Brevard Contractors School
1
Prepare To Pass
Copyright 2004 – 2006 ©
Day 1 Exam Review
Accounting Review:
The Chart of Accounts is used to catalog all Sources and Uses of Funds. The Chart of
Accounts is a list of all categories of a company's Assets, Liabilities and Equities. The
Chart of Accounts are numbered to provide a shorthand method to apply costs and
income.
The Chart of Accounts is basically a list of places (accounts). These accounts can either
be sources of money or uses of money. Asset accounts typically carry what is called a
Debit Balance and are located on the left side of the Balance Sheet, while Liabilities and
Equity typically carry what is called a Credit Balance, and they are located on the right
side of the Balance Sheet. An asset is anything a business owns that has a money value.
Anything a business owes is a liability. The difference between what a business owns and
what it owes is called equity or capital. Equity can also be called Net Worth. Net Worth
is the amount of equity or money that would remain if all the debts of the business were
paid and the business were liquidated. This is the portion of the business that belongs to
the owner(s). The summary document that lists assets, liabilities, and equity is called a
Balance Sheet. It is called the Balance Sheet because the left Asset side of the
spreadsheet must equal the right Liability + Equity side of the spreadsheet.
Assets = Liabilities + Net Worth.
Brevard Contractors School
2
Prepare To Pass
Copyright 2004 – 2006 ©
Chart of Accounts
Assets
Current Assets
Petty Cash Funds
Cash in Banks
Cash in Escrow Accounts
Notes Receivable
Accounts Receivable
Reserve for Bad Debts
Retainage
Inventories
Long-term Assets
Land
Building
Furniture and Fixtures
Autos and Trucks
Equipment
Machinery
Small Tools
Improvements
Accumulated Depreciation
Furniture and Fixtures
Accumulated Depreciation - Autos and Trucks
Accumulated Depreciation - Equipment
Accumulated Depreciation - Improvements
Suspense Account
Accrued Construction-In-Progress Debits (Income) Deferred Construction-in-Progress
Debits (expenses) Intangible Assets
Covenants Not to Compete
Goodwill
Brevard Contractors School
3
Prepare To Pass
Copyright 2004 – 2006 ©
Liabilities
Current Liabilities
Accounts Payable
Payroll Taxes Payable
Sales Taxes Payable
Income Taxes Payable
Other Taxes Payable
Accrued Expenses Payable
Notes Payable - Current Portion Long-term Liabilities
Notes Payable - Long-term Portion Other Credits
Deferred Construction-in-Progress Credits Suspense Account
Net Worth
Net Worth Accounts (for corporations) Capital Stock
Retained Earnings
Profit and Loss - Corporations
Net Worth Accounts (for partnerships) Owners' Equity Accounts
Owners' Drawing Accounts
Profit and Loss - Partnerships
Net Worth Accounts (for sale owners)
Financial data is entered into a database that uses The Chart of Accounts for the
category headings. This allows the accounts or "fields" to be summarized.
These summaries of financial data are called Financial Statements. The three primary
financial statements are the Balance Sheet, the Income Statement (Profit and Loss
Statement) and the Sources and Uses of Funds Statement.
The classic accounting equation is:
Assets = Liabilities + Net Worth.
Type of account to decrease to increase typical balance
Asset credit debit debit
Liability debit credit credit
Capital debit credit credit
Income debit credit credit
Expense credit debit debit
Brevard Contractors School
4
Prepare To Pass
Copyright 2004 – 2006 ©
This relationship between assets and liabilities plus net worth is evident in the classic
presentation of the Balance Sheet.
Assets: Debit Credit Debit Credit
Assets
Cash xxx
Accounts Receivable xxx
Bad Debt Reserves xxx
Fixed Assets xxx
Depreciation Reserve xxx
Liabilities xxx
Accounts Payable xxx
Taxes Payable xxx
Notes Payable xxx
Net Worth xxx
Capital Stock xxx
Retained Earnings xxx
Look at the Balance Sheet, it has 3 accounts, Assets on the left side, and Liabilities
and Net Worth on the right side of the page. The two sides allow for a debit or credit
balance for each account. The left column is called the debit side and the right side
column is called the credit side. Assets usually carry a debit balance, which means there
is a positive number located on the left side of the equation. Liabilities and Net Worth
usually carry a credit balance. The two sides of the balance sheet must always balance or
equal each other. The two sides of the account are like a mirror image of each other.
Debit Credit Debit Credit
X = X
Assets = Liabilities + Net Worth
Anytime the Asset side of the equation increases or decreases the Liabilities or Net Worth
side of the equation must also increase or decrease in an equal amount. In double entry
bookkeeping, any change will affect a minimum of 2 accounts. In asset accounts a debit
increases the account, and a credit decreases an account. In the Liabilities and Net Worth
Brevard Contractors School
5
Prepare To Pass
Copyright 2004 – 2006 ©
account a debit decreases the account and a credit increases the account. In this way the
double entry accounting system is maintained in balance.
