2. Questions
How do I know if the molder is giving the mold a chance to perform?
How do I know if the processor has the mold in the correct machine?
How do I know if this machine is even capable?
Why, when we adjust the tool steel to meet the dimensions, are they
not correct the next time they try it out?
We have modified this mold six times and it still is not correct!
They got good parts out of this mold at the other molder, why can’t
you?
It fits between the tie bars and you have enough shot size, so what is
the problem?
These are a small sampling of questions that cause process problems and cost
money. With increasing pressure from a global economy and local competition we
need to be more thorough in bringing the mold to production either as a new
production or a tool that has been transferred from another molder.
2 - Lean
3. Start-Up Companies
Domestic & Foreign Investment Groups
Your Company Your Competitors
Your Building Their Building
Your Equipment Their Equipment
Your Employees Their Employees
Your Customers Seeking Your Customers
What sets you apart from your competitors?
KNOWLEDGE!
And how you use it 3 - Lean
4. Systematic Molding Defined
Making operational decisions based on data and
analysis as opposed to only intuition, opinions and
politics to achieve optimal results.
Using monitoring, containment and control to
achieve a level of quality always exceeding the
customer’s expectation.
4 - Lean
5. “Progress Always Involves Risk.
You can’t steal second base and
keep your foot on first base.”
Frederick Wilcox
5 - Lean
7. Request for Quote
The part: AB Switch Housing
Material: Polypropylene MFI 4
Quantity: 100,000 annually
Cost: $$$$$$ per number of parts or per part
Time: Six weeks to production
Tooling Budget: $$$$$
Quality: First Article or PPAP
Gate Location: Cosmetic concerns
7 - Lean
9. Potential Problem Areas
How can we fix this?
How do we communicate this to the customer?
Will the customer allow a design change?
9 - Lean
10. PART RELEASE
As plastic parts cool and shrink in the mold they:
Pull away from the cavity
Draw down tightly onto the core
Since the part must slide out of the mold without distortion, draft angles
parallel to. Part release are necessary on all draw surfaces.
The degree of draft required is a function of:
Material shrinkage rate and abrasiveness
Part surface requirements
Uniformity of wall thickness
Depth of draw
Any draft is better than none.
Specify the largest that the functional requirements of the part will
allow. 10 - Lean
11. Validating Draft for Part Release
If we cannot have draft our strategy must change to remove the
part from the mold (mechanically) and cavity pressures may
need to be kept low (process), therefore shrink rates go up.
11 - Lean
12. RADIUS
In the design of the injection-molded parts, sharp corners should always be
avoided
Inside corners on the molded parts are highly stressed and have historically
been the highest single cause of part failure
Outside corners are difficult to fill and trap air and gas, which creates burn marks
Generally desirable to be greater than 25% of the wall thickness
Sufficient Radii
Distribute stress
Improve flow It is rare when one size is best for all
Promote uniform shrinkage corners
Reduce sink, voids and There may be locations (such as parting
warpage line) where radius is impractical
Eliminate trapped air 12 - Lean
14. Wall thickness
If the functional requirements of a part require a departure from
nominal wall, the designer must visualize how plastic flow and
shrinkage will interact with the design to affect properties.
Wall thickness changes should be minimal and gradual
As a general guideline, wall thickness changes should be less than
25% of the nominal. This is more important with semi-crystalline
plastics
Lack of uniform nominal wall thickness is the single most troublesome
problem encountered relative to part design
14 - Lean
16. Additions & Subtractions
Additions are part features that present a non-linear
extension of the wall
Ribs
Bosses
Gussets
Raised areas
All have much in common from a design point of view
The design issues relate to:
Shape
Spacing
SHAPE
The primary goal is to reduce the effect of modifying the
constant wall thickness by keeping the base as small as
possible
Generally, around 1/2 the wall thickness (50% of the
wall thickness)
Projections on parts are formed by depressions in the
mold
Those depressed areas are difficult to fill and vent
To minimize the effect, projections should be kept as
short as possible (generally less than three times the
wall thickness)
Shrinkage of plastic between vertical projections can
cause stresses, particularly at the corners
To minimize this effect, projections should not be placed
too close together (generally not closer than two times
the wall thickness)
16 - Lean
18. There is Still a Problem
Depressions into the wall to create holes
Through
Blind
Round
Square
Irregular
Slots
Grooves
Threads (inside and outside)
Square or irregular holes with sharp corners create stresses
which can cause cracks in parts as they shrink or during
ejection
To minimize this effect, radius corners as much as the
functional requirements of the part will allow
The part will be less stressed and progressively stronger as
radius is increased 18 - Lean
22. Gate and Location
What type of gate would we use?
Benefits
Concerns
Where would the gate be placed?
What quality issues might we have?
What if the budget for the mold was a concern or limited, what
options do we have?
Should I be concerned with gate seal time at this time?
What information do I need to make a decision on gate size?
Where the knit line be?
22 - Lean
23. Developing a Setup Sheet
Prior to Cutting Steel
Measuring Risk of Producing this Product.
23 - Lean
24. Solid Model
Key Information from Solid Model
Cubic inch volume of the solid model is 5.09
Sprue / Runner volume is 2.73 cubic inches
Square inches at the parting line is 7.99
Key Information from Flow Analysis
Fill Time is .95 seconds
Pressure near gate is 12,000 ppsi
Pressure at end of part 2,600 ppsi
Average pressure in the mold to produce a good
part is 7300ppsi
Tons per square inch is 3.65
Cooling Time 16 seconds
Pack/Hold Time 7 seconds
Pack/Hold Pressure 14,370ppsi
Set up Sheet
We can establish a shot size, transfer position and cushion from the volume.
We can establish the clamp force needed based on the square inches and the
average cavity pressure.
