification of manufacturing equipment.KhushbooKunkulol
 
Qualification Of Autoclave
Qualification Of AutoclaveQualification Of Autoclave
Qualification Of Autoclave8669290285
 
Auditing of sterile poduction
Auditing of sterile poductionAuditing of sterile poduction
Auditing of sterile poductionprakhar rai pk
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemPRANJAY PATIL
 
Validation of dry heat sterilization
Validation of dry heat sterilizationValidation of dry heat sterilization
Validation of dry heat sterilizationDeepak Shanbhag
 
Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .Aditi Roy
 
Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)magareasmi
 

Similar a Validation ppt (20)

FBD ppt
FBD pptFBD ppt
FBD ppt
 
Equipment validation of fbd
Equipment validation of fbdEquipment validation of fbd
Equipment validation of fbd
 
Qualification of Manufacturing Equipments.
Qualification of Manufacturing Equipments. Qualification of Manufacturing Equipments.
Qualification of Manufacturing Equipments.
 
HVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdfHVAC Validation (Air Handling Units).pdf
HVAC Validation (Air Handling Units).pdf
 
Validatn of fbd
Validatn of fbdValidatn of fbd
Validatn of fbd
 
equipmentsvalidation.pdf
equipmentsvalidation.pdfequipmentsvalidation.pdf
equipmentsvalidation.pdf
 
Autoclave validation maliba
Autoclave validation malibaAutoclave validation maliba
Autoclave validation maliba
 
EQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVENEQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVEN
 
Qualification of Autoclave - Dipankar.pptx
Qualification of Autoclave - Dipankar.pptxQualification of Autoclave - Dipankar.pptx
Qualification of Autoclave - Dipankar.pptx
 
Validation of hvac system
Validation of hvac systemValidation of hvac system
Validation of hvac system
 
Qualification of manufacturing equipment.
Qualification of manufacturing equipment.Qualification of manufacturing equipment.
Qualification of manufacturing equipment.
 
instrument validation
instrument validationinstrument validation
instrument validation
 
Qualification Of Autoclave
Qualification Of AutoclaveQualification Of Autoclave
Qualification Of Autoclave
 
Auditing of sterile poduction
Auditing of sterile poductionAuditing of sterile poduction
Auditing of sterile poduction
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Fbd(Fluidized Bed Dryer)
Fbd(Fluidized Bed Dryer)Fbd(Fluidized Bed Dryer)
Fbd(Fluidized Bed Dryer)
 
Validation of dry heat sterilization
Validation of dry heat sterilizationValidation of dry heat sterilization
Validation of dry heat sterilization
 
Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .Validation of dry_powder_mixer_ .
Validation of dry_powder_mixer_ .
 
Manufacturing facility of parentarals as per schedule m
Manufacturing facility of parentarals as per schedule mManufacturing facility of parentarals as per schedule m
Manufacturing facility of parentarals as per schedule m
 
Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)
 

Último

TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 

Último (20)

TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 

Validation ppt

  • 1.
  • 2. CONTENTS  Introduction.  Construction of Fluidized Bed Dryer (FBD).  Working of FBD.  Validation of FBD.  Validation protocol .  Design Qualification (DQ).  Installation Qualification (IQ).  Operational Qualification (OQ).  Performance Qualification (PQ).  Conclusion.  References. 2
  • 3.  Fluid bed drying is most widely used technique for drying Pharmaceutical powders , granules and slurries  Fluid bed processing involves drying, mixing, granulation, and coating of particulate materials.  In fluid bed drying, heat is supplied by the fluidization gas, but the gas flow need not be the only source. Heat may be effectively introduced by heating surfaces (panels or tubes) immersed in the fluidized layer. 3
  • 4. contd…  The direct contact between particles and air/gas is possible in fluid bed system.  Fluid bed drying is suited for powders, granules, agglomerates, and pellets with an average particle size normally between 50 to 5,000 microns. Very fine, light powders or highly elongated particles may require vibration for successful fluid bed drying.  Materials with moisture content up to 80% such as some polymers, dye stuffs and molecular sieve catalysts can also be accommodated. 4
  • 5.  Fluidized bed dryer requires less time to complete drying. i.e., 20 to 40 min.  Hot spots are not observed in the dryer, because of its excellent mixing and drying capacities.  The thermal efficiency is 2 to 6 times greater than tray dryer.  It facilitates the drying of thermolabile substances , since the contact time for drying is short. 5
  • 6.  The dryer is made up of stainless steel or plastic.  It consist of a hollow vertical chamber where dry, heated air enters through the bottom of the chamber and exhaust air exits through the top of the chamber.  A detachable bowl is placed at the bottom of the dryer, which is used for charging and discharging of material. 6
  • 7.  The bowl has a perforated bottom with a wire mesh support for placing materials to be dried and to diffuse the upward flowing air which helps to create a stable and uniform fluidized bed.  A fan is mounted in the upper part for circulating hot air.  Fresh air inlet, pre-filter and heat exchanger are connected serially to heat the air to the required temperature.  Bag filters are placed above the drying bowl for the recovery of fines. 7
  • 8. 8
  • 9.  The main principle involved in fluidized bed dryer is “Fluidization”.  In this state the granules are completely suspended in a stream of hot air which is being supplied from the bottom of the container.  Fluidization produces full agitation of solid particles and since each particle gets surrounded by hot air, heat transfer is extremely high and uniform. 9
  • 10.  The product is dried fast without appreciable loss of heat. Filter bags prevent particles escaping from the dryer.  The material is left for some time in the dryer for reaching ambient temperature.  The end product is free flowing.  Warning:- The FBD is not an explosion proof instrument and therefore samples having volatile compounds that are flammable or able to reach their flash point should not be used with this dryer. 10
  • 11. Drying of granules in FBD 11
  • 12. 12 Fixed parameters:  Porosity of filter bags,  Bowl sieve. Variable ( to be monitored):  Inlet/exhaust air temperature,  Product temperature,  Drying time,  Air volume,  Humidity of incoming air and exhaust air.
  • 13. VALIDATION “ Establishing documented evidence that provides a high degree of assurance that a specific process will consistently produce a product meeting its predetermined specifications and quality attributes.” Validation applies to processes or analytical methods. 12
  • 14.  Validation provides an approach to prove quality, functionality and performance of a pharmaceutical/biotechnological manufacturing process.  This approach can be applied to individual pieces of equipment as well as the manufacturing process as a whole. 14
  • 15. QUALIFICATION “Qualification is a process of assurance that the specific system, premises or equipment are able to achieve the predetermined acceptance criteria to confirm the attributes what it purports to do.’’ Qualification applies to equipment. 15
  • 16. Equipment Qualification: Studies which establish with confidence that the process equipment and ancillary systems are capable of consistently operating within established limits and tolerances. The studies must include equipment specifications, installation qualification (IQ), operational qualification (OQ) and performance qualification all major equipment to be used in the manufacture of commercial scale batches. Equipment qualification should simulate actual production conditions, including "worst case"/ stressed conditions. Worst Case Condition: The highest and /or lowest value of a given parameter actually evaluated in the validation exercise. 16
  • 17. • A Validation Protocol is an approved document which outlines the program to be employed, the tests that will be made and the acceptance criteria for those tests. Validation Phases:  DQ- Design Qualification  IQ- Installation Qualification  OQ-Operational Qualification  PQ- Performance Qualification
