2. Project scope
design and implementation of a real-time system
running of automotive specific diagnostics services in the car
mobile phone service selection
05.11.2013
2
3. Project resources
Human resources:
SW developer: Cristina Solomon
HW developer: Andrei Rist
Logistics:
Bluetooth module
Microcontroller
Development kit
Android OS based mobile phone
CAN communication based vehicle
05.11.2013
3
4. System block diagram
OBD II
CAN
Android
LM3S8962
Bluetooth
UART
BTM-222
SelfDiagData
SelfDiag
05.11.2013
4
5. Constraints
high cost of development board
low performance of phone
low performance of bluetooth module of the phone (radio
transmission)
time constraints(deadline: 30th of April)
05.11.2013
5
9. Project risks
HW components damage short before project deadline
HW-SW incompatibility
too long acquisition time for HW components
resource unavailability
wrong time, tasks, difficulty estimations
05.11.2013
9
10. Conclusions
A well defined project management plan is mandatory for this
project because of his different parts, tasks and resources
The plan should offer an entirely overview of all stages and
activities, but also the main risks of the project
Microsoft Project is a very good solution in this direction,
because it offers a good overview and the interaction in a time
frame between resources and tasks of this project. Also the
main threats of the project can be observed and solved in time.
05.11.2013
10