General Information
Start Date 2 May 2016
Target Completion 2 July 2016
Works Grading of site including construction of
concrete path, irrigation and new turf area as well as relocation of
the BMX track and demolition of timber retaining walls across the
site.
Throughout the construction program, the majority of the reserve
will be closed to the public. However, the North East corner of the
reserve will be maintained open for dog walkers and for
pedestrians accessing the Windsor Train Station. Once the new
paths are constructed, pedestrian access from the North West will
be re-opened. Pedestrian diversions will be in place to safely guide
people to their destinations and around the works site.
It is recommended that dog walkers use surrounding parks such as
Princes Gardens, Victoria Gardens (sunken oval only) or South
Yarra Siding to exercise their dogs during the construction
program
FAQ:
Q. Will “Vehicle Access” be affected?
A. NO. vehicle access will be maintained
Q. Will “Pedestrian Access” be affected?
A. YES, pedestrian use of the park will be limited during
construction works. It is recommended that Gladstone Gardens be
used by pedestrians during this construction program.
Q. Will “Parking” be affected?
A. NO. Parking will be maintained
Q. Will the surrounding facilities be affected?
A. NO. The works site is contained within the reserve with
pedestrian and vehicle access to surrounding facilities maintained
throughout the construction program
NO GO ZONE:
As part of Worksafe and OH&S practices parking and pedestrians
will not be permitted in the Construction Zone
The City of Stonnington’s Urban & Infrastructure Department
wishes to advise traders and residents that works to the Windsor
Siding Reserve will be commencing on Monday 2 May for a three
month period.
The contract for the works has been awarded to PTA Landscapes
and the works will include:
-Regrading of site
-Construction of new concrete paths
-Installation of new turf with irrigation
-Relocation of the existing BMX track and
-Demolition of existing retaining walls
These works form part of stage 1 for the Windsor Siding
Masterplan previously developed with the community.
Working hours are 7am to 5pm Monday to Friday and 8am to 5pm
on Saturday, if required.
PTA Landscapes and Stonnington Council will endeavour to
minimise disruption at all times. We appreciate your patience and
cooperation during this time as we work to improving the reserve.
Yours sincerely
Simon McKenzie-McHarg
CAPITAL WORKS PROJECT BULLETIN NO. 1
Windsor Siding Reserve
Construction of Masterplan Stage 1 Wednesday 20 April
Who to contact if you have issues on site?
Contact:
PTA Landscapes
Contact Dion Loncar
Number 9872 3055
If not resolved, contact:
Councils Project Manager
Name Simon McKenzie-McHarg
Number 8290 2059
OUT OF HOURS: Council’s Emergency No.8290 1333
WINDSOR SIDING- BETWEEN UNION AND PEEL STREET WINDSOR- LOCATION
PLAN (NOT TO SCALE)

Más contenido relacionado

La actualidad más candente

Campbell River Community Presentation Feb 21, 2013
Campbell River Community Presentation Feb 21, 2013Campbell River Community Presentation Feb 21, 2013
Campbell River Community Presentation Feb 21, 2013
Island Health
 
Beech worth montessori school
Beech worth montessori schoolBeech worth montessori school
Beech worth montessori school
Mythili Vinayagam
 
NIHP VIHA Board Presentation
NIHP VIHA Board PresentationNIHP VIHA Board Presentation
NIHP VIHA Board Presentation
Island Health
 
Whitby Feasibility Study final final 555 final final
Whitby Feasibility Study final final 555 final finalWhitby Feasibility Study final final 555 final final
Whitby Feasibility Study final final 555 final final
Edison Mugoya
 

La actualidad más candente (20)

Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...
Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...
Achieving Separated Cycling Facilities in a Constrained Town Centre Environme...
 
