SlideShare una empresa de Scribd logo
1 de 40
Risk Event Modeling
Risk event modeling in part of Intaver
Institute’s presentations on project risk
management and risk analysis
Intaver Institute Inc.
303, 6707, Elbow Drive S.W, Calgary, AB, Canada
Tel: +1(403)692-2252
Fax: +1(403)459-4533
www.intaver.com
The Project Management Problem
05/07/14 2009 Intaver Institute 2
Many projects are unsuccessful!Many projects are unsuccessful!
05/07/14 2009 Intaver Institute 3
The Project Management Problem
05/07/14 2009 Intaver Institute 4
The Project Management Problem
05/07/14 2009 Intaver Institute 5
The Project Management Problem
05/07/14 2009 Intaver Institute 6
The Project Management Problem
Benefits
05/07/14 2009 Intaver Institute 7
Risk Event Modeling Workflow
05/07/14 2009 Intaver Institute 8
Risk Definition
• Risks
– Risks are “events” that have a probability of occurring during a project
– Risks are identified and assigned to tasks or resources
– Define impact of risks by assigning:
• Chance of occurrence
• Outcome (e.g. delay, increase in cost)
• Result (percentage or fixed value of outcome)
05/07/14 2009 Intaver Institute 9
What is Monte Carlo
Monte Carlo simulation is a mathematical method used in risk
analysis. Monte Carlo simulations are used to approximate the
distribution of potential results based on probabilistic inputs.
Monte Carlo Simulations
Input Parameters Output Parameters
Calculation
Engine
Critical Path
Scheduling
Engine
(
)
Task duration
cost, finish time,
etc.
cost, finish time,
etc.
Project duration
Monte Carlo Schedule Analysis
4 5 6321 7 7 82 3 654 1 4 5 632 7
8 9 10 11 12 13 14 15 16
1
2
3
4
5
6
7
Task 1
Task 2
Task 3
Two Approaches to Estimating Probabilities
• The relative frequency approach, where probability equals
the number of occurrences of specific outcome (or event)
divided by the total number of possible outcomes.
• The subjective approach represents an expert’s degree of
belief that a particular outcome will occur.
Two Approaches for Defining Uncertainties
• Distribution-based approach
• Event-based approach
Which Distribution Should Be Used?
Normal Triangual Uniform
Also useful:
• Lognornal
• Beta
Distribution Fitting
Before Eliciting Judgment You Need to Have:
• A clearly defined problem
• An identified list of risks, or a risk
breakdown structure, for the project
• A project schedule
• A clearly defined set of questions you will
ask experts
In addition, your team of experts should be aware
of any personal interest that expert may have
regarding particular issues. It helps to mitigate
motivational biases.
Psychological Factors
• Availability heuristic: people judge the probability of the
occurrence of events by how easily these events are brought to
mind.
• Anchoring heuristic: refers to the human tendency to remain close
to the initial estimate.
• Wishful thinking: when we overestimate the probabilities of
opportunities and underestimate the probabilities of risks.
Overestimating the Probability of Compound
Events
If the probability of a defect in a component is 20% and the
device uses three redundant components, the probability of the
defective device will be (0.2 * 0.2 * 0.2) = 0.008%.
People tend to think this number is much higher.
Ignoring Base-Rate Frequencies
• Historically, the probability that a particular
component will be defective is 1%.
• The component is tested before installation.
• The test showed that the component is defective.
• The test usually successfully identifies defective
components 80% of the time.
• What is the probability that a component is
defective?
The correct answer is close to 4%, however, most
people would think that answer is a little bit lower
than 80%.
Eliciting Judgment About Probabilities of
Single Events
• Pose a direct question: “What is the probability that the project
will be canceled due to budgetary problems?”
• Ask the experts two opposing questions: (1) “What is the
probability that the project will be canceled?” and (2) “What is
the probability the project will be completed?” The sum of
these two assessments should be 100%.
• Break compound events into simple events and review them
separately.
Probability Wheel
25% No delay of activity
35% 3 day delay of activity
40% 5 day delay of activity
Task Duration
4
8
12
16
20 100%
80%
60%
40%
20%
Frequency
Probability
2 3 4 5 6
(days)
Question: What is the chance that duration
is less than 3 days?
Eliciting Judgment: Probability Method
Eliciting Judgment: Method of Relative Heights
Task Duration
2
4
6
8
10
2 3 4 5 6
50%
40%
30%
20%
10%Frequency
Probability
(days)
Question: How many times the duration
will be between 2 and 3 days?
How Many Trials Are Required?