  • 18. DESIGN QUALIFICATION  Documented verification that the proposed design of equipment/systems is suitable for the intended purpose.  Requirements are best created before “shopping” is undertaken.  Requirements are created by the needs of the system/process of which the equipment/system will be a part. 18
  • 19. INSTALLATION QUALIFICATION  “Assurance that the intended equipment is received as designed and specified”.  Verifying proper installation of utilities; water, steam, electrical, compressed air, ventilation, etc.  Instruments for measuring temperature, humidity, time, air volume , pressure as well as recording devices for these variables should be calibrated. 19
  • 20. OPERATIONAL QUALIFICATION  The documented evidence that the system or equipment performs as intended throughout all anticipated operating ranges.  “Confirmation that the equipment functions as specified and operates correctly”.  Verifies correct operation of critical components and operating ranges as defined by the specification and required performance.  Operational Tests: Empty Chamber Mapping 20
  • 21. PERFORMANCE QUALIFICATION  The documented evidence that the system, equipment or process is capable of consistently producing a safe product of high quality.  Tests to demonstrate that the equipment/system performs in an actual as-used scenario. › Heat Distribution Studies › Heat Penetration Studies 21
  • 22.  Design qualification is the documentation of the planning phase, including the decision making for the equipment.  The goal is to perform something similar to a risk analysis and to check the design documents of a technical system to ensure that it fulfils the user requirements.  Design qualification takes place before the equipment is constructed. The risk analysis is often part of the design qualification. The earlier risks can be recorded and evaluated, the sooner their minimisation can be taken into consideration in the equipment construction phase. 22
  • 23.  In fluidized bed dryer the design of the instrument should be:  Should occupy the small place.  Based on our requirement we can go for horizontal or vertical.  All technical considerations should be kept in mind while doing the design.  Every fluid bed dryer must have explosion relief device of required size 23
  • 24. Installation Qualification for fluidized bed dryer include the following steps:  Verifying the approved purchase order.  Verify model number, serial number.  Ensure that all relevant documentation is received: User manual, Maintenance manual, List of change parts, Electrical drawings. 24
  • 25.  Check the manufacturer and supplier.  Check for any physical damage.  Confirm location and installation requirements per recommendation of manufacturer.  Verify that the utilities required are available.  Dust free area and moisture free air should be provided.  Installation shall be conducted per instructions provided in the manual. 25
  • 26.  Verify alarm control.  Operate the equipment at low, medium, and high speed per operations manual to verify the operating control.  Verify that all switches and push buttons are functioning properly.  Establish procedures for operation, maintenance, and calibration.  Establish training program for relevant staff.  All the electrical fittings in the room must conform to ISI specifications of Flameproof Electrical fittings.  Do the tests for uniform distribution of air. 26
  • 27. Run three batches of each product and analyze for:  Active ingredients homogeneity.  Moisture content.  Particle size distribution.  Percentage fines. Based on this data we can fix drying end points for each process. 27
  • 28. Specially for FBD: i. Air temperature distribution: Using thermocouples. ii. Inlet air installation: a) Delay time for achieving constant air conditions: Using thermocouple and hygrometer. b) Microbiological quality of the inlet air: Using centrifugal air sampler. 28
  • 29. It is check up of what we want actually for that particular process from the equipment. i. Inlet air speed. ii. Quality of air. iii. Uniform distribution of air. iv. Mixing of air with temperature. Run the trial batch during operation and there should not be any change in the: 1. Size, 2. Shape , 3.Surface characteristics of the material which we kept for drying. 29
  • 30.  Validation provides an approach to prove quality, functionality and performance of a pharmaceutical/biotechnological manufacturing process.  Each time before use of the equipment it should be calibrated and maintained and proper precautions should be taken to increase the life span of the equipment. 30
  • 31.  C.V.S. Subrahmanyam et al, page no. 396-398,Pharmaceutical Engineering.  Development Pharmaceutics and Process Validation, CPMP, 1988.  Guidelines on the Validation of Manufacturing Process, WHO, 1996.  Principles of Qualification and Validation in Pharmaceutical Manufacture, PIC, 1996.  www.google.co.in 31
  • 32.  www.pharmainfo.net  www.ikev.org/haber/bozzonejune1.pdf  www.pharmweb.net  en.wikipedia.org/wiki/Validation  www.ikev.org/haber/inspection/.../ Turkey Qualification_Validation.pdf  http://www.qclabequipment.com/Sherwood_Digital___Analo gue.pdf 32
  • 33. 33

Notas del editor

  1. Drying of granules in FBD