SlideShare una empresa de Scribd logo
1 de 86
Descargar para leer sin conexión
Project Execution Plan for High Rise Building
Details how the construction will be executed, monitored and controlled.
YouTube Link https://youtu.be/_gikBOisPH8
DavidHMoloney
17thJuly2016
Brief Description
The purpose of this presentation is to give an understanding of the Methods,
Plant and Sequence to construct a high-rise building.
This presentation can be used to engage Stakeholders and to get the Site Teams
commitment to the programme. Also can be used for Induction Training and as a
way to capture and share knowledge. Can be use to demonstrate entitlement
for delays and additional payment.
Project Execution Plan (PEP) details how a project will be executed, monitored
and controlled. High in Educational Value and easily understood. Recommended
for Continuing Professional Development (CPD)
This Presentation is innovative and has many beneficial uses.
Table of Contents
Floor Construction
Observation Deck on Floor 124
Floor Construction Cycle Time
Floor Construction Cycle timeGeneralItems
Formwork Quantities
Column formwork = ½ set (50%)
Core wall formwork = 1 set (100%)
Slab formwork = 2 sets (200%) Table forms
Formwork types
Columns - Crane handled units
Core Walls - self climbing floor to floor
Slabs Formwork & Falsework – Table forms Crane handled
Cycle Time
7 working days cycle per floor
Programme
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7
Columns Rebar, Shutter
& Pour 50%
Rebar, Shutter &
Pour 50%
Strip shutters
Walls Pour walls Climb up Fix Rebar Fix shutters
Floor Strike & Move
Forms
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Pour slab
100%
Floor Construction Overview
ⓒ David H Moloney
GeneralItems
Floor Construction Formwork Types
Shuttering to ColumnsGeneralItems
Brief Description
Column formwork can be moved with
only one crane lift complete with push-
pull props and concreting platform with
guard rails and ladder – alternatively
moved by hand using transportation
wheels.
QUATTRO system by Peri
Shuttering – Columns
ⓒ David H Moloney
GeneralItems
Shuttering to Core ( Lifts & Stairs)GeneralItems
Brief Description
Automatic climbing formwork system
lifts itself upwards on rails bolted to
the walls using hydraulic jacks
Doka Xclimb 60
ⓒ David H Moloney
GeneralItems
Shuttering to Core ( Lifts & Stairs)
Shuttering Self Climbing for Core
Concrete
Cycle Time 4 Days
Shuttering to Floor Slabs – Table formsGeneralItems
Brief Description
Table forms are preassembled formwork
and false units and are moved
horizontally on wheels or a trolley and
vertically from floor to floor by crane or
by a lift fixed to the outside of the
building
Shuttering to Floor Slabs – Table formsGeneralItems
Leapfrog
table forms
Shuttering – Floor Slabs
ⓒ David H Moloney
GeneralItems
Shuttering – StairsGeneralItems
Shuttering – Stairs
ⓒ David H Moloney
GeneralItems
Dubai High Rise Buildings
ⓒ David H Moloney
Main Equipment
Climbing Tower Cranes
Brief Description
A climbing tower crane lifts itself up using a climbing
attachment with hydraulic jacks that surrounds the mast.
The climbing attachment lifts itself up off the erected mast
and inserts a new mast section.
GeneralItems
Climbing Tower Cranes
Miscellaneous
Climbing Tower Cranes – Tie-in Assembly
Miscellaneous
Concrete Pump – Self ClimbingGeneralItems
Brief Description
The concrete is pumped by a diesel powered, static
concrete pump, through a fixed 125 mm pipeline, to
the folding placing boom. The boom is mounted on
a steel column of up to 20 metres high. The column
is supported by a cross base or a system of floor
frames set into the concrete floors.
With floor frames , the whole column / boom
assembly can climb with the building as the work
progresses.
For placing concrete pumping is faster than using a
crane and skip and is less likely to be adversely
affected by high winds.
Concrete Pump
Miscellaneous
Protection Screen - Self climbingGeneralItems
Brief Description
Protection screens enclose the top floors of a high
rise enabling construction work to be carry out in
great safety, and protected from the weather.
The screen will contain any debris and tools that
would otherwise fall to the surface.
The Protection screen can be moved upwards
hydraulically or using a tower crane.
Ensuring VerticalityGeneralItems
Brief Description
Leave 3 holes in the floor, forming a
right angle. Use a laser plumb bob and a
transparent sheet on the floors above.
"Jump" the laser every 5 or 6 floors.
