SlideShare una empresa de Scribd logo
1 de 40
Descargar para leer sin conexión
INTRODUCTION TO COST
MANAGEMENT &
CONTROL IN
CONSTRUCTION
PROJECTS
TYPE OF COSTS
Type of Cost Description
Direct Cost
Direct cost is directly attributable to the project and spent only on
the project work.
Indirect Cost
Indirect cost is cost that is needed for a project but not restricted
to it; it could be used by other projects as well. It is likely there are
other groups or activities benefiting from such items, and your
project pays its part as well.
Fixed Cost
Fixed cost is cost that is consistent on a project regardless of how
many are used.
Variable Cost
Variable cost is one that fluctuates with what is produced. The
more of something you produce, the more of this type of cost you
incur.
PROJECT SELECTION TECHNIQUES
Project
Selection
Technique
Name
Also
Kno
wn
As
Option to Select Example
Return On
Investment
ROI
The biggest number or percentage.
Typically the biggest number or
percentage among the projects under
consideration.
$50,000 or 7%
Internal
Rate of
Return
IRR
Select the biggest percentage.
Often used in capital budgeting, interest
rate makes the net present value of all
cash flow equal zero.
15.5%
Net Present
Value
NPV
Select the biggest number (Years are
already factored in)
$47,000 US
Benefit Cost
Ratio
BCR Select the biggest ratio 3.5:1
COST BASED PROJECT SELECTION
TECHNIQUES (CONT.)
Project
Selection
Technique
Name
Also
Known
As
Option to Select Example
Opportunity
Cost
The amounts that are not
selected
Choose Project A ($7,000)
over Project B ($5000). The
opportunity cost is $5000 to
select Project A.
Payback
Period
Select the shortest
duration
7 months
COST BASED PROJECT SELECTION
DISCUSSIONS
Project Selection
Technique
Discussion
Return On
Investment
(ROI)
Return on Investment (ROI) is a general term. You may calculate
it a variety of ways. Typically, you would choose the biggest
number or percentage among the projects under consideration.
Internal Rate of
Return
(IRR)
Often used in capital budgeting. Interest rate makes the net
present value of all cash flow equal zero. In the case of IRR and
project selection, select the larger number.
COST BASED PROJECT SELECTION
DISCUSSIONS (CONT.)
Project Selection
Technique
Discussion
Net Present
Value
(NPV)
Net Present Value (NPV) is used in capital budgeting where the
present value of cash inflows is subtracted for the present value
of cash outflows. NPV compares the value of a dollar today
versus the value of that same dollar in the future after taking
inflation and return into account.
I wouldn’t worry about calculating this, you should know how to
select a project using it. For example, with Project A have a NPV
of $150,000 and 6 months or Project B having a NPV of $295,000
and 1 year, you would select Project B because it has the bigger
number AND the years are already factored into the dollar
amount.
COST BASED PROJECT SELECTION
DISCUSSIONS (CONT.)
Project Selection
Technique
Discussion
Benefit Cost
Ratio
(BCR)
Benefit Cost Ratio (BCR) is the project selection and analysis
technique that involves comparing the benefit to the cost of the
initiative. The format is 3.65:1 that means that the benefits of
the project outweighs the costs 3.65:1.
You should not be concerned about profit in this area. That is
simply noise; the benefit, cost, and ratio between them are the
main components. There could also be a project that has a BCR
of less then one (.75:1) for example. This would mean that the
project had a benefit of $.75 for ever $1.00 invested. Typically,
you would not approve such a project unless there was some
underlying factor such as Y2K issues.
COST BASED PROJECT SELECTION
DISCUSSIONS (CONT.)
Project Selection
Technique
Discussion
Opportunity
Cost
Opportunity Cost is associated with taking another opportunity.
It is what you give up or leave on the table to take the other
opportunity. For example, if you take a $75,000 a year job over a
$60,000 a year job, then the opportunity cost of taking the
$75,000 is $60,000.
Payback Period
Payback period is the amount of time needed to earn back the
original investment on the project. PMI® suggests that you select
the project with the shortest payback period.
FUTURE VALUE (FV)
• Future value is the value of something such as cash or an investment at
