SlideShare una empresa de Scribd logo
1 de 14
Bralorne Sewer Project
Community Information Meeting
Bralorne Fire Hall
June 28th 2018
Agenda
1. Brief history of the Bralorne Sewer system
2. Current operations and wastewater discharge
3. Overview of project
• What has been completed
• What is outstanding
4. Options to move forward
5. Questions
Bralorne Sewer Background
• Constructed in the early 1900’s by the
mining company to support the town
of Bralorne
• Single owner/occupier of the land
• Late 1960’s Marmot Enterprises buys
the town and subdivides it.
• Water system improvements are made
but no major investments in sewer
infrastructure
• SLRD assumed ownership in the 1989
• Nearly a Century
Old
• 4”-8” vitrified clay
collection piping
• 62% of collection
system is in
trespass with no
statutory rights of
way
• Septic tank with
outfall to
Cadwallader creek
• Unknown water
infiltration and
leakage rates
• Original 1974
operating permit
PE – 3157
Bralorne Sewer today Townsite #1
Bralorne Sewer today Townsite #2
• Nearly a Century Old
• 4”-8” vitrified clay
collection piping
• 41% of collection
system is in trespass
with no statutory
rights of way
• Septic tank with outfall
to Cadwallader creek
• Unknown water
infiltration and leakage
rates
• Original 1974
operating permit PE –
3157
Letter from the Ministry of Environment…
Bralorne Sewer Upgrade Project
Project summary: Replace existing end-of-life sewer infrastructure with a
modern watertight system in proper rights of way. Combine sewer systems to provide a
single discharge with passive secondary treatment.
Project Includes:
2,460 meters of piping, 107 service connections, 43 Manholes, new septic tanks and Secondary treatment.
What is complete:
• Gas Tax grant funding: $1,999,530
• Detailed Engineering Design
• Acceptance of Rights-of-way (ROW’s)
• Approval of the Environmental Impact Assessment
• MOTI Construction Permits
• New MOE Discharge Permit
• Location for the secondary treatment plant
• Approved Construction Contract
Results from Tender
• 4 responses
• Prices ranging from $2.47 – $6.4 Million
• Low Bidder Hazelwood Construction Services
• Still $829,000 over budget
• Additional funding sources
• Bralorne Sewer Reserve Contribution $38,000
• Area A Gas Tax Amenity Funds $91,000
Project Budget
Update June 19th 2018
Original Funding sources
Gas Tax Grant 1,999,530$
Bralorne Gold Mine Contribution 10,000$
Bralorne Sewer Reserve Contribution 22,000$
Additional Funding Post May 23/24 Board Meeting
Area A Gas Tax Community Works Funds 91,000$
Unallocated Bralorne Sewer Reserve 38,000$
Total Available Funds 2,160,530$
Project Costs
Engineering 110,659$
Geotechnical 28,688$
Environmental Studies 32,267$
Permits ect. 10,000$
Land purchase and transfer costs 40,000$
Construction 2,469,129$
Reduced Scope (167,000)$
Additional Scope 140,000$
Contingency 196,787$
Updated Project Budget 2,860,530$
Funding Shortfall (700,000)$
Options to move forward
OPTION 1 - Cancel tender, seek additional funding and retender next
spring.
Pros – Buys time to address funding shortfall
Cons/Risk – Pricing escalation risk; Project delay, Grant Deadline.
OPTION 2 – Phase project; award contract for sewer collection system
with option to include treatment plant subject to Elector Approval.
Pros – Allows for construction to start this summer with known costs and
good contractor.
Cons/Risks – If additional funding is not secured for phase 2, we could
lose 15% of grant funding (300K) if project is not completed. Note: MOE
will require secondary treatment in the future.
What is an Alternative Approval Process?
A form of approval that allows electors to indicate whether they are
against a local government proposal to move forward. The process will
take about 3 months to complete.
How much will it cost me?
• Current Sewer Parcel Tax is $285.28/parcel per year
• The SLRD estimates the loan financing costs will be ~$418.15/parcel per
year
• Total Sewer cost ~$703.43
The SLRD is seeking Electoral Approval
via Alternative Approval Process to borrow up to
$700,000 to complete the sewer upgrade project.
Questions???