The Income Statement is a snap shot of the business on a given day in time. Since a
business can make money or lose money the Income Statement is also called a Profit
and Loss Statement or the Summary of Operations. The Income Statement lists
income, direct costs, operating expenses and profits.
Construction Company
Income Statement
For the year 2002
Eared Income xxx
Returns and Allowances xxx
Net Sales xxx
Cost of Goods Sold xxx
Gross Profit xxx
Selling Expenses xxx
Profit before fixed Overhead xxx
Fixed Overhead xxx
Net Income xxx
Sources and Uses of Funds Statement also called The Statement of Cash Flows
summaries the management of cash during a specified period. The Statement of Cash
Flows is in many ways the most valuable report you can have.
The Builder's Guide to Accounting begins by asking how are you going to
manage asset and liability accounts in your company. The decisions you make have cash
consequences as well as tax consequences.
Look again at the Balance Sheet; each of these accounts can be managed. The cash
category, called the cash account can and must be monitored to insure that enough cash is
available to run the business. It is normal to keep a cash journal to make it easier to do
sales tax reports. Charge sales are kept in a separate journal from cash sales so they can
be monitored as accounts receivable. Cash flow problems are common to builders
because the construction business requires large investments.
Brevard Contractors School
6
Prepare To Pass
Copyright 2004 – 2006 ©
A cash budget should accomplish the following;
• Make cash available for day-to-day operations.
• Plan for the use of excess funds.
• Time operations for seasonal business changes.
• Provide for levels of inventory.
• Prepare for tax liabilities.
• Control the purchase of materials and help prevent over or under buying.
• Help you maintain a good credit rating.
Ratio Test for Cash
The Current Ratio compares current assets (cash, receivables and inventories) to current
liabilities (current notes payable, accounts payable, accrued taxes).
Current Ratio = Current Assets / Current Liabilities
A good current ratio is 2:1 or higher, which means current assets are double current
liabilities. A 1:1 ratio is weak. A negative ratio is cause for concern, not only is the
company low on cash, but growth potential is negative as well. It is common to try and
obtain more cash to increase the ratio, instead try to reduce your current liabilities. The
current ratio is the most popular and widely used test for a cash position.
The Quick Ratio compares current assets (not including inventories) to current liabilities.
An acceptable ratio rate is 1:1 or better. This quick ratio is also called the Acid Test
because it tests the ability of a company to pay its current debts from its current cash and
near cash assets. The acid test is a more consistent test as inventories are variable.
Quick Ratio = (Current Assets – Inventories) / Current Liabilities
Ratio analysis: Using the Balance Sheet and Income Statement it is possible to do
analysis on a business. Ratios are a quick and easy way to understand how well a
business is performing.
Also, one can obtain a SIC – Standard Industrial Classification for a
comparable class of industry and compare this companies ratios with the industry
standard. The analysis takes the form of ratio analysis. Certain accounts in the Balance
Statement or Income Statement are divided by other accounts to obtain ratios.
Brevard Contractors School
7
Prepare To Pass
Copyright 2004 – 2006 ©
Balance Sheet Ratios:
Both parts of the ratio are found on the balance sheet.
Current Ratio = current assets / current liabilities.
Quick Assets Ratio (acid test) = Current Assets-Inventories / Current Liabilities.
Owner's Investment vs. Creditors Investment = Capital / Current Liabilities.
Ability to Meet Obligations = Working Capital / Funded Debt.
Working Capital = Current Assets – Current Liabilities.
Owner Financing vs. Debt Financing = Net Worth / Assets.
Income Statement Account Ratios:
Both parts of the ratio are found on the income statement.
Percentage of Gross Profit = Gross Profit / Sales.
Expense Control Ratio = Operating Expenses / Sales Volume.
Margin of Profit = Net Income / Sales.
Combined Ratios:
One part is found on the income statement and one part is from the balance
sheet.
Trend in Charge Sales = Sales / Accounts Receivable.
Real Turnover = Cost of Sales / Inventory at Cost.
Day’s of Inventory Available = Total Working Days Per Year / Turnover.
True Investment Yield = Net Income / Net Worth.
There are two ways to prepare a cash budget. One is the Cash Movement Method and
the other is the Sources and Application of Funds Method.
The Cash Movement Method involves budgeting for the flow of actual cash in and
out of your business. The Sources and Application of Funds Method assumes an
operating budget and then subtracts expenses from cash flow to calculate the level of
available working capital.