24 - Lean
25. Measuring Risk of Potential
Problem Areas
Square corners equals risk of 5
Additions to walls equals risk of 5
Change in wall thickness equals risk of 5 if
gate location is on opposing end of part
25 - Lean
26. Modified Part
High Risk Part Design Low Risk Part Design
Square corners equals risk of 5
Square corners equals risk of 2
Additions to walls equals risk of 5
Additions to walls equals risk of 5
Change in wall thickness equals risk of 5 if
gate location is on opposing end of part Change in wall thickness equals risk of 3
26 - Lean
27. Selected Number of Cavities
Risk
Runner layout: a risk of 2
Gate location: a risk of 5
Gate Type: a risk of 3
Balance of Fill 3
Risk of cold slug well/puller design 5 27 - Lean
29. Our Potential Molding Machine
220 ton clamp force
1.77 in diameter screw
2600 psi hydraulic pump
12.2:1 Intensification Ratio
Maximum Plastic pressure generated is 31,720 ppsi
General Purpose Screw with a compression ration of 2.0
L/D of 20:1
Square pitch flight pattern of 10/5/5
12 inch linear shot capability
Maximum Injection Speed 10.2
29 - Lean
30. Decoupled II Pre Process
Setup Sheet
Plastic Flow Rate
Shot Size 10.668 inches Transfer Position 1.454 inches Cushion .969 inches Decompress .312 inches
Fill Time .95 seconds Injection Speed 9.7 inches per second Fill Only Part Weight 72.07 grams
Clamp Force
Clamp Force 136 Tons
30 - Lean
32. Decoupled II Pre Process Setup Sheet
Plastic Flow Rate
Shot Size 10.668 inches Transfer Position 1.454 inches Cushion .969 inches Decompress .312 inches
Fill Time .95 seconds Injection Speed 9.7 inches per second Fill Only Part Weight 72.07 grams
Clamp Force
Clamp Force 136 Tons
Plastic Temperature
Melt Temperature 412.5 degrees Back Pressure 61.5psi RPM 75
Nozzle 412.5 degrees Front Zone 412.5 degrees Middle Zone 412.5 degrees Rear Zone 412.5 degrees
Plastic Pressure
Pack/Hold Time 7 seconds Pack/Hold Pressure 14,370 ppsi Full Part Weight 75.87 grams
Gate Seal Yes
Plastic Cooling
Cooling Timer 16 seconds Mold Temperature 120 degrees
32 - Lean
33. Measuring the Risk of the Setup
Plastic Flow Rate
Shot Size 10.668 inches5 Transfer Position 1.454 inches1 Cushion .969 inches1 Decompress .312inches1
Fill Time .95 seconds5 Injection Speed 9.7 inches per second5 Fill Only Part Weight 72.07 grams1
Clamp Force
Clamp Force 136 Tons3
Plastic Temperature
Melt Temperature 412.5 degrees2 Back Pressure 61.5ps1 RPM 751
Nozzle 412.5 degrees1 Front Zone 412.5 degrees1 Middle Zone 412.5 degrees1 Rear Zone 412.5 degrees1
Plastic Pressure
Pack/Hold Time 7 seconds1 Pack/Hold Pressure 14,370 ppsi1 Full Part Weight 75.87 grams1
Gate Seal Yes
Plastic Cooling
Cooling Timer 16 seconds1 Mold Temperature 120 degrees1
33 - Lean
34. The Risk
The Process
Shot Size 10.668 inches5 Transfer Position 1.454 inches1 Cushion .969 inches1 Decompress .312inches1
Fill Time .95 seconds5 Injection Speed 9.7 inches per second5 Fill Only Part Weight 72.07 grams1
Clamp Force 136 Tons3 Back Pressure 61.5ps1 RPM 751
Melt Temperature 412.5 degrees2
Nozzle 412.5 degrees1 Front Zone 412.5 degrees1 Middle Zone 412.5 degrees1 Rear Zone 412.5 degrees1
Pack/Hold Time 7 seconds1 Pack/Hold Pressure 14,370 ppsi1 Full Part Weight 75.87 grams1
Gate Seal 1 Cooling Timer 16 seconds1 Mold Temperature 120 degrees1
The Part
Square corners equals risk of 5 Additions to walls equals risk of 5 Change in wall thickness equals risk of 5
Cavity Layout
Runner layout: a risk of 5 Gate location: a risk of 5 Gate Type: a risk of 3 Balance of Fill 5
Risk of cold slug well/puller design 5
Potential Total Risk of 29 topics at a Our Risk of Producing this Product is 74 which is a
severe rating of 5 equals very average part to produce
145 74
34 - Lean
35. Systematic Tool Transfers Defined
Systematic Tool Transfer uses information from
all available sources and data from sensors to
establish a normalized setup which can be
recreated with a high degree of certainty on other
correct and capable machines.
35 - Lean
36. Reasons for tool transfers
New Tool Launch with tryout at tool builders facility
Intra company tool transfers
Reorganization
Reduction (manpower, Building usage, Consolidation)
Outside Tool Transfer (Some may be Hostile)
Lack of Profits
Poor repeatable quality from production
Poor tool quality
Better Logistics
In this seminar will focus on Intra and Outside Tool Transfers.
36 - Lean
37. Tool Transfer Methodology
Step 1: Risk Analysis Step 2: Risk Mitigation (Transfer Strategy) Step 3: Implementation
Traditional Start Over
Transfer Build New Process
Transfer Process
Paper Setup Sheet
(Med-High Risk)
Re-Build Process
Tool Transfer Machine
Strategy Normalized
Transfer Process
Graphical Machine Data
(Med-Low Risk)
Re-Build Process
Transfer Process
Cavity
Pressure
Re-Build Process
37 - Lean
38. Step 1: Risk Analysis
Properly size mold to machine (on sending and
receiving side)
Max shot capacity and % of shot capacity actually used
Maximum injection pressure capacity and max injection
pressure setting used (Ri) – must accommodate 20%
viscosity shift
Maximum injection speed capacity and injection speed
used
Tie bar spacing and actual size of the mold
Clamp tonnage capacity and actual clamp tonnage used
Clamp design (toggle vs.. hydraulic)
Thermolator flow and temperature capability
Drier throughput
Screw type
38 - Lean
40. Step 1: Risk Analysis Cont.
Part Design
Uniform wall
Radiusing
Part Thickness
Better Candidate for a transfer.
Pressure loss or study
(can get from flow
analysis)
Solid Model Information
Part Draft
Weld Line Concerns
Transferring a poorly designed part will not fix it.
40 - Lean
41. Step 1: Risk Analysis Cont.
Runner Layout
Naturally Balanced vs..
Imbalanced
Measurement of actual
balance
Hot vs. Cold Runner
Pressure losses (actual
measurements)
Family Tool?
Gate and Gate Type
Gate Type
Gate Location
Weld Line Concerns
41 - Lean
42. Step 1: Risk Analysis Cont.
Material
Viscosity (amount and
consistency)
Injection Grade vs.. Extrusion
Grade
Wide Spec Material
Uncontrolled Regrind
Screw design appropriate?