Platforms, Chutes & LiftsGeneralItems
ⓒ David H Moloney
GeneralItems
Platforms, Chutes & Lifts
General Items
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
GeneralItems
Brief Description
Contractors Site facilities comprise:
Offices, Canteens, Toilets, Drying Rooms,
Stores, Plant Yard, generators and
Workshops.
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
Dewatering
ⓒ David H Moloney
GeneralItems
Site Hoarding examples
ⓒ David H Moloney
GeneralItems
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
GeneralItems
Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Safety & Environmental
Emergency Phone Numbers & Response
Health,Safety&Environment
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE statistics and historical trends
Health,Safety&Environment
Safety Precautions
Health,Safety&Environment
Signs Examples
Health,Safety&Environment
Hazardous Substances Symbols
Health,Safety&Environment
COSHH stands for the
Control of Substances
Hazardous to Health
Shown are the new
hazard symbols
Environmentally Friendly Site Air, Noise, Water & Soil PollutionHealth,Safety&Environment
Segregation of WasteHealth,Safety&Environment
Segregation of waste for proper disposal and
recycling. Less waste goes to landfill and
hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Water Pollution PreventionHealth,Safety&Environment
Existing Underground Utilities
ⓒ David H Moloney
Brief Description
Before digging establish the
location and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Health,Safety&Environment
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Trench - Safety Measures
Health,Safety&Environment
Trench - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Earthworks
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes
Earthworks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
Excavation for Trench with Stepped FacesEarthworks
Excavation for Trench with Battered FacesEarthworks
Concrete
Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
BIM 3D Model Shutter Fibreglass
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
Concrete batching plant comprises -
concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.
Concrete
Concrete Batching Plant
ⓒ David H Moloney
Concrete
Concrete Batching Plant 3Nr.
ⓒ David H Moloney
Concrete
Concrete Batching Plant - Liebherr Betomix Animation
Concrete
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
.
The mixing is computer controlled
and has a dynamic screen display,
showing the process. The material
storage capacity is, to match two
days concrete production.
Concrete
Concrete Batching Plant – Computer Controlled
ⓒ David H Moloney
Concrete
Concrete Mix Proportions per Cu M
Brief Description
.
Details of Mix for C40
1. Concrete Grade C40
2. Cement Type = OPC
3. Slump =125mm
4. Max size aggregate = 20mm
5. Max water / Cementitious ration =0.42
Concrete
Materials Qty Units
Cement 310 Kgs
Fly ash 100 Kgs
Micro-silica 12 Kgs
Washed Sand 670 Kgs
Fine Sand 106 Kgs
10mm Crushed aggregate 400 Kgs
20mm Crushed aggregates 725 Kgs
Water 145 Ltr.
Additive Rheobuild 7.5 Ltr.
Early age strength concrete is
required for quick floor cycle
time
Reinforcement Cutting & Bending Yard
ⓒ David H Moloney
Concrete
Brief Description
Reinforcement in 12 m lengths.
Delivery in 3 ton Bundles
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Concrete
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Vibrating Concrete
ⓒ David H Moloney
Concrete
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Piling
Piling Construction - Plant, Methods & SequencePiling
Piling Construction - Plant & MethodsPiling
Piling Construction - Vertical PilesPiling
Pile Load Test
ⓒ David H Moloney
Piling
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
Pile Load Test
ⓒ David H Moloney
Piling
Progress Monitoring & Administration
Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progress and historical trends
Histogram Charts for Resources & Outputs
Manpower per Discipline
Concrete per Location
Man-hours for each month of the Project
Quantity for each month of the Project
ⓒ David H Moloney
Brief Description
Histograms shows resources etc. for each month of a project.
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Staff Directory
Brief Description
List of staff and their
contact details
Quality Assurance
Quality Assurance Dashboard
Dashboard is a single page, graphical representation of current
statistics and historical trends
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