Brevard Contractors School
8
Prepare To Pass
Copyright 2004 – 2006 ©
It is important to obtain a line of credit to insure that the construction company
has available cash for emergences. A manager must be careful not to rely upon 30 day
and 90 days materials revolving accounts in the event a customer does not pay. A
contractor must be careful not to take on more jobs than he/she has cash to buy materials
and pay labors until the contracts are completed.
Reserve for Bad Debts
A company needs a policy for collecting debts and for dealing with un-collectable debts.
Recognizing when a customer is late paying, and holding the customer to a payment
schedule can greatly reduce bad debts.
Debts can only be written off the books when;
• A debtor abandons his/her business.
• The debtor cannot be contacted.
• The debtor dies and leaves a worthless estate.
It is important to monitor bad debts to make sure the ratio of charge sales to bad debts are
not increasing. If they are, the company's policy or process used in evaluating charge
sales must be reevaluated.
Bad Debt Ratio: Total Credit Sales / Actual Bad Debt Losses.
Since the contractor knows that some percentage of receivables will never be collected
he/she makes an account for bad debts. The objective is to make sure the company does
not come to depend on cash that will never materialize.
Receivables:
The next account that can be managed is receivables. Receivables are short-term debts
(for a period of less than one year) that must be monitored and managed to make sure as
much as possible turns into cash. Also, a company will commonly set a dollar limit on
receivables, to make sure the company does not run out of cash. A second option is to sell
or pledge receivables at a bank against a revolving line of credit. It is important to track
your receivables trend as; if customers begin to take longer to pay, it is more likely that
bad debts will increase. This is particularly important in a declining economy.
Brevard Contractors School
9
Prepare To Pass
Copyright 2004 – 2006 ©
Average Days Receivables = (Average Receivables / (12 Month's
Charges)) x 365
When a receivable is assigned to a collection agency or considered a bad debt it should be
listed in a separate column in your accounts receivable and these amounts should be
excluded from monthly totals.
The next asset account is Long Term Receivables. These must also be managed to
insure that they turn into cash at maturity. It is also important to know that it is possible
to sell or pledge long term notes receivables to obtain financing. Banks, mortgage
companies, and factors will buy long term receivables, often at a discount. Long-term
receivables are often called Notes Receivable. Keep this in mind when agreeing to hold
paper on a construction job.
To qualify as a Notes Receivable the debt must be in writing in a formal legal
document, signed by both parties. For this reason a signed lease for more than one year
also qualifies as a note receivable. If you plan to sell off notes receivable your notes need
to carry an interest rate premium of 2 to 3 percentage points above the market average or
your notes will be severely discounted.
Retainage:
These are hold backs that customers kept, usually about 10% of the bid amount to insure
that the contractor does the "punch list" items and resolves all the incidental problems
which may exist after the project is "substantially complete" or has received a CO,
"certificate of occupancy.”
Retainages can't be considered past due receivables, and they must be separated
from delinquent receivables.
Long-Term Assets:
Long-term assets are assets that are expected to remain on the books for more than one
year before they are turned into cash. Some assets, such as trucks, front-end loaders, and
barns are used in the course of business and there is no intention to turn such long-term
assets into cash.
Brevard Contractors School
10
Prepare To Pass
Copyright 2004 – 2006 ©
Prepaid Assets and Deferred Assets:
Prepaid assets are sometimes called deferred assets. Some debts are paid for in advance,
such as insurance, deposits on real estate, utilities deposits, office supplies, and loan
interest: These prepaid assets should be listed on the books as assets. The distinction
between prepaid assets and deferred assets is that deferred assets are not put on the books
until the item is available for use, even though it has been paid for.
Intangible Assets:
Intangible assets are typically non-physical assets such as the "goodwill" that a
businessperson's reputation will earn, as well as non-competition clauses. Anytime you
pay more for an asset than it's appraised or "fair market" value the difference is classified
as "goodwill." Such non-tangible assets are listed on the books and amortized over a
period of years.
Current Liabilities:
These are debts the company must pay within 12 months. Notes payable, current: these
are accounts, which are due and payable before the end of the fiscal year, usually
December 31. Long Term Notes Payable: These are debts that are due and payable at a
future date beyond the current year.
Accounts Payable: are typically vendor accounts for materials and rentals, but they can
be truck and equipment loans, electric bills, and current real estate taxes.
Taxes: taxes of all sorts, employee taxes, sales taxes, income taxes, are collected for the
state and federal government and must be deposited at the bank or mailed out on a
periodic basis.
Depreciation Methods
• Straight Line Depreciation
• S/L -For Residential Real Estate
• S/L -For Commercial Real Estate
• 200% Declining Balance Depreciation
• 150% Declining Balance Depreciation
• MACRS
Brevard Contractors School
11
Prepare To Pass
Copyright 2004 – 2006 ©
In Declining Balance Depreciation you always use the asset life as the depreciation
factor. Do not use the remaining years as the depreciation factor.