Material Delivery System
Dryer Capability
Validation of Material Conditions
42 - Lean
43. Step 1: Risk Analysis Cont.
Decoupled II, 2-Stage Molding
Process Sheet
Setup Sheet from Mold #: Trim RH Footwell Template Name: Cycle Time: Under 90 sec
Material Information
Current Process Resin Type: Solvay 2420 TPO
Nozzle Type: Straight Inject
Color: Dk Gray
Dk Taupe
Color %:
Blowing Agent: n/a
B/A %: n/a
Dryer Temp: 100 °F GAS psi: n/a Nozzle Tip Size: record for us
Material Processing Plastic Temperature
Guide 30/30: 440 Charge Time: 2 to 4 seconds
Plastic Flow Rate
BP (ppsi): 800-1000 plastic pressure
Fill Time: 3.5 seconds Part(s) weight: 2.16 lbs Inject Delay: n/a
Peak Plastic Pressure/Mold: 10,381 ppsi Air: record this for us
Plastic Pressure
Pack/Hold Time: 15.5 seconds Inject Timer: Toshiba setting n/a
F&P Part(s) weight: 2.275 lbs
Hold Time: 15.5 seconds Hold Plastic psi: 6229 ppsi
Gate Seal: yes Final part weight: 2.275 lbs
Plasitc Cooling
Cooling timer: 60 seconds
Coolant:
A Temp(in) 80 °F Temp(out) +/- 5 °F Flow:
B Temp(in) 80 °F Temp(out) +/- 5 °F
Clamp
Force: 1052 tons Gate 1 open: n/a Gate 2 open: n/a
Type: record this Gate 1 closed: n/a Gate 2 closed: n/a
toggle/hydr
Gate 3 open: n/a Gate 4 open: n/a
Gate 3 closed: n/a Gate 4 closed: n/a
43 - Lean
44. Step 1: Risk Analysis Cont.
Does Mold Currently Make Good Parts
Consistently?
Tool Condition
Is it in the Correct Machine Now?
Any Deviations
First Article or PPAP
44 - Lean
45. Step 1: Risk Analysis Cont.
Graphical Process Data
eDART™
Cavity Pressure Curves
Temperature Sensors
Delta Pressure for cooling
Appropriate Machine Signals/Triggers
45 - Lean
46. Tool Transfer Methodology
Step 1: Risk Analysis Step 2: Risk Mitigation (Transfer Strategy) Step 3: Implementation
Traditional Start Over
Transfer Build New Process
Transfer Process
Paper Setup Sheet
(Med-High Risk)
Re-Build Process
Tool Transfer Machine
Strategy Normalized
Transfer Process
Graphical Machine Data
(Med-Low Risk)
Re-Build Process
Transfer Process
Cavity
Pressure
Re-Build Process
46 - Lean
47. Step 2: Risk Mitigation
Runner Layout (Transfer Strategy)
Naturally Balanced vs. Graphical Process Data
Imbalanced eDART™
Measurement of actual Cavity Pressure Curves
balance Part Design Temperature Sensors
Hot vs. Cold Runner Uniform wall Delta Pressure for cooling
Pressure losses (actual Radiusing Appropriate Machine
measurements) Part Thickness Signals/Triggers
Family Tool? Pressure loss or study (can get from
Gate and Gate Type flow analysis)
Press Performance (sending and
Gate Type Solid Model Information
receiving)
Gate Location Part Draft
Pressure response
Weld Line Concerns Weld Line Concerns
Optional:
Injection Speed
Properly size mold to machine (on sending and receiving side)
Linearity
Max shot capacity and % of shot capacity actually used
Pressure
Maximum injection pressure capacity and max injection
Response
pressure setting used (Ri) – must accommodate 20% viscosity
Load Sensitivity
shift
Check-ring Study
Maximum injection speed capacity and injection speed used
Maximum Plastic
Tie bar spacing and actual size of the mold
Pressure
Clamp tonnage capacity and actual clamp tonnage used Setup Sheet from Current Process
Clamp design (toggle vs. hydraulic) Material Processing Guide
Thermolator flow and temperature capability
Drier throughput
Material Does Mold Currently Make Good Parts
Screw type
Viscosity (amount and Consistently?
consistency) Tool Condition
Injection Grade vs.. Is it in the Correct Machine Now?
Extrusion Grade Any Deviations
Wide Spec Material First Article or PPAP
Uncontrolled Regrind
Screw design appropriate?
Material Delivery System
Dryer Capability
Validation of Material
Conditions
The more information missing, the higher the RISK 47 - Lean
48. Three types of Tool Transfers
High Risk
Tool Shows up with no parts, prints and no setup sheet
Middle Risk
Mold shows up with a prints, a part and setup sheet from
prior process
Low Risk
We have Prints, short shots, full shot and setup sheet
We have their machine evaluations
We have all graphical data from the process with cavity
curves
48 - Lean
49. Tool Transfer Methodology
Traditional High Risk Start Over
Transfer Build New Process
Middle Risk Transfer Process
Paper Setup Sheet
(Med-High Risk)
Re-Build Process
Tool Transfer Machine
Strategy Normalized
Transfer Process
Graphical Machine Data
(Med-Low Risk)
Re-Build Process
Low Risk
Transfer Process
Cavity
Pressure
Re-Build Process
49 - Lean
50. What is a High Risk Tool Transfer
Traditional High Risk Start Over
Transfer Build New Process
Middle Risk Transfer Process
Paper Setup Sheet
(Med-High Risk)
Re-Build Process
Tool Transfer Machine
Strategy Normalized
Transfer Process
Graphical Machine Data
(Med-Low Risk)
Re-Build Process
Low Risk
Transfer Process
Cavity
Pressure
Re-Build Process
50 - Lean
51. Items Transferred
Mold
How was the water lines installed during production?
Was the clamp forced optimized or set at maximum?
Traditional Setup Sheet (maybe)
Could the machine actually go that many inches per second?
What screw diameter did they use?
How full was the part at transfer or was it a pressure limited process?
How do I convert these pressures, not knowing the intensification ratio?
Parts (maybe)
Are these the parts that they ran before sending the mold or are these when
the mold was new?
For the Receiving Machine this is a Mystery Tool
There is no plan for success with this (lack of)
information.
51 - Lean
52. Tool Transfer Methodology
Traditional High Risk Start Over
Transfer Build New Process
Middle Risk Transfer Process
Paper Setup Sheet
(Med-High Risk)
Re-Build Process
Tool Transfer Machine
Strategy Normalized
Transfer Process
Graphical Machine Data
(Med-Low Risk)
Re-Build Process
Low Risk
Transfer Process
Cavity
Pressure
Re-Build Process
52 - Lean
53. Middle Risk
With setup sheet (higher risk than using data acquisition)
Transfer a GOOD PROCESS (based on risk assessment)
Sprue Orifice Diameter
Clamp Force (may depend on tie bar spacing due to platen deflection)
Fill Time (must be consistent measurement – includes decomp or
not?)
