3. CONSTRUCTION ACTIVITIES
3
Location Activity Approx. Date & Duration
O’Connor Stop to
Ionview Stop
• Light poles installation (stops) • Completed March
O’Connor Stop
(Victoria Park Ave)
• Shelter finishing activities; platform ramps, walls • Ongoing through April
Pharmacy Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April
Hakimi Lebovic Stop
• Concrete for both east & west planter curbs
• Shelter finishing activities; platform ramps, walls
• Completed March
• Ongoing through April
Golden Mile Stop
(Warden Ave)
• Shelter finishing activities; platform ramps, walls • Ongoing through April
Birchmount Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April
Massey Creek Culvert
• West wing wall construction
• Backfill
• Completed March
• Ongoing through April
Ionview Stop • Shelter finishing activities; platform ramps, walls • Ongoing until April
4. ROSEMOUNT DRIVE AND EGLINTON AVE E
4
Until as early as April 2021
• North side closure for Massey Creek
Construction
• Crews have completed filling old culvert
• Crews have completed the wingwall
construction
• Crews continue with backfilling and minor
paving activities
8. KENNEDY STATION UPDATE
8
Location Activity Approx. Date & Duration
Kennedy Rd and Eglinton Ave E • Pedestrian Change • Ongoing for approx. six months
Kennedy Portal
(west of Kennedy Road)
• Track works • Ongoing through Spring
Kennedy Station Main Entrance
• Conduit installation, plumbing and sheet metal
works, tiling, masonry works
• Elevator & escalator installation
• TPSS & TVS electrical fit up
• Ongoing through 2021
• Ongoing through 2021
• Ongoing until May
Kennedy Station Box
• Concrete works, rebar, and shoring
• Floor tiling
• Ongoing through Spring
• Ongoing through 2021
Kennedy Station GO Entrance and
Platform
• GO entrance precast installation
• Excavation & concrete works
• Retaining wall construction
• Weekend utility work
• Completed March
• Ongoing through June
• Ongoing through Spring
• April 2 - 4
Kennedy Station – East of GO
• Final invert pour; waterproofing
• Concrete & masonry works
• Platform construction, track & drainage
alignment
• Electrical and mechanical works
• Completed March
• Ongoing through Spring
• Ongoing through 2021
• Ongoing through 2021
10. UTILITY CASING CROSSING
10
• Installation of utility casing includes the use
of excavators, front end loaders, rollers,
and tampers
• Crews will be excavating to install the
casing, and then refilling and levelling the
demolition site with fresh granular material
and compaction of the material into the
ground
• Noise and vibration can be expected
April 2-4, 2021
11. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
11
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station have temporarily relocated the west
GO Transit platform
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place for
approximately one year.
August 17, 2020 for approx. one year