Two ways to solve the problem:
Straight Line Depreciation rate = 1 / life of asset
1/life of asset = constant factor
constant rate = constant factor x depreciation factor (2 or 1.5 or 1.25)
yearly amount due = constant rate x book value
The yearly depreciation schedule for double declining with a 10 year life would be:
Year Depreciation Expense Accumulated Depreciation Book Value
1 .10 x 2 x 60000 12,000 $48,000
2 .10 x 2 x 48000 9,600 $38,400
Year Depreciation Expense Accumulated Depreciation Book Value
1 60,000 /10 years = 6000 * 2 = 12,000 $48,000
2 48,000 / 10 years = 4800 * 2 = 9,600 $38,400
Double Declining Balance Depreciation Method
The double declining balance (DDB) method is an accelerated depreciation method in
which more depreciation expense is recognized in earlier years and less is recognized in
later years. This method gets its name from the fact that it uses a rate twice the straight-
line rate. To compute depreciation expense using the DDB method, the following steps
are used.
1) Determine the straight-line rate per year. For instance, if the useful life of an asset is
ten years, The straight-line rate is 1/10 or 10%. If the useful life is five years, the straight
line rate is 1/5 or 20%.
2) Determine the DDB rate. This is simply double the straight-line rate. A straight-line
rate of 10% becomes 20% and a straight-line rate of 20% becomes 40%.
Brevard Contractors School
12
Prepare To Pass
Copyright 2004 – 2006 ©
3) Compute the current year's DDB depreciation. Assume that Mythical purchased a
machine costing $100,000 with an estimated useful life of five years and an estimated
salvage value of $10,000. The straight-line rate would be 20%. The DDB rate would be
40%. Depreciation for year one is $100,000 X 40% = $40,000. NOTE: Under the DDB
method, any salvage value is ignored in computing depreciation expense. Remember,
you never depreciate an asset below its salvage value.
As is true with all depreciation problems, you should prepare a depreciation schedule.
The depreciation schedule for this asset is shown below.
The journal entry to record depreciation expense is exactly the same regardless of the
method used. For any accounting period you would debit depreciation expense and credit
accumulated depreciation.
Calculator for MACRS:
http://www.pine-grove.com/depreciation/MACRS_Screen.htm
Calculator for Declining Balance depreciation:
http://www.acsu.buffalo.edu/~thill/programs/JavaScript/financial/dbc.html
Brevard Contractors School
13
Prepare To Pass
Copyright 2004 – 2006 ©
MACRS:
Modified Accelerated Cost Recovery System has 3,5,7, 10 year categories and uses the
following conventions.
• 3, 5, 7, 10 year assets are depreciated at 200% declining balance.
• 15 and 20 year assets are depreciated at 150% declining balance.
• Autos and trucks are depreciated for 5 years at 200%
• Office equipment such as computers are depreciated for 5 years at 200%
• Commercial Real Estate 39 years straight line only
• Residential real estate 27.5 years straight line only
Generally all property put in place under the MACRS system uses the mid-year
conversion. It is assumed that all assets are put in service at the middle of the year, and
the first year you are entitled to 1/2 the annual deduction.
Straight Line Depreciation for Real Estate:
It is currently required that you use straight line (SL) depreciation on all real estate.
Chapter 3 of the Contractors Manual details depreciation. Commercial Real Estate placed
in service after May 12, 1993 must be depreciated for 39 years. Residential rental
property is depreciated for 27.5 years.
Straight line depreciation rate = 1 / life of asset (either 27.5 or 39 years)
1/life of asset = constant factor (1/39 = .02564 or 1/27.5 = .03636)
yearly amount due = constant rate x book value
Depreciation has two functions. On the one hand you want to depreciate the
assets so you know how much has been used up and how much useful life the asset has
remaining. A secondary or tax objective is to match depreciation schedules with income
flows to shield the maximum amount of income from taxation. For this reason many
companies maintain two depreciation schedules on long term and real assets.
Brevard Contractors School
14
Prepare To Pass
Copyright 2004 – 2006 ©
Types of Business Entities:
• Proprietorship
• Partnership
• Corporation
Proprietorship is simply an individual in business for him or herself. The proprietorship
lacks a distinct legal form; there is no legal difference between the business and the
owner of the business. Partnership is two or more individuals in business for the
common good. A Corporation is a legal entity separate and distinct from the people who
own and manage the corporation.
Accounting Methods:
The Builders Guide to Accounting is not a great introduction to accounting; a
better booklet is "Step by Step Bookkeeping, the complete handbook for the small
business" by Robert C. Ragan, C.P.A. The Builders Guide to Accounting takes the
approach of asking the reader to consider their options in handling various accounting
conventions.
