3. Project Details
• Identified in 2016 Wastewater Master Plan update
• Parallel line from Lick Creek WWTP to north side of
William D. Fitch
• Route through Lick Creek Park and Pebble Creek Country
Club
• 54-inch and 48-inch PVC pipe
4. Contract Details
• $10,932,672.50
• Thalle Construction Company, Inc.
• 510 days
• Golf course work to occur between November 1, 2019
and February 29, 2020