Más contenido relacionado

La actualidad más candente

THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
SSudhaVelan
 
Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 

La actualidad más candente (20)

Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concrete
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Formwork
FormworkFormwork
Formwork
 
Slipform
SlipformSlipform
Slipform
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Defects in buildings & remedies
Defects in buildings & remediesDefects in buildings & remedies
Defects in buildings & remedies
 
Construction process
Construction processConstruction process
Construction process
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 

Similar a Project Execution Plan for High Rise Building

PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)
Crysmond Goh
 
Site visit report
Site visit reportSite visit report
Site visit report
Doreen Yeo
 
Colt Construction Canopy Cleaning
Colt Construction Canopy CleaningColt Construction Canopy Cleaning
Colt Construction Canopy Cleaning
Aaron Chapman
 
Colt Construction Canopy Cleaning
Colt Construction Canopy CleaningColt Construction Canopy Cleaning
Colt Construction Canopy Cleaning
Ben Urry
 

Similar a Project Execution Plan for High Rise Building (20)

Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction Details
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction Explained
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
 
B.con slide
B.con slideB.con slide
B.con slide
 
B.con slide
B.con slideB.con slide
B.con slide
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)PROJECT 1 (BUILDING CONSTRUCTION 1)
PROJECT 1 (BUILDING CONSTRUCTION 1)
 
Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in Tunnels
 
BUILDING CONSTRUCTION
BUILDING CONSTRUCTION BUILDING CONSTRUCTION
BUILDING CONSTRUCTION
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Colt Construction Canopy Cleaning
Colt Construction Canopy CleaningColt Construction Canopy Cleaning
Colt Construction Canopy Cleaning
 
Colt Construction Canopy Cleaning
Colt Construction Canopy CleaningColt Construction Canopy Cleaning
Colt Construction Canopy Cleaning
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Ez
EzEz
Ez
 

Más de David H Moloney

Más de David H Moloney (15)

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside Construction
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 km
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulage
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 

Último

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Último (20)

Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 

Project Execution Plan for High Rise Building

  • 1. Project Execution Plan for High Rise Building Details how the construction will be executed, monitored and controlled. YouTube Link https://youtu.be/_gikBOisPH8 DavidHMoloney 17thJuly2016 Brief Description The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a high-rise building. This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge. Can be use to demonstrate entitlement for delays and additional payment. Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD) This Presentation is innovative and has many beneficial uses.
  • 5. Floor Construction Cycle timeGeneralItems Formwork Quantities Column formwork = ½ set (50%) Core wall formwork = 1 set (100%) Slab formwork = 2 sets (200%) Table forms Formwork types Columns - Crane handled units Core Walls - self climbing floor to floor Slabs Formwork & Falsework – Table forms Crane handled Cycle Time 7 working days cycle per floor Programme Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Columns Rebar, Shutter & Pour 50% Rebar, Shutter & Pour 50% Strip shutters Walls Pour walls Climb up Fix Rebar Fix shutters Floor Strike & Move Forms Slab Formwork Rebar MEP Slab Formwork Rebar MEP Slab Formwork Rebar MEP Slab Formwork Rebar MEP Pour slab 100%
  • 6. Floor Construction Overview ⓒ David H Moloney GeneralItems
  • 8. Shuttering to ColumnsGeneralItems Brief Description Column formwork can be moved with only one crane lift complete with push- pull props and concreting platform with guard rails and ladder – alternatively moved by hand using transportation wheels. QUATTRO system by Peri
  • 9. Shuttering – Columns ⓒ David H Moloney GeneralItems
  • 10. Shuttering to Core ( Lifts & Stairs)GeneralItems Brief Description Automatic climbing formwork system lifts itself upwards on rails bolted to the walls using hydraulic jacks Doka Xclimb 60
  • 11. ⓒ David H Moloney GeneralItems Shuttering to Core ( Lifts & Stairs)
  • 12. Shuttering Self Climbing for Core Concrete Cycle Time 4 Days
  • 13. Shuttering to Floor Slabs – Table formsGeneralItems Brief Description Table forms are preassembled formwork and false units and are moved horizontally on wheels or a trolley and vertically from floor to floor by crane or by a lift fixed to the outside of the building
  • 14. Shuttering to Floor Slabs – Table formsGeneralItems Leapfrog table forms
  • 15. Shuttering – Floor Slabs ⓒ David H Moloney GeneralItems
  • 17. Shuttering – Stairs ⓒ David H Moloney GeneralItems
  • 18. Dubai High Rise Buildings ⓒ David H Moloney
  • 20. Climbing Tower Cranes Brief Description A climbing tower crane lifts itself up using a climbing attachment with hydraulic jacks that surrounds the mast. The climbing attachment lifts itself up off the erected mast and inserts a new mast section. GeneralItems
  • 22. Climbing Tower Cranes – Tie-in Assembly Miscellaneous
  • 23. Concrete Pump – Self ClimbingGeneralItems Brief Description The concrete is pumped by a diesel powered, static concrete pump, through a fixed 125 mm pipeline, to the folding placing boom. The boom is mounted on a steel column of up to 20 metres high. The column is supported by a cross base or a system of floor frames set into the concrete floors. With floor frames , the whole column / boom assembly can climb with the building as the work progresses. For placing concrete pumping is faster than using a crane and skip and is less likely to be adversely affected by high winds.
  • 25. Protection Screen - Self climbingGeneralItems Brief Description Protection screens enclose the top floors of a high rise enabling construction work to be carry out in great safety, and protected from the weather. The screen will contain any debris and tools that would otherwise fall to the surface. The Protection screen can be moved upwards hydraulically or using a tower crane.
  • 26. Ensuring VerticalityGeneralItems Brief Description Leave 3 holes in the floor, forming a right angle. Use a laser plumb bob and a transparent sheet on the floors above. "Jump" the laser every 5 or 6 floors.
  • 27. Platforms, Chutes & LiftsGeneralItems
  • 28. ⓒ David H Moloney GeneralItems Platforms, Chutes & Lifts
  • 30. Contractor’s Temporary Site Facilities ⓒ David H Moloney GeneralItems Brief Description Contractors Site facilities comprise: Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops.
  • 31. Dewatering ⓒ David H Moloney GeneralItems Brief Description Construction dewatering is the removal or drainage of groundwater and or surface / rain water usually by pumping to keep the works dry.
  • 32. Dewatering ⓒ David H Moloney GeneralItems Brief Description Construction dewatering is the removal or drainage of groundwater and or surface / rain water usually by pumping to keep the works dry.
  • 33. Dewatering ⓒ David H Moloney GeneralItems
  • 34. Site Hoarding examples ⓒ David H Moloney GeneralItems
  • 35. Temporary Electricity Supply & Tower Lights ⓒ David H Moloney GeneralItems
  • 36. Welfare Facilities ⓒ David H Moloney GeneralItems Toilets – Washing Canteen, Drying Room, Toilet & Generator
  • 38. Emergency Phone Numbers & Response Health,Safety&Environment
  • 39. HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of current HSE statistics and historical trends Health,Safety&Environment