a specific point in the future. For example, if you had $1,000 now and
could get 8% interest over three years, what is the future value?
• The formula is shown below with PV = present value, r = interest rate, n
= number of periods, and FV = future value.
PRESENT VALUE
Present value is the value of something today that you need
to create a certain amount of investment in the future. For
example: if you wanted to have $2,500 in three years, what
amount of money do you need today to produce this amount
if the money was earning 8%?
PLAN COST MANAGEMENT
WHAT IS COST AND PROJECT COST
MANAGEMENT?
• Cost is a resource sacrificed or foregone to achieve a specific
objective or something given up in exchange
• Costs are usually measured in monetary units like dollars
• Project cost management includes the processes required to ensure
that the project is completed within an approved budget
ESTIMATE COSTS
• Cost estimates are a prediction that is based on the information known at
a given point in time
• Cost estimates include the identification and consideration of costing
alternatives to initiate and complete the project
• Cost estimates are generally expressed in units of some currency
• The accuracy of a project estimate will increase as the project progresses
through the project life cycle.
– For example, a project in the initiation phase may have a rough order
of magnitude (ROM) estimate in the range of −25% to +75%.
– Later in the project, as more information is known, definitive
estimates could narrow the range of accuracy to -5% to +10%.
ESTIMATE COSTS
ANALOGOUS ESTIMATES
Method Description Scenarios
Analogous
(Top Down)
This estimate is usually a total time or
cost estimate that has no significant
detail.
Advantage: Can be created quickly.
Disadvantage: It lacks detail or
individual piece estimates.
An executive or someone
who is subject matter
expert (SME) creates a high
level estimate based on
experience or past project
history with the company.
PARAMETRIC ESTIMATES
Method Description Scenarios
Parametric
Based on existing parameters, this
method is usually created by industry
standards or past experience.
Advantage: It can be done quickly
and is usually accurate.
A house builder quotes a
house for $75.00 per square
foot. A carpet installer
quotes $2 per square foot
for installation.
BOTTOM UP ESTIMATES
Method Description Scenarios
Bottom Up
This is a detailed estimate that usually
involves team input.
Advantage: There is detail and
accuracy associated with it.
Disadvantage: It can take significant
time to create and the team can pad
the estimates to compensate for
unknowns.
A project manager and the
team work together to
create a complete estimate
from the bottom (Activity
level) up and roll it up to
the total estimate.
ESTIMATE COSTS METHODS:
MONTE CARLO
Method Description Scenarios
Computerized
/Monte Carlo
This estimate involves using a
computerized program to simulate
different variables associated with
project outcome.
Advantages: (1) Accuracy of the
estimate; (2) The “what-if” analysis
that can be performed
Disadvantages: The ramp-up time
and costs associated with the setup
of the tool.
Variables simulated could
include the overall time and
cost estimates as well as the
confidence levels of the
estimates. Variables could
also include the number of
people needed to achieve
project goals.
COST RANGE ESTIMATES
DETERMINE BUDGET
• Determine Budget is the process of aggregating the
estimated costs of individual activities or work
packages to establish an authorized cost baseline.
• The key benefit of this process is that it determines
the cost baseline against which project
performance can be monitored and controlled.
• A project budget includes all the funds authorized
to execute the project.
• The cost baseline is the approved version of the
time-phased project budget, but excludes
management reserves.
DETERMINE BUDGET
DETERMINE BUDGET
Project Funding Requirements
– Total funding requirements and periodic funding
requirements (e.g., quarterly, annually) are derived
from the cost baseline.
– The cost baseline will include projected
expenditures plus anticipated liabilities.
– Funding often occurs in incremental amounts that
are not continuous, and may not be evenly
distributed
– The total funds required are those included in the
cost baseline, plus management reserves, if any.
