SlideShare una empresa de Scribd logo
1 de 13
January 12, 2021
Eglinton Crosstown LRT
Construction Update
Victoria Park Avenue to Kennedy Station
Section Three and Four At-Grade:
O’Connor Stop to Ionview Stop
CONSTRUCTION ACTIVITIES
3
Location Activity Approx. Date & Duration
Section 3 & 4 • All shelters installed • Completed December 2020
O’Connor Stop
(Victoria Park Ave)
• Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
Pharmacy Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
Hakimi Lebovic Stop
• Formwork for guard rail
• Concrete works for stop curbs, pedestrian ramps
• Ongoing through January 2021
• Ongoing until April 2021
Golden Mile Stop
(Warden Ave)
• Formwork for guard rail
• Concrete works for stop curbs, pedestrian ramps
• Ongoing through January 2021
• Ongoing until April 2021
Birchmount Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
Massey Creek Culvert
• Fill old culvert complete
• Build west wing wall
• Complete
• Ongoing until February 2021
Ionview Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
ROSEMOUNT DRIVE AND EGLINTON AVE E
4
Until as early as February 2021
• North side closure for Massey Creek Construction
• Crews will fill the old culvert and then construct the west wing wall
CONSTRUCTION PROGRESS PHOTOS
5
TACTILE PLATES INSTALLED
PHARMACY STOP
REBAR INSTALLATION FOR RAMP & FORMWORK
GOLDEN MILE STOP
CONSTRUCTION PROGRESS PHOTOS
6
SHELTERS INSTALLED
IONVIEW STOP
GUARDRAIL REBAR INSTALLATION
GOLDEN MILE STOP
Kennedy Station
KENNEDY STATION UPDATE
8
Location Activity Approx. Date & Duration
Kennedy Station Main Entrance
• Conduit installation, plumbing and sheet metal
works, tiling, masonry works
• Elevator painting
• Elevator installation and painting
• TPSS & TVS room electrical fit up
• Ongoing through 2021
• Completed
• Ongoing into 2021
• Ongoing through 2021
Kennedy Station – East of GO
• Concrete works
• Electrical and mechanical works
• Wall pour
• Ongoing until early 2021
• Ongoing until late 2021
• Completed
Kennedy Station Concourse Level
• Concrete works, rebar and shoring
• Floor tiling
• Ongoing until as early as May 2021
• Ongoing through 2021
Kennedy Portal (west of Kennedy
Road)
• Railing installation
• Track works
• Ongoing until early 2021
• Ongoing until early 2021
Kennedy Station Go Platform
• Excavation for new east platform
• Structural steel erection
• Ongoing until early 2021
• Ongoing for approximately one month
KENNEDY CURRENT TRAFFIC CONFIGURATION
9
December 2020 for approx. eight months
GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
10
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station have temporarily relocated the west
GO Transit platform
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place for
approximately one year.
August 17, 2020 for approx. one year
CONSTRUCTION PROGRESS PHOTOS
11
GO ENTRANCE
STRUCTURAL STEEL ERECTION
WALL POUR
GO EAST PLATFORM
CONSTRUCTION PROGRESS PHOTOS
12
FLOOR TILING
CONCOURSE LEVEL INVERT AND FOOTING POUR
GO TUNNEL
Eastern Segment 5 works monthly meeting January 2021

Más contenido relacionado

La actualidad más candente

Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Crosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Crosstown TO
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
 
Western works final
Western works final Western works final
Western works final Crosstown TO
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020Crosstown TO
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Crosstown TO
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCrosstown TO
 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Crosstown TO
 
Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Crosstown TO
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Crosstown TO
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)Crosstown TO
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingCrosstown TO
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Crosstown TO
 

La actualidad más candente (20)

Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Western works final
Western works final Western works final
Western works final
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022
 
Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)Cedarvale & Forest Hill Construction Update (November 24, 2021)
Cedarvale & Forest Hill Construction Update (November 24, 2021)
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 

Similar a Eastern Segment 5 works monthly meeting January 2021

CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021Crosstown TO
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Crosstown TO
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House DeckCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Crosstown TO
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Crosstown TO
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 Crosstown TO
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Crosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Crosstown TO
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020 Crosstown TO
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Crosstown TO
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxCrosstown TO
 

Similar a Eastern Segment 5 works monthly meeting January 2021 (20)

CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 

Más de Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

Más de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Último

Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...Hemant Purohit
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...tanu pandey
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escortssonatiwari757
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escortsaditipandeya
 

Último (20)

Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 

Eastern Segment 5 works monthly meeting January 2021

  • 1. January 12, 2021 Eglinton Crosstown LRT Construction Update Victoria Park Avenue to Kennedy Station
  • 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  • 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration Section 3 & 4 • All shelters installed • Completed December 2020 O’Connor Stop (Victoria Park Ave) • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 Pharmacy Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 Hakimi Lebovic Stop • Formwork for guard rail • Concrete works for stop curbs, pedestrian ramps • Ongoing through January 2021 • Ongoing until April 2021 Golden Mile Stop (Warden Ave) • Formwork for guard rail • Concrete works for stop curbs, pedestrian ramps • Ongoing through January 2021 • Ongoing until April 2021 Birchmount Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 Massey Creek Culvert • Fill old culvert complete • Build west wing wall • Complete • Ongoing until February 2021 Ionview Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
  • 4. ROSEMOUNT DRIVE AND EGLINTON AVE E 4 Until as early as February 2021 • North side closure for Massey Creek Construction • Crews will fill the old culvert and then construct the west wing wall
  • 5. CONSTRUCTION PROGRESS PHOTOS 5 TACTILE PLATES INSTALLED PHARMACY STOP REBAR INSTALLATION FOR RAMP & FORMWORK GOLDEN MILE STOP
  • 6. CONSTRUCTION PROGRESS PHOTOS 6 SHELTERS INSTALLED IONVIEW STOP GUARDRAIL REBAR INSTALLATION GOLDEN MILE STOP
  • 8. KENNEDY STATION UPDATE 8 Location Activity Approx. Date & Duration Kennedy Station Main Entrance • Conduit installation, plumbing and sheet metal works, tiling, masonry works • Elevator painting • Elevator installation and painting • TPSS & TVS room electrical fit up • Ongoing through 2021 • Completed • Ongoing into 2021 • Ongoing through 2021 Kennedy Station – East of GO • Concrete works • Electrical and mechanical works • Wall pour • Ongoing until early 2021 • Ongoing until late 2021 • Completed Kennedy Station Concourse Level • Concrete works, rebar and shoring • Floor tiling • Ongoing until as early as May 2021 • Ongoing through 2021 Kennedy Portal (west of Kennedy Road) • Railing installation • Track works • Ongoing until early 2021 • Ongoing until early 2021 Kennedy Station Go Platform • Excavation for new east platform • Structural steel erection • Ongoing until early 2021 • Ongoing for approximately one month
  • 9. KENNEDY CURRENT TRAFFIC CONFIGURATION 9 December 2020 for approx. eight months
  • 10. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR 10 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station have temporarily relocated the west GO Transit platform • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year. August 17, 2020 for approx. one year
  • 11. CONSTRUCTION PROGRESS PHOTOS 11 GO ENTRANCE STRUCTURAL STEEL ERECTION WALL POUR GO EAST PLATFORM
  • 12. CONSTRUCTION PROGRESS PHOTOS 12 FLOOR TILING CONCOURSE LEVEL INVERT AND FOOTING POUR GO TUNNEL