  • 42. Hazardous Substances Symbols Health,Safety&Environment COSHH stands for the Control of Substances Hazardous to Health Shown are the new hazard symbols
  • 43. Environmentally Friendly Site Air, Noise, Water & Soil PollutionHealth,Safety&Environment
  • 44. Segregation of WasteHealth,Safety&Environment Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe. Colour Code for Skips & Bins
  • 46. Existing Underground Utilities ⓒ David H Moloney Brief Description Before digging establish the location and route of underground utilities. Locator to find Utilities Spray Paint to mark pavement Health,Safety&Environment
  • 47. Existing Underground Utilities & Overhead Cables - Safety Measures ⓒ David H Moloney Health,Safety&Environment
  • 48. Trench - Safety Measures Health,Safety&Environment
  • 49. Trench - Safety Measures ⓒ David H Moloney Health,Safety&Environment
  • 51. Excavate & Load, Cart, Tip & Return Brief Description Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes Earthworks 7 minutes 14 minutes 3 minutes 14 minutes 7 km 7 km
  • 52. Excavation for Trench with Stepped FacesEarthworks
  • 53. Excavation for Trench with Battered FacesEarthworks
  • 55. Concrete Full Scale Trial Castings of Pier ⓒ David H Moloney Brief Description The full-scale trial casting(s) shall demonstrate/document that all requirements to the concrete and the execution of the work are fulfilled simultaneously using the actual methods and performed by personnel as for the future production. Concrete BIM 3D Model Shutter Fibreglass
  • 56. Concrete Batching Plant David H Moloney ⓒ David H Moloney Brief Description Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. Concrete
  • 57. Concrete Batching Plant ⓒ David H Moloney Concrete
  • 58. Concrete Batching Plant 3Nr. ⓒ David H Moloney Concrete
  • 59. Concrete Batching Plant - Liebherr Betomix Animation Concrete
  • 60. Concrete Batching Plant David H Moloney ⓒ David H Moloney Brief Description . The mixing is computer controlled and has a dynamic screen display, showing the process. The material storage capacity is, to match two days concrete production. Concrete
  • 61. Concrete Batching Plant – Computer Controlled ⓒ David H Moloney Concrete
  • 62. Concrete Mix Proportions per Cu M Brief Description . Details of Mix for C40 1. Concrete Grade C40 2. Cement Type = OPC 3. Slump =125mm 4. Max size aggregate = 20mm 5. Max water / Cementitious ration =0.42 Concrete Materials Qty Units Cement 310 Kgs Fly ash 100 Kgs Micro-silica 12 Kgs Washed Sand 670 Kgs Fine Sand 106 Kgs 10mm Crushed aggregate 400 Kgs 20mm Crushed aggregates 725 Kgs Water 145 Ltr. Additive Rheobuild 7.5 Ltr. Early age strength concrete is required for quick floor cycle time
  • 63. Reinforcement Cutting & Bending Yard ⓒ David H Moloney Concrete Brief Description Reinforcement in 12 m lengths. Delivery in 3 ton Bundles
  • 64. Reinforcement Cutting & Bending ⓒ David H Moloney Concrete
  • 65. Reinforcement Cutting & Bending ⓒ David H Moloney Concrete
  • 66. Reinforcement Cutting & Bending Yard David H Moloney ⓒ David H Moloney Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site Concrete
  • 67. Reinforced Wall Construction Sequence ⓒ David H Moloney Concrete Brief Description The sequence to construct a reinforced concrete wall is as follows: Tie the reinforcement. Erect stop-ends and the wall shutters. Pour and vibrate the concrete mix. Remove the shutters after the concrete has hardened. . Cycle Time Pour per Day
  • 68. Reinforced Wall Construction Sequence ⓒ David H Moloney Concrete
  • 69. Vibrating Concrete ⓒ David H Moloney Concrete
  • 71. Piling Construction - Plant & Methods Brief Description Piling Plant, Equipment and Material; Crawler Crane, Piling Hammer, Temporary Casing, Piling Rig, Concrete Pump, Concrete Mixer Trucks, Tremie Pipe and Reinforcement Cage Piling
  • 72. Piling Construction - Plant, Methods & SequencePiling
  • 73. Piling Construction - Plant & MethodsPiling
  • 74. Piling Construction - Vertical PilesPiling
  • 75. Pile Load Test ⓒ David H Moloney Piling Brief Description A jack is used to load the pile in steps and gauges measure any settlement.
  • 76. Pile Load Test ⓒ David H Moloney Piling
  • 77. Progress Monitoring & Administration
  • 78. Progress Monthly, Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of current progress and historical trends
  • 79. Histogram Charts for Resources & Outputs Manpower per Discipline Concrete per Location Man-hours for each month of the Project Quantity for each month of the Project ⓒ David H Moloney Brief Description Histograms shows resources etc. for each month of a project.
  • 80. Plant & Equipment List & Worker’s Job Titles ⓒ David H Moloney
  • 81. Daily Work Record Brief Description Daily Work Records showing the allocation of resources, materials and work activities carried out daily.
  • 82. Organogram Brief Description Shown are the line and lateral relationships between the various team members and their relative position in the site organisation.
  • 83. Staff Directory Brief Description List of staff and their contact details
  • 85. Quality Assurance Dashboard Dashboard is a single page, graphical representation of current statistics and historical trends
  • 86. Production by David H Moloney My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