You are asked to consider whether your company will use Percentage of
Completion or Completed Contract method for recording income and expenses. This
relates directly to a primary accounting question; will your company use the cash
accounting method or the accrual accounting method? What method will your
company use for depreciation? Do you know how to match income with depreciation
schedules? The Builders Guide then tells you how to handle a number of journals, such
as payables journal, receivables journal, materials journal, petty cash journal, and how to
reconcile your checkbook.
Cash Accounting Method Vs Accrual Accounting Method:
A cash based accounting system records income and expenses only when the CASH
actually changes hands. For construction this would equate to completed contract
method. In an accrual based system a transaction is entered on the books as soon as the
transaction takes place, regardless of when cash is exchanged. Many companies use a
modified cash basis. They may reflect income and materials expenses on an accrual basis,
but do all other accounts on a cash basis to minimize bookkeeping. But remember that the
Brevard Contractors School
15
Prepare To Pass
Copyright 2004 – 2006 ©
IRS requires you to:
• use a method that clearly reflects income and
• requires that your company use this method consistently.
The Income Statement lists income, direct costs, operating expenses and profits.
Income Statement
Earned Income xxx
Returns and Allowances <xxx>
Net Sales xxx
Cost of Goods Sold <xxx>
Gross Profit xxx
Selling Expenses <xxx>
Profit before fixed Overhead xxx
Fixed Overhead <xxx>
Net Income xxx
Percentage of Completion VS Completed Contract Method:
Under the Completed Contract Method the income and the costs of a given
project are shown on the income statement only when the project is 100% complete. Both
the income from the project and any cost associated with the project are recorded at the
same time. Periodic payments, costs, and profits, are not recorded while the project is
under construction. Usually, completed contract method is limited to small jobs of short
duration. The IRS will not allow companies with revenues in excess of 10 million
annually to use completed contract method for tax purposes.
The Percentage of Completion Method is the most desirable method for contract
accounting. It requires you to start with an estimate of the total cost to construct the entire
project in advance. The percentage of completion method of accounting will allow you to
recognize the amount of money you have earned on a project at any given time. This is
then compared to how much you have invoiced the owner at the same particular time.
The result may be that you are under billed, or accrued income. (You have not billed as
much as you have earned). Or over billed, have unearned or deferred income (you have
billed more than you have earned). The formula for percentage of completion accounting
is performed in the following steps;
Brevard Contractors School
16
Prepare To Pass
Copyright 2004 – 2006 ©
Cost to Date = % of Completion
(Cost to Date + Estimated Cost to Complete)
% of Completion * Contract Amount = Revenue Earned
Revenue Earned – Amount Invoiced = Deferred OR Accrued
Income
Petty Cash Fund:
The Petty Cash Fund is a fixed amount of money that is set aside for purchases that are
too small to warrant writing a check. The fund must be controlled if the petty cash fund is
to work. The major control in the petty cash system is the voucher slip. Anytime money
is taken from the petty cash box a voucher must be presented to the person who keeps the
petty cash box. The controller of the cash fund then issues cash for voucher ticket.
This is called the voucher system. The petty cash fund should be replenished by
writing a check to petty cash which is supported by source documents (receipts) for the
money that has been spent out of the fund. Do not write a check to CASH as this is
difficult to document.
Petty Cash Voucher:
No: Date _________
RECEIVED OF PETTY CASH
Amount $________
For _________________________________________________________
Charge to:____________________________________________________
Received by: Approved by:
________________________ ________________________
Brevard Contractors School
17
Prepare To Pass
Copyright 2004 – 2006 ©
Reconciling the Petty Cash Fund is done as follows;
1: add all expenses on vouchers
2: add cash remaining in fund
3: determine shortage or overage
4: calculate petty cash remaining balance
5: Check amount = Fund limit – actual cash balance
eg:
Office Supplies 60.32
Postage 28.80
Parking 22.00
Delivery exp 28.15
Coffee 9.47
Printing expense 42.18
Expenses: 109.92
Calculating Shortage
Cash on hand = $300 – 190.92 = 109.08
Actual cash on hand 107.45
Shortage 1.63
Check to replenish fund $300 – 107.45 = 192.55
Cash Receipts Daily Journal
Brevard Contractors School
18
Prepare To Pass
Copyright 2004 – 2006 ©
Daily Summary of Sales and Cash Receipts
1: Cash Sales
Materials __________
Services __________
2: Misc. Sales __________
3: Collection of accounts receivable __________
4: TOTAL DAILY RECEIPTS __________
5: Cash in Petty Cash Box __________
6: Petty Cash vouchers and receipts __________
7: Total in Petty Cash Box __________
8: Petty Cash fund Limit = $300.00
9: Line 8 – line 5 = ________
10: Cash short / over ________
11: Total Cash and Daily Receipts (add lines 1-7) =========
Deduct Petty Cash Fund limit from deposit <__________>
12: Total Deposit __________
Sales Summary
13: Cash Sales ___________
14: Charge Sales ___________
15: Total Daily Sales ___________
Check Writing:
When you write a check there must be enough information on the check and the check
stub to readily allow you to reconstruct the expense and assign it to a ledger account.