Más contenido relacionado

La actualidad más candente

Alamo Heights CCM 01.08.18 - Item #4 ppt CM Report
Alamo Heights CCM 01.08.18 - Item #4   ppt CM ReportAlamo Heights CCM 01.08.18 - Item #4   ppt CM Report
Alamo Heights CCM 01.08.18 - Item #4 ppt CM Report
ahcitycouncil
 
Half yearly results for the six months to June 2013
Half yearly results for the six months to June 2013Half yearly results for the six months to June 2013
Half yearly results for the six months to June 2013
Company Spotlight
 

La actualidad más candente (20)

City council june 18, 2013 hickory update
City council june 18, 2013   hickory updateCity council june 18, 2013   hickory update
City council june 18, 2013 hickory update
 
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community RoomOak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
 
Bray Main Street Works 2013
Bray Main Street Works 2013Bray Main Street Works 2013
Bray Main Street Works 2013
 
Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13
 
Interlocal Agreement with Wellborn SUD
Interlocal Agreement with Wellborn SUDInterlocal Agreement with Wellborn SUD
Interlocal Agreement with Wellborn SUD
 
Sprinkler Talks. People Listen.
Sprinkler Talks. People Listen.Sprinkler Talks. People Listen.
Sprinkler Talks. People Listen.
 
Alamo Heights CCM 01.08.18 - Item #4 ppt CM Report
Alamo Heights CCM 01.08.18 - Item #4   ppt CM ReportAlamo Heights CCM 01.08.18 - Item #4   ppt CM Report
Alamo Heights CCM 01.08.18 - Item #4 ppt CM Report
 
Premier oil13a pres
Premier oil13a presPremier oil13a pres
Premier oil13a pres
 
Gas infrastructure development in archipelagic country sampe l. purba
Gas infrastructure development in archipelagic country   sampe l. purbaGas infrastructure development in archipelagic country   sampe l. purba
Gas infrastructure development in archipelagic country sampe l. purba
 
Sussex sewer district presentation to city 11262018
Sussex sewer district  presentation to city   11262018Sussex sewer district  presentation to city   11262018
Sussex sewer district presentation to city 11262018
 
SH 6 Waterline Easements
SH 6 Waterline EasementsSH 6 Waterline Easements
SH 6 Waterline Easements
 
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
Tuscarora Lateral Project - Open House Presentation on New 17-Mile Pipeline i...
 
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
 
Waste-to-energy plants - public private partnership Singapore
Waste-to-energy plants - public private partnership SingaporeWaste-to-energy plants - public private partnership Singapore
Waste-to-energy plants - public private partnership Singapore
 
Half yearly results for the six months to June 2013
Half yearly results for the six months to June 2013Half yearly results for the six months to June 2013
Half yearly results for the six months to June 2013
 
Lick Creek Trail Restoration
Lick Creek Trail RestorationLick Creek Trail Restoration
Lick Creek Trail Restoration
 
2018 SRFB PSAR Project List for
2018 SRFB PSAR Project List for2018 SRFB PSAR Project List for
2018 SRFB PSAR Project List for
 
ORGANICS3 Municipal Site Development: Life Beyond the Landfill, Dan Barrett
ORGANICS3 Municipal Site Development: Life Beyond the Landfill, Dan BarrettORGANICS3 Municipal Site Development: Life Beyond the Landfill, Dan Barrett
ORGANICS3 Municipal Site Development: Life Beyond the Landfill, Dan Barrett
 
Overall analysis of the onshore sector of Albania and current developments
Overall analysis of the onshore sector of Albania and current developmentsOverall analysis of the onshore sector of Albania and current developments
Overall analysis of the onshore sector of Albania and current developments
 
TWCOG
TWCOGTWCOG
TWCOG
 

Similar a SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)

K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
ascemiami-dade
 
20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award
Samat Jain
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
HartTWI
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christi
jeshaml10
 
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike RickmanA New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
TWCA
 
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Andrew Gelston
 

Similar a SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018) (20)

Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
2018 SRFB PSAR Project Ranked List
2018 SRFB PSAR Project Ranked List2018 SRFB PSAR Project Ranked List
2018 SRFB PSAR Project Ranked List
 
20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
Old Courthouse Spring Branch at Ashgrove Historic Park Stream Restoration Pro...
Old Courthouse Spring Branch at Ashgrove Historic Park Stream Restoration Pro...Old Courthouse Spring Branch at Ashgrove Historic Park Stream Restoration Pro...
Old Courthouse Spring Branch at Ashgrove Historic Park Stream Restoration Pro...
 
Disco Road Biogas Utilization Project
Disco Road Biogas Utilization ProjectDisco Road Biogas Utilization Project
Disco Road Biogas Utilization Project
 
LTCP meeting 11-16-05
LTCP meeting 11-16-05LTCP meeting 11-16-05
LTCP meeting 11-16-05
 
Water presentation port of corpus christi
Water presentation port of corpus christiWater presentation port of corpus christi
Water presentation port of corpus christi
 
Wastewater Master Plan Update
Wastewater Master Plan UpdateWastewater Master Plan Update
Wastewater Master Plan Update
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation Project
 
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike RickmanA New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
 
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
 
WHCRWA Town Hall Meeting 11-10-2014
WHCRWA Town Hall Meeting 11-10-2014WHCRWA Town Hall Meeting 11-10-2014
WHCRWA Town Hall Meeting 11-10-2014
 
