Feb. 2013 Champion Corporate Presentation - English
1. Building the Next
Major Iron Ore Mine
in the Labrador Trough
Corporate Presentation
2014
Oct 19th,2013
21 February 2014
| championironmines.com
FSE: P02
CPMNF
2. FORWARD-LOOKING STATEMENTS
Certain information contained herein regarding Champion Iron Mines Ltd., including
management’s assessment of future plans & operations, may constitute forward-looking
statements under applicable securities law & necessarily involve risks, including but not limited
to risks associated with mining exploration, operating costs, production costs, volatility of share
prices, currency fluctuations, imprecision of resource & reserve estimates, environmental risks
& ability to access sufficient capital from internal & external sources.
As a consequence, actual results may differ materially from those anticipated in any forward
looking statements. Plans, intentions or expectations disclosed in any forward-looking
statements or information should not be read as guarantees of future results or events, & will
not necessarily be accurate indications of whether or when or by which such results or events
will be achieved.
Except as required by law, Champion Iron Mines Ltd., expressly disclaims any intention &
undertakes no obligation to update any forward looking statements or information as conditions
change.
The historical mineral resources mentioned are strictly historical in nature & are non-compliant
to National Instrument 43-101 mineral resources & mineral reserves standards, & should
therefore not be relied upon. A qualified person has not done sufficient work to upgrade or
classify the historical mineral resources as current National Instrument NI-43-101 compliant.
2
3. About Champion Iron Mines
Advanced iron ore exploration & development projects located in
Canada’s principal iron ore district, the Labrador Trough
Fermont Holdings (755 km2)
121 projects in the Fermont Iron Ore District
Flagship Consolidated Fire Lake North (“CFLN”) Project
Prefeasibility Study (“PFS”) announced Feb. 7, 2013
5.1 billion tonnes of NI 43-101 compliant Mineral Resource
Estimates of iron ore
910 million tonnes of Measured + Indicated Resources
4,185 million tonnes of Inferred Mineral Resources
100% direct interest; option to buy back 0.5% of the NSR
for C$1.5 million, resulting in a 2.5% NSR overall)
Attikamagen Project (310 km2)
1.7 billion tonnes @ 31.3% FeT & a plan for a 2 Mtpa2 DSO project
Champion retains a 2% NSR in the Attikamagen Project that is owned through
a joint venture between Century Iron Mines and Wuhan3
1. Champion signed a definitive option agreement with Cartier Iron to earn a 65% interest in 7 of its projects (Cluster 3)
2. As reported by Champion Iron’s JV Partner on Mar. 25, 2013 press release
3. As reported in Champion Iron’s October 3, 2013 press release
3
4. Québec’s Next
Major Iron Ore Mine
CFLN Prefeasibility Study
Feb. 7, 2013 PFS indicated an average production
rate of 9.3 Mtpa of iron concentrate for the 20 year
mine life
First 5 year average: 9.8 Mtpa
Net Present Value of $3.3B at a discounted cash flow
rate of 8% with an Internal Rate of Return of 30.9% &
a payback period of 3.4 years
Established Fermont Iron Ore District
Canada produces 47 Mtpa of iron ore concentrate & this
is expected to increase to a total of 200 Mtpa over the
next 10 years if all proposed development projects are
realized
Established rail, power & port infrastructure
- Competitive power rates are available
- Port of Sept-Îles is building a world-class 50 Mtpa
multi-user wharf project for the iron ore industry
which is on schedule & on budget
4
5. Capital Structure
Share Data & Cash Position as of September 30, 2013.
Total Shares – Outstanding
Warrants
Options
137.4
Issued
7,000,000 at $3.00 (expire May 17, 2015) - Fancamp
15,000,000 at $0.25 (expire July 17, 2015) – Baotou
Outstanding
7,000,000
15,000,000
22,000,000
8.34 M @ C$1.00 (avg. exercise price)
Total Shares – Fully Diluted
168.0 M
Outstanding Share Market
Capitalization
(based on $0.25 share price)
C$34M
Cash & Receivables
C$15M
Management / Insiders Ownership
~ 26.7%
Analyst Coverage
5
6. Board of Directors
Over 200 years of combined exploration & mine operations experience
B OARD
OF
D IRECTORS
Tom Larsen*
Donald A. Sheldon, LLB., P.Eng.*
Alexander Horvath, P.Eng.*
William Harding
Francis Sauvé
Harry Burgess, P.Eng.