Every check should have a source document to support the reason the check
was written. The supporting document can be a bill, a time card, a petty cash summary
voucher. Every check should have the date, payee, amount, purpose and job number or
name, and purpose of the payment.
Brevard Contractors School
19
Prepare To Pass
Copyright 2004 – 2006 ©
Reconciling the Checkbook:
There are two parts of reconciling the checkbook. You must first reconcile the bank
statement and then reconcile the check book.
To Reconcile the Bank Statement:
1: List balance as shown on statement balance
2: ADD checks in transit (not cleared)
3: DEDUCT checks outstanding
4: ADD/DEDUCT incorrect charges
5: The net amount is the reconciled bank statement
To Reconcile the Checkbook to the Bank Statement:
1: List balance as shown in checkbook
2: Deduct service charges
3: Deduct bad check charges
4: The net amount is the reconciled checkbook statement
These two numbers should be the same, at least on the test!
Review: The Income Statement:
The Income Statement summarizes business operations within a time period. The
Income Statement lists income, direct costs, operating expenses and profit.
Brevard Contractors School
20
Prepare To Pass
Copyright 2004 – 2006 ©
The Income Statement's standard divisions are;
Gross Sales
Less direct costs
Equals gross profit
Gross Profit
Less operating expenses
Equals income from operations
Income from operations
Less provision for taxes
Equals Net Profit
Construction Company
Income Statement
For the year 2002
Earned Income xxx
-Returns and Allowances xxx
=Net Sales xxx
-Cost of Goods Sold xxx
=Gross Profit xxx
-Selling Expenses xxx
=Profit before fixed Overhead xxx
-Fixed Overhead xxx
=Net Income xxx
Brevard Contractors School
21
Prepare To Pass
Copyright 2004 – 2006 ©
Review: The Balance Sheet:
The Balance Sheet is a summary of existing conditions of the business. The Balance
Sheet lists Assets, Liabilities, and Net Worth.
The Balance Sheet
Assets: Debit Credit Debit Credit
Assets
Cash xxx
Accounts Receivable xxx
Bad Debt Reserves xxx
Fixed Assets xxx
Depreciation Reserve xxx
Liabilities xxx
Accounts Payable xxx
Taxes Payable xxx
Notes Payable xxx
Net Worth xxx
Capital Stock xxx
Retained Earnings xxx
The Balance Sheet: (has the following major categories)
Current Assets
Current assets are liquid and near liquid assets. These assets include cash, accounts
receivable, inventories and other current assets.
Fixed Assets
Fixed Assets includes the gross value of equipment and machinery, small tools,
improvements, furniture, fixtures, structures, and land.
Other Assets
Intangible assets include such as covenant not to compete, and Goodwill of a business.
Brevard Contractors School
22
Prepare To Pass
Copyright 2004 – 2006 ©
Current Liabilities
Include such accounts as accounts payable, taxes payable, notes, contracts, ad deposits to
be refunded.
Long Term Liabilities
Some liabilities exist on the books for more than one year. If a liability is not paid off
inside of one year keep the remaining portion of the assets value separate from current
liabilities.
Contingent Liabilities
These are debts that have not occurred now, but are pending, such as pending lawsuits.
Equity Account
Capital stock or owners equity represents the original investment of the owners of the
business. Capital stock accounts are only changed by the addition of new capital or the
removal of old capital.
Retained Earnings
Each year’s profit and losses
Net Profit
Each year’s net profit or loss is recorded and placed into an earnings account when the
books are closed at the end of the year. This account may be called a retained earnings
account or equity account.
Brevard Contractors School
23
Prepare To Pass
Copyright 2004 – 2006 ©
Statement of Cash Flows
Is a summary of the sources and uses of cash. The Statement of Cash Flows shows
changes in long-term assets and liabilities and capital accounts.
The Statement of Cash Flows is often called the most important financial
statement, even though it is often the least used financial statement.
The Statement of Cash Flows has two sections:
• Fixed or long-term provisions of funds.
• Change in current assets and liabilities.
Sources of Capital
Net profit on a cash basis
Funds received from the sale of capital assets
Funds received in the form of a loan proceeds
Investments of capital by stockholders
Increases in long-term liabilities
Uses or (applications) of Capital
Funds paid for the acquisition of capital assets
Reduction in long-term liabilities
Dividends paid or payments to stockholders
Decreases in long-term liability accounts
The net difference between these two accounts, long term assets, and long term liability
and capital accounts result in a net increase or decrease in funds for the period.