Fill Only Part Weight (consistent fill only part measurement strategy)
Hold Pressure (plastic)
Hold Time
Screw Run Time
Back Pressure (plastic)
Mold Clamped Time (ideally)
Cycle Time
Temperature Map (understanding challenges) – including temp in/out
Better: Water Temp in/out and volumetric water flow
Melt Temperature: 30/30
Better: Thin wire temperature probe
Cushion: 5-10% of shot size (not ¼” everywhere)
Decompression: Just over check ring throw
Have all process testing information
Have all machine testing information
Have Graphical Data for Machine Injection and Screw Run
53 - Lean
54. Middle Risk Cont.
Transfer a MOLD with a POOR PROCESS
(re-establish process)
Have most of process/machine tests
We can’t run to that speed because our machine is out
of tune.
Our machine has never been squared and leveled.
Our screw is worn out.
Check-ring leaks bad so we use a large cushion.
Have no way of validating the material moisture.
We use Maximum clamp force because we always
have.
The shot size is only 14% of the barrel capacity.
54 - Lean
55. Tool Transfer Methodology
Traditional High Risk Start Over
Transfer Build New Process
Middle Risk Transfer Process
Paper Setup Sheet
(Med-High Risk)
Re-Build Process
Tool Transfer Machine
Strategy Normalized
Transfer Process
Graphical Machine Data
(Med-Low Risk)
Re-Build Process
Low Risk
Transfer Process
Cavity
Pressure
Re-Build Process
55 - Lean
56. Low Risk
Transfer a MOLD with a POOR
PROCESS and Graphical Data (re-
establish process)
Shot size less than 20% or more than
80%
Clamp force set less than 50%
Mold covers less than 60% of the platens.
Wrong screw design
56 - Lean
57. Low Risk Cont.
With eDART™ (volume and plastic injection pressure data) – lower
risk than just normalized setup sheet
Transfer a GOOD PROCESS (based on risk assessment)
Sprue Orifice Diameter and length known
Clamp Force (may depend on tie bar spacing due to platen deflection)
Fill Time (volumetric flow rate)
Fill Only Part Weight (maybe match relative shape of injection volume curve)
Hold Pressure (plastic)
Hold Time
Screw Run Time
Back Pressure (plastic)
Mold Clamped Time (ideally)
Cycle Time
Temperature Map (understanding challenges) – including temp in/out
Better: Water Temp in/out and volumetric water flow
Melt Temperature: 30/30
Better: Thin wire temperature probe
Cushion: 5-10% of shot size (not ¼” everywhere)
Decompression: Just over check ring throw
Possibly a Decoupled III process
Process Match has high potential success.
57 - Lean
58. Lowest Risk
Low Risk (With Cavity Pressure, and ideally Cavity
Temperature)
Ideally (but not mandatory) have information about
processing window (rheology curve, flow
simulation, solid model, etc)
For some applications (e.g. thick walled crystalline
parts), cavity temperature may be more important
than cavity pressure
MATCH 4 PLASTICS VARIABLES
This process has the best opportunity for a match.
58 - Lean
61. Process control involves reduction of
normal variation of all primary variables
during all phases of the cycle
Drying the plastic
Melting the plastic
Filling the mold
Packing
Holding
Cooling rate and time
Releasing the part
61 - Lean
62. Are You Lost in the Variable Maze?
res
s PLASTIC CONDITIONS
ture
flow
ssu
pera tion pera
ture
hea
m tica
pre
l te tem
we mp
rate
re s nt
bar pla nme
t ex
igh er
lic
nviro v
(fill
rau
s e
cha
hydr
oil leak
t
te
aulic alv
dim
tion
tim
mold
hyd
flow e
nge
wear rates x ing wea
cool
en
le) i
ess
os i
im t
atu
i
sio
warp time r
rs
ol m
kp
ity
re
in
ns
rs
swi
mid tim lyc s
anl
ille ture
c
f ing g
u consistency
-ba
era
tch
th ne
cle
erro
n
me sur ate r yle emp
k
PID oil t
erro
eth
suc
oil
on fac gr tun
vir olin ing
r
en orc
e ef
inis co FINISHED PART PROPERTIES
f ol regrind t h
p h ro rans ngt
c lam water le d p age fg r r
e e stre crew run tim
e
flow
n ozz slip nin spo s
crew d tu nse
MACHINE CONDITIONS s r-dampe scr
osc
illati
colo
r ad
e wa ew on di
undco ter pos
pre
ssu scr tives
nta tem iti ew
mi pe mold on re
gra rpm
na rat
nts ure deflectio die
nt
n
62 - Lean
64. First Scenario
Non-Instrumented Tool Transfer
No eDART™ Graphical Data
64 - Lean
65. A Tool Transfer is Information from many
Sources
Inputs
Flow Analysis Outputs
Fill only short shot
Machine Sizing
Current Setup Sheet
Machine Performance Evaluations
Part Prints or Solid Model
Full shot (parts and runner) Transfer Mold To
Material Processing Guide
Machine Performance Evaluations
Quality Inspections and Deviations
Graphical Cycle Data from Sensored Mold with Cavity Pressure
As more information is missing, the RISK of the transfer rises.
65 - Lean
66. Robust Molds
“Poor tool maintenance - easily tolerated in the old
batch system - repeatedly stopped the whole cell.”
“Our tools had deteriorated to a shocking extent without
the management ever realizing what was happening.”
Tool audits and maintenance
are a Key Part of Lean.
66 - Lean
67. Robust Machines
Always reliable and ready to produce on demand
Robust Preventive maintenance is essential
67 - Lean
68. High Risk
Mold is delivered with a part print only.
With only this information, I can only establish what my tie bar
spacing should be. (mold is 14in x 14in)
I will have to guess at shot size, transfer, cushion, injection
speed, rpm, back pressure and many more attributes to the
process.
Which means potentially I will not duplicate the same shear rates
in the cavity so the part will not be the same. This effects the
following:
Pressure distribution in the cavity.
Temperature distribution across the mold and part.
Shrink rates across the part.
68 - Lean
69. 220 ton clamp force 250 Ton clamp force 200 Ton clamp force
1.77 in diameter screw 2.0in diameter screw 1.625 diameter screw
2600 psi hydraulic pump 2150 psi pump 1800 psi pump
12.2:1 Intensification Ratio 11.2 Intensification Ratio 10.2 Intensification Ratio
Maximum Plastic pressure 31,720 Maximum Plastic Pressure 24,080 Maximum Plastic Pressure
ppsi ppsi 18,360 ppsi
General Purpose Screw General purpose screw General Purpose Screw
12 inch linear shot capability 12.5 in linear shot capability 11.1 linear shot capacity
Maximum Injection Speed 10.2 Maximum injection speed 8.6 Maximum injection speed
in/sec in/sec 10.5 in/sec
Utilization is at 85% Utilization is at 46% Utilization is at 67%
Tie Bar Spacing is 17in x 17in Tie bar spacing is 20in x 20in Tie bar spacing is 15in x
15in
Based on our High Risk Tool Transfer, What Molding
Machine would you chose?