Paul Ankcorn
James Wang
PRESIDENT
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR
DIRECTOR
M AN AGEM E NT T E AM
Tom Larsen
Miles Nagamatsu
Alexander Horvath, P.Eng.
Martin Bourgoin, P.Geo.
Beat Frei
Jeff Hussey, P.Geo.
Jean-Luc Chouinard, P.Eng., M.Sc.
Bruce Mitton, P.Geo.
Jorge Estepa
PRESIDENT & CEO
CHIEF FINANCIAL OFFICER
EXECUTIVE VICE PRESIDENT, EXPLORATION & PROJECT DEVELOPMENT
EXECUTIVE VICE PRESIDENT, OPERATIONS
SENIOR VICE PRESIDENT, PROJECT FINANCE
SENIOR VICE PRESIDENT, CORPORATE COMMUNICATIONS
VICE PRESIDENT, PROJECT DEVELOPMENT
VICE PRESIDENT, EXPLORATION
VICE PRESIDENT, SECRETARY & TREASURER
CORPORATE ADVISORS
Doug Bache; Jérome Cliche
6
7. Why invest in Champion Iron Mines?
Favourable Operating
Environment
October 7th 2013, Government
announce a pre-feasibity study for a
new multi-users rail – accessible to
all
The forecast for Iron ore prices over
the mid to long term remain positive
Favourable tax environment
(40% tax rebate on exploration
expenditures)
Champion Iron Mines
Competitive Advantage
Fermont Holdings: 12 iron ore brownfield
projects (755 km2)
CFLN Prefeasibility Study of coarse
grained specular hematite surficial
deposits
Easier to liberate
Deleterious elements in
concentrate are well below
industry specifications limits
Access to low-cost power & close to
rail & port infrastructure
Team with experience in mine start-ups
including construction and commissioning
Québec is a very stable jurisdiction to
develop & operate mines
Upside potential for short, mid, & long term
growth is high with 5.1 billion tonnes of
iron ore resources
Skilled labor work force in Québec
Environmental: Iron ore beneficiation
includes crushing & grinding to
liberate the iron; followed by gravity
& magnetic separation of iron ore
from gangue minerals rather than the
use of reagents
Several de-risking initiatives underway
including a multi-user rail solution,
Environmental & Social Impact Study that
is near completion & permit applications
underway
Closest t project development to the St.
Lawrence Seaway & electrical power
infrastructure
7
8. Global Mineral Resources
NI 43-101 Compliant Mineral Resource Estimates
Consolidated Fire Lake North Mineral Resource Estimates @ 15% FeT cut-off
Deposit
FLN - West*
FLN - East*
FLN - Don Lake
Bellechasse
Oil Can - Oxide
Oil Can - Mixed
Total
*Total Resource under Prefeasibility Study
Total Resource Tonnes (millions)
Measured
tonnes
(millions)
24
3
0
Grade
FeT%
35.4
34.2
21.4
Indicated
tonnes
(millions)
405
262
52
Grade
FeT%
32.6
29.6
26.5
-
-
-
-
27
1,215
35.0
719
31.0
Inferred
tonnes
(millions)
329
192
188
215
972
924
2,821
Grade
FeT%
30.9
28.7
25.3
28.7
33.2
24.1
28.8
3,567
Other Fermont Holdings Mineral Resource Estimates @ 15% FeT cut-off
Harvey-Tuttle
Moire Lake
Other Fermont Projects Total Resources Tonnes
(millions)
Total Fermont Holdings Mineral Resources Tonnes
(millions)
164
27
35.0
30.5
947
417
883
30.9
4,185
23.2
29.4
27.6
5,095
3.567 billion tonnes, out of the 5.1 billion tonnes of global resources, are within the confines of the
CFLN Project; the resource base has the potential to produce up to 35-40 Mtpa of iron concentrate;
that could support an independent rail solution, if necessary. Oil Can has the potential for 16-20 Mtpa.
