DESIGN AND CONSTRUCTION OF THE “FIERA MILANO BUILDING”
Ing. Luca ROMANO – I QUADRO INGEGNERIA – GENOVA
LOCATION OF THE “FIERA MILANO BUILDING”

PLAN VIEW

AERIAL VIEW
INTERNATIONAL TENDER
The design of this building followed from an international tender, in which different groups of architects, engineers and constructioncompanies proposed their ideas for the new offices of the “Fiera Milano building”.
The winning proposal was conceived as a golden, horizontal tower at the east entrance of the “Fiera di Milano”.
Here you can see some early images of the winning idea for the tender:
DESCRIPTION OF THE BUILDING

During the competition phase various solutions were studied in order to match construction time and costs. This resulted in a mixed
steel-concrete structure that allowed to complete the building in less than two years and to respect tender costs.

Design consists of a 132.5 m long building of 15.60 m depth and about 60 m height.
The Building is divided in two by a joint: building “A” is composed by 12 floors while building “B” is composed by 13 floors.
They are separated but connected by the foyer with staircases and footbridges.
In order to provide an helicopter landing pad, an important cantilever steel structure was built on the roof of building “B”.

Side of the building in the actual destination

Rear of the building with view of the landing pad
Here are some views of the finished building:

Side of the building with view of the cantilever landing pad

View of the rear of the building
The building is composed by two parts connected by a foyer and footbridges at different floors.

BUILDING “A”

FOYER

Plan view of the building, with the landing pad on the right

BUILDING “B”
STRUCTURE

Structural Strategy And Description

The structure was very long, so it was divided in two structures separated by a joint. Here you can see the typical floor plan:
joint
BUILDING “B”

BUILDING “A”

plan view of the typical floor

Longitudinally the structure is a repetition of 6.25 m spaced columns; they are aligned along the perimeter and on an internal position.
Transversely two precast, prestressed slabs - 4.25 m and 10.7 m long - connect the longitudinal steel beams.
These beams are made with welded plates, to reduce thickness.
STRUCTURE
Each building is a core supported structure, with shear walls, to resist lateral forces from wind and earthquakes.
In this way steel columns are pinned at the base and resist only to vertical loads.

This classical strategy was adopted to realize the structure in few months, with respect of tender costs:
steel structures was produced on workshop, while on construction site we realized reinforced concrete core structures.

Core structures of the two buildings - floors in construction
Concrete core structures were realized with climbing form-works.
In the picture you can see also the steel boxes provided in the walls for the connection of steel beams:

Climbing form-works for the shear walls of stair cases
In this way the steel structure was a simple assembly of pinned columns and hinged beams:

Pinned connections of the steel columns
Steel beams were composed with welded plates, hinged and dimensioned to support precast slabs:
To reduce thickness, slabs were supported on bottom flange:

Prestressed slabs are placed on the wide bottom flanges of the steel beams and casted in situ.
Slabs were 30 cm thick, 10.25 metres long, with a layer of 5 cm of concrete cast in situ.

In the following details you can see the intersection beam-slab:
Here are some pictures of the construction phases of the floors:

Positioning of precast slab of floors

Detail of the intersection between slab and steel beams (view from above and from below)
FOOTBRIDGES

The connecting foyer has footbridges 12 metres long, at various floors. These structures are free to move to absorb lateral movements
due to wind, earthquakes and thermal effects.
They are composed by IPE 500 steel beams with a composite slab on cold-formed steel decking.

Main steel beams of the two footbridges connecting the two buildings: fixed on one side and free to move on the other.
FOYER
The foyer is an hollow structure with staircases and footbridges connecting people at each floor.
Windows in front of the foyer have a complicate pinned systems that permits movements of translation and rotation of the two
buildings. These windows are linked to a steel tree-structure, pinned to building “B” and free to move in the connection of building “A”.
Cinematic was important to prevent window crashes and all calculated displacements were given to the facade developers to take
care of relative movements.

view of the foyer connecting the two buildings

view of the finished foyer from below, in the entrance
Here you can see the structural detail of the hinges of the tree-structure of the foyer:

General and detailed view of the Pinned and slipping connections of the facade of the foyer

STRUCTURE “A”

STRUCTURE “B”

Plan view detail of the foyer
Construction phases were important.
Before finishing the roof, the wall at the rear of the foyer was 54 metres high, 40 cm thick, separated by joint and free at the top.
Because of stability check, you can see some provisional beams positioned.
You can also see the joint which separates the two structures.

joint
HELICOPTER LANDING PAD:
On the roof of building “B” an helicopter landing pad was realized.
The structure is made with cantilever “I” beams, 10 metres apart from the facade, connected by damping supports to the steel columns
of the building, not to transmit vibrations.
The deck was formed by aluminium box section supported by the beams.

General view of the structure of the landing pad

detail of the structure extremity
Here you can see the design of the steel structure:

the plan view on the left and the cross section of the cantilever on the right.

Only extremity columns were used as support, to prevent traction.

10 m

building
FOUNDATIONS
In order to prevent ground displacements and subsidence, we realized a steel sheet-pile bulkhead, 10 metres long, installed by
vibratory hammer.
In the picture one can see this earth retaining wall without dead space near existing buildings:

Positioning of steel sheet piles before digging
Another problem was the presence of the Underground of Milan, that didn’t accept any pressure against its existing walls. That’s why
we had to dig till the bottom of the tube, realize a joint and replace the ground with casting concrete, able to resist to the pressure of
the new building transmitting forces only to the bottom of the foundation.