Comox Valley Community Presentation - June 2nd, 2015
Comox Valley Community Presentation - June 2nd, 2015Comox Valley Community Presentation - June 2nd, 2015
Comox Valley Community Presentation - June 2nd, 2015
 
Campbell River Community Information Meeting presentation Sept. 18, 2014
Campbell River Community Information Meeting presentation Sept. 18, 2014Campbell River Community Information Meeting presentation Sept. 18, 2014
Campbell River Community Information Meeting presentation Sept. 18, 2014
 
Campbell River Community Information Meeting
Campbell River Community Information MeetingCampbell River Community Information Meeting
Campbell River Community Information Meeting
 
Campbell River Community Presentation Feb 21, 2013
Campbell River Community Presentation Feb 21, 2013Campbell River Community Presentation Feb 21, 2013
Campbell River Community Presentation Feb 21, 2013
 
Comox Valley Community Presentation - December 8, 2015
Comox Valley Community Presentation - December 8, 2015Comox Valley Community Presentation - December 8, 2015
Comox Valley Community Presentation - December 8, 2015
 
St Andrew's Centre minor highways project supported by Histon & Impington Par...
St Andrew's Centre minor highways project supported by Histon & Impington Par...St Andrew's Centre minor highways project supported by Histon & Impington Par...
St Andrew's Centre minor highways project supported by Histon & Impington Par...
 
Hon. Edmund Estephane's 2020/2021 Budget Presentation
Hon. Edmund Estephane's 2020/2021 Budget PresentationHon. Edmund Estephane's 2020/2021 Budget Presentation
Hon. Edmund Estephane's 2020/2021 Budget Presentation
 
Selected_Work-reduced
Selected_Work-reducedSelected_Work-reduced
Selected_Work-reduced
 
Campbell River Community Information Meeting presentation March 12, 2015
Campbell River Community Information Meeting presentation March 12, 2015Campbell River Community Information Meeting presentation March 12, 2015
Campbell River Community Information Meeting presentation March 12, 2015
 
Beech worth montessori school
Beech worth montessori schoolBeech worth montessori school
Beech worth montessori school
 
Campbell River Community Information Meeting presentation
Campbell River Community Information Meeting presentationCampbell River Community Information Meeting presentation
Campbell River Community Information Meeting presentation
 
Campbell River Community Meeting June 3, 2013
Campbell River Community Meeting June 3, 2013Campbell River Community Meeting June 3, 2013
Campbell River Community Meeting June 3, 2013
 
Comox Valley Community Meeting June 11, 2013
Comox Valley Community Meeting June 11, 2013Comox Valley Community Meeting June 11, 2013
Comox Valley Community Meeting June 11, 2013
 
NIHP Comox Valley Community Presentation
NIHP Comox Valley Community PresentationNIHP Comox Valley Community Presentation
NIHP Comox Valley Community Presentation
 
Greville and King Engagement Analysis Report August 2015
Greville and King Engagement Analysis Report August 2015Greville and King Engagement Analysis Report August 2015
Greville and King Engagement Analysis Report August 2015
 
NIHP VIHA Board Presentation
NIHP VIHA Board PresentationNIHP VIHA Board Presentation
NIHP VIHA Board Presentation
 
Comox Valley Community Meeting October 23, 2013
Comox Valley Community Meeting October 23, 2013Comox Valley Community Meeting October 23, 2013
Comox Valley Community Meeting October 23, 2013
 
Comox Valley Community Information Meeting presentation March 11, 2015
Comox Valley Community Information Meeting presentation March 11, 2015Comox Valley Community Information Meeting presentation March 11, 2015
Comox Valley Community Information Meeting presentation March 11, 2015
 
Whitby Feasibility Study final final 555 final final
Whitby Feasibility Study final final 555 final finalWhitby Feasibility Study final final 555 final final
Whitby Feasibility Study final final 555 final final
 

Similar a Capital Works Project Bulletin: Windsor Siding

Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27
loyalj
 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Maureen Kenney
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
May Begum
 
