CAPM Exam Study – Session 4
Agenda
• Questions from Asynchronous Content
• Knowledge Areas & Processes
• CPI & SPI
• Critical Path Example
• Q&A
Mapping Knowledge Areas to Domains
Copyright © 2017 Techknowledgy, Inc. All Rights Reserved
CPI and SPI
The cost performance index (CPI) is a measure of the
conformance of the actual work completed (measured by its
earned value) to the actual cost incurred: CPI = EV / AC.
The schedule performance index (SPI) is a measure of the
conformance of actual progress (earned value) to the
planned progress: SPI = EV / PV.
SV = EV – PV
The variation in a project's actual schedule, as compared to its
planned schedule, is measured by its schedule variance (SV),
which measures the difference between the earned value (EV)
(the value of work actually performed) and the planned value
(PV), so SV = EV – PV.
However, SV is expressed as a monetary unit (e.g., in dollars),
which makes it difficult to understand as a variance in the
schedule, which should presumably be measured in time units,
such as days or months.
Cost Performance Index (CPI) is the measure of the cost efficiency of
project. It is expressed as a ratio of earned value to actual cost.
Schedule Performance Index (SPI) is the measure of schedule
efficiency of the project. It is expressed as the ratio of earned value to
planned value.
Example:
A project is going to be completed in 6 months and the budget for the
project is $50,000. After the 3 months it is found that only 40% of the
total work has been done to date and $30,000 has been spent.
Actual Cost = $30,000
Planned Value = 50% of $50,000 = $25,000
Earned Value = 40% of $50,000 = $20,000
Cost Performance Index = Earned Value / Actual Cost
= $20,000 / $30,000 = 0.67
Schedule Performance Index (SPI) = Earned Value / Planned Value
= $20,000 / $25,000 = 0.8
A project is going to be completed in 6 months
and the budget for the project is $50,000. After
the 3 months it is found that only 40% of the
total work has been done to date and $30,000
has been spent.
Actual Cost = $30,000
Planned Value = 50% of $50,000 = $25,000
Earned Value = 40% of $50,000 = $20,000
Cost Performance Index = Earned Value / Actual Cost
= $20,000 / $30,000 = 0.67
Schedule Performance Index (SPI) = Earned Value / Planned Value
= $20,000 / $25,000 = 0.8
A project is going to be completed in 6 months
and the budget for the project is $50,000. After
the 3 months it is found that only 40% of the
total work has been done to date and $30,000
has been spent.
Conclusion: It can be concluded that the project is over budget and behind schedule.
Critical Path
Activities for this project are as below
(output from Define Activities process):
1. Assemble two-tier bridge (10)
2. Join winding tracks (20)
3. Assemble and add train station (5)
4. Place standalone items around (10)
5. Assemble and add construction site (2)
6. Join train engine and bogies (4)
7. Place the train on the track (2)
8. Start the engine and let it chug! (2)
Build a Network Diagram
Build a Network Diagram
Build a Network Diagram
Build a Network Diagram
Build a Network Diagram
The network path with longest total duration is the critical
path!
Critical path is the shortest duration required to complete
the project successfully.
Build a Network Diagram
The network path with longest total duration is the critical
path!
Critical path is the shortest duration required to complete
the project successfully.
In our example this is the second
path: A -> B -> C -> D -> G -> H,
which comes to 49 minutes.
CAPM study session 4

Más contenido relacionado

La actualidad más candente

Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
simu_mihai
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
Nicola2903
 

La actualidad más candente (20)

Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 
Pert+cpm
Pert+cpmPert+cpm
Pert+cpm
 
Project management technique PERT & CPM
Project management technique PERT & CPMProject management technique PERT & CPM
Project management technique PERT & CPM
 
Lesson in fs cpm,cpa
Lesson in fs cpm,cpaLesson in fs cpm,cpa
Lesson in fs cpm,cpa
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
PROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERTPROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERT
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Pert
PertPert
Pert
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)
 
PERT
PERTPERT
PERT
 

Similar a CAPM study session 4

Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..
EngrMuhammadJavidNaw
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
ejlp12
 

Similar a CAPM study session 4 (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Earned value 01
Earned value 01Earned value 01
Earned value 01
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Earned Value
Earned ValueEarned Value
Earned Value
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 

Más de Kinetic Potential

Más de Kinetic Potential (18)

Career Exploration Week 3.pptx
Career Exploration Week 3.pptxCareer Exploration Week 3.pptx
Career Exploration Week 3.pptx
 
Access Control and Maintenance.pptx
Access Control and Maintenance.pptxAccess Control and Maintenance.pptx
Access Control and Maintenance.pptx
 
Quantum Leap Class 3 Slide.pptx
Quantum Leap Class 3 Slide.pptxQuantum Leap Class 3 Slide.pptx
Quantum Leap Class 3 Slide.pptx
 
Quantum Leap Class 2 Slide.pptx
Quantum Leap Class 2 Slide.pptxQuantum Leap Class 2 Slide.pptx
Quantum Leap Class 2 Slide.pptx
 
Quantum Leap Class 1 Slide.pptx
Quantum Leap Class 1 Slide.pptxQuantum Leap Class 1 Slide.pptx
Quantum Leap Class 1 Slide.pptx
 