Steel sheet piles and base of the mat foundation. On the left the existing Underground

Concrete casting near the Underground, to prevent earth pressure against existing walls
Underground of Milan asked the simulation of the construction phases.
Here you can see the vertical section, with the Tube on the left, the mat foundations on the right and the concrete layer in the middle:

The simulation analysis was performed in 5 steps with a bi-dimensional model, to answer the Underground of Milan in terms of
subsidence:
Mat Foundation

Due to the good soil characteristic, we designed a mat foundation, continuous under the entire building.
Instead, the building itself was divided in two structures, which were separated by a joint.
The thickness of the mat was 1 metre under the steel columns and 1.5 metres under the core structures. It was reduced to 40 cm near
the steel sheet piles, in order to reduce the cantilever.
In the following plan view you can see the foundation: 137 metres long and 30 metres wide:
In the next picture you can see the positioning of reinforcement in the mat:

Reinforcement of the mat foundation before casting
ANALYSIS
The structure had many particularities, but is was not so unusual.
So we decided to realize models for design purpose, easy to handle and to understand.

Here you can see the finite element model of the structure, performed with Straus 7.

The model simulate the exact structural stiffness by mean of:
2084 element beam
12427 element plate
for a total of 46994 degrees of freedom

View of the model
Mat foundations are modelled with plate elements on ground support:

Modulus of Subgrade Reaction

These plates have either membrane or bending properties, calculated through their thickness.

Earth retaining walls are modelled with plate elements.

Columns and beams are modelled with beam elements, hinged at the end.

shear walls forming the box shaped cores around stairs and elevators, are modelled with plate elements, which have either membrane
or bending properties, calculated through their thickness.
This is a spatial system capable of resisting all types of loads: vertical forces, shear forces and bending moments in all directions, as
well as torsion.
In this way we realized an efficient lateral load resistance structure for the two buildings.
Slabs are modelled with load patch elements and rigid floor links.

This plate element does not have any property attributes. It is used solely as a way of transferring distributed area loads and nonstructural mass to beams that may be connected around the perimeter of the plate:

In this way you don’t influence the stiffness of beams and you consider the rigid link of each floor.

The software Straus 7 allows the definition of different non structural mass for various load condition and to any of them one can
associate a dynamic factor that define the mass to be considered in dynamic analysis. In this way you have the maximum of
possibilities of simulating seismic conditions.
Analysis performed during design were of three types:

-

Static:

load conditions – SLS and ULS combinations - envelopes

-

Dynamic:

natural frequencies – mode shapes

-

Spectral response:

seismic base excitation

During construction phases we performed also various static analysis on partial models, to help the construction company to reduce
construction time.
Static analysis are performed considering various load conditions:

-

Self weight is automatically determined by Straus 7

-

Either permanent or live loads were introduced through non structural mass in different load cases

-

Wind was introduced through forces acting on facade load patch elements. These forces change of intensity with height

Solutions were combined to maximize effects on beams and columns.
Various combinations were performed, in order to obtain Service and Ultimate Limit State conditions.
For example next figure represent maxima axial forces at ULS for the columns:
In next image we see the values of axial forces in columns and stresses in shear walls of a single floor.
They are used for resistance and stability check required by Code:
The natural frequency solver was used to calculate free vibration frequencies and corresponding mode shapes of the undamped
structure.
It is possible to determine the participation factors for all directions to be sure to involve more than 85% of the global mass of the
structure:

100 mode shapes were necessary.

In next figure you see the first mode shape of structure “A”:

first bending mode shape in the transverse direction: 0.61 Hz of frequency
In next figure you see the first six mode shapes of structure “A”:

First six mode shapes of structure “A”
Seismic design

The Spectral Response solver calculates the response of a structure subjected to a random dynamic loading.
In this spectral response analysis, the random dynamic loads applied are base excitation (earthquake)
The spectrum input used is Response Spectrum, defined by seismic Italian code: a spectral curve as a function of period.

The site is considered as low seismic and Code provide a ground acceleration of 0.05 g

Considering the building braced by concrete core structures, irregular and low ductile, a structural factor of 1.68 was adopted.
In this way we can calculate spectral acceleration for SLD and SLV conditions, to be used in spectral analysis:

SLV spectral curve

Seismic forces were combined with vertical and gravity forces as in Code requirements:

γEE+ γGGk + γPPk + Σ i (ψ2i γQQki)
Control of seismic displacement for the two structures and dimension of joint:

Displacement in x direction of structure “A”

Displacement in x direction of structure “B”

To determine the entity of the joint we adopted a safety factor gF = 1.4 for the displacements calculated (sum of displacements of
building “A” plus “B”):
wind:

Δx = (0.41+0.12)•gF = 0.53 •1.4 = 0.75 cm

seismic displacements:

Δx = (3.75+3.22)•gF = 6.97 •1.4 = 9.76 cm

A joint of 10 cm was realized between the two buildings.
Foundations

The model was supported by plates on ground support, of thickness corresponding to the mat foundation.
In this way you can have a response on the soil and structure interaction, calculating subsidence and pressure on ground.
In the following image you can see the example of pressure calculated under building “A”:

Max pressure on ground for building “A” (kg/cm2)
In the same way you can obtain the envelope of the maximum Bending moment in the x and y direction, to dimension reinforcement
and check Service and Ultimate limit states:

Plate moment Mxx max envelope in x direction
It is possible to create an envelope combined to obtain the percentage of rebars to be positioned every metre.
In the following image it is possible to see the maximum envelope, produced to estimate the percentage of top rebar in the mat
foundation, for x direction:

We decided to position a net of ø20mm rebars every 20 cm either on the bottom or on the top of the mat, so you can obtain an image
of the place where we have to integrate rebars in the x direction:
Serviceability Limit State: deflection control

Calculation of deformations under SLS combinations were used to control limitations given by Code.
Deflection of the building under wind loads were useful to dimension facades and window elements.