8
9. Existing Rail Infrastructure
REGIONAL LOCATION MAP &
INFRASTRUCTURE
Québec North Shore & Labrador Railway
(“QNS&L”):
CFLN PEA Base Case connection to Bloom
Lake railway required 62 km of rail + 32 km of
loops and sidings including 14 km for the CFA1
railway for a total of 94 km of rail
New option under study: multi-user railway
QNS&L links to Sept-Îles & Pointe Noire
Bloom Lake & QNS&L railways are considered
common carriers
Common carriers allocate capacity on a firstcome, first-serve basis
Cartier Railway:
Privately owned by ArcelorMittal
Chemin de Fer Arnaud
Transports ore from ArcelorMittal’s Fire Lake
Mine northward to Mt. Wright concentrator
1
Links Mont Wright to Port-Cartier (Max 30Mtpa)
Within CFLN Project boundary
9
10. World Class Port of Sept-Îles Infrastructure
Expanding to Meet Demand
Pointe Noire Multi-Users Wharf
Completion Mar. 31, 2014; 18 months prior
to “CFLN" startup
Federal Government announced $55M
funding or 25% of project
Phase 1: 50 Mtpa for $220M
Phase 2: Planning for 100 Mtpa
Port of Sept-Iles
Sept-Iles
Pointe Noire
Port of Sept-Îles
Port of Sept-Iles
RTZ-IOC shipping facility
Port-Cartier
Pointe Noire
ArcelorMittal shipping facility
$2.1B expansion is underway & will include
concentrator expansion with port & rail
infrastructure upgrades
China Max ship capacity 300kt
Located 62 km west of Sept-Îles
Courtesy of the Port de Sept Îles
10
13. Consolidated Fire Lake North Project
Prefeasibility Study – February 2013
Key Results
Pre-Tax Basis
Internal Rate of Return (IRR) (8% Discount Rate) 1
30.9%
Undiscounted Cash Flow
$9.0B
Net Present Value @ 5% Discounted Cash Flow
$4.7B
Net Present Value @ 8% Discounted Cash Flow
$3.3B
Net Present Value @ 10% Discounted Cash Flow
$2.6B
Payback Period (8% Discount Rate)
3.4 Years
Pre-production Capital Expenditures:
Direct Operating Costs2
US$1,607.9M* (Fire Lake North & Pointe Noire)*
US$34.58 per tonne (average 20 years);
US$27.99 per tonne (average years 1 to 5)
Iron Ore Spot Price Assumptions3
US$115 per tonne of concentrate at 62% Fe (years 1 -5)
US$110 per tonne of concentrate at 62% Fe (years 6-20)
Mine-Life
19.6 years
Exchange Rate
$1.00 USD to $1.00 CDN
Overall Stripping Ratio
2.74:1 for the current 20 year mine-life
1.56:1 (years 1-3 of production); 2.02:1 (years 1-5 of operation)
Mineral Resource Estimate (MRE)
East & West Pits
Measured & Indicated Resources 693.5 Mt grading 31.5% FeT (NI43-101)
Inferred Resources 521.6 Mt grading 30.1% FeT @ 15% FeT cut-off (NI43-101)
Proven & Probable Reserves
464.6 million tonnes grading 32.4% Fe at a 15% cut-off grade;
1. This includes railway capital repayment and interest
2. Direct operating costs excludes railway capital repayment & interest
3. Iron ore spot price assumption does not take into account that Champion will be producing a 66% FeTconcentrate and can command a $2-5 premium
per percentage above 62% FeT, for each tonne of ore.
