3. 3
Upcoming Construction Activities
Activities Area & Impacts Duration
Tentative
Date
Eglinton Avenue East
between Brentcliffe Road and
Leslie Street (see map on
next page)
• Eastbound and westbound
traffic will be rerouted to a
temporary road south of the
construction zone to
accommodate the continued
construction of the Brentcliffe
Portal.
• Traffic will continue to be one
lane in each direction.
• The pedestrian sidewalk will be
available on the south side of
Eglington Avenue East only.
Approx. 6
months
Mid-
November
Celestica Bridge New traffic configuration Approx. 4
months
Mid-
November
4. 4
Brentcliffe Portal – Traffic Change
.
• Road work is underway southeast of the portal to prepare for
upcoming traffic change.
• Upcoming traffic change planned for mid-November 2018
• Traffic will be shifted to the south side of Eglinton Avenue, otherwise
all other traffic movements and lane allowance remain the same.
5. 5
Ongoing Construction Activities
Activities Area & Impacts Duration
Tentative
Date
Celestica Bridge • New traffic configuration to be
implemented mid-November
• Lane reductions between Leslie
Street and Don Mills Road
3-4 months Underway
as of mid-
August
Telecommunications
relocation work in the
Leslie area
• Work is to prepare for future
Sunnybrook Park stop
• Work crews along Eglinton
between east of Brentcliffe Road
and Leslie Street
Ongoing Underway
until late
2018
Watermain relocation
east of Leslie
• Construction zone at north east
corner of Eglinton Ave East and
Leslie Street intersection
Approx. 4
weeks
* Some overnight
works
Underway
as of late
October
2018
Green Wall (retaining
wall) construction at
E.T. Seton Park
• Staircase removed while this
work takes place.
• Access from Eglinton Avenue East
remains temporarily closed
4-5 months Underway
since
August
2018
6. 6
Brentcliffe Portal – Progress
Ongoing activities within the construction zone include:
• Forming, pouring concrete and placing rebar for the north and south
walls and at the west headwall is ongoing
• Duct banks works ongoing inside the tunnel
• Forming and rebar installation on the roof slab is ongoing
Progress at the headwall Duct Bank Works
7. 7
Brentcliffe Portal – Progress
.
Roadway works Headwall Waterproofing
Backfill on top roof
areas
9. 9
Science Centre Station Construction Activities
SOE & Excavation
• Excavation, tie backs and bracing continue in the station box area and east
portal
• Support of existing utilities at pedestrian tunnel, station box and east portal
ongoing until November
• Bulk excavation continues under the decking, at the pedestrian tunnel and at
the west side of the bus terminal
Utilities
• Utility support work is on going
Structural
• Concrete and rebar work underway at main entrance
• Strut installation is ongoing at the Pedestrian Tunnel
• Form and concrete work underway at the bus terminal
• Form work for the electrical/mechanical and condenser pit walls is ongoing
• Rebar installation on the roof slab is in progress
• Formwork installation is complete for the north inner wall
• Footings rebar between the gridline is in progress and the mud slab was poured
10. 10
Current Traffic Configuration at Science Centre Station
The current traffic configuration at Science Centre Station was implemented October
17,2018. This phase is expected to last (4) months.
The north-south crosswalk on the east side of the intersection will be reopen for the
duration of this set up.
11. 11
Science Centre Station - Progress
Strut Installation at the Pedestrian Tunnel
Station box Rebar Installation
14. 14
Upcoming Construction Activities
Activities Area & Impacts Duration
Tentative
Date
Traffic Changes for utilities
works and rehabilitation
of the Wynford Drive
Bridge
• Don Valley Parkway Ramp to
Wynford Drive Bridge
• Existing work zone will shift to
the south side of the bridge
(currently on north side).
Approx. 6
months
As soon as
November
4
Road Reconstruction at
Swift and Credit Union
Drive
Approx. 6
weeks
As soon as
November
10
Traffic change at East Don
River Bridge
Approx. 6
months
As soon as
November
15
Don Valley Parkway West
Intersection - Storm Work
and Road Reconstruction
TBD TBD
Wilson Brooke Culvert:
Watermain, Sanitary and
Storm Sewer Work
• Construction zone will shift to
south side (currently on north
side)
Approx. 4
months
Mid-
December
15. 15
Section 2 At-Grade – Traffic Change
Don Valley Parkway Ramp to Wynford Drive Bridge
16. 16
• The sidewalk on the south side of Eglinton Avenue East between the Don Valley
South Off-Ramp and Wynford Drive will be closed for the duration of the work to
protect the safety of pedestrians.
• The pedestrian staircase on the south side of the Wynford Drive Bridge will also be
closed for the duration of the work.
• Pedestrians will be required to use the Don Mills Intersection, the Don Valley
Parkway East intersection or temporary crossing east of Wynford Drive to cross
Eglington Avenue East.
• The eastbound TTC bus stop located on southwest side of the Wynford Bridge will
be removed for the duration of the work.
Section 2 At-Grade – Wynford Drive Bridge
17. 17
Ongoing Construction Activities
Activities Area & Impacts Duration
Tentative
Date
Wilson Brook Culvert
Work
• Continues East of future Sloane
Stop
• Work zone in place on the
south and north side of
Eglinton in front of 1730
Eglinton Avenue East
Approx. 4
months
Underway
as of mid-
August
2018
Wynford Drive Bridge &
East Don River Bridge
• Bridge rehabilitation works on
the north side of Eglinton,
traffic shifted south
Approx. 3 - 4
months (north
side)
Underway
as of July
2018
Overnight watermain,
storm and sanitary
relocation at Swift Drive
• Lane reductions and turn
restrictions during overnight
work
• North-south crosswalk on the
east side of Eglinton Avenue
East and Swift Drive
intersection will be closed
during works
Approx. 2-3
weeks
Underway
as of late
October
2018