Brevard Contractors School
24
Prepare To Pass
Copyright 2004 – 2006 ©
Funds Flow Analysis
Sources of Funds
Profit from operations __________________________
Depreciation __________________________
Decrease in cash __________________________
Decrease in receivables __________________________
Decrease in Inventories __________________________
Decrease in other assets __________________________
Increase in payables __________________________
Increase in notes __________________________
Increase in common stock __________________________
Increase in accrued expenses __________________________
Increase in deferred taxes __________________________
Gain form sale of asset __________________________
Other __________________________
TOTAL =======================
Uses of Funds
Increase in accounts receivable __________________________
Increase in notes receivable __________________________
Increase in inventory __________________________
Increase in plant and equipment __________________________
Increase in prepaids __________________________
Decrease in notes payable __________________________
Decrease in secured notes __________________________
Dividends __________________________
Decrease in mortgage __________________________
Increase in Cash __________________________
TOTAL =======================
Brevard Contractors School
25
Prepare To Pass
Copyright 2004 – 2006 ©
Summary:
The Balance Sheet is a general indicator of the strength of your operation.
The Income Statement shows how well you're controlling costs and expenses. The
yield on your operations, and the volume of business you're doing.
The Statement of Cash Flows tells you whether your operation is handling cash
properly.
Management Ratios:
Cost of goods sold = cost of goods sold / net sales
Goss margin = net sales – cost of goods sold / net sales
Profit margin = net profit / net sales
Profit margin = net profit before taxes $ interest / net sales
Profit margin = net profit after taxes, before interest / net sales
Expense radio = various expense items / net sales
Contribution to fixed cost and profit = net sales – direct costs (variable costs) / net sales
Net sales / gross assets
Gross assets / net sales
Net sales / net assets
Average inventory / net sales
Average inventory / cost of goods sold
Net sales / average inventory
Cost of goods sold / average inventory
Net sales / days of the year
Accounts receivable / sales per day
Net profit / assets
Net profit / net assets (capitalization)
Net profit before interest and taxes / net assets (capitalization)
Net profit after taxes, before interest / assets
Net profit after taxes, before interest / net assets (capitalization)
Owners Ratios:
Net profit / net worth
Net profit to common / common equity
Earnings per share = net income / average number of sales outstanding
Brevard Contractors School
26
Prepare To Pass
Copyright 2004 – 2006 ©
Lenders Ratios:
Current assets / current liabilities
Cash + marketable securities + receivables / current liabilities
Total debt / total assets
Long term debt / capitalization (net assets)
Total debt / net worth (equity)
Long term debt / capitalization – long term debt
Working Capital refers to the net difference between current assets and current
liabilities.
The Trial Balance:
This worksheet proves that the general ledger is in balance. In all cases debits should
equal credits.
Closing Adjustments:
This is much like reconciling the bank statement that we did last week, except there are
more accounts to reconcile.
1: debits to expense accounts
2: adjustments for coding errors in your books
3: Bank reconciliation adjustments
4: write-offs for bad debts
5: Changes in inventory based on your year-end physical
6: Recording of depreciation and amortization
7: Adjustments to the notes payable liability for the years interest
8: Corrections to liability and expense accounts for tax liabilities
9: Adjustments to percentage of completion report
10: adjustment for completed contract accounting
Brevard Contractors School
27
Prepare To Pass
Copyright 2004 – 2006 ©
Markup Profit
There are two methods for calculating Markup Profit, which are detailed in BGA,
Walker's and the Contractors Manual.
• Markup from Cost
• Markup from Selling Price
Markup from Cost:
Take (the percentage allocated to overhead + the required profit margin)= %
Direct cost of job * (1+ %) = bid
24% (.24) percent for overhead + 18% (.18) percent required profit = 42% or .42
54,000 * 1.42 = $76,680
Markup on Selling Price:
100 – (overhead + profit margin) = multiplier
Job cost / multiplier = bid
100 – 24% (.24) + 18% (.18%) = 58% or .58
54,000 / .58 = $93,103
What BGA wants you to see is how you calculate profit can make a big difference in how
much money your company earns. The exam board does not tell you to use Markup on
Selling Price, but it stands to reason that if you are a construction manager, and you
agree to do a job for cost plus a percentage, you want to use Markup on Selling Price.
Always use markup on selling price unless the contract specifically requires you to use
Markup from Cost. On the exam they will probably ask questions to test your
knowledge of the difference between these two methods.
Brevard Contractors School
28
Prepare To Pass
Copyright 2004 – 2006 ©
AIA
AIA documents are very structured construction contracts.
• They make the architect the arbitrator or mediator between the owner and the
contractor. The architect will charge extra for this service.
• In so precisely spelling out the contractor's duties and obligations these contracts
place a lot of pressure on the contractor to perform.