In the following figure the displacements due to wind on the long direction:

2.83 cm < H/500
Serviceability Limit State: stress control

Calculation of stress under SLS combinations were used to control limitations given by Code.

Serviceability limit states: envelope stress in all members
Lateral bracing system
Calculation of stress under ULS combinations were used to check resistance
Here we can see the vertical stress in shear walls forming the box shaped cores around stairs and elevators, modelled with plate
elements.
We can see the stress distribution on all the core and the integration of stresses on a wall, to obtain the forces needed to evaluate
Ultimate Limit State Resistance:

distribution of stresses in the core

Integration of stresses in the shear wall

Ultimate Limit State Resistance
Helicopter landing pad
Live load were given for the helicopter with dynamic action in landing and emergency conditions.
We can see the cantilever landing pad from the global model:

And a global view of the results in terms of stress in ULS conditions:

Cantilever landing pad: envelope stresses in members
In next image there is the simulation of vertical displacements of the cantilever beams, calculated for testing of the structures:
they were compared with experimental results.

Vertical displacements
CONCLUSIONS

The simulations here performed are design-oriented.

They were necessary to give a quick response to structural problems either for the final solutions or for construction problems.
In fact it was usual to be on yard with various models and take decision analysing the partial model in construction phases.
This is a correct way to optimize construction time safely.

With simulation analysis for such a particular structure we could check:

-

displacements to correctly dimension window-facades and guaranty serviceability for the whole structure

-

resistance and stability for all members

DESIGN AND CONSTRUCTION OF THE “FIERA MILANO BUILDING”
Ing. Luca ROMANO – I QUADRO INGEGNERIA – GENOVA

Más contenido relacionado

La actualidad más candente

Structural System Overview
Structural System OverviewStructural System Overview
Structural System Overview
Amjed Bin-Ali
 
Dynamic analysis of steel tube structure with bracing systems
Dynamic analysis of steel tube structure with bracing systemsDynamic analysis of steel tube structure with bracing systems
Dynamic analysis of steel tube structure with bracing systems
eSAT Journals
 

La actualidad más candente (20)

Understanding Gridshell Structures - Mannheim Multihalle Case Study
Understanding Gridshell Structures - Mannheim Multihalle Case StudyUnderstanding Gridshell Structures - Mannheim Multihalle Case Study
Understanding Gridshell Structures - Mannheim Multihalle Case Study
 
Space frames-modular construction technology
Space frames-modular construction technologySpace frames-modular construction technology
Space frames-modular construction technology
 
Tube Frame Structures:An overview
Tube Frame Structures:An overviewTube Frame Structures:An overview
Tube Frame Structures:An overview
 
Rigid frame systems
Rigid frame systemsRigid frame systems
Rigid frame systems
 
Structural System Overview
Structural System OverviewStructural System Overview
Structural System Overview
 
The technologies of building resists the wind load and earthquake
The technologies of building resists the wind load and earthquakeThe technologies of building resists the wind load and earthquake
The technologies of building resists the wind load and earthquake
 
Tube structures
Tube structuresTube structures
Tube structures
 
Indian examples of long span structures
Indian examples of long span structuresIndian examples of long span structures
Indian examples of long span structures
 
Long span structure
Long span structureLong span structure
Long span structure
 
Large span structures
Large span structuresLarge span structures
Large span structures
 
Dynamic analysis of steel tube structure with bracing systems
Dynamic analysis of steel tube structure with bracing systemsDynamic analysis of steel tube structure with bracing systems
Dynamic analysis of steel tube structure with bracing systems
 
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang SchuellerSpanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
 
Tall buildings
Tall buildingsTall buildings
Tall buildings
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 
Tube structures
 Tube structures  Tube structures
Tube structures
 
Buildings Structure system
Buildings Structure systemBuildings Structure system
Buildings Structure system
 
Bundled Tube Structural System
 Bundled Tube Structural System Bundled Tube Structural System
Bundled Tube Structural System
 
Long span structure
Long span structureLong span structure
Long span structure
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)
 
Tos syllabus
Tos syllabusTos syllabus
Tos syllabus
 

Destacado

O2 Arena Booklet
O2 Arena BookletO2 Arena Booklet
O2 Arena Booklet
eileen_0692
 
Millennium dome %28 pp%29
Millennium dome %28 pp%29Millennium dome %28 pp%29
Millennium dome %28 pp%29
carodriguez21
 
STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOMESTUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
Haya Haroon
 

Destacado (20)