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
Pavitter Virdi
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
Hayley Sharp
 
Nethermayne Site Planning Application
Nethermayne Site Planning ApplicationNethermayne Site Planning Application
Nethermayne Site Planning Application
heppellf
 
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
Candice Spiroski
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
City%20of%20Manassas%20-%20snow%20removal%20plan_3
City%20of%20Manassas%20-%20snow%20removal%20plan_3City%20of%20Manassas%20-%20snow%20removal%20plan_3
City%20of%20Manassas%20-%20snow%20removal%20plan_3
Steve Burke
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
Jade Keswick
 

Similar a Capital Works Project Bulletin: Windsor Siding (20)

Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27
 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
Nethermayne Site Planning Application
Nethermayne Site Planning ApplicationNethermayne Site Planning Application
Nethermayne Site Planning Application
 
Nick Kennedy cv
Nick Kennedy cvNick Kennedy cv
Nick Kennedy cv
 
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Stephen parish c.v. 14 03-17
Stephen parish c.v. 14 03-17Stephen parish c.v. 14 03-17
Stephen parish c.v. 14 03-17
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Perth Stadium community briefing presentation
Perth Stadium community briefing presentationPerth Stadium community briefing presentation
Perth Stadium community briefing presentation
 
Kenya Railways SGR presentation
Kenya Railways SGR presentationKenya Railways SGR presentation
Kenya Railways SGR presentation
 
City%20of%20Manassas%20-%20snow%20removal%20plan_3
City%20of%20Manassas%20-%20snow%20removal%20plan_3City%20of%20Manassas%20-%20snow%20removal%20plan_3
City%20of%20Manassas%20-%20snow%20removal%20plan_3
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meeting
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 

Más de Stonnington Connect

Más de Stonnington Connect (18)

Greville and King St Concept Plans
Greville and King St Concept PlansGreville and King St Concept Plans
Greville and King St Concept Plans
 
Windsor Siding Implementation Staging Plan June 2016
Windsor Siding Implementation Staging Plan June 2016Windsor Siding Implementation Staging Plan June 2016
Windsor Siding Implementation Staging Plan June 2016
 
Windsor Siding Implementation Staging Plan June 2016
Windsor Siding Implementation Staging Plan June 2016Windsor Siding Implementation Staging Plan June 2016
Windsor Siding Implementation Staging Plan June 2016
 
Greville and King St Traffic Notifications
Greville and King St Traffic NotificationsGreville and King St Traffic Notifications
Greville and King St Traffic Notifications
 
Local Law Permit in Greville/King Streets
Local Law Permit in Greville/King StreetsLocal Law Permit in Greville/King Streets
Local Law Permit in Greville/King Streets
 
November 2015: CCTV
November 2015: CCTVNovember 2015: CCTV
November 2015: CCTV
 
Location of Princes Gardens
Location of Princes GardensLocation of Princes Gardens
Location of Princes Gardens
 
Princes Gardens Masterplan of Existing Conditions
 Princes Gardens Masterplan of Existing Conditions  Princes Gardens Masterplan of Existing Conditions
Princes Gardens Masterplan of Existing Conditions
 
Hawksburn Village Structure Plan Report
Hawksburn Village Structure Plan ReportHawksburn Village Structure Plan Report
Hawksburn Village Structure Plan Report
 
Greville and King Streets Improvement Plan
Greville and King Streets Improvement PlanGreville and King Streets Improvement Plan
Greville and King Streets Improvement Plan
 
Aged Services Client Satisfaction
Aged Services Client SatisfactionAged Services Client Satisfaction
Aged Services Client Satisfaction
 
Open Space Strategy
Open Space StrategyOpen Space Strategy
Open Space Strategy
 
July 2015: Local Business (Connect Stonnington Group)
July 2015: Local Business (Connect Stonnington Group)July 2015: Local Business (Connect Stonnington Group)
July 2015: Local Business (Connect Stonnington Group)
 