DETERMINE BUDGET
Cost Baseline
– The cost baseline is the approved version of the
time-phased project budget, excluding any
management reserves, which can only be
changed through formal change control
procedures and is used as a basis for
comparison to actual results.
– It is developed as a summation of the approved
budgets for the different schedule activities.
DETERMINE BUDGET
DETERMINE BUDGET
CONTROL COSTS
• Control Costs is the process of monitoring the status
of the project to update the project costs and
managing changes to the cost baseline.
• The key benefit of this process is that it provides the
means to recognize variance from the plan in order
to take corrective action and minimize risk.
CONTROL COSTS
Project cost control includes:
– Influencing the factors that create changes to the authorized cost
baseline
– Ensuring that all change requests are acted on in a timely manner;
– Managing the actual changes when and as they occur
– Ensuring that cost expenditures do not exceed the authorized funding
by period, by WBS component, by activity, and in total for the project
– Monitoring cost performance to isolate and understand variances
from the approved cost baseline
– Monitoring work performance against funds expended
– Preventing unapproved changes from being included in the reported
cost or resource usage
– Informing appropriate stakeholders of all approved changes and
associated cost
– Bringing expected cost overruns within acceptable limits
EARNED VALUE
Earned Value Management (EVM) :
• Is a project management methodology used to track project performance as
well as forecast future performance. EVM integrates the scope baseline,
schedule baseline and cost to provide performance measurements. Results can
be expressed in dollars and/or percentage. EVM can be used to report
current/past project performance, and predict future project performance based
on current/past performance. Variance Analysis Forecasting Current/Past
Performance Future Performance
EARNED VALUE
EARNED VALUE PARAMETERS
EARNED VALUE FORMULAS
CV
Cost Variance
EV – AC
Where:
EV = Earned Value
AC = Actual Cost
SV
Schedule Variance
EV – PV
Where:
EV = Earned Value
PV = Planned
Value
CPI
Cost Performance
Index
EV / AC
Where:
EV = Earned Value
AC = Actual Cost
SPI
Schedule
Performance
Index
EV / PV
Where:
EV = Earned Value
PV = Planned
Value
EARNED VALUE FORMULAS
• EV – AC
CV - Cost Variance
• The difference between Earned
Value and Actual CostEV – AC
• Cost Overrun or over budget
Negative
• Under Budget
Positive
• On Budget
Zero
EARNED VALUE FORMULAS
• EV – PVSV - Schedule
Variance
• The difference between Earned
Value and Planned Value
EV – AC
• Project performance behind
schedule
Negative
• Project performance ahead
schedule
Positive
• Project Performance on
schedule
Zero
EARNED VALUE FORMULAS
• EV /PVSPI - Cost
Performance Index
• The ratio of Earned Value to
Planned Value
EV/PV
• Cost over budget
Value < 1
• Cost below budget
Value > 1
• On Budget
Value= 1
EARNED VALUE FORMULAS
• EV /ACCPI - Cost
Performance Index
• The ratio of Earned Value to
Actual Cost
EV/AC
• Project performance behind
schedule
Value < 1
• Project performance ahead
schedule
Value > 1
• Project Performance on
schedule
Value= 1
EARNED VALUE ANALYSIS
FORECASTS
ESTIMATE AT COMPLETION (EAC) :
• Is a periodic evaluation of the project status, used to estimate what is will cost
to complete the project based on the performance today (CPI) – usually
performed monthly or if significant changes have been identified.
ESTIMATE AT COMPLETION (EAC)
FORECASTS
ESTIMATE TO COMPLETE (ETC) :
• The estimate to complete (ETC represents the amount needed to finish the
project based on the current spending efficiency of the project.)
ESTIMATE TO COMPLETE (ETC)
FORECASTS
TO COMPLETE PERFORMANCE INDEX (TCPI)
TO COMPLETE PERFORMANCE INDEX (TCPI):
• It is an indicator of how performance needs to improve to close the deviation
between planned values and actual performance, (efficiency level needed from
the remaining resources to meet the cost goals of the project)
FORECASTS
VARIANCE AT COMPLETION (VAC)
VARIANCE AT COMPLETION (VAC):
• It is the difference between the budget at completion (BAC) and the estimate at
completion (EAC). This difference tells how much over or under budget the
project finished