O2 Arena Booklet
O2 Arena BookletO2 Arena Booklet
O2 Arena Booklet
 
TENSILE / FABRIC ARCHITECTURE SEMINAR
TENSILE / FABRIC ARCHITECTURE SEMINARTENSILE / FABRIC ARCHITECTURE SEMINAR
TENSILE / FABRIC ARCHITECTURE SEMINAR
 
TENSEGRITY - Smart Structures - G@T
TENSEGRITY - Smart Structures -  G@TTENSEGRITY - Smart Structures -  G@T
TENSEGRITY - Smart Structures - G@T
 
Steel structures practical_design_studies_mac_ginley_2nd_ed
Steel structures practical_design_studies_mac_ginley_2nd_edSteel structures practical_design_studies_mac_ginley_2nd_ed
Steel structures practical_design_studies_mac_ginley_2nd_ed
 
Structure as Architecture
Structure as ArchitectureStructure as Architecture
Structure as Architecture
 
Millennium dome %28 pp%29
Millennium dome %28 pp%29Millennium dome %28 pp%29
Millennium dome %28 pp%29
 
BRIHADEESWARAR TEMPLE - An Ancient Architectural marvel
BRIHADEESWARAR TEMPLE - An Ancient Architectural marvelBRIHADEESWARAR TEMPLE - An Ancient Architectural marvel
BRIHADEESWARAR TEMPLE - An Ancient Architectural marvel
 
Base Structures Tensile Fabric Webinar 2: Realising your tensile fabric vision
Base Structures Tensile Fabric Webinar 2: Realising your tensile fabric visionBase Structures Tensile Fabric Webinar 2: Realising your tensile fabric vision
Base Structures Tensile Fabric Webinar 2: Realising your tensile fabric vision
 
STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOMESTUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
STUDY OF FAILED PROJECT ---- THE MILLENNIUM DOME
 
The cables structure system
The cables structure systemThe cables structure system
The cables structure system
 
Tensile Fabric Structures
Tensile Fabric StructuresTensile Fabric Structures
Tensile Fabric Structures
 
Tensile structures
Tensile structuresTensile structures
Tensile structures
 
Roof
RoofRoof
Roof
 
Long span structures
Long span structures  Long span structures
Long span structures
 
Long span cable
Long span cableLong span cable
Long span cable
 
Cable strucutres(presentation)
Cable strucutres(presentation)Cable strucutres(presentation)
Cable strucutres(presentation)
 
Beijing National Stadium
Beijing National StadiumBeijing National Stadium
Beijing National Stadium
 
Roof
RoofRoof
Roof
 
The shell structure system
The shell structure systemThe shell structure system
The shell structure system
 
The cable in building structures
The cable in building structuresThe cable in building structures
The cable in building structures
 

Similar a CAE Conference - Luca Romano - 21 october 2013

Similar a CAE Conference - Luca Romano - 21 october 2013 (20)

Heydar Aliyev Cultural Centre
Heydar Aliyev Cultural CentreHeydar Aliyev Cultural Centre
Heydar Aliyev Cultural Centre
 
Long span structures case study.pptx
Long span structures case study.pptxLong span structures case study.pptx
Long span structures case study.pptx
 
Turning torso
Turning torsoTurning torso
Turning torso
 
MDC.pptx
MDC.pptxMDC.pptx
MDC.pptx
 
Bcon
BconBcon
Bcon
 
Bcon bus shelter skeletal construction P1
Bcon bus shelter skeletal construction P1Bcon bus shelter skeletal construction P1
Bcon bus shelter skeletal construction P1
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
Building construction ii (1)
Building construction ii (1)Building construction ii (1)
Building construction ii (1)
 
Building construction ii
Building construction iiBuilding construction ii
Building construction ii
 
Building construction 02
Building construction 02Building construction 02
Building construction 02
 
Building Construction 02 (Project1)
Building Construction 02 (Project1)Building Construction 02 (Project1)
Building Construction 02 (Project1)
 
Denver Art Museum
Denver Art MuseumDenver Art Museum
Denver Art Museum
 
Steel uses in buildings
Steel uses in buildingsSteel uses in buildings
Steel uses in buildings
 
Masonry structures confined with concrete beams an dcolumns
Masonry structures confined with concrete beams an dcolumnsMasonry structures confined with concrete beams an dcolumns
Masonry structures confined with concrete beams an dcolumns
 
B con 2
B con 2B con 2
B con 2
 
Lecture 8 THigh Rise structures.pdf
Lecture 8 THigh Rise structures.pdfLecture 8 THigh Rise structures.pdf
Lecture 8 THigh Rise structures.pdf
 
Heydar Aliyev Center Structural system and materials
Heydar Aliyev Center Structural system and materialsHeydar Aliyev Center Structural system and materials
Heydar Aliyev Center Structural system and materials
 
Case Study: Catenary Structures
Case Study: Catenary StructuresCase Study: Catenary Structures
Case Study: Catenary Structures
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
Cube tower mexico
Cube tower mexicoCube tower mexico
Cube tower mexico
 

Más de Franco Bontempi

La realtà dei ponti e dei viadotti: controllo e manutenzione
La realtà dei ponti e dei viadotti: controllo e manutenzioneLa realtà dei ponti e dei viadotti: controllo e manutenzione
La realtà dei ponti e dei viadotti: controllo e manutenzione
Franco Bontempi
 

Más de Franco Bontempi (20)