July 2015: Sustainable Environment (Connect Stonnington Group)
July 2015: Sustainable Environment (Connect Stonnington Group)July 2015: Sustainable Environment (Connect Stonnington Group)
July 2015: Sustainable Environment (Connect Stonnington Group)
 
March 2015: Transport Safety (Connect Stonnington Group)
March 2015: Transport Safety (Connect Stonnington Group)March 2015: Transport Safety (Connect Stonnington Group)
March 2015: Transport Safety (Connect Stonnington Group)
 
March 2015: Sustainable Transport (Connect Stonnington Group)
March 2015: Sustainable Transport (Connect Stonnington Group)March 2015: Sustainable Transport (Connect Stonnington Group)
March 2015: Sustainable Transport (Connect Stonnington Group)
 
Recreation Strategy 2014 2024
Recreation Strategy 2014 2024Recreation Strategy 2014 2024
Recreation Strategy 2014 2024
 
Possible Synthetic Surface Infill Option
Possible Synthetic Surface Infill OptionPossible Synthetic Surface Infill Option
Possible Synthetic Surface Infill Option
 

Último

Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
 

Último (20)

Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 

Capital Works Project Bulletin: Windsor Siding

  • 1. General Information Start Date 2 May 2016 Target Completion 2 July 2016 Works Grading of site including construction of concrete path, irrigation and new turf area as well as relocation of the BMX track and demolition of timber retaining walls across the site. Throughout the construction program, the majority of the reserve will be closed to the public. However, the North East corner of the reserve will be maintained open for dog walkers and for pedestrians accessing the Windsor Train Station. Once the new paths are constructed, pedestrian access from the North West will be re-opened. Pedestrian diversions will be in place to safely guide people to their destinations and around the works site. It is recommended that dog walkers use surrounding parks such as Princes Gardens, Victoria Gardens (sunken oval only) or South Yarra Siding to exercise their dogs during the construction program FAQ: Q. Will “Vehicle Access” be affected? A. NO. vehicle access will be maintained Q. Will “Pedestrian Access” be affected? A. YES, pedestrian use of the park will be limited during construction works. It is recommended that Gladstone Gardens be used by pedestrians during this construction program. Q. Will “Parking” be affected? A. NO. Parking will be maintained Q. Will the surrounding facilities be affected? A. NO. The works site is contained within the reserve with pedestrian and vehicle access to surrounding facilities maintained throughout the construction program NO GO ZONE: As part of Worksafe and OH&S practices parking and pedestrians will not be permitted in the Construction Zone The City of Stonnington’s Urban & Infrastructure Department wishes to advise traders and residents that works to the Windsor Siding Reserve will be commencing on Monday 2 May for a three month period. The contract for the works has been awarded to PTA Landscapes and the works will include: -Regrading of site -Construction of new concrete paths -Installation of new turf with irrigation -Relocation of the existing BMX track and -Demolition of existing retaining walls These works form part of stage 1 for the Windsor Siding Masterplan previously developed with the community. Working hours are 7am to 5pm Monday to Friday and 8am to 5pm on Saturday, if required. PTA Landscapes and Stonnington Council will endeavour to minimise disruption at all times. We appreciate your patience and cooperation during this time as we work to improving the reserve. Yours sincerely Simon McKenzie-McHarg CAPITAL WORKS PROJECT BULLETIN NO. 1 Windsor Siding Reserve Construction of Masterplan Stage 1 Wednesday 20 April Who to contact if you have issues on site? Contact: PTA Landscapes Contact Dion Loncar Number 9872 3055 If not resolved, contact: Councils Project Manager Name Simon McKenzie-McHarg Number 8290 2059 OUT OF HOURS: Council’s Emergency No.8290 1333
  • 2. WINDSOR SIDING- BETWEEN UNION AND PEEL STREET WINDSOR- LOCATION PLAN (NOT TO SCALE)