Más contenido relacionado

La actualidad más candente

1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
Ali Juma Albahrani
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
341741357
 

La actualidad más candente (20)

1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
Project cost management
Project cost management Project cost management
Project cost management
 
122 value engineering
122 value engineering122 value engineering
122 value engineering
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
Chapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptxChapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptx
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 

Similar a Introduction to cost management &amp; control in construction projects

con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
Asa Chan
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
selinasimpson1601
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting Decision
Ashish Khera
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 

Similar a Introduction to cost management &amp; control in construction projects (20)

Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
2 b agile domains
2 b agile domains2 b agile domains
2 b agile domains
 
Pmp inititating process group
Pmp inititating process groupPmp inititating process group
Pmp inititating process group
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Capital Budgeting Decision
Capital Budgeting DecisionCapital Budgeting Decision
Capital Budgeting Decision
 
Initiating_Projects.pptx
Initiating_Projects.pptxInitiating_Projects.pptx
Initiating_Projects.pptx
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
Pm assignment
Pm assignmentPm assignment
Pm assignment
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Project_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptProject_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.ppt
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 

Más de Essam Lotffy, PMP®, CCP®

Más de Essam Lotffy, PMP®, CCP® (18)

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
 

Último

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 

Último (20)

Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 

Introduction to cost management &amp; control in construction projects

  • 1. INTRODUCTION TO COST MANAGEMENT & CONTROL IN CONSTRUCTION PROJECTS
  • 2. TYPE OF COSTS Type of Cost Description Direct Cost Direct cost is directly attributable to the project and spent only on the project work. Indirect Cost Indirect cost is cost that is needed for a project but not restricted to it; it could be used by other projects as well. It is likely there are other groups or activities benefiting from such items, and your project pays its part as well. Fixed Cost Fixed cost is cost that is consistent on a project regardless of how many are used. Variable Cost Variable cost is one that fluctuates with what is produced. The more of something you produce, the more of this type of cost you incur.
  • 3. PROJECT SELECTION TECHNIQUES Project Selection Technique Name Also Kno wn As Option to Select Example Return On Investment ROI The biggest number or percentage. Typically the biggest number or percentage among the projects under consideration. $50,000 or 7% Internal Rate of Return IRR Select the biggest percentage. Often used in capital budgeting, interest rate makes the net present value of all cash flow equal zero. 15.5% Net Present Value NPV Select the biggest number (Years are already factored in) $47,000 US Benefit Cost Ratio BCR Select the biggest ratio 3.5:1
  • 4. COST BASED PROJECT SELECTION TECHNIQUES (CONT.) Project Selection Technique Name Also Known As Option to Select Example Opportunity Cost The amounts that are not selected Choose Project A ($7,000) over Project B ($5000). The opportunity cost is $5000 to select Project A. Payback Period Select the shortest duration 7 months
  • 5. COST BASED PROJECT SELECTION DISCUSSIONS Project Selection Technique Discussion Return On Investment (ROI) Return on Investment (ROI) is a general term. You may calculate it a variety of ways. Typically, you would choose the biggest number or percentage among the projects under consideration. Internal Rate of Return (IRR) Often used in capital budgeting. Interest rate makes the net present value of all cash flow equal zero. In the case of IRR and project selection, select the larger number.
  • 6. COST BASED PROJECT SELECTION DISCUSSIONS (CONT.) Project Selection Technique Discussion Net Present Value (NPV) Net Present Value (NPV) is used in capital budgeting where the present value of cash inflows is subtracted for the present value of cash outflows. NPV compares the value of a dollar today versus the value of that same dollar in the future after taking inflation and return into account. I wouldn’t worry about calculating this, you should know how to select a project using it. For example, with Project A have a NPV of $150,000 and 6 months or Project B having a NPV of $295,000 and 1 year, you would select Project B because it has the bigger number AND the years are already factored into the dollar amount.