84-91 UNI RM - Bontempi REV.pdf
84-91 UNI RM - Bontempi REV.pdf84-91 UNI RM - Bontempi REV.pdf
84-91 UNI RM - Bontempi REV.pdf
 
PGS - lezione 63 - robustness.pdf
PGS - lezione 63 - robustness.pdfPGS - lezione 63 - robustness.pdf
PGS - lezione 63 - robustness.pdf
 
PGS - lezione 60 - evidences of failures.pdf
PGS - lezione 60 - evidences of failures.pdfPGS - lezione 60 - evidences of failures.pdf
PGS - lezione 60 - evidences of failures.pdf
 
La realtà dei ponti e dei viadotti: controllo e manutenzione
La realtà dei ponti e dei viadotti: controllo e manutenzioneLa realtà dei ponti e dei viadotti: controllo e manutenzione
La realtà dei ponti e dei viadotti: controllo e manutenzione
 
ANALISI DEL RISCHIO PER LA SICUREZZA NELLE GALLERIE STRADALI.
ANALISI DEL RISCHIO PER LA SICUREZZA NELLE GALLERIE STRADALI.ANALISI DEL RISCHIO PER LA SICUREZZA NELLE GALLERIE STRADALI.
ANALISI DEL RISCHIO PER LA SICUREZZA NELLE GALLERIE STRADALI.
 
RISK ANALYSIS FOR SEVERE TRAFFIC ACCIDENTS IN ROAD TUNNELS
RISK ANALYSIS FOR SEVERE TRAFFIC ACCIDENTS IN ROAD TUNNELSRISK ANALYSIS FOR SEVERE TRAFFIC ACCIDENTS IN ROAD TUNNELS
RISK ANALYSIS FOR SEVERE TRAFFIC ACCIDENTS IN ROAD TUNNELS
 
Approccio sistemico al progetto dei grandi ponti
Approccio sistemico al progetto dei grandi pontiApproccio sistemico al progetto dei grandi ponti
Approccio sistemico al progetto dei grandi ponti
 
PGS - lezione D - grandi strutture.pdf
PGS - lezione D - grandi strutture.pdfPGS - lezione D - grandi strutture.pdf
PGS - lezione D - grandi strutture.pdf
 
PGS - lezione F - ingegneria forense.pdf
PGS - lezione F - ingegneria forense.pdfPGS - lezione F - ingegneria forense.pdf
PGS - lezione F - ingegneria forense.pdf
 
PGS - lezione C - controllo e manutenzione.pdf
PGS - lezione C - controllo e manutenzione.pdfPGS - lezione C - controllo e manutenzione.pdf
PGS - lezione C - controllo e manutenzione.pdf
 
PSA_MF_05_05_23.pdf
PSA_MF_05_05_23.pdfPSA_MF_05_05_23.pdf
PSA_MF_05_05_23.pdf
 
PSA_MF_04_05_23.pdf
PSA_MF_04_05_23.pdfPSA_MF_04_05_23.pdf
PSA_MF_04_05_23.pdf
 
Fenomeni di instabilita'
Fenomeni di instabilita'Fenomeni di instabilita'
Fenomeni di instabilita'
 
Introduzione al Calcolo Elasto – Plastico «a freddo» delle strutture in acciaio
Introduzione al Calcolo Elasto – Plastico «a freddo» delle strutture in acciaioIntroduzione al Calcolo Elasto – Plastico «a freddo» delle strutture in acciaio
Introduzione al Calcolo Elasto – Plastico «a freddo» delle strutture in acciaio
 
FB - PSA Esercitazione 1_12_18-II parte.pdf
FB - PSA Esercitazione 1_12_18-II parte.pdfFB - PSA Esercitazione 1_12_18-II parte.pdf
FB - PSA Esercitazione 1_12_18-II parte.pdf
 
Gestione di Ponti e Grandi Strutture: Spalle - Pile - Antenne
Gestione di Ponti e Grandi Strutture: Spalle - Pile - AntenneGestione di Ponti e Grandi Strutture: Spalle - Pile - Antenne
Gestione di Ponti e Grandi Strutture: Spalle - Pile - Antenne
 
Esplosioni.
Esplosioni.Esplosioni.
Esplosioni.
 
PGS - lezione 04 - MODELLAZIONI DISCRETE.pdf
PGS - lezione 04 - MODELLAZIONI DISCRETE.pdfPGS - lezione 04 - MODELLAZIONI DISCRETE.pdf
PGS - lezione 04 - MODELLAZIONI DISCRETE.pdf
 
PGS - lezione 03 - IMPALCATO DA PONTE E PIASTRE.pdf
PGS - lezione 03 - IMPALCATO DA PONTE E PIASTRE.pdfPGS - lezione 03 - IMPALCATO DA PONTE E PIASTRE.pdf
PGS - lezione 03 - IMPALCATO DA PONTE E PIASTRE.pdf
 
INCENDIO
INCENDIOINCENDIO
INCENDIO
 

Último

➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
amitlee9823
 
ab-initio-training basics and architecture
ab-initio-training basics and architectureab-initio-training basics and architecture
ab-initio-training basics and architecture
saipriyacoool
 
Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...
Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...
Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...
amitlee9823
 
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
amitlee9823
 
➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men 🔝Kolkata🔝 Escorts...
➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men  🔝Kolkata🔝   Escorts...➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men  🔝Kolkata🔝   Escorts...
➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men 🔝Kolkata🔝 Escorts...
amitlee9823
 
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
gajnagarg
 
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
amitlee9823
 
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
amitlee9823
 
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
nirzagarg
 

Último (20)

High Profile Escorts Nerul WhatsApp +91-9930687706, Best Service
High Profile Escorts Nerul WhatsApp +91-9930687706, Best ServiceHigh Profile Escorts Nerul WhatsApp +91-9930687706, Best Service
High Profile Escorts Nerul WhatsApp +91-9930687706, Best Service
 
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men  🔝dehradun🔝   Escor...
➥🔝 7737669865 🔝▻ dehradun Call-girls in Women Seeking Men 🔝dehradun🔝 Escor...
 
