SlideShare una empresa de Scribd logo
1 de 16
Descargar para leer sin conexión
May 5, 2022
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
METROLINX LAND ACKNOWLEDGMENT
2
“Metrolinx acknowledges that it operates on the traditional territory of Indigenous
Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples.
In particular these lands are covered by 20 Treaties, and we have a responsibility
to recognize and value the rights of Indigenous Nations and Peoples and conduct
business in a manner that is built on the foundation of trust, respect and
collaboration.
Metrolinx is committed to building meaningful relationships with Indigenous
Peoples, and to working towards meaningful reconciliation with the original
caretakers of this land. “
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADE UPDATE
4
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Road and Sidewalk Restoration Brentcliffe – Don Mills Ongoing through Spring 2022
Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Resuming Spring 2022
Landscaping along Eglinton Brentcliffe – Kennedy Ongoing through Summer 2022
Watermain Restoration Work Brentcliffe Ongoing until approximately June 3, 2022
Brentcliffe Retaining Wall - Landscape
Restoration Works
North side of Eglinton Ave, east of
Brentcliffe Rd
Ongoing through Summer 2022
Multi-use path construction -
Landscaping works
Serena Gundy Park – West of Leslie St. Ongoing through Summer 2022
• Architectural finishes
• Electrical finishes
Sunnybrook Park Stop Ongoing through Spring 2022
EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through Spring 2022.
• Dynamic Testing began August 24, 2021, and
will last through Spring 2022.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
LESLIE TRAFFIC CONFIGURATION FOR WATERMAIN RESTORATION WORK
6
• The south sidewalk on Eglinton Avenue East between Brentcliffe Road and Leslie Street well be closed
for approximately 5 weeks to facilitate the watermain works taking place by Brentcliffe Road.
• Pedestrians will be directed to the north sidewalk.
• The west crosswalk at Leslie Street will remain closed.
Ongoing until approximately May 13, 2022
WATERMAIN CONNECTION WORK – EGLINTON AVENUE EAST AND BRENTCLIFFE ROAD
7
• Phase One: Eastbound traffic on
Eglinton Ave E reduced to one lane
between Brentcliffe Rd and east of
Glassworks Dr. Approx. 2 weeks
• Phases Two and Three: Traffic on
Eglinton Ave E reduced to one lane in
each direction between Brentcliffe Rd
and Glassworks Dr. Phase Two Approx. 3
weeks, Phase Three Approx. 1 week.
• Phase Four: Brentcliffe Rd closed at
Eglinton Ave E. Westbound traffic on
Eglinton Ave E reduced to one through-
lane and one left-turn lane. Eastbound
traffic on Eglinton Ave E reduced to a
single lane. Approx. 2 weeks
Ongoing until approximately June 3, 2022
• Watermain connection works on Eglinton Avenue East between Brentcliffe Road
and east of Glassworks Drive.
• Will include the installation of a new watermain line and four fire hydrants
• Work between 6:00 a.m. and 11:00 p.m.
CONSTRUCTION PROGRESS PHOTOS
8
LESLIE RETAINING WALL CONSTRUCTION
COMPLETED
WATERMAIN WORK ONGOING
BETWEEN BRENTCLIFFE ROAD AND
GLASSWORS DRIVE
GUARDRAIL INSTALLTION COMPLETED AT
WEST DON RIVER BRIDGE
Science Centre Station
SCIENCE CENTRE STATION UPDATE
10
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Road and Sidewalk Restoration Brentcliffe – Don Mills Ongoing through Spring 2022
Landscaping along Eglinton Brentcliffe – Kennedy Ongoing through Summer 2022
Finishing Activities:
• Ceiling tiling, mechanical, electrical,
and architectural, finishes. Systems
testing and inspections.
Station Box
Ongoing through Spring 2022
Finishing Activities:
• Ceiling tiling, cladding, electrical and
architectural finishes.
Bus Terminal
Ongoing through Spring 2022
Finishing Activities:
• Ceiling tiling, cladding, electrical and
architectural installations
Main Entrance
Ongoing through Spring 2022
SCIENCE CENTRE TRAFFIC CONFIGURATION
11
Ongoing through Spring 2022
CONSTRUCTION PROGRESS PHOTOS
12
SIGN BAND INSTALLATION
COMPLETED AT PLATFORM LEVEL
INSTALLATION OF EXTERIOR
FURNITURE COMPLETED
ESCALATOR 5 AND 6 INSPECTION
COMPLETED
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTION TWO AT-GRADE UPDATE
14
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing
Road and Sidewalk Restoration Brentcliffe – Don Mills Ongoing through Spring 2022
Landscaping along Eglinton Brentcliffe – Kennedy Ongoing through Summer 2022
• Architectural finishes
• Electrical finishes
Aga Khan Park & Museum Stop
Sloane Stop
O’Connor Stop
Ongoing through Spring 2022
CONSTRUCTION PROGRESS PHOTOS
15
SIDEWALK AND DRIVEWAY RESTORATION
COMPLETED AT 1730 EGLINTON AVENUE EAST
INTERLOCKING PAVER INSTALLATIONS
ONGOING ALONG EGLINTON AVENUE EAST
LANDSCAPING ONGOIGN ALONG EGLINTON
AVENUE EAST – DVP RAMPS TO DON MILLS
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf

Más contenido relacionado

Similar a CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf

CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 

Similar a CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf (20)

Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
 
CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022CLC Pharmacy to Kennedy - May 31 2022
CLC Pharmacy to Kennedy - May 31 2022
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Leaside-Laird CLC - July 11, 2022 compressed .pptx
Leaside-Laird CLC - July 11, 2022 compressed .pptxLeaside-Laird CLC - July 11, 2022 compressed .pptx
Leaside-Laird CLC - July 11, 2022 compressed .pptx
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Eglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptx
Eglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptxEglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptx
Eglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 

Más de Crosstown TO

Más de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 

Último

2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
MadhuKothuru
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ScottMeyers35
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
ScottMeyers35
 

Último (20)

2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
 
Lorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final PresentationLorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final Presentation
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Vivek @ Cheap Call Girls In Kamla Nagar | Book 8448380779 Extreme Call Girls ...
Vivek @ Cheap Call Girls In Kamla Nagar | Book 8448380779 Extreme Call Girls ...Vivek @ Cheap Call Girls In Kamla Nagar | Book 8448380779 Extreme Call Girls ...
Vivek @ Cheap Call Girls In Kamla Nagar | Book 8448380779 Extreme Call Girls ...
 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
 
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girlsPakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdfPeace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
 

CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf

  • 1. May 5, 2022 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. METROLINX LAND ACKNOWLEDGMENT 2 “Metrolinx acknowledges that it operates on the traditional territory of Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples. In particular these lands are covered by 20 Treaties, and we have a responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct business in a manner that is built on the foundation of trust, respect and collaboration. Metrolinx is committed to building meaningful relationships with Indigenous Peoples, and to working towards meaningful reconciliation with the original caretakers of this land. “
  • 3. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 4. SECTION ONE AT-GRADE UPDATE 4 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Road and Sidewalk Restoration Brentcliffe – Don Mills Ongoing through Spring 2022 Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Resuming Spring 2022 Landscaping along Eglinton Brentcliffe – Kennedy Ongoing through Summer 2022 Watermain Restoration Work Brentcliffe Ongoing until approximately June 3, 2022 Brentcliffe Retaining Wall - Landscape Restoration Works North side of Eglinton Ave, east of Brentcliffe Rd Ongoing through Summer 2022 Multi-use path construction - Landscaping works Serena Gundy Park – West of Leslie St. Ongoing through Summer 2022 • Architectural finishes • Electrical finishes Sunnybrook Park Stop Ongoing through Spring 2022
  • 5. EAST TESTING & COMMISSIONING 5 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through Spring 2022. • Dynamic Testing began August 24, 2021, and will last through Spring 2022. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 6. LESLIE TRAFFIC CONFIGURATION FOR WATERMAIN RESTORATION WORK 6 • The south sidewalk on Eglinton Avenue East between Brentcliffe Road and Leslie Street well be closed for approximately 5 weeks to facilitate the watermain works taking place by Brentcliffe Road. • Pedestrians will be directed to the north sidewalk. • The west crosswalk at Leslie Street will remain closed. Ongoing until approximately May 13, 2022
  • 7. WATERMAIN CONNECTION WORK – EGLINTON AVENUE EAST AND BRENTCLIFFE ROAD 7 • Phase One: Eastbound traffic on Eglinton Ave E reduced to one lane between Brentcliffe Rd and east of Glassworks Dr. Approx. 2 weeks • Phases Two and Three: Traffic on Eglinton Ave E reduced to one lane in each direction between Brentcliffe Rd and Glassworks Dr. Phase Two Approx. 3 weeks, Phase Three Approx. 1 week. • Phase Four: Brentcliffe Rd closed at Eglinton Ave E. Westbound traffic on Eglinton Ave E reduced to one through- lane and one left-turn lane. Eastbound traffic on Eglinton Ave E reduced to a single lane. Approx. 2 weeks Ongoing until approximately June 3, 2022 • Watermain connection works on Eglinton Avenue East between Brentcliffe Road and east of Glassworks Drive. • Will include the installation of a new watermain line and four fire hydrants • Work between 6:00 a.m. and 11:00 p.m.
  • 8. CONSTRUCTION PROGRESS PHOTOS 8 LESLIE RETAINING WALL CONSTRUCTION COMPLETED WATERMAIN WORK ONGOING BETWEEN BRENTCLIFFE ROAD AND GLASSWORS DRIVE GUARDRAIL INSTALLTION COMPLETED AT WEST DON RIVER BRIDGE
  • 10. SCIENCE CENTRE STATION UPDATE 10 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Road and Sidewalk Restoration Brentcliffe – Don Mills Ongoing through Spring 2022 Landscaping along Eglinton Brentcliffe – Kennedy Ongoing through Summer 2022 Finishing Activities: • Ceiling tiling, mechanical, electrical, and architectural, finishes. Systems testing and inspections. Station Box Ongoing through Spring 2022 Finishing Activities: • Ceiling tiling, cladding, electrical and architectural finishes. Bus Terminal Ongoing through Spring 2022 Finishing Activities: • Ceiling tiling, cladding, electrical and architectural installations Main Entrance Ongoing through Spring 2022
  • 11. SCIENCE CENTRE TRAFFIC CONFIGURATION 11 Ongoing through Spring 2022
  • 12. CONSTRUCTION PROGRESS PHOTOS 12 SIGN BAND INSTALLATION COMPLETED AT PLATFORM LEVEL INSTALLATION OF EXTERIOR FURNITURE COMPLETED ESCALATOR 5 AND 6 INSPECTION COMPLETED
  • 13. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 14. SECTION TWO AT-GRADE UPDATE 14 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing Road and Sidewalk Restoration Brentcliffe – Don Mills Ongoing through Spring 2022 Landscaping along Eglinton Brentcliffe – Kennedy Ongoing through Summer 2022 • Architectural finishes • Electrical finishes Aga Khan Park & Museum Stop Sloane Stop O’Connor Stop Ongoing through Spring 2022
  • 15. CONSTRUCTION PROGRESS PHOTOS 15 SIDEWALK AND DRIVEWAY RESTORATION COMPLETED AT 1730 EGLINTON AVENUE EAST INTERLOCKING PAVER INSTALLATIONS ONGOING ALONG EGLINTON AVENUE EAST LANDSCAPING ONGOIGN ALONG EGLINTON AVENUE EAST – DVP RAMPS TO DON MILLS