The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a high-rise building.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
Project Execution Plan for High Rise Building
1. Project Execution Plan for High Rise Building
Details how the construction will be executed, monitored and controlled.
YouTube Link https://youtu.be/_gikBOisPH8
DavidHMoloney
17thJuly2016
Brief Description
The purpose of this presentation is to give an understanding of the Methods,
Plant and Sequence to construct a high-rise building.
This presentation can be used to engage Stakeholders and to get the Site Teams
commitment to the programme. Also can be used for Induction Training and as a
way to capture and share knowledge. Can be use to demonstrate entitlement
for delays and additional payment.
Project Execution Plan (PEP) details how a project will be executed, monitored
and controlled. High in Educational Value and easily understood. Recommended
for Continuing Professional Development (CPD)
This Presentation is innovative and has many beneficial uses.
5. Floor Construction Cycle timeGeneralItems
Formwork Quantities
Column formwork = ½ set (50%)
Core wall formwork = 1 set (100%)
Slab formwork = 2 sets (200%) Table forms
Formwork types
Columns - Crane handled units
Core Walls - self climbing floor to floor
Slabs Formwork & Falsework – Table forms Crane handled
Cycle Time
7 working days cycle per floor
Programme
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7
Columns Rebar, Shutter
& Pour 50%
Rebar, Shutter &
Pour 50%
Strip shutters
Walls Pour walls Climb up Fix Rebar Fix shutters
Floor Strike & Move
Forms
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Slab
Formwork
Rebar MEP
Pour slab
100%
8. Shuttering to ColumnsGeneralItems
Brief Description
Column formwork can be moved with
only one crane lift complete with push-
pull props and concreting platform with
guard rails and ladder – alternatively
moved by hand using transportation
wheels.
QUATTRO system by Peri
10. Shuttering to Core ( Lifts & Stairs)GeneralItems
Brief Description
Automatic climbing formwork system
lifts itself upwards on rails bolted to
the walls using hydraulic jacks
Doka Xclimb 60
11. ⓒ David H Moloney
GeneralItems
Shuttering to Core ( Lifts & Stairs)
13. Shuttering to Floor Slabs – Table formsGeneralItems
Brief Description
Table forms are preassembled formwork
and false units and are moved
horizontally on wheels or a trolley and
vertically from floor to floor by crane or
by a lift fixed to the outside of the
building
20. Climbing Tower Cranes
Brief Description
A climbing tower crane lifts itself up using a climbing
attachment with hydraulic jacks that surrounds the mast.
The climbing attachment lifts itself up off the erected mast
and inserts a new mast section.
GeneralItems
23. Concrete Pump – Self ClimbingGeneralItems
Brief Description
The concrete is pumped by a diesel powered, static
concrete pump, through a fixed 125 mm pipeline, to
the folding placing boom. The boom is mounted on
a steel column of up to 20 metres high. The column
is supported by a cross base or a system of floor
frames set into the concrete floors.
With floor frames , the whole column / boom
assembly can climb with the building as the work
progresses.
For placing concrete pumping is faster than using a
crane and skip and is less likely to be adversely
affected by high winds.
25. Protection Screen - Self climbingGeneralItems
Brief Description
Protection screens enclose the top floors of a high
rise enabling construction work to be carry out in
great safety, and protected from the weather.
The screen will contain any debris and tools that
would otherwise fall to the surface.
The Protection screen can be moved upwards
hydraulically or using a tower crane.
30. Contractor’s Temporary Site Facilities
ⓒ David H Moloney
GeneralItems
Brief Description
Contractors Site facilities comprise:
Offices, Canteens, Toilets, Drying Rooms,
Stores, Plant Yard, generators and
Workshops.
31. Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
32. Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
39. HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE statistics and historical trends
Health,Safety&Environment
46. Existing Underground Utilities
ⓒ David H Moloney
Brief Description
Before digging establish the
location and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Health,Safety&Environment
51. Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes
Earthworks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
55. Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
BIM 3D Model Shutter Fibreglass
56. Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
Concrete batching plant comprises -
concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.
Concrete
60. Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
.
The mixing is computer controlled
and has a dynamic screen display,
showing the process. The material
storage capacity is, to match two
days concrete production.
Concrete
66. Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Concrete
67. Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
78. Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progress and historical trends
79. Histogram Charts for Resources & Outputs
Manpower per Discipline
Concrete per Location
Man-hours for each month of the Project
Quantity for each month of the Project
ⓒ David H Moloney
Brief Description
Histograms shows resources etc. for each month of a project.
81. Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
82. Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.