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
 
ab-initio-training basics and architecture
ab-initio-training basics and architectureab-initio-training basics and architecture
ab-initio-training basics and architecture
 
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 104, Noida Call girls :8448380779 Model Escorts | 100% verified
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
 
Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...
Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...
Vip Mumbai Call Girls Borivali Call On 9920725232 With Body to body massage w...
 
Sweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptxSweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptx
 
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men  🔝jhansi🔝   Escorts S...
➥🔝 7737669865 🔝▻ jhansi Call-girls in Women Seeking Men 🔝jhansi🔝 Escorts S...
 
8377087607, Door Step Call Girls In Majnu Ka Tilla (Delhi) 24/7 Available
8377087607, Door Step Call Girls In Majnu Ka Tilla (Delhi) 24/7 Available8377087607, Door Step Call Girls In Majnu Ka Tilla (Delhi) 24/7 Available
8377087607, Door Step Call Girls In Majnu Ka Tilla (Delhi) 24/7 Available
 
Sector 105, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 105, Noida Call girls :8448380779 Model Escorts | 100% verifiedSector 105, Noida Call girls :8448380779 Model Escorts | 100% verified
Sector 105, Noida Call girls :8448380779 Model Escorts | 100% verified
 
UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...
UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...
UI:UX Design and Empowerment Strategies for Underprivileged Transgender Indiv...
 
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
💫✅jodhpur 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATISFACT...
 
➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men 🔝Kolkata🔝 Escorts...
➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men  🔝Kolkata🔝   Escorts...➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men  🔝Kolkata🔝   Escorts...
➥🔝 7737669865 🔝▻ Kolkata Call-girls in Women Seeking Men 🔝Kolkata🔝 Escorts...
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
 
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
Just Call Vip call girls dharamshala Escorts ☎️9352988975 Two shot with one g...
 
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
 
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men  🔝dharamshala🔝  ...
➥🔝 7737669865 🔝▻ dharamshala Call-girls in Women Seeking Men 🔝dharamshala🔝 ...
 
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
Nisha Yadav Escorts Service Ernakulam ❣️ 7014168258 ❣️ High Cost Unlimited Ha...
 