Huge number of trials (> 1000) usually does not increase
accuracy of analysis
• Incorporate rare events
• Use convergence monitoring
What Is The Chance That a Project Will Be on Time And Within
Budget?
Analysis of Monte Carlo Results
• Sensitivity and Correlations
• Critical Indices
• Crucial tasks
• Critical Risks
• Probabilistic Calendars
• Deadlines
• Conditional Branching
• Probabilistic Branching
• Chance of Task Existence
Analyze Results
05/07/14 2009 Intaver Institute 28
Result Gant
05/07/14 2009 Intaver Institute 29
When you have project
schedule and risk
breakdown structure ready
click here to perform Monte
Carlo simulations
When you have project
schedule and risk
breakdown structure ready
click here to perform Monte
Carlo simulations
RiskyProject employs
convergence monitoring
to ensure fast calculation
RiskyProject employs
convergence monitoring
to ensure fast calculation
Risk Register
Pre-mitigation Probability, Impact,
And Score
Pre-mitigation Probability, Impact,
And Score
05/07/14 2009 Intaver Institute 30
Result Gantt Chart
05/07/14 2009 Intaver Institute 31
White bars represent
original project
schedule (no risks)
White bars represent
original project
schedule (no risks)
Blue bars represent
project schedule with
risks
Blue bars represent
project schedule with
risks
Because of risks, project duration
significantly increased
Because of risks, project duration
significantly increased
Results of Risk Analysis
05/07/14 2009 Intaver Institute 32
Project Summary:
project duration,
cost, and finish time
with and without
risks
Project Summary:
project duration,
cost, and finish time
with and without
risks
Results of analysis
for project cost,
finish time, and
duration
Results of analysis
for project cost,
finish time, and
duration
Double click on any chart to view detailed informationDouble click on any chart to view detailed information
Detailed Results of Analysis
05/07/14 2009 Intaver Institute 33
Move the slider to determine the
chance that project will be within
budget
Move the slider to determine the
chance that project will be within
budget
Get detailed
statistical data
Get detailed
statistical data
Data can be exported
as an image or text
Data can be exported
as an image or text
Detailed results can be shown for each tasks
or whole project for cost, duration, start
time, finish time, and income.
Detailed results can be shown for each tasks
or whole project for cost, duration, start
time, finish time, and income.
Sensitivity
05/07/14 2009 Intaver Institute 34
Tornado chart shows risks or
other parameters have the most
affect on the project schedule
Tornado chart shows risks or
other parameters have the most
affect on the project schedule
Top critical risks need to
be mitigated first
Top critical risks need to
be mitigated first
Crucial Tasks
05/07/14 2009 Intaver Institute 35
Crucial tasks have the
most affect on the
project schedule
Crucial tasks have the
most affect on the
project schedule
Crucial tasks for project cost and
duration can be different
Crucial tasks for project cost and
duration can be different
Success Rate
05/07/14 2009 Intaver Institute 36
A task can be canceled if it reaches a task or a project deadline or if it is affected
by risk with a “Cancel task” outcome.
Success rate is calculated
based on number of
times the task is not
canceled
Success rate is calculated
based on number of
times the task is not
canceled
Risk Chart
05/07/14 2009 Intaver Institute 37
Risk chart show risks, associated with task versus duration or cost
This task has low
duration but high
risk
This task has low
duration but high
risk
These tasks have
balanced risk versus
duration ratio.
These tasks have
balanced risk versus
duration ratio.
Risk Matrix
05/07/14 2009 Intaver Institute 38
Risk matrix shows probability/impact on 5x5 matrix
Double-click on a
risk to view risk
assignments
Double-click on a
risk to view risk
assignments
Risk Probability,
Impact and Score for
the current schedule
Risk Probability,
Impact and Score for
the current schedule
Risk Planning
05/07/14 2009 Intaver Institute 39
Modeling risk mitigation efforts
•Risk handling strategies
•Transfer
•Mitigate
•Eliminate
•Ignore
•Risk mitigation efforts represent their own costs etc.
which must be accounted for
•Create multiple baselines that model pre and post
mitigation risk handling efforts
•View results of risk handling efforts
•Select project alternative based on criteria (cost,
duration, start and finish time, success rate)
Future Reading
Lev Virine and Michael Trumper
Project Decisions:
The Art and Science
Management Concepts, Vienna, VA, 2007
Lev Virine and Michael Trumper
Project Think:
Why Good Managers Make Poor Project Choices
Gower, 2013