69 - Lean
70. Normalization of Machines
Make all machines interchangeable from
The Plastic’s Point of View
Starts with an Audit 70 - Lean
71. We will be guessing on what is going on with
our tool transfer especially if the wrong
machine is chosen.
We were told this mold made great parts, what’s the
problem?!?!? 71 - Lean
72. Middle Risk
Mold is delivered with Part
prints
Received setup sheets from
different machines. (none like
ours)
Received a set of parts
(hopefully the last shot)
Four of these, no runner
Would we still choose the same machine?
72 - Lean
73. Setup Sheet from Old Process
Plastic Flow Rate If we don’t know screw diameter
we can not calculate any of these.
Shot Size 8.33 inches Transfer Position 1.097 inches Cushion .73 inches Decompress .250 inches
Fill Time .95 seconds Injection Speed 7.6 inches per second Fill Only Part Weight 78.90 grams
Clamp Force If we don’t know the Intensification Ratio
Without knowing the machines Clamp Force 250 Tons We can not convert the back pressure
Clamp force we don’t know if Or Pack/Hold Settings.
optimized or set at max.
Plastic Temperature
Melt Temperature 412.5 degrees Back Pressure 66.45 psi RPM 60
Nozzle 450.5 degrees Front Zone 420 degrees Middle Zone 425 degrees Rear Zone 430 degrees
Don’t know if this is a general purpose screw
or High compression for Polypro, so we can not
Plastic Pressure trust these settings.
Pack/Hold Time 8 seconds Pack/Hold Pressure 1500 psi Full Part Weight 82.57 grams
Gate Seal Yes
How do I know that the part is
Plastic Cooling not over-packed?
Cooling Timer 18 seconds This sheet does not tell us how the mold was Mold Temperature 120 degrees
plumbed nor how well it was performing.
Without any information from the prior molding machine we can not do much with
this information to create a new setup for our new process. 73 - Lean
74. Low Risk
Mold arrives with the following:
Part prints, solid model,
flow analysis
Quality inspections
including any deviations
Setup sheets
Short shot at transfer
Full shot including the
runner
Fully sensored mold with
graphical data for cavity
pressure.
Machine evaluations
74 - Lean
75. Do you practice a need for Absolutely
Capable Process?
IQ - Installation Qualification: quot;Did you
put the thing together right?quot;
OQ - Operational Qualification: Create a
good process and define the process
limits
PQ - Performance Qualification: Make
sure good parts can be made over time
using an extended run
75 - Lean
76. IQ - Installation Qualification:
IQ has nothing to do with your intelligence (or lack
thereof). Instead, IQ asks one basic question: quot;Did you put the
thing together rightquot;. In the case of an injection molding process,
that can refer to the machine, the mold, or the auxiliaries. Did the
steel get cut right? Are the water lines hooked up correctly? Is
the mold sized correctly for the machine it is in? Is the
equipment properly calibrated? The list can get pretty long, but
the point is doing your home work up front so you don't overlook
something simple.
The Items Needed:
Solid Model
Flow Analysis
Machine sizing information (coming from and going to)
Performance information of both machines
76 - Lean
77. Actual Machine Evaluation
Testing Data
Machine Testing:
Injection Speed Linearity
Load Sensitivity
Pressure Response
Check Ring Study
Repeatability
77 - Lean
78. Injection Speed Linearity
Stroke (include decompression): 270.97 mm 10.67
1st-2nd Position Transfer: 36.83 mm 1.45
MAX MACHINE VELOCITY IN/SEC 10.2 in/sec
Actual
MACHINE SET Machine Set Machine Expected Fill
VELOCITY % Velocity IN/SEC Fill Time Velocity Time % Difference
99 10.00 1.45 6.36 0.92 -57.3%
89 9.00 1.49 6.19 1.02 -45.5%
79 8.00 1.73 5.33 1.15 -50.1%
69 7.00 1.89 4.88 1.32 -43.5%
59 6.00 1.98 4.66 1.54 -28.9%
49 5.00 2.15 4.29 1.84 -16.6%
39 4.00 2.50 3.69 2.30 -8.5%
29 3.00 3.15 2.93 3.07 -2.5%
19 2.00 5.75 1.60 4.61 -24.8%
9 1.00 12.44 0.74 9.22 -35.0%
Average % Difference:
-31%
This machine can not achieve the desired fill time the flow analysis
suggested, therefore it will be impossible to achieve the desired
shear rates. This would get a high risk of 5 for this test.
78 - Lean
79. Load Sensitivity
Choose Type of Pressure
Fill Time (mold) 1.45 sec
X Fill Time (air) 1.03 sec
Peak Pressure (mold) 15,256 PSI
Peak Pressure (air) 5,245 PSI
*Fill in highlighted Areas*
Actual Test %
2.89%
Acceptable Range: 3%
This machine is not sensitive to a load change therefore receiving a
risk of 2.
79 - Lean
80. Pressure Response
X
Time 1 1.5600 sec
Pressure 1 15256.00 ppsi
Time 2 1.7600 sec
Pressure 2 14370.00 ppsi
Actual Response Time: 2.257336343
Acceptable Response Time: <0.2 sec/1000 psi
Pressure Response is somewhat challenged with a risk of 4.
80 - Lean
81. Measuring the Risk of
Potential Problem Areas
Square corners equals risk of 5
Additions to walls equals risk of 5
Change in wall thickness equals risk of 5 if gate location is on
opposing end of part
We have either blue prints and/or solid model
81 - Lean
information
82. Information from Solid Model and Flow Analysis
Key Information from Solid Model
Cubic inch volume of the solid model is 5.09
Sprue / Runner volume is 2.73 cubic inches
Square inches at the parting line is 7.99
Key Information from Flow Analysis
Fill Time is .95 seconds
Pressure near gate is 12,000 ppsi
Pressure at end of part 2,600 ppsi
Average pressure in the mold to produce a good
part is 7300ppsi
Tons per square inch is 3.65
Cooling Time 16 seconds
Pack/Hold Time 7 seconds
Development of Set up Sheet Pack/Hold Pressure 14,370ppsi
We can establish a shot size, transfer position and cushion from the
volume based on screw diameter.
We can establish the clamp force needed based on the square inches
and the average cavity pressure. 82 - Lean
83. Decoupled II Pre Process
Setup Sheet
Plastic Flow Rate
Shot Size 10.7 inches Transfer Position 1.5 inches Cushion 1 inch Decompress .31inches
Fill Time .95 seconds Injection Speed 9.7 inches per second Fill Only Part Weight 72.1 grams
Clamp Force
Clamp Force 136 Tons
These can be calculated based on
our transfer machine information.