13
* includes $213.4M for multi-user rail
14. Consolidated Fire Lake North Project
Prefeasibility Study – Feb. 2013
OPERATING EXPENDITURES (US$/TONNE OF CONCENTRATE)
COST PARAMETERS
AVERAGE 20 YEARS
AVERAGE YEARS 1 to 5
Mining
18.89
12.76
Concentrating, crushing & processing
4.38
3.89
Site infrastructure, sales & general administration
4.05
3.66
Environmental tailings & management
0.13
0.12
Rail transport including lease for rolling stock
4.80
5.42
Port facilities
2.34
2.14
34.58
27.99
Railway capital repayment ($1,133.6M)
6.22
7.40
Railway interest payment ($592.6M)
3.25
7.29
44.05
42.68
Total Direct Operating Cost
Total Operating Cost
PRE-PRODUCTION CAPITAL EXPENDITURES (US$ MILLIONS)
Fire Lake North & Pointe Noire
Total Capital
in
$ MILLIONS
Direct Costs
COST AREA
Indirect Costs
Railway
Mining
687.7
Pointe Noire
106.5
Project Indirect Costs
140.5
Contingency
200.0
Rolling Stock Leasing
13.4
53.2
Engineering, Procurement, Construction & Mgmt. (EPCM)
Railway
158.2
Owner’s Cost
Total Capital in
$ MILLIONS
133.7
Concentrator & FLN Site Infrastructure
COST AREA
114.6
Sub-total
1,394.4
Grand Total (100% of the project)
Sub-total
1,607.9
213.4
14
15. Consolidated Fire Lake North
Project Schedule
2011
2012
2013
2014
2015
2016
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CFLN Definition Drilling
Scoping Study
Updated PEA
Metallurgical Results - CFLN, Moire
Lake, Oil Can
Pre-Feasibility Study
Environmental and Social Impact
Assessment (ongoing)
Community Consultation
Oil Can Definition Drilling Planned
Feasibility Study
Permitting
Construction
Production
Legend:
Critical point: Project Schedule will be revised and updated once the feasibility study of the railway solution is confirmed
Completed milestones
16. Consolidated Fire Lake North Project
Growth Through Development
Prefeasibility Study results released Feb. 7, 2013
Feasibility Study with 20 Mtpa production rate
scope underway
West Pit
Area
East Pit
Area
West (3500m) & East (2400m) Pits are both
synformal fold closures that are open at depth
Don Lake
Area
Mineral Resource Estimate (MRE) announced on
Jan. 9, 2013 (COG 15% FeT):
Measured & Indicated Resources
693.5 M tonnes grading 31.5% total iron (FeT)
Inferred Resources
521.6 M tonnes grading 30.1% total iron (FeT)
Several de-risking initiatives are underway
See www.championironmines.com for reports maps & assays
16
17. Consolidated Fire Lake North Metallurgy
Press Release, August 1, 2012
High quality sinter concentrate with very low deleterious elemental content
Weight recovery @ 39.9%; no magnetic separation required
Liberates at 850 micron (-20 mesh) & produces a 65-66% iron concentrate
Assuming a concentrate with 66% Fe ; No magnetic separation circuit required
Alumina is 0.52% versus industry standard of 2%
Silica content is < 5%
Al2O3 : SiO2 ratio of 0.14 versus the upper industry specification limit of 1
This very low alumina to silica ratio is an ideal blending product for steel mills
High Grade, Coarse Specular Hematite
Quartz Specular Hematite
17
18. Consolidated Fire Lake North Project
Economic Projections based on PFS Metrics
Assumptions: 1Projections of an expansion plan at CFLN for a second concentrator production line
are listed in the table below. This projection of an 18-20 Mtpa production rate of iron concentrate is
not NI 43-101 compliant but rather an estimation of mid term potential:
IRR = 34.7%
NPV (M$)
Payback (yrs)
0%
$18,441 M
3.9
5%
$9,400 M
4.1
8%
$6,465 M
4.32
10%
$5,081 M
4.4
Discount Rate
2Payback
period at an 8% discounted rate is estimated from the production start of the 1st
concentrator production line, the payback for the 2nd production line is 1.9 years after it starts based
on the additional CAPEX for the 2nd line of US$587M including indirect (mine and concentrator)
costs, railway capital repayment and interest.
Feasibility Study Objectives:
•
•
•
•
Potential to integrate a Multi-Users rail solution
Reduce CFLN sustaining capital in the economic model.
Continue metallurgical test work with the objective of eliminating the second AG mill ($100 million sustaining capital) in year.
Continue negotiations with Hydro-Québec to find ways to reduce the $217.5 million participation in sustaining capital for the
construction of a new 315 kV power line.
• Review iron ore deposits at both CFLN & Oil Can to increase Measured & Indicated Resources and reduce the overall strip ratio.