Más contenido relacionado

La actualidad más candente

Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Root cause analysis master plan
Root cause analysis master planRoot cause analysis master plan
Root cause analysis master planGlen Alleman
 
Measurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersMeasurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersTechWell
 
Decision making in the oil and gas industry
Decision making in the oil and gas industryDecision making in the oil and gas industry
Decision making in the oil and gas industryPalantir_Solutions
 
Dealing with Estimation, Uncertainty, Risk, and Commitment
Dealing with Estimation, Uncertainty, Risk, and CommitmentDealing with Estimation, Uncertainty, Risk, and Commitment
Dealing with Estimation, Uncertainty, Risk, and CommitmentTechWell
 
Root Cause Analysis
Root Cause AnalysisRoot Cause Analysis
Root Cause Analysistqmdoctor
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
Root Cause Analysis and Corrective Actions
Root Cause Analysis and Corrective ActionsRoot Cause Analysis and Corrective Actions
Root Cause Analysis and Corrective ActionsHannah Stewart
 
Measurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersMeasurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersTechWell
 
Root Cause And Corrective Action Workshop Cinci Asq 2009
Root Cause And Corrective Action Workshop  Cinci Asq 2009Root Cause And Corrective Action Workshop  Cinci Asq 2009
Root Cause And Corrective Action Workshop Cinci Asq 2009roycohen
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo
 
Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...
Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...
Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...Target Health, Inc.
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 
Unit 8-risk manaegement (1) -
Unit 8-risk manaegement (1) - Unit 8-risk manaegement (1) -
Unit 8-risk manaegement (1) - Shashi Kumar
 
Risks of Risk-Based Testing
Risks of Risk-Based TestingRisks of Risk-Based Testing
Risks of Risk-Based Testingrrice2000
 

La actualidad más candente (20)

Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Root cause analysis master plan
Root cause analysis master planRoot cause analysis master plan
Root cause analysis master plan
 
Measurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersMeasurement and Metrics for Test Managers
Measurement and Metrics for Test Managers
 
Decision making in the oil and gas industry
Decision making in the oil and gas industryDecision making in the oil and gas industry
Decision making in the oil and gas industry
 
Dealing with Estimation, Uncertainty, Risk, and Commitment
Dealing with Estimation, Uncertainty, Risk, and CommitmentDealing with Estimation, Uncertainty, Risk, and Commitment
Dealing with Estimation, Uncertainty, Risk, and Commitment
 
Root Cause Analysis
Root Cause AnalysisRoot Cause Analysis
Root Cause Analysis
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
Root Cause Analysis and Corrective Actions
Root Cause Analysis and Corrective ActionsRoot Cause Analysis and Corrective Actions
Root Cause Analysis and Corrective Actions
 
Risk Management by Roger Pressman
Risk Management by Roger PressmanRisk Management by Roger Pressman
Risk Management by Roger Pressman
 
Measurement and Metrics for Test Managers
Measurement and Metrics for Test ManagersMeasurement and Metrics for Test Managers
Measurement and Metrics for Test Managers
 
Presentation1
Presentation1Presentation1
Presentation1
 
Root Cause And Corrective Action Workshop Cinci Asq 2009
Root Cause And Corrective Action Workshop  Cinci Asq 2009Root Cause And Corrective Action Workshop  Cinci Asq 2009
Root Cause And Corrective Action Workshop Cinci Asq 2009
 
Root Cause Analysis
Root Cause AnalysisRoot Cause Analysis
Root Cause Analysis
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
 
Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...
Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...
Impact of Risk-Based Monitoring and eSource Methodologies on Clinical Sites, ...
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Unit 8-risk manaegement (1) -
Unit 8-risk manaegement (1) - Unit 8-risk manaegement (1) -
Unit 8-risk manaegement (1) -
 