From the flow analysis
Weighing parts or flow
analysis can give us this
information.
Reduce the amount of guessing during the startup of
your transfer tool.
83 - Lean
84. Selected Number of Cavities
Risk
Runner layout: a risk of 2
Gate location: a risk of 5
Gate Type: a risk of 3
Balance of Fill 3
Risk of cold slug well/puller design 5
84 - Lean
85. If we have the short shot, we can
see potential problems.
Risk of Balance 5
Flow Analysis can also give us a snapshot of this problem.
85 - Lean
87. Cycle from the
Plastics’ Point of View
Heat it up Flow it Pressurize it Cool it
The rest are details:
The devil’s in those details!
87 - Lean
88. A Strategy Based on the
4 Plastics’ Variables
“Helps Injection Molders Succeed”
Temperature
Flow Rate
Pressure
Cooling
88 - Lean
89. Decoupled II Pre Process Setup Sheet for
the 220 Ton Machine
Plastic Flow Rate
Shot Size 10.7 inches Transfer Position 1.5 inches Cushion 1 inch Decompress .3 inches
Fill Time .95 seconds Injection Speed 9.7 inches per second Fill Only Part Weight 72.1 grams
Clamp Force
Information From material
Clamp Force 136 Tons processing guide
Plastic Temperature
Melt Temperature 412 degrees Back Pressure 61psi RPM 75
Nozzle 412 degrees Front Zone 412 degrees Middle Zone 412 degrees Rear Zone 412 degrees
Plastic Pressure
Pack/Hold Time 7 seconds Pack/Hold Pressure 14,370 ppsi Full Part Weight 75.87 grams
Gate Seal Yes Peak at Transfer 15,256ppsi
Plastic Cooling
Cooling Timer 16 seconds Mold Temperature 120 degrees
This information could be gathered from Could weigh the parts you
a former setup sheet or flow analysis. received with your mold or ask
89 - Lean
the flow analysis
90. Only Choice
220 ton clamp force 250 Ton clamp force 200 Ton clamp force
1.77 in diameter screw 2.0in diameter screw 1.625 diameter screw
2600 psi hydraulic pump 2150 psi pump 1800 psi pump
12.2:1 Intensification Ratio 11.2 Intensification Ratio 10.2 Intensification Ratio
Maximum Plastic pressure 31,720 Maximum Plastic Pressure 24,080 Maximum Plastic Pressure
ppsi ppsi 18,360 ppsi
General Purpose Screw General purpose screw General Purpose Screw
12 inch linear shot capability 12.5 in linear shot capability 11.1 linear shot capacity
Maximum Injection Speed 10.2 Maximum injection speed 7.6 Maximum injection speed
in/sec in/sec 10.5 in/sec
Utilization is at 85% Utilization is at 46% Utilization is at 67%
Tie Bar Spacing is 17in x 17in Tie bar spacing is 20in x 20in Tie bar spacing is 15in x
15in
This machine would fail due
From our selection of machines, this This machine would fail due
to lack of Max. Plastic
is the only machine that is capable to lack of injection speed
of making the same part. capability, I could not Pressure, it would become
pressure limited when the
duplicate the same shear
viscosity changed.
rates.
90 - Lean
91. Setup Sheet from Old Process for the
250 Ton Molding Machine
Plastic Flow Rate
Shot Size 8.33 inches Transfer Position 1.097 inches Cushion .73 inches Decompress .250 inches
Fill Time .95 seconds Injection Speed 7.6 inches per second Fill Only Part Weight 72.1 grams
Fill Time will be impossible to meet Clamp Force
Injection Speed is maxed OUT
Clamp Force 136 Tons
Only using 54% of Clamp Force
Plastic Temperature
Melt Temperature 412.5 degrees Back Pressure 66.45 psi RPM 60
Nozzle 412 degrees Front Zone 412 degrees Middle Zone 412 degrees Rear Zone 412 degrees
Plastic Pressure
Pack/Hold Time 7 seconds Pack/Hold Pressure 14,370 ppsi Full Part Weight 75.87 grams
Gate Seal Yes
Plastic Cooling
Cooling Timer 16 seconds Mold Temperature 120 degrees
Putting the Mold in this Machine Would be Extremely High Risk as
we can not achieve the Shear rates due to the fact it will need to be
slowed down. 91 - Lean
92. Setup Sheet from Old Process for the
200 Ton Molding Machine
Max Linear Shot for this Machine is 11.1
We can not achieve the volume Plastic Flow Rate
Shot Size 12.5 inches Transfer Position 1.66 inches Cushion 1.1 inches Decompress .250 inches
Fill Time .95 seconds Injection Speed 11.4 inches per second Fill Only Part Weight 72.1 grams
Clamp Force
Max Injection Speed is only 10.5 in/sec
Fill time can not be Reached Clamp Force 136 Tons
We can not achieve the Shear Rates for the Plastic
Plastic Temperature
Melt Temperature 412.5 degrees Back Pressure 66.45 psi RPM 60
Nozzle 412 degrees Front Zone 412 degrees Middle Zone 412 degrees Rear Zone 412 degrees
Plastic Pressure
Pack/Hold Time 7 seconds Pack/Hold Pressure 14,370 ppsi Full Part Weight 75.87 grams
Gate Seal Yes
Plastic Cooling
Cooling Timer 16 seconds Mold Temperature 120 degrees
Putting the Mold in this Machine Would be a Disaster as we can
not achieve the Shear rates nor do we have enough volume of
92 - Lean
plastic in our shot.
93. OQ - Operational Qualification:
OQ is quot;the heart of validationquot;. This is
where the process is created. Bottom line is, make
sure the process is a good one. Here is where we can
really help molders. Make sure the melt temperature
is at the manufacturer's midrange. Set a fill speed
based on your rheology curve. Transfer when the part
is 95-98% full. Sound familiar?
93 - Lean
94. RIGOROUS MOLD Transfer
(Rigorous: Severe; Logical; Uncompromising)
OBJECTIVES:
Challenge a mold early and hard so that it’s weaknesses can be quickly defined
and corrected before it must produce parts in a production environment.
“NEVER AGAIN PUT A BAD TRANSFER MOLD INTO PRODUCTION”
Develop, refine and center machine independent process conditions for optimum
product quality.
During successive tryouts, parts made under the same plastic processing conditions can
be compared to evaluate mold rework
Establish alarm limits for ongoing process monitoring and automatic suspect part
containment.
