2. Basic internal process review conducted during FY 12
Identified need to bring in system experts to conduct
formal needs analysis and assessment
RFP 12-092 issued late FY 12 for ERP Consultant –
BerryDunn selected.
Needs Assessment and Gap Analysis completed –
Recommendation to select new system
Requirements identified
RFP 13-078 released June 28, 2013 for ERP system
software and implementation services
3. December 13, 2012 – Initial brief on ERP Project,
Approval of BerryDunn Consultant Contract Phase I&II
March 28, 2013 – BerryDunn presented
Recommendations and Action Plan to Council
April 25, 2013 – Berry Dunn Consultant Contract
Phase III – V approved by Council
Periodic updates included in weekly Council Updates
4. ERP High and Low One-Time Cost Estimates ($)
Vendor Low Estimate High Estimate
Velocity (Lawson ERP Software) $3,367,475 $4,071,223
Tyler Technologies (MUNIS ERP Software) Not Provided $1,859,600
Microsoft (Dynamics AX 2012 ERP Software) $1,505,200 $2,535,840
Oracle (JD Edwards Enterprise One ERP Software) $760,000 $1,130,000
SunGard (ONESolution ERP Software) $645,000 Not Provided
Point Solution High and Low One-Time Cost Estimates ($)
Vendor Low Estimate High Estimate
Advanced Utilities (Utility Billing) $1,101,000 $1,514,000
EnerGov (Permitting and Land Management Suite) $450,000 $645,000
*From BerryDunn 3-28 presentation.
5. Total Estimated Costs by Cost Area
Functional Area Core Financials HR and Payroll
P&DS and
Revenue Utility Billing TOTAL
Software Licensing 500,000 100,000 325,000 155,000 1,080,000
Data Conversion 35,000 25,000 35,000 35,000 130,000
Professional Services 500,000 100,000 325,000 300,000 1,225,000
Training 100,000 30,000 90,000 85,000 305,000
Project Management 250,000 250,000 150,000 150,000 800,000
Project Oversight 130,000 130,000 75,000 75,000 410,000
Expenses (misc) 150,000 100,000 105,000 100,000 455,000
Annual Maintenance 100,000 20,000 70,000 30,000 220,000
4,625,000
10% $ 5,087,500
Staff Time$ 97,500
Total Project$ 5,185,000
6. Required Experience
8-10 yr Project Management experience
Direct and relevant work experience in ERP project
management capacity
B.A./B.S. in Business, Information Systems, Computer Science,
Public Administration, or in a related field with ERP
management experience
Contracted Position
PM Salary
Firm overhead
Misc items (computer, mileage or car allowance, cell phone)
Estimated 2 1/2 – 3 ½ years
7. Bring PM Contract to Council
RFP Evaluations (due Aug 2nd )
Vendor Demos (Oct 14-18, 23-25)
Contract Negotiations
Contract Award (Estimated Dec 13 – Jan 14)
Implementation of Phase I (Core Financials)
9. According to Gartner, nearly 50 percent
of all ERP implementations fail to deliver
even one third of their expected business
benefits
Lack of software fit.
Unrealistic implementation expectations.
Lack of executive buy-in and support.
Propensity to customize software rather than
leverage standard functionality.
Lack of ERP implementation expertise.