18
21. Oil Can Project
Initial Mineral Resource Estimate
Potential for low strip ratio < 1–1.5
972 Mt of iron oxide grading 33.2% at a
15% iron cut-off
924 Mt of mixed iron oxide-silicate
mineralization
This deposit is open at depth
Orientation metallurgical tests indicate
a relatively coarse liberation grind size
Commercial grade magnetite sinter feed
concentrate can be produced
2011 drill program returned long
magnetite-hematite
iron
formation
intersections up to 545 metres in length
Inferred Resources drilled on 400 metre
sections is completed
To view a larger more detailed version of this map please visit:
http://www.championironmines.com/vns-site/page-oil_can.html
21
22. Moiré Lake Project
Initial Mineral Resource Estimate: March 29, 2012
Mineral Resource Estimate:
Arcelor Mittal Property Boundary
Indicated Resources:
164 M tonnes grading 30.5% FeT
Inferred Resources:
417 M tonnes grading 29.4% FeT
DDH LM11-12: 503 M @ 31% FeT
A’
Kilometric synform with hematite &
magnetite outcrops at surface
Adjacent to ArcelorMittal Mont-Wright mine
A
500
meters
22
23. Moiré Lake Project
Infrastructure: Adjacent to Bloom Lake Railway (8km), road, & power
442 Mt @ 30.1% FeT;
Zone B: 285 Mt @ 30.1% FeT
500
meters
23
24. Oil Can Project
Exploration Upside
South & East Zones
Section 9800N (Facing North)
South Zone
OC11-05
OC11-07
East Zone
OC11-08
OC11-02
OC11-19
OC11-01
Ovb
IF
OC11-07
OC11-019
IF
197.2m @ 26.8%
incl. 145.5 @
28.1%
163.1m @
30.5%
OC11-01
190.9m @
30.6%
OC11-05
303.4m @ 34.7%
incl. 130.8m @
36.5%
OC11-02
401.5m @ 30.7%
incl. 213.5 @
33.1%
OC11-08
545.7m @ 33.7%
incl. 442.3 @
36.4%
200 metres
24
30. Global Steel Production Shows
Continued Demand for Iron Ore
1,600,000
China’s CAGR* is 9.88% over
the last 30 years vs. 2.30% for
total global steel production
over the same period.
1,400,000
Kilotonnes
1,200,000
1,000,000
China
800,000
Japan
600,000
Rest of the
World
400,000
200,000
1980
1985
Source: World Steel Association website
* CAGR: Compound Annual Growth Rate
1990
1995
2000
2005
2010
30
31. Labrador Trough Annual Production
Iron Ore Production Upside
Current Annual
Production
Future
Annual Forecast
IOC/RTZ
17 Mtpa + 6 Mtpa
23 Mtpa
ArcelorMittal
16 Mtpa + 8 Mtpa
24 Mtpa
Cliffs Natural Resources (Wuhan)
12 Mtpa + 8 Mtpa
20 Mtpa
2 Mtpa1
5 Mtpa1
0
50 Mtpa2
Company
Labrador Iron Mines
Adriana Resources (Wuhan)
New Millennium (Tata)
0
4 Mtpa1
24 Mtpa2
2 Mtpa1
Century Iron Mines (Wuhan)
0
Champion Iron Mines Limited
0
~20 Mtpa
Alderon Iron Ore Corp.
0
~16 Mtpa
47 + 22 Mtpa
~208 Mtpa
Total Current & Forecasted Production
1.
2.
Direct shipping ore
Taconite fine grained iron ore
20 Mtpa2
31
32. Fermont Iron Ore District
(“FIOD”)
Historically, before 2003, the Fermont &
Labrador mining camps produced 33 Mtpa.
RTZ/IOC = 17 Mtpa; increased now to 24
ArcelorMittal = 13 Mtpa; increased now to 24
Wabush = 3-4 Mtpa
Price
“ Marginal Era”:
For 30-40 years pre-2003
the price per tonne of concentrate
was $15- $30/tonne for 62% Fe,
costs per tonne were similar.