Production launch can be machine independent with predictable results
94 - Lean
95. But OQ goes one step further.
In addition to building and documenting a good process, OQ requires that the
molder quot;define the key processing parameters and their associated rangesquot;. Or,
in simple terms, what press settings have an impact on part quality? How much
can the operator adjust these settings and still make a good part? For example,
the target fill speed might be 5 inches per second, but how much faster or slower
is acceptable? The example below shows the target with the max and min
settings.
Press Setting Min Target Max
Fill Speed 4.5 in/s 5 in/s 5.5 in/s
This is OK, but is useless if the mold is transferred to another press. The
mold would have to be validated every time the mold is moved to a different
machine! A better approach is to document the process settings and ranges
in quot;Machine Independentquot; terms based on the 4 Plastics Variables. Instead
of fill speed, the FILL TIME should be used. Here's an example of the same
process setting from above:
Press Setting Min Target Max
Fill Time 0.55 sec 0.6 sec 0.7 sec
Using a Machine Independent Process Setup Sheet, the OQ stage can usually be avoided
(or at least greatly reduced), saving the molder lots of time and money.
95 - Lean
98. Part of process control involves knowing if and when gate
seal occurs on all cavities for all molds.
Without Instrumentation
we use part weight study
With instrumentation we use post
gate psi curve including hold time
Gate Seal = Best Dimensional Control
Allowing discharge or backflow out of the gate after a set period of time:
Can reduce compressive stresses near the gate
Can affect pressure gradient caused warpage
98 - Lean
99. Pressure Loss Study
15,256 ppsi
9,628 ppsi
8,343 ppsi
What happens if the
viscosity changes?
5,245ppsi
99 - Lean
100. How do we know how much RISK we
are taking to mold these products?
Example: The shot size for this process is 10.668 linear inches.
The molding machine’s maximum stroke is 12 inches.
You are using 88.9% of the barrel capacity, 80% is the
maximum usage which gives us a rating of 5.
NOTE:
1 is a low risk condition
3 is an average amount of risk
5 is high risk and could result in process challenges
100 - Lean
101. The Risk including the Machine Performance
The Process
Shot Size 10.7 inches5 Transfer Position 1.5 inches1 Cushion 1 inch1 Decompress .3 inches1
Fill Time .95 seconds5 Injection Speed 9.7 inches per second5 Fill Only Part Weight 72.1 grams1
Clamp Force 136 Tons3 Back Pressure 62 ps1 RPM 751 Melt Temperature 412 degrees2
Nozzle 412 degrees1 Front Zone 412 degrees1 Middle Zone 412 degrees1 Rear Zone 412 degrees1
Pack/Hold Time 7 seconds1 Pack/Hold Pressure 14,370 ppsi1 Full Part Weight 75.87 grams1
Gate Seal 1 Cooling Timer 16 seconds1 Mold Temperature 120 degrees1
The Part
Square corners equals risk of 5 Additions to walls equals risk of 5 Change in wall thickness equals risk of 5
Cavity Layout
Runner layout: a risk of 5 Gate location: a risk of 5 Gate Type: a risk of 3 Balance of Fill 5
Risk of cold slug well/puller design 5
Machine Performance
Injection Speed Linearity 5 Pressure Response 4 Load Sensitivity 2
Potential Total Risk of 32 topics at a Our Risk of Producing this Product is 85
severe rating of 5 equals which is a very average part to produce
160 85
101 - Lean
102. Only Choice
220 ton clamp force 250 Ton clamp force 200 Ton clamp force
1.77 in diameter screw 2.0in diameter screw 1.625 diameter screw
2600 psi hydraulic pump 2150 psi pump 1800 psi pump
12.2:1 Intensification Ratio 11.2 Intensification Ratio 10.2 Intensification Ratio
Maximum Plastic pressure 31,720 Maximum Plastic Pressure 24,080 Maximum Plastic Pressure
ppsi ppsi 18,360 ppsi
General Purpose Screw General purpose screw General Purpose Screw
12 inch linear shot capability 12.5 in linear shot capability 11.1 linear shot capacity
Maximum Injection Speed 10.2 Maximum injection speed 7.6 Maximum injection speed
in/sec in/sec 10.5 in/sec
Utilization is at 85% Utilization is at 46% Utilization is at 67%
Tie Bar Spacing is 17in x 17in Tie bar spacing is 20in x 20in Tie bar spacing is 15in x
15in
This machine would fail due
From our selection of machines, this This machine would fail due
to lack of Max. Plastic
is the only machine that is capable to lack of injection speed
of making the same part. capability, I could not Pressure, it would become
pressure limited when the
duplicate the same shear
viscosity changed.
rates.
102 - Lean
103. Other Items to Consider
Viscosity shift should also be
considered.
Our average maximum pressure at the parting line without flashing is:
Clamp force in pounds (440,000) divided by the total square inches of (32.96 sq/in) equals
a pressure of 13,349ppsi in the cavity.
A good part requires an average pressure of 7,300ppsi (from flow analysis) which provides
a nice process window.
If 20% viscosity shift or regrind is used our good part may require 7,300 times 1.2 (1 = part,
.2 = viscosity shift) which equates to a new average pressure for a good part of 8,760ppsi
in the cavity. Many times looking at the risk of utilizing regrind is never considered and
could cause a pressure limit condition be default. Another risk factor that could be
considered. 103 - Lean
104. Does the Molding Machine Have enough
Performance when Viscosity Changes?
Peak pressure at transfer
was 15,256ppsi (from Flow
Analysis).
220 ton clamp force
1.77 in diameter screw If viscosity goes up 20%
2600 psi hydraulic pump
12.2:1 Intensification Ratio
our new peak pressure at
Maximum Plastic pressure 31,720 ppsi transfer would be
General Purpose Screw
12 inch linear shot capability
18,307ppsi
Maximum Injection Speed 10.2 in/sec
Utilization is at 85%
Tie Bar Spacing is 17in x 17in
This would be Low Risk
104 - Lean
105. How much will your dimensions
change over time?
Note: The longer a flow Post Gate control
transducer @
front has to travel the
12,000 psi
more pressure loss that
will exist.
Pressure Loss 10,000psi
.500 post detail
with a tolerance of
± .002 EOC monitor
transducer @
2000 psi
Calculation for Dimensional Change Using Actual Data
Peak End of Cavity Pressure Peak End of Cavity Pressure Low
x Compressib ility x Dimension % of dimension change
1000psi
*amorphous .005
.5% = .005 amorphous per 1000 psi
.75% = .0025 low crystalline per 1000 psi
.1% = .01 high crystalline per 1000 psi
105 - Lean
106. PQ - Performance Qualification:
The objective of PQ is to show that good parts can be made
over time. In PQ, the process is run for an extended period
(24 hours is not uncommon) and parts are monitored
carefully to make sure they are acceptable. Parts are
inspected regularly, and some parts will usually be sent off
for functional testing (putting the parts into a final assembly
to make sure they actually work!)
