3. CONSTRUCTION ACTIVITIES
3
Location Activity Approx. Date & Duration
Section 3 & 4 • All shelters installed • Completed December 2020
O’Connor Stop
(Victoria Park Ave)
• Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
Pharmacy Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
Hakimi Lebovic Stop
• Formwork for guard rail
• Concrete works for stop curbs, pedestrian ramps
• Ongoing through January 2021
• Ongoing until April 2021
Golden Mile Stop
(Warden Ave)
• Formwork for guard rail
• Concrete works for stop curbs, pedestrian ramps
• Ongoing through January 2021
• Ongoing until April 2021
Birchmount Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
Massey Creek Culvert
• Fill old culvert complete
• Build west wing wall
• Complete
• Ongoing until February 2021
Ionview Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
4. ROSEMOUNT DRIVE AND EGLINTON AVE E
4
Until as early as February 2021
• North side closure for Massey Creek Construction
• Crews will fill the old culvert and then construct the west wing wall
8. KENNEDY STATION UPDATE
8
Location Activity Approx. Date & Duration
Kennedy Station Main Entrance
• Conduit installation, plumbing and sheet metal
works, tiling, masonry works
• Elevator painting
• Elevator installation and painting
• TPSS & TVS room electrical fit up
• Ongoing through 2021
• Completed
• Ongoing into 2021
• Ongoing through 2021
Kennedy Station – East of GO
• Concrete works
• Electrical and mechanical works
• Wall pour
• Ongoing until early 2021
• Ongoing until late 2021
• Completed
Kennedy Station Concourse Level
• Concrete works, rebar and shoring
• Floor tiling
• Ongoing until as early as May 2021
• Ongoing through 2021
Kennedy Portal (west of Kennedy
Road)
• Railing installation
• Track works
• Ongoing until early 2021
• Ongoing until early 2021
Kennedy Station Go Platform
• Excavation for new east platform
• Structural steel erection
• Ongoing until early 2021
• Ongoing for approximately one month
10. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
10
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station have temporarily relocated the west
GO Transit platform
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place for
approximately one year.
August 17, 2020 for approx. one year