CAE Conference - Luca Romano - 21 october 2013

  • 1. CAE CONFERENCE 2013 Lazise (VR) 21÷22 october 2013 DESIGN AND CONSTRUCTION OF THE “FIERA MILANO BUILDING” Ing. Luca ROMANO – I QUADRO INGEGNERIA – GENOVA
  • 2. LOCATION OF THE “FIERA MILANO BUILDING” PLAN VIEW AERIAL VIEW
  • 3. INTERNATIONAL TENDER The design of this building followed from an international tender, in which different groups of architects, engineers and constructioncompanies proposed their ideas for the new offices of the “Fiera Milano building”. The winning proposal was conceived as a golden, horizontal tower at the east entrance of the “Fiera di Milano”. Here you can see some early images of the winning idea for the tender:
  • 4. DESCRIPTION OF THE BUILDING During the competition phase various solutions were studied in order to match construction time and costs. This resulted in a mixed steel-concrete structure that allowed to complete the building in less than two years and to respect tender costs. Design consists of a 132.5 m long building of 15.60 m depth and about 60 m height. The Building is divided in two by a joint: building “A” is composed by 12 floors while building “B” is composed by 13 floors. They are separated but connected by the foyer with staircases and footbridges. In order to provide an helicopter landing pad, an important cantilever steel structure was built on the roof of building “B”. Side of the building in the actual destination Rear of the building with view of the landing pad
  • 5. Here are some views of the finished building: Side of the building with view of the cantilever landing pad View of the rear of the building
  • 6. The building is composed by two parts connected by a foyer and footbridges at different floors. BUILDING “A” FOYER Plan view of the building, with the landing pad on the right BUILDING “B”
  • 7. STRUCTURE Structural Strategy And Description The structure was very long, so it was divided in two structures separated by a joint. Here you can see the typical floor plan: joint BUILDING “B” BUILDING “A” plan view of the typical floor Longitudinally the structure is a repetition of 6.25 m spaced columns; they are aligned along the perimeter and on an internal position. Transversely two precast, prestressed slabs - 4.25 m and 10.7 m long - connect the longitudinal steel beams. These beams are made with welded plates, to reduce thickness.
  • 8. STRUCTURE Each building is a core supported structure, with shear walls, to resist lateral forces from wind and earthquakes. In this way steel columns are pinned at the base and resist only to vertical loads. This classical strategy was adopted to realize the structure in few months, with respect of tender costs: steel structures was produced on workshop, while on construction site we realized reinforced concrete core structures. Core structures of the two buildings - floors in construction
  • 9. Concrete core structures were realized with climbing form-works. In the picture you can see also the steel boxes provided in the walls for the connection of steel beams: Climbing form-works for the shear walls of stair cases
  • 10. In this way the steel structure was a simple assembly of pinned columns and hinged beams: Pinned connections of the steel columns
  • 11. Steel beams were composed with welded plates, hinged and dimensioned to support precast slabs: To reduce thickness, slabs were supported on bottom flange: Prestressed slabs are placed on the wide bottom flanges of the steel beams and casted in situ. Slabs were 30 cm thick, 10.25 metres long, with a layer of 5 cm of concrete cast in situ. In the following details you can see the intersection beam-slab:
  • 12. Here are some pictures of the construction phases of the floors: Positioning of precast slab of floors Detail of the intersection between slab and steel beams (view from above and from below)
  • 13. FOOTBRIDGES The connecting foyer has footbridges 12 metres long, at various floors. These structures are free to move to absorb lateral movements due to wind, earthquakes and thermal effects. They are composed by IPE 500 steel beams with a composite slab on cold-formed steel decking. Main steel beams of the two footbridges connecting the two buildings: fixed on one side and free to move on the other.
  • 14. FOYER The foyer is an hollow structure with staircases and footbridges connecting people at each floor. Windows in front of the foyer have a complicate pinned systems that permits movements of translation and rotation of the two buildings. These windows are linked to a steel tree-structure, pinned to building “B” and free to move in the connection of building “A”. Cinematic was important to prevent window crashes and all calculated displacements were given to the facade developers to take care of relative movements. view of the foyer connecting the two buildings view of the finished foyer from below, in the entrance
  • 15. Here you can see the structural detail of the hinges of the tree-structure of the foyer: General and detailed view of the Pinned and slipping connections of the facade of the foyer STRUCTURE “A” STRUCTURE “B” Plan view detail of the foyer
  • 16. Construction phases were important. Before finishing the roof, the wall at the rear of the foyer was 54 metres high, 40 cm thick, separated by joint and free at the top. Because of stability check, you can see some provisional beams positioned. You can also see the joint which separates the two structures. joint
  • 17. HELICOPTER LANDING PAD: On the roof of building “B” an helicopter landing pad was realized. The structure is made with cantilever “I” beams, 10 metres apart from the facade, connected by damping supports to the steel columns of the building, not to transmit vibrations. The deck was formed by aluminium box section supported by the beams. General view of the structure of the landing pad detail of the structure extremity
  • 18. Here you can see the design of the steel structure: the plan view on the left and the cross section of the cantilever on the right. Only extremity columns were used as support, to prevent traction. 10 m building
  • 19. FOUNDATIONS In order to prevent ground displacements and subsidence, we realized a steel sheet-pile bulkhead, 10 metres long, installed by vibratory hammer. In the picture one can see this earth retaining wall without dead space near existing buildings: Positioning of steel sheet piles before digging
  • 20. Another problem was the presence of the Underground of Milan, that didn’t accept any pressure against its existing walls. That’s why we had to dig till the bottom of the tube, realize a joint and replace the ground with casting concrete, able to resist to the pressure of the new building transmitting forces only to the bottom of the foundation. Steel sheet piles and base of the mat foundation. On the left the existing Underground Concrete casting near the Underground, to prevent earth pressure against existing walls
  • 21. Underground of Milan asked the simulation of the construction phases. Here you can see the vertical section, with the Tube on the left, the mat foundations on the right and the concrete layer in the middle: The simulation analysis was performed in 5 steps with a bi-dimensional model, to answer the Underground of Milan in terms of subsidence:
  • 22. Mat Foundation Due to the good soil characteristic, we designed a mat foundation, continuous under the entire building. Instead, the building itself was divided in two structures, which were separated by a joint. The thickness of the mat was 1 metre under the steel columns and 1.5 metres under the core structures. It was reduced to 40 cm near the steel sheet piles, in order to reduce the cantilever. In the following plan view you can see the foundation: 137 metres long and 30 metres wide:
  • 23. In the next picture you can see the positioning of reinforcement in the mat: Reinforcement of the mat foundation before casting
