2. Tools required for the task
• Spirit level/Water level
• Pencil
• Length of wood
• Measuring tape
• Tile nippers
• Notched trowel
• Gauging trowel
• Tile cutter
• Chalk line
R Hammond / G Turner2
3. R Hammond / G Turner3
Using a spirit level
check the window
reveals for plumb.
4. R Hammond / G Turner4
Again using a spirit
level check the
window sill and
soffit for level.
5. R Hammond / G Turner5
Use a measuring
tape to find the
centre of the
window sill and
mark using a
pencil.
6. R Hammond / G Turner6
Using a spirit level
and pencil to
transfer the centre
line to the top and
the bottom of the
wall. Then transfer
between the two
points with a chalk
line
7. R Hammond / G Turner7
Using the staff
stick check the
cuts to the reveals
and both sides of
the wall. Choose
which method of
centre works best
for your wall centre
of a tile or a centre
of a joint
8. R Hammond / G Turner8
Using the staff
stick check the
cuts to the sill and
soffit if the cuts are
to small adjust the
staff stick to suit.
9. R Hammond / G Turner9
Once position of
tiles has been
worked out mark
the wall on top and
bottom of the
window using the
staff stick with a
pencil.
10. R Hammond / G Turner10
Using the staff
stick you can now
check the cutting
at the ceiling and
floor. If these are
not suitable start
again at the
window.
11. R Hammond / G Turner11
Using water level
transfer setting out
height around
room and mark
with chalk line.
12. R Hammond / G Turner12
You can now use
your staff stick to
set the tile baton to
the nearest whole
tile from the floor.
13. R Hammond / G Turner13
After setting tile
batons and plumb
lines you are now
ready to start tiling
14. R Hammond / G Turner14
Fix the tiles to
window height you
can now put plumb
lines up both sides
of the window this
will help when you
get to top of the
window to ensure
gap doesn't close
or open up
15. R Hammond / G Turner15
Continue tiling up
both sides of
window ensuring
tiles are kept
plumb and level
throughout
16. R Hammond / G Turner16
Use the staff stick
to ensure tiles
work in .
17. R Hammond / G Turner17
Finish cuts around
outside of window
18. R Hammond / G Turner18
Complete tiling up
to ceiling
19. R Hammond / G Turner19
Remove tile baton,
cut and fix base
tile.
20. R Hammond / G Turner20
Apply tile trim to
window reveals
soffit and sill mitred
in each corner. Tile
window reveals
soffit and sill
ensure all tiling is
flush with tile trim
and all the joints
line through.