Current 3 year moving average is
$115/tonne (62% Fe)
Current Spot Price Average
~$130-135/tonne (Oct. 2013)
(62% Fe)
32
34. Advanced Exploration
Bellechasse Deposit
Harvey Tuttle Project
Deposit located within CFLN
NI 43-101 Resource Estimate: Inferred Resources
estimate; 215 Mt @ 29% Fe; potential for more
Magnetite rich iron formation
Adjacent to Hwy 389
Synform geometry is favorable for open pit mining
NI 43-101 Inferred Resource Estimate:
717 Mt @ 25% Fe; magnetite rich iron formation
Intersected multiple significant iron formation
intervals in 2010 drill program
Total of 13,165 m of drilling completed
Less than 50% of the kilometric scale magnetic
anomalies have been tested
25 km W-NW of CFLN
Within conveying distance from CFLN planned
concentrator (20-30 km)
34
Notas del editor
Added bullets at910 MT of Measured + Indicated 4,185 MT of Inferred Mineral Resources – changedMtpy for Mtpa on all document – August 30th
RemovePreliminary and changedit to Prefeasibility : Oct 3rd
Sept 3rd – removed -2- of August 2ndSept 11th Changed total share – fully diluted at 171,423,333 as per Tom’s requestRemoved Dundee CapitalMoved analysts Changed the date. Changed the Outstanding – the total shares and the issued numbers –Moved the total share part under the options
August 30thAdded last topicFavourable Operating Environment:Environmental: Iron ore beneficiation includes crushing & grinding to liberate the iron; followed by gravity & magnetic separation of iron ore from gangue minerals rather than the use of reagentsSept 3rd, removed 2012 port agreement (5th bullet in second square), removed press release…. Also. Added in Québec on 6th statement of first squareAddedof iron ore resources on 4th bullet of second square
August 30th – As per Alex and Jeff commentsChanged the titlesRemovedProperty on the secondtitle, removed the (S) of resources and addedestimates on both tablesSwitch the Total Resource Under Prefeasibilitywith Total Resource Tonnes (first table)On second table changedtitle of thirdstatement (Fermontproject Total Resources and last one also)Changes 3.6 billion tonnes to 3.567Sept 3rd.:Biggertextat the bottom
August 30thon the CHM proposed Rail route – added a cercle2nd statement added Champion in the front and 310 km longOn cartier Railway sectionChanged the second statement Transports ore fromArcelorMittal’sFire Lake Mine northward to Mt. Wright to concentratorSept: Cercled the proposed railtitle and highlighted the rail path in redChampion’s proposed southern multi-user railway option is 310 km long
September 2013 Removed the red. If highlighted by Tom, leave it like thatRemoved % Weight Recovery = 39.9% added it to slide 17 BUT using 40% (not 40.0 but 40 only)Oct 3r, added :3. Iron ore spot price assumption does not take into account that Champion will be producing a 66% Fet concentrate and can command a $5 premium per tonne of extra percentage above 62% Fet. And changed the 66% to 64% (JLC)
Removed the slash between results and releasedSept 3rd.: Removed strike length (as per Alex comments)Sept 19th Removed preliminary and added Prefeasibility insteadRemoved NEW of 4th statement (New mineral resource…) and East & west PitEDITED Image – Check – Removed LIMB and wrote PIT
Sept 11th; Added weight recovery 40%
Need to update
Need to update
< changed 1:1 for 1 – 1.5
Sept 19Made some space on Indicated and Inferred resources
Changes made sept 2013 with Chrystal
Changes made sept 2013 with Chrystal
Changes made sept 2013 with Chrystal
Check red; might want to change.Check strikethrough might want to deleteSept 3rd: AddedIRR 30.9%; 3.4 year payback period on first bulletCreated a bullet for 5.1 billion tonnes of NI 43-101 compliant resource on second statementAdded CFLN on forth bulletRemoved the statement about the signed agreement with Sept-Iles PortRemoved – Near 5 existing mines on the last statement since it was mentioned on the second one.
China’s 8% + annual GDP growth driving unprecedented demand for Iron Ore China has high cost & low grade iron mines ; Domestic supply decreasing Forecast: By 2015 global seaborne market will grow by 50%Current moving average is $115 vs $46 for CLMIndia: An up & coming force to be reckoned with!!!Canada: “The iron ore concentration process requires water & power, in Canada abundant & inexpensive
Sept 3rd:Addediron ore instead of material on the comment number 2