  • 24. ANALYSIS The structure had many particularities, but is was not so unusual. So we decided to realize models for design purpose, easy to handle and to understand. Here you can see the finite element model of the structure, performed with Straus 7. The model simulate the exact structural stiffness by mean of: 2084 element beam 12427 element plate for a total of 46994 degrees of freedom View of the model
  • 25. Mat foundations are modelled with plate elements on ground support: Modulus of Subgrade Reaction These plates have either membrane or bending properties, calculated through their thickness. Earth retaining walls are modelled with plate elements. Columns and beams are modelled with beam elements, hinged at the end. shear walls forming the box shaped cores around stairs and elevators, are modelled with plate elements, which have either membrane or bending properties, calculated through their thickness. This is a spatial system capable of resisting all types of loads: vertical forces, shear forces and bending moments in all directions, as well as torsion. In this way we realized an efficient lateral load resistance structure for the two buildings.
  • 26. Slabs are modelled with load patch elements and rigid floor links. This plate element does not have any property attributes. It is used solely as a way of transferring distributed area loads and nonstructural mass to beams that may be connected around the perimeter of the plate: In this way you don’t influence the stiffness of beams and you consider the rigid link of each floor. The software Straus 7 allows the definition of different non structural mass for various load condition and to any of them one can associate a dynamic factor that define the mass to be considered in dynamic analysis. In this way you have the maximum of possibilities of simulating seismic conditions.
  • 27. Analysis performed during design were of three types: - Static: load conditions – SLS and ULS combinations - envelopes - Dynamic: natural frequencies – mode shapes - Spectral response: seismic base excitation During construction phases we performed also various static analysis on partial models, to help the construction company to reduce construction time.
  • 28. Static analysis are performed considering various load conditions: - Self weight is automatically determined by Straus 7 - Either permanent or live loads were introduced through non structural mass in different load cases - Wind was introduced through forces acting on facade load patch elements. These forces change of intensity with height Solutions were combined to maximize effects on beams and columns. Various combinations were performed, in order to obtain Service and Ultimate Limit State conditions. For example next figure represent maxima axial forces at ULS for the columns:
  • 29. In next image we see the values of axial forces in columns and stresses in shear walls of a single floor. They are used for resistance and stability check required by Code:
  • 30. The natural frequency solver was used to calculate free vibration frequencies and corresponding mode shapes of the undamped structure. It is possible to determine the participation factors for all directions to be sure to involve more than 85% of the global mass of the structure: 100 mode shapes were necessary. In next figure you see the first mode shape of structure “A”: first bending mode shape in the transverse direction: 0.61 Hz of frequency
  • 31. In next figure you see the first six mode shapes of structure “A”: First six mode shapes of structure “A”
  • 32. Seismic design The Spectral Response solver calculates the response of a structure subjected to a random dynamic loading. In this spectral response analysis, the random dynamic loads applied are base excitation (earthquake) The spectrum input used is Response Spectrum, defined by seismic Italian code: a spectral curve as a function of period. The site is considered as low seismic and Code provide a ground acceleration of 0.05 g Considering the building braced by concrete core structures, irregular and low ductile, a structural factor of 1.68 was adopted. In this way we can calculate spectral acceleration for SLD and SLV conditions, to be used in spectral analysis: SLV spectral curve Seismic forces were combined with vertical and gravity forces as in Code requirements: γEE+ γGGk + γPPk + Σ i (ψ2i γQQki)
  • 33. Control of seismic displacement for the two structures and dimension of joint: Displacement in x direction of structure “A” Displacement in x direction of structure “B” To determine the entity of the joint we adopted a safety factor gF = 1.4 for the displacements calculated (sum of displacements of building “A” plus “B”): wind: Δx = (0.41+0.12)•gF = 0.53 •1.4 = 0.75 cm seismic displacements: Δx = (3.75+3.22)•gF = 6.97 •1.4 = 9.76 cm A joint of 10 cm was realized between the two buildings.
  • 34. Foundations The model was supported by plates on ground support, of thickness corresponding to the mat foundation. In this way you can have a response on the soil and structure interaction, calculating subsidence and pressure on ground. In the following image you can see the example of pressure calculated under building “A”: Max pressure on ground for building “A” (kg/cm2)
  • 35. In the same way you can obtain the envelope of the maximum Bending moment in the x and y direction, to dimension reinforcement and check Service and Ultimate limit states: Plate moment Mxx max envelope in x direction
  • 36. It is possible to create an envelope combined to obtain the percentage of rebars to be positioned every metre. In the following image it is possible to see the maximum envelope, produced to estimate the percentage of top rebar in the mat foundation, for x direction: We decided to position a net of ø20mm rebars every 20 cm either on the bottom or on the top of the mat, so you can obtain an image of the place where we have to integrate rebars in the x direction:
  • 37. Serviceability Limit State: deflection control Calculation of deformations under SLS combinations were used to control limitations given by Code. Deflection of the building under wind loads were useful to dimension facades and window elements. In the following figure the displacements due to wind on the long direction: 2.83 cm < H/500
  • 38. Serviceability Limit State: stress control Calculation of stress under SLS combinations were used to control limitations given by Code. Serviceability limit states: envelope stress in all members
  • 39. Lateral bracing system Calculation of stress under ULS combinations were used to check resistance Here we can see the vertical stress in shear walls forming the box shaped cores around stairs and elevators, modelled with plate elements.
  • 40. We can see the stress distribution on all the core and the integration of stresses on a wall, to obtain the forces needed to evaluate Ultimate Limit State Resistance: distribution of stresses in the core Integration of stresses in the shear wall Ultimate Limit State Resistance
  • 41. Helicopter landing pad Live load were given for the helicopter with dynamic action in landing and emergency conditions. We can see the cantilever landing pad from the global model: And a global view of the results in terms of stress in ULS conditions: Cantilever landing pad: envelope stresses in members
  • 42. In next image there is the simulation of vertical displacements of the cantilever beams, calculated for testing of the structures: they were compared with experimental results. Vertical displacements
  • 43. CONCLUSIONS The simulations here performed are design-oriented. They were necessary to give a quick response to structural problems either for the final solutions or for construction problems. In fact it was usual to be on yard with various models and take decision analysing the partial model in construction phases. This is a correct way to optimize construction time safely. With simulation analysis for such a particular structure we could check: - displacements to correctly dimension window-facades and guaranty serviceability for the whole structure - resistance and stability for all members DESIGN AND CONSTRUCTION OF THE “FIERA MILANO BUILDING” Ing. Luca ROMANO – I QUADRO INGEGNERIA – GENOVA