Cyber Families - Incident Response.pptx
Cyber Families - Incident Response.pptxCyber Families - Incident Response.pptx
Cyber Families - Incident Response.pptx
 
DRHA KPLIFE BOOTCAMP.pptx
DRHA KPLIFE BOOTCAMP.pptxDRHA KPLIFE BOOTCAMP.pptx
DRHA KPLIFE BOOTCAMP.pptx
 
Financial Literacy
Financial LiteracyFinancial Literacy
Financial Literacy
 
Abuse Prevention, Identification and Reporting: Training & Education
Abuse Prevention, Identification and Reporting: Training & EducationAbuse Prevention, Identification and Reporting: Training & Education
Abuse Prevention, Identification and Reporting: Training & Education
 
CAPM Study Session 3
CAPM Study Session 3CAPM Study Session 3
CAPM Study Session 3
 
CAPM Study Session 2
CAPM Study Session 2CAPM Study Session 2
CAPM Study Session 2
 
CAPM Exam Study Session 1
CAPM Exam Study Session 1CAPM Exam Study Session 1
CAPM Exam Study Session 1
 
Lesson 2 making rules
Lesson 2 making rulesLesson 2 making rules
Lesson 2 making rules
 
Nist 800 53 deep dive 20210813
Nist 800 53 deep dive 20210813Nist 800 53 deep dive 20210813
Nist 800 53 deep dive 20210813
 
What is a cybersecurity assessment 20210813
What is a cybersecurity assessment  20210813What is a cybersecurity assessment  20210813
What is a cybersecurity assessment 20210813
 
Intro to cybersecurity concepts 20210813
Intro to cybersecurity concepts 20210813Intro to cybersecurity concepts 20210813
Intro to cybersecurity concepts 20210813
 
Lesson 8 safety
Lesson 8 safetyLesson 8 safety
Lesson 8 safety
 
My career interest
My career interestMy career interest
My career interest
 

Último

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Último (20)

A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 

CAPM study session 4

  • 1. CAPM Exam Study – Session 4 Agenda • Questions from Asynchronous Content • Knowledge Areas & Processes • CPI & SPI • Critical Path Example • Q&A
  • 2. Mapping Knowledge Areas to Domains Copyright © 2017 Techknowledgy, Inc. All Rights Reserved
  • 3. CPI and SPI The cost performance index (CPI) is a measure of the conformance of the actual work completed (measured by its earned value) to the actual cost incurred: CPI = EV / AC. The schedule performance index (SPI) is a measure of the conformance of actual progress (earned value) to the planned progress: SPI = EV / PV.
  • 4. SV = EV – PV The variation in a project's actual schedule, as compared to its planned schedule, is measured by its schedule variance (SV), which measures the difference between the earned value (EV) (the value of work actually performed) and the planned value (PV), so SV = EV – PV. However, SV is expressed as a monetary unit (e.g., in dollars), which makes it difficult to understand as a variance in the schedule, which should presumably be measured in time units, such as days or months.
  • 5. Cost Performance Index (CPI) is the measure of the cost efficiency of project. It is expressed as a ratio of earned value to actual cost. Schedule Performance Index (SPI) is the measure of schedule efficiency of the project. It is expressed as the ratio of earned value to planned value. Example: A project is going to be completed in 6 months and the budget for the project is $50,000. After the 3 months it is found that only 40% of the total work has been done to date and $30,000 has been spent.
  • 6. Actual Cost = $30,000 Planned Value = 50% of $50,000 = $25,000 Earned Value = 40% of $50,000 = $20,000 Cost Performance Index = Earned Value / Actual Cost = $20,000 / $30,000 = 0.67 Schedule Performance Index (SPI) = Earned Value / Planned Value = $20,000 / $25,000 = 0.8 A project is going to be completed in 6 months and the budget for the project is $50,000. After the 3 months it is found that only 40% of the total work has been done to date and $30,000 has been spent.
  • 7. Actual Cost = $30,000 Planned Value = 50% of $50,000 = $25,000 Earned Value = 40% of $50,000 = $20,000 Cost Performance Index = Earned Value / Actual Cost = $20,000 / $30,000 = 0.67 Schedule Performance Index (SPI) = Earned Value / Planned Value = $20,000 / $25,000 = 0.8 A project is going to be completed in 6 months and the budget for the project is $50,000. After the 3 months it is found that only 40% of the total work has been done to date and $30,000 has been spent. Conclusion: It can be concluded that the project is over budget and behind schedule.
  • 8.
  • 9.
  • 10. Critical Path Activities for this project are as below (output from Define Activities process): 1. Assemble two-tier bridge (10) 2. Join winding tracks (20) 3. Assemble and add train station (5) 4. Place standalone items around (10) 5. Assemble and add construction site (2) 6. Join train engine and bogies (4) 7. Place the train on the track (2) 8. Start the engine and let it chug! (2)
  • 11. Build a Network Diagram
  • 12. Build a Network Diagram
  • 13. Build a Network Diagram
  • 14. Build a Network Diagram
  • 15. Build a Network Diagram The network path with longest total duration is the critical path! Critical path is the shortest duration required to complete the project successfully.
  • 16. Build a Network Diagram The network path with longest total duration is the critical path! Critical path is the shortest duration required to complete the project successfully. In our example this is the second path: A -> B -> C -> D -> G -> H, which comes to 49 minutes.