  • 7. COST BASED PROJECT SELECTION DISCUSSIONS (CONT.) Project Selection Technique Discussion Benefit Cost Ratio (BCR) Benefit Cost Ratio (BCR) is the project selection and analysis technique that involves comparing the benefit to the cost of the initiative. The format is 3.65:1 that means that the benefits of the project outweighs the costs 3.65:1. You should not be concerned about profit in this area. That is simply noise; the benefit, cost, and ratio between them are the main components. There could also be a project that has a BCR of less then one (.75:1) for example. This would mean that the project had a benefit of $.75 for ever $1.00 invested. Typically, you would not approve such a project unless there was some underlying factor such as Y2K issues.
  • 8. COST BASED PROJECT SELECTION DISCUSSIONS (CONT.) Project Selection Technique Discussion Opportunity Cost Opportunity Cost is associated with taking another opportunity. It is what you give up or leave on the table to take the other opportunity. For example, if you take a $75,000 a year job over a $60,000 a year job, then the opportunity cost of taking the $75,000 is $60,000. Payback Period Payback period is the amount of time needed to earn back the original investment on the project. PMI® suggests that you select the project with the shortest payback period.
  • 9. FUTURE VALUE (FV) • Future value is the value of something such as cash or an investment at a specific point in the future. For example, if you had $1,000 now and could get 8% interest over three years, what is the future value? • The formula is shown below with PV = present value, r = interest rate, n = number of periods, and FV = future value.
  • 10. PRESENT VALUE Present value is the value of something today that you need to create a certain amount of investment in the future. For example: if you wanted to have $2,500 in three years, what amount of money do you need today to produce this amount if the money was earning 8%?
  • 12. WHAT IS COST AND PROJECT COST MANAGEMENT? • Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange • Costs are usually measured in monetary units like dollars • Project cost management includes the processes required to ensure that the project is completed within an approved budget
  • 13. ESTIMATE COSTS • Cost estimates are a prediction that is based on the information known at a given point in time • Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project • Cost estimates are generally expressed in units of some currency • The accuracy of a project estimate will increase as the project progresses through the project life cycle. – For example, a project in the initiation phase may have a rough order of magnitude (ROM) estimate in the range of −25% to +75%. – Later in the project, as more information is known, definitive estimates could narrow the range of accuracy to -5% to +10%.
  • 15. ANALOGOUS ESTIMATES Method Description Scenarios Analogous (Top Down) This estimate is usually a total time or cost estimate that has no significant detail. Advantage: Can be created quickly. Disadvantage: It lacks detail or individual piece estimates. An executive or someone who is subject matter expert (SME) creates a high level estimate based on experience or past project history with the company.
  • 16. PARAMETRIC ESTIMATES Method Description Scenarios Parametric Based on existing parameters, this method is usually created by industry standards or past experience. Advantage: It can be done quickly and is usually accurate. A house builder quotes a house for $75.00 per square foot. A carpet installer quotes $2 per square foot for installation.
  • 17. BOTTOM UP ESTIMATES Method Description Scenarios Bottom Up This is a detailed estimate that usually involves team input. Advantage: There is detail and accuracy associated with it. Disadvantage: It can take significant time to create and the team can pad the estimates to compensate for unknowns. A project manager and the team work together to create a complete estimate from the bottom (Activity level) up and roll it up to the total estimate.
  • 18. ESTIMATE COSTS METHODS: MONTE CARLO Method Description Scenarios Computerized /Monte Carlo This estimate involves using a computerized program to simulate different variables associated with project outcome. Advantages: (1) Accuracy of the estimate; (2) The “what-if” analysis that can be performed Disadvantages: The ramp-up time and costs associated with the setup of the tool. Variables simulated could include the overall time and cost estimates as well as the confidence levels of the estimates. Variables could also include the number of people needed to achieve project goals.