Root cause analysis training
Root cause analysis trainingRoot cause analysis training
Root cause analysis training
 
Risks of Risk-Based Testing
Risks of Risk-Based TestingRisks of Risk-Based Testing
Risks of Risk-Based Testing
 
Root cause analysis
Root cause analysisRoot cause analysis
Root cause analysis
 

Destacado

Danielle lovelace[1]
Danielle lovelace[1]Danielle lovelace[1]
Danielle lovelace[1]AntwanF
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysisrupeshmisal
 
Introduction to human resource development
Introduction to human resource developmentIntroduction to human resource development
Introduction to human resource developmentsaumyadvd
 
Human Resource Development (HRD)
Human Resource Development (HRD)Human Resource Development (HRD)
Human Resource Development (HRD)Prakash Dhakal
 
Risk & Risk Management
Risk & Risk ManagementRisk & Risk Management
Risk & Risk Managementansula
 
Human resource development
Human resource developmentHuman resource development
Human resource developmentGeethu Mary
 

Destacado (13)

Danielle lovelace[1]
Danielle lovelace[1]Danielle lovelace[1]
Danielle lovelace[1]
 
Risky projectpresentation rus
Risky projectpresentation rusRisky projectpresentation rus
Risky projectpresentation rus
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Midtown grid
Midtown   gridMidtown   grid
Midtown grid
 
Small midtown
Small midtownSmall midtown
Small midtown
 
Introduction to human resource development
Introduction to human resource developmentIntroduction to human resource development
Introduction to human resource development
 
Human Resource Development (HRD)
Human Resource Development (HRD)Human Resource Development (HRD)
Human Resource Development (HRD)
 
Hrd
HrdHrd
Hrd
 
Risk & Risk Management
Risk & Risk ManagementRisk & Risk Management
Risk & Risk Management
 
Human resource development
Human resource developmentHuman resource development
Human resource development
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 

Similar a Project Risk Analysis with Risk Event and Event Chain

Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisIntaver Insititute
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project RiskGlen Alleman
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned valueGlen Alleman
 
Twelve Risks to Enterprise Software Projects-And What to Do About Them
Twelve Risks to Enterprise Software Projects-And What to Do About ThemTwelve Risks to Enterprise Software Projects-And What to Do About Them
Twelve Risks to Enterprise Software Projects-And What to Do About ThemTechWell
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxSUBHI7
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 
Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides SlideTeam
 
Risk Management Plan PowerPoint Presentation Slides
Risk Management Plan PowerPoint Presentation SlidesRisk Management Plan PowerPoint Presentation Slides
Risk Management Plan PowerPoint Presentation SlidesSlideTeam
 
Risk Management Plan Powerpoint Presentation Slides
Risk Management Plan Powerpoint Presentation SlidesRisk Management Plan Powerpoint Presentation Slides
Risk Management Plan Powerpoint Presentation SlidesSlideTeam
 
A Guide to Risk Management
A Guide to Risk ManagementA Guide to Risk Management
A Guide to Risk ManagementProjectCon
 
Risk Evaluation And Mitigation Strategies PowerPoint Presentation Slide
Risk Evaluation And Mitigation Strategies PowerPoint Presentation SlideRisk Evaluation And Mitigation Strategies PowerPoint Presentation Slide
Risk Evaluation And Mitigation Strategies PowerPoint Presentation SlideSlideTeam
 
Rethinking Risk-Based Project Management in the Emerging IT initiatives.pptx
Rethinking Risk-Based Project Management in the Emerging IT initiatives.pptxRethinking Risk-Based Project Management in the Emerging IT initiatives.pptx
Rethinking Risk-Based Project Management in the Emerging IT initiatives.pptxInflectra
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...p6academy
 
Prevention And Control Strategies PowerPoint Presentation Slides
Prevention And Control Strategies PowerPoint Presentation SlidesPrevention And Control Strategies PowerPoint Presentation Slides
Prevention And Control Strategies PowerPoint Presentation SlidesSlideTeam
 

Similar a Project Risk Analysis with Risk Event and Event Chain (20)

Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Twelve Risks to Enterprise Software Projects-And What to Do About Them
Twelve Risks to Enterprise Software Projects-And What to Do About ThemTwelve Risks to Enterprise Software Projects-And What to Do About Them
Twelve Risks to Enterprise Software Projects-And What to Do About Them
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docx
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
Project Risk management
Project Risk management Project Risk management
Project Risk management
 
Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015
 
Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides
 
Risk Management Plan PowerPoint Presentation Slides
Risk Management Plan PowerPoint Presentation SlidesRisk Management Plan PowerPoint Presentation Slides
Risk Management Plan PowerPoint Presentation Slides
 
Risk Management Plan Powerpoint Presentation Slides
Risk Management Plan Powerpoint Presentation SlidesRisk Management Plan Powerpoint Presentation Slides
Risk Management Plan Powerpoint Presentation Slides
 
A Guide to Risk Management
A Guide to Risk ManagementA Guide to Risk Management
A Guide to Risk Management
 
Risk Evaluation And Mitigation Strategies PowerPoint Presentation Slide
Risk Evaluation And Mitigation Strategies PowerPoint Presentation SlideRisk Evaluation And Mitigation Strategies PowerPoint Presentation Slide
Risk Evaluation And Mitigation Strategies PowerPoint Presentation Slide
 
Rethinking Risk-Based Project Management in the Emerging IT initiatives.pptx
Rethinking Risk-Based Project Management in the Emerging IT initiatives.pptxRethinking Risk-Based Project Management in the Emerging IT initiatives.pptx
Rethinking Risk-Based Project Management in the Emerging IT initiatives.pptx
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
 
Risk analysis
Risk analysis Risk analysis
Risk analysis
 
Prevention And Control Strategies PowerPoint Presentation Slides
Prevention And Control Strategies PowerPoint Presentation SlidesPrevention And Control Strategies PowerPoint Presentation Slides
Prevention And Control Strategies PowerPoint Presentation Slides
 

Más de Intaver Insititute

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2Intaver Insititute
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectIntaver Insititute
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction IndustryIntaver Insititute
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear ProjectsIntaver Insititute
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingIntaver Insititute
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Intaver Insititute
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear ProjectsIntaver Insititute
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Intaver Insititute
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosIntaver Insititute
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesIntaver Insititute
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryIntaver Insititute
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project ManagementIntaver Insititute
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive managementIntaver Insititute
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project ManagementIntaver Insititute
 
Risky project Cloud presentation rus
Risky project Cloud presentation rusRisky project Cloud presentation rus
Risky project Cloud presentation rusIntaver Insititute
 
Risky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementRisky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementIntaver Insititute
 

Más de Intaver Insititute (20)

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - Reporting
 
Project Cost Analysis
Project Cost AnalysisProject Cost Analysis
Project Cost Analysis
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project Portfolios
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
RiskyProject 7
RiskyProject 7RiskyProject 7
RiskyProject 7
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
 
RiskyProject Enterprise
RiskyProject EnterpriseRiskyProject Enterprise
RiskyProject Enterprise
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace Industry
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project Management
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project Management
 
Risky project Cloud presentation rus
Risky project Cloud presentation rusRisky project Cloud presentation rus
Risky project Cloud presentation rus
 
Risky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementRisky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagement
 

Último

WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...apidays
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Angeliki Cooney
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityWSO2
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdfSandro Moreira
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 

Último (20)

WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 

Project Risk Analysis with Risk Event and Event Chain

  • 1. Risk Event Modeling Risk event modeling in part of Intaver Institute’s presentations on project risk management and risk analysis Intaver Institute Inc. 303, 6707, Elbow Drive S.W, Calgary, AB, Canada Tel: +1(403)692-2252 Fax: +1(403)459-4533 www.intaver.com
  • 2. The Project Management Problem 05/07/14 2009 Intaver Institute 2 Many projects are unsuccessful!Many projects are unsuccessful!
  • 3. 05/07/14 2009 Intaver Institute 3 The Project Management Problem
  • 4. 05/07/14 2009 Intaver Institute 4 The Project Management Problem
  • 5. 05/07/14 2009 Intaver Institute 5 The Project Management Problem
  • 6. 05/07/14 2009 Intaver Institute 6 The Project Management Problem
  • 8. Risk Event Modeling Workflow 05/07/14 2009 Intaver Institute 8
  • 9. Risk Definition • Risks – Risks are “events” that have a probability of occurring during a project – Risks are identified and assigned to tasks or resources – Define impact of risks by assigning: • Chance of occurrence • Outcome (e.g. delay, increase in cost) • Result (percentage or fixed value of outcome) 05/07/14 2009 Intaver Institute 9
  • 10. What is Monte Carlo Monte Carlo simulation is a mathematical method used in risk analysis. Monte Carlo simulations are used to approximate the distribution of potential results based on probabilistic inputs.
  • 11. Monte Carlo Simulations Input Parameters Output Parameters Calculation Engine Critical Path Scheduling Engine ( ) Task duration cost, finish time, etc. cost, finish time, etc. Project duration
  • 12. Monte Carlo Schedule Analysis 4 5 6321 7 7 82 3 654 1 4 5 632 7 8 9 10 11 12 13 14 15 16 1 2 3 4 5 6 7 Task 1 Task 2 Task 3
  • 13. Two Approaches to Estimating Probabilities • The relative frequency approach, where probability equals the number of occurrences of specific outcome (or event) divided by the total number of possible outcomes. • The subjective approach represents an expert’s degree of belief that a particular outcome will occur.
  • 14. Two Approaches for Defining Uncertainties • Distribution-based approach • Event-based approach
  • 15. Which Distribution Should Be Used? Normal Triangual Uniform Also useful: • Lognornal • Beta
  • 17. Before Eliciting Judgment You Need to Have: • A clearly defined problem • An identified list of risks, or a risk breakdown structure, for the project • A project schedule • A clearly defined set of questions you will ask experts In addition, your team of experts should be aware of any personal interest that expert may have regarding particular issues. It helps to mitigate motivational biases.
  • 18. Psychological Factors • Availability heuristic: people judge the probability of the occurrence of events by how easily these events are brought to mind. • Anchoring heuristic: refers to the human tendency to remain close to the initial estimate. • Wishful thinking: when we overestimate the probabilities of opportunities and underestimate the probabilities of risks.
  • 19. Overestimating the Probability of Compound Events If the probability of a defect in a component is 20% and the device uses three redundant components, the probability of the defective device will be (0.2 * 0.2 * 0.2) = 0.008%. People tend to think this number is much higher.
  • 20. Ignoring Base-Rate Frequencies • Historically, the probability that a particular component will be defective is 1%. • The component is tested before installation. • The test showed that the component is defective. • The test usually successfully identifies defective components 80% of the time. • What is the probability that a component is defective? The correct answer is close to 4%, however, most people would think that answer is a little bit lower than 80%.
  • 21. Eliciting Judgment About Probabilities of Single Events • Pose a direct question: “What is the probability that the project will be canceled due to budgetary problems?” • Ask the experts two opposing questions: (1) “What is the probability that the project will be canceled?” and (2) “What is the probability the project will be completed?” The sum of these two assessments should be 100%. • Break compound events into simple events and review them separately.
  • 22. Probability Wheel 25% No delay of activity 35% 3 day delay of activity 40% 5 day delay of activity
  • 23. Task Duration 4 8 12 16 20 100% 80% 60% 40% 20% Frequency Probability 2 3 4 5 6 (days) Question: What is the chance that duration is less than 3 days? Eliciting Judgment: Probability Method
  • 24. Eliciting Judgment: Method of Relative Heights Task Duration 2 4 6 8 10 2 3 4 5 6 50% 40% 30% 20% 10%Frequency Probability (days) Question: How many times the duration will be between 2 and 3 days?
  • 25. How Many Trials Are Required? Huge number of trials (> 1000) usually does not increase accuracy of analysis • Incorporate rare events • Use convergence monitoring
  • 26. What Is The Chance That a Project Will Be on Time And Within Budget?
  • 27. Analysis of Monte Carlo Results • Sensitivity and Correlations • Critical Indices • Crucial tasks • Critical Risks • Probabilistic Calendars • Deadlines • Conditional Branching • Probabilistic Branching • Chance of Task Existence