During PQ, the process is often quot;challengedquot; by throwing in
common sources of variation to make sure that parts still
come out good. For example, the fill speed might be
adjusted from the high to the low range settings (using our
example from above). The point is to try to catch problems
that might not be caught in a short term run. Note that
practices here vary. Some customers quot;challengequot; the
process during PQ, some during OQ
106 - Lean
107. Changes in Dimensions?
Why do part dimensions vary???
Over time?
Shot to shot?
During startups?
107 - Lean
108. 2nd Scenario
A Fully Instrumented Mold Transfer
Using eDART™ Graphical Data
108 - Lean
109. Data Analysis
A.
B.
A. Summary Screen: Displays summary data values in a
running bar chart for analyzing trends over time.
B. Cycle Graph Screen: Displays each cycle versus time as a
graphical waveform. 109 - Lean
110. Typical Cycle Graph
10,000 Plastic
Injection Shot Volume
PRESSURE (PSI)
Pressure
Gate End
Mold Pressure
End of Cavity
Mold Pressure
0 TIME 16
(SECONDS)
110 - Lean
111. End of Cavity Pressure
20,000 Most Variable
Best For Monitoring
PRESSURE (PSIP)
Contain Short Shots!!
Peak PSI
Cooling Rate
No Dynamic PSI
Part is Full
Pack Rate
0 TIME (SECONDS) 15
111 - Lean
112. Gate End Pressure
20,000
Best For Control
Fill Dynamics
PRESSURE (PSIP)
Gate Seal
Peak
PSI
Pack
Rate
Sudden Pressure
Reduction due to
Cooling Discharge
Rate
Full Packed
0 Cavity
Fill Time TIME (SECONDS)
112 - Lean
113. Cavity Pressure Integrals
The most useful data for process monitoring is the end-of-cavity pressure.
The area under this curve represents the packing of the mold to a peak
pressure and then this time delay of pressure during cooling.
Changes to the rate and degree of packing, or the rate of cooling affect the
end-of-cavity cycle integral.
PRESSURE (PSI)
Pack & Hold
End of Cavity
Mold Pressure
0 Start Mold TIME (SECONDS) 16
Fill Time
113 - Lean
114. Cavity Pressure
Gate End Showing Discharge
This is best detected by monitoring the integral
Fill Pack Hold A chart with two seconds less
2nd stage time is shown where
plastic is allowed to run back
out of the cavity, at point F
D
This is called discharge or
backflow
PRESSURE (PSI)
Discharge is not always
undesirable in molding
Many center gated parts,
E especially ones where flatness
is desirable, must be allowed to
F discharge for correct part
characteristics
B
C
Gate End
A Mold Pressure
0 Start Mold TIME (SECONDS) 15
Fill Time
114 - Lean
115. Historical Data for Steady State
108 second stop
8 cycles
Start of process
Small Steel Mold 115 - Lean
116. Before the Mold is Prepared for Transfer a
Graphical Snap Shot of the Process is Taken
116 - Lean
117. Problem
Post Gate
End of Cavity
The original process traces are saved as dotted lines to become our template. It is
imperative to match what goes on inside the cavity (Post Gate and End of Cavity).
117 - Lean
118. Mold temperature was fluctuating
About 10 degrees
Thermal stability is challenged and will affect part quality.
118 - Lean
119. Cushion
Screw Trace
Shot Size
Transfer Position
Decompress
119 - Lean
120. Decoupled II Pre Process Setup Sheet for
the 220 Ton Machine
Plastic Flow Rate
Shot Size 10.7 inches Transfer Position 1.5 inches Cushion 1 inch Decompress .3 inches
Fill Time .95 seconds Injection Speed 9.7 inches per second Fill Only Part Weight 72.1 grams
Clamp Force
This information can be found Clamp Force 136 Tons
on the Screw Trace
Plastic Temperature
Melt Temperature 412 degrees Back Pressure 61psi RPM 75
Nozzle 412 degrees Front Zone 412 degrees Middle Zone 412 degrees Rear Zone 412 degrees
Plastic Pressure
Pack/Hold Time 7 seconds Pack/Hold Pressure 14,370 ppsi Full Part Weight 75.87 grams
Gate Seal Yes Peak at Transfer 15,256ppsi
Plastic Cooling
Cooling Timer 16 seconds Mold Temperature 120 degrees
120 - Lean
121. Peak Pressure at
Transfer
Injection Speed Pack and Hold Pressure
Fill Time In Cavity Pack Time
121 - Lean
122. Decoupled II Pre Process Setup Sheet for
the 220 Ton Machine
Plastic Flow Rate
Shot Size 10.7 inches Transfer Position 1.5 inches Cushion 1 inch Decompress .3 inches
Fill Time .95 seconds Injection Speed 9.7 inches per second Fill Only Part Weight 72.1 grams
Clamp Force From the Screw Trace
From Graphical Data
Clamp Force 136 Tons Turn Pack and Hold Off
To Verify
Plastic Temperature
Melt Temperature 412 degrees Back Pressure 61psi RPM 75
Nozzle 412 degrees Front Zone 412 degrees Middle Zone 412 degrees Rear Zone 412 degrees
Plastic Pressure
Pack/Hold Time 7 seconds Pack/Hold Pressure 14,370 ppsi Full Part Weight 75.87 grams
Gate Seal Yes Peak at Transfer 15,256ppsi From the Machine Pressure
Trace
Plastic Cooling
Cooling Timer 16 seconds Mold Temperature 120 degrees
122 - Lean
123. Temperature Information from
Inside the Cavity
Screw Run Information
Back Pressure
Pack and Hold Time
123 - Lean
124. Decoupled II Pre Process Setup Sheet for the
220 Ton Machine
Plastic Flow Rate
Shot Size 10.7 inches Transfer Position 1.5 inches Cushion 1 inch Decompress .3 inches
Fill Time .95 seconds Injection Speed 9.7 inches per second Fill Only Part Weight 72.1 grams
Clamp Force
From the Temperature Trace From the Screw Trace
Inside the Cavity Clamp Force 136 Tons
From the Machine Pressure
Plastic Temperature Trace
Melt Temperature 412 degrees Back Pressure 61psi RPM 75
Nozzle 412 degrees Front Zone 412 degrees Middle Zone 412 degrees Rear Zone 412 degrees
Plastic Pressure
Pack/Hold Time 7 seconds Pack/Hold Pressure 14,370 ppsi Full Part Weight 75.87 grams
Gate Seal Yes Peak at Transfer 15,256ppsi
From the Machine Pressure Trace Plastic Cooling
Cooling Timer 16 seconds Mold Temperature 120 degrees
124 - Lean