  • 20. DETERMINE BUDGET • Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. • The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled. • A project budget includes all the funds authorized to execute the project. • The cost baseline is the approved version of the time-phased project budget, but excludes management reserves.
  • 22. DETERMINE BUDGET Project Funding Requirements – Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline. – The cost baseline will include projected expenditures plus anticipated liabilities. – Funding often occurs in incremental amounts that are not continuous, and may not be evenly distributed – The total funds required are those included in the cost baseline, plus management reserves, if any.
  • 23. DETERMINE BUDGET Cost Baseline – The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures and is used as a basis for comparison to actual results. – It is developed as a summation of the approved budgets for the different schedule activities.
  • 26. CONTROL COSTS • Control Costs is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline. • The key benefit of this process is that it provides the means to recognize variance from the plan in order to take corrective action and minimize risk.
  • 27. CONTROL COSTS Project cost control includes: – Influencing the factors that create changes to the authorized cost baseline – Ensuring that all change requests are acted on in a timely manner; – Managing the actual changes when and as they occur – Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS component, by activity, and in total for the project – Monitoring cost performance to isolate and understand variances from the approved cost baseline – Monitoring work performance against funds expended – Preventing unapproved changes from being included in the reported cost or resource usage – Informing appropriate stakeholders of all approved changes and associated cost – Bringing expected cost overruns within acceptable limits
  • 28. EARNED VALUE Earned Value Management (EVM) : • Is a project management methodology used to track project performance as well as forecast future performance. EVM integrates the scope baseline, schedule baseline and cost to provide performance measurements. Results can be expressed in dollars and/or percentage. EVM can be used to report current/past project performance, and predict future project performance based on current/past performance. Variance Analysis Forecasting Current/Past Performance Future Performance
  • 31. EARNED VALUE FORMULAS CV Cost Variance EV – AC Where: EV = Earned Value AC = Actual Cost SV Schedule Variance EV – PV Where: EV = Earned Value PV = Planned Value CPI Cost Performance Index EV / AC Where: EV = Earned Value AC = Actual Cost SPI Schedule Performance Index EV / PV Where: EV = Earned Value PV = Planned Value
  • 32. EARNED VALUE FORMULAS • EV – AC CV - Cost Variance • The difference between Earned Value and Actual CostEV – AC • Cost Overrun or over budget Negative • Under Budget Positive • On Budget Zero
  • 33. EARNED VALUE FORMULAS • EV – PVSV - Schedule Variance • The difference between Earned Value and Planned Value EV – AC • Project performance behind schedule Negative • Project performance ahead schedule Positive • Project Performance on schedule Zero
  • 34. EARNED VALUE FORMULAS • EV /PVSPI - Cost Performance Index • The ratio of Earned Value to Planned Value EV/PV • Cost over budget Value < 1 • Cost below budget Value > 1 • On Budget Value= 1
  • 35. EARNED VALUE FORMULAS • EV /ACCPI - Cost Performance Index • The ratio of Earned Value to Actual Cost EV/AC • Project performance behind schedule Value < 1 • Project performance ahead schedule Value > 1 • Project Performance on schedule Value= 1
  • 37. FORECASTS ESTIMATE AT COMPLETION (EAC) : • Is a periodic evaluation of the project status, used to estimate what is will cost to complete the project based on the performance today (CPI) – usually performed monthly or if significant changes have been identified. ESTIMATE AT COMPLETION (EAC)
  • 38. FORECASTS ESTIMATE TO COMPLETE (ETC) : • The estimate to complete (ETC represents the amount needed to finish the project based on the current spending efficiency of the project.) ESTIMATE TO COMPLETE (ETC)
  • 39. FORECASTS TO COMPLETE PERFORMANCE INDEX (TCPI) TO COMPLETE PERFORMANCE INDEX (TCPI): • It is an indicator of how performance needs to improve to close the deviation between planned values and actual performance, (efficiency level needed from the remaining resources to meet the cost goals of the project)
  • 40. FORECASTS VARIANCE AT COMPLETION (VAC) VARIANCE AT COMPLETION (VAC): • It is the difference between the budget at completion (BAC) and the estimate at completion (EAC). This difference tells how much over or under budget the project finished