Southmost Regional Water Authority, Judy Adams
Southmost Regional Water Authority, Judy AdamsSouthmost Regional Water Authority, Judy Adams
Southmost Regional Water Authority, Judy Adams
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive ImpactJeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
Jeff Polenik, Robindale Energy,"Leanor GFCC - A Positive Impact
 

Último

Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
ScottMeyers35
 
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ScottMeyers35
 

Último (20)

2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
 
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s education
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx
 
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In MumbaiVasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 

SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)

  • 1. Bralorne Sewer Project Community Information Meeting Bralorne Fire Hall June 28th 2018
  • 2. Agenda 1. Brief history of the Bralorne Sewer system 2. Current operations and wastewater discharge 3. Overview of project • What has been completed • What is outstanding 4. Options to move forward 5. Questions
  • 3. Bralorne Sewer Background • Constructed in the early 1900’s by the mining company to support the town of Bralorne • Single owner/occupier of the land • Late 1960’s Marmot Enterprises buys the town and subdivides it. • Water system improvements are made but no major investments in sewer infrastructure • SLRD assumed ownership in the 1989
  • 4. • Nearly a Century Old • 4”-8” vitrified clay collection piping • 62% of collection system is in trespass with no statutory rights of way • Septic tank with outfall to Cadwallader creek • Unknown water infiltration and leakage rates • Original 1974 operating permit PE – 3157 Bralorne Sewer today Townsite #1
  • 5. Bralorne Sewer today Townsite #2 • Nearly a Century Old • 4”-8” vitrified clay collection piping • 41% of collection system is in trespass with no statutory rights of way • Septic tank with outfall to Cadwallader creek • Unknown water infiltration and leakage rates • Original 1974 operating permit PE – 3157
  • 6. Letter from the Ministry of Environment…
  • 7. Bralorne Sewer Upgrade Project Project summary: Replace existing end-of-life sewer infrastructure with a modern watertight system in proper rights of way. Combine sewer systems to provide a single discharge with passive secondary treatment. Project Includes: 2,460 meters of piping, 107 service connections, 43 Manholes, new septic tanks and Secondary treatment.
  • 8. What is complete: • Gas Tax grant funding: $1,999,530 • Detailed Engineering Design • Acceptance of Rights-of-way (ROW’s) • Approval of the Environmental Impact Assessment • MOTI Construction Permits • New MOE Discharge Permit • Location for the secondary treatment plant • Approved Construction Contract
  • 9. Results from Tender • 4 responses • Prices ranging from $2.47 – $6.4 Million • Low Bidder Hazelwood Construction Services • Still $829,000 over budget • Additional funding sources • Bralorne Sewer Reserve Contribution $38,000 • Area A Gas Tax Amenity Funds $91,000
  • 10. Project Budget Update June 19th 2018 Original Funding sources Gas Tax Grant 1,999,530$ Bralorne Gold Mine Contribution 10,000$ Bralorne Sewer Reserve Contribution 22,000$ Additional Funding Post May 23/24 Board Meeting Area A Gas Tax Community Works Funds 91,000$ Unallocated Bralorne Sewer Reserve 38,000$ Total Available Funds 2,160,530$ Project Costs Engineering 110,659$ Geotechnical 28,688$ Environmental Studies 32,267$ Permits ect. 10,000$ Land purchase and transfer costs 40,000$ Construction 2,469,129$ Reduced Scope (167,000)$ Additional Scope 140,000$ Contingency 196,787$ Updated Project Budget 2,860,530$ Funding Shortfall (700,000)$
  • 11. Options to move forward OPTION 1 - Cancel tender, seek additional funding and retender next spring. Pros – Buys time to address funding shortfall Cons/Risk – Pricing escalation risk; Project delay, Grant Deadline. OPTION 2 – Phase project; award contract for sewer collection system with option to include treatment plant subject to Elector Approval. Pros – Allows for construction to start this summer with known costs and good contractor. Cons/Risks – If additional funding is not secured for phase 2, we could lose 15% of grant funding (300K) if project is not completed. Note: MOE will require secondary treatment in the future.
  • 12. What is an Alternative Approval Process? A form of approval that allows electors to indicate whether they are against a local government proposal to move forward. The process will take about 3 months to complete. How much will it cost me? • Current Sewer Parcel Tax is $285.28/parcel per year • The SLRD estimates the loan financing costs will be ~$418.15/parcel per year • Total Sewer cost ~$703.43 The SLRD is seeking Electoral Approval via Alternative Approval Process to borrow up to $700,000 to complete the sewer upgrade project.
  • 13.

Notas del editor

  1. Undersized compared with modern standards No secondary treatment as required by modern standards
  2. According to MOE this system is most in need of an upgrade of any system in the lower