  • 28. Analyze Results 05/07/14 2009 Intaver Institute 28
  • 29. Result Gant 05/07/14 2009 Intaver Institute 29 When you have project schedule and risk breakdown structure ready click here to perform Monte Carlo simulations When you have project schedule and risk breakdown structure ready click here to perform Monte Carlo simulations RiskyProject employs convergence monitoring to ensure fast calculation RiskyProject employs convergence monitoring to ensure fast calculation
  • 30. Risk Register Pre-mitigation Probability, Impact, And Score Pre-mitigation Probability, Impact, And Score 05/07/14 2009 Intaver Institute 30
  • 31. Result Gantt Chart 05/07/14 2009 Intaver Institute 31 White bars represent original project schedule (no risks) White bars represent original project schedule (no risks) Blue bars represent project schedule with risks Blue bars represent project schedule with risks Because of risks, project duration significantly increased Because of risks, project duration significantly increased
  • 32. Results of Risk Analysis 05/07/14 2009 Intaver Institute 32 Project Summary: project duration, cost, and finish time with and without risks Project Summary: project duration, cost, and finish time with and without risks Results of analysis for project cost, finish time, and duration Results of analysis for project cost, finish time, and duration Double click on any chart to view detailed informationDouble click on any chart to view detailed information
  • 33. Detailed Results of Analysis 05/07/14 2009 Intaver Institute 33 Move the slider to determine the chance that project will be within budget Move the slider to determine the chance that project will be within budget Get detailed statistical data Get detailed statistical data Data can be exported as an image or text Data can be exported as an image or text Detailed results can be shown for each tasks or whole project for cost, duration, start time, finish time, and income. Detailed results can be shown for each tasks or whole project for cost, duration, start time, finish time, and income.
  • 34. Sensitivity 05/07/14 2009 Intaver Institute 34 Tornado chart shows risks or other parameters have the most affect on the project schedule Tornado chart shows risks or other parameters have the most affect on the project schedule Top critical risks need to be mitigated first Top critical risks need to be mitigated first
  • 35. Crucial Tasks 05/07/14 2009 Intaver Institute 35 Crucial tasks have the most affect on the project schedule Crucial tasks have the most affect on the project schedule Crucial tasks for project cost and duration can be different Crucial tasks for project cost and duration can be different
  • 36. Success Rate 05/07/14 2009 Intaver Institute 36 A task can be canceled if it reaches a task or a project deadline or if it is affected by risk with a “Cancel task” outcome. Success rate is calculated based on number of times the task is not canceled Success rate is calculated based on number of times the task is not canceled
  • 37. Risk Chart 05/07/14 2009 Intaver Institute 37 Risk chart show risks, associated with task versus duration or cost This task has low duration but high risk This task has low duration but high risk These tasks have balanced risk versus duration ratio. These tasks have balanced risk versus duration ratio.
  • 38. Risk Matrix 05/07/14 2009 Intaver Institute 38 Risk matrix shows probability/impact on 5x5 matrix Double-click on a risk to view risk assignments Double-click on a risk to view risk assignments Risk Probability, Impact and Score for the current schedule Risk Probability, Impact and Score for the current schedule
  • 39. Risk Planning 05/07/14 2009 Intaver Institute 39 Modeling risk mitigation efforts •Risk handling strategies •Transfer •Mitigate •Eliminate •Ignore •Risk mitigation efforts represent their own costs etc. which must be accounted for •Create multiple baselines that model pre and post mitigation risk handling efforts •View results of risk handling efforts •Select project alternative based on criteria (cost, duration, start and finish time, success rate)
  • 40. Future Reading Lev Virine and Michael Trumper Project Decisions: The Art and Science Management Concepts, Vienna, VA, 2007 Lev Virine and Michael Trumper Project Think: Why Good Managers Make Poor Project Choices Gower, 2013

Notas del editor

  1. Why is this easy
  2. Risk register is central point of entry into risk analysis and management system Shows calculated project risk scores – ranks and identifies critical project risks. Add two screen shots. Risk Register Risk Assignment Add slide with Risk Mitigation Waterfall diagram with descriptive names
  3. Change to put calculated results in the Result Gantt chart
  4. Detailed results show certainty levels or the chance that a project parameter will be a certain value. Allows you to see the values e.g. managing at 75% certainty as well as setting buffers or contingencies.
  5. Calculates the success rates of tasks or project based upon deadlines or constraints