• This is a good contract if you are certain you can meet the building schedule
requirements, or if the other party to the contract is in a superior position.
In Florida, the following contractual rules apply;
• Written text supercedes typed text
• Typed text supercedes printed text
• Florida courts tend to rule against the writer of the contract in the event of
disagreement.
•
A valid contract has to have the following elements;
• An offer (the bid is an offer)
• Acceptance
• Consideration by both parties.
So when you make a bid, determine how much time and money it cost to calculate the bid
– and include a preliminary invoice. Ok, if the owner accepts your offer you have already
supplied consideration when you prepared the bid, therefore you have a contract.
Sometimes people will change their mind, and they will get their lawyer to write and say
the contract did not exist because you have not begun work, i.e. you have not provided
consideration. You circumvent this problem by including an invoice with the bid that
details the amount of time and expense it took to create the bid and working drawings to
demonstrate that you have provided consideration. This invoice needs to be for $101.00
or more to have a binding contract.
Brevard Contractors School
29
Prepare To Pass
Copyright 2004 – 2006 ©
INVOICE:
TO: Beasley's Construction
320 N. Atlantic Ave 1A
Cocoa Beach, Fl. 32931
Bob Hansen estimating $250
Tom Richards – working drawings $175
(5) Copies blue prints - Architect $100
8 hours (John Beasley)
Site Inspection
Summary of Contract Law
The courts generally rule that a contract exists whenever the parties manifest the intention
to be bound by an agreement. Courts generally allow a party to be excused from a
contract by reason of fraud, duress, undue influence, a mistake, unconscionability, or
impossibility of intent.
Fraud = cheated, lied, misrepresented intent
Duress = made you do it, not a free will choice
Undue influence, if you were tricked or suckered or manipulated
Mistake = clearly did not understand the intent of the agreement or facts
Unconscionability = asked to do something that no average sane person would do
Impossibility = looked good on paper, but simply can not be done
The Law of Contracts is generally covered by each states common law. Another type
of law is the Federal Uniform Commercial Code. Personal Property is any type of
property other than real property. Most personal property sold around the United States is
covered under Article 2 of the Uniform Commercial Code. The exception to items
covered under the U.C.C. is real property (land) or land with improvements such as
buildings, as well as employment contracts, service contracts, and insurance contracts. A
sale is a contact (or agreement) involving the transfer of title to goods from a seller to a
buyer for a price (for consideration). A contract is a collection of promises the courts
will enforce. A breach of contract is a failure to perform on those promises.
The Essential Elements of a Contract
1: Mutual consent or assent. The parties to a contract must show by word or deed that
they have agreed to enter into a contract. This usually constitutes an offer and acceptance
of the offer.
Brevard Contractors School
30
Prepare To Pass
Copyright 2004 – 2006 ©
2: Consideration. Each party to a contract must intentionally exchange something of
value as an incentive to get the other party to the contract to return the exchange.
3: Legality. The objectives of the contract (to be enforceable by the courts) must be for a
legal activity.
4: Capacity. Each party to the contract must have contractual capacity. The person must
not have been declared incompetent by a court, must be of legal age, and not intoxicated.
If all of these four elements of a contract are available, then in most cases an oral contract
is a binding and enforceable agreement by the courts. Contracts for the sale of real estate
must be in writing; as well contracts for more than $500 dollars generally must be in
writing.
Types and Classification of Contracts
Express contracts are contracts where the parties have manifested their agreement by
oral or written agreement. An implied contract is one which can be discerned from the
conduct of both parties, but is not totally spoken or written.
A bilateral contract is one in which both parties exchange promises to do
something. Typically think of these as (AND) contracts. You do this AND I will do that.
Each party is obligated to perform under a bilateral contract. A bilateral contract is
accepted by way of an agreement.
A unilateral contract is one where one party makes an offer to the other party,
but the second party is not obligated to take the offer. IF – THEN contracts. IF you do
this, THEN I will do that. Rather of a take it or leave it offer. Only the offering party is
obligated to perform on the contract IF the offer is accepted. A unilateral contract is
accepted by performance. The contract is a done deal when the performance is
completed.
Example: I will pay you 1,000 dollars to put up the sheetrock. If the person responds by
starting to put up sheetrock what you have is acceptance of a unilateral contract. If the
person puts up half the sheetrock and quits, no contract exists.
If the person responds by handing the offeror a work order and says, sign this and we
will get started next Tuesday, then the contract has become a bilateral contract.
An executed contract is one where all the parties to the contract have fully performed on
their promises. An executory contract is one that is yet to be performed. One or more
parties to the contract have one or more promises as yet to perform.
Brevard Contractors School
31
Prepare To Pass
Copyright 2004 – 2006 ©
Essentials of an offer
1: An offer must be communicated to the offeree.
2: Both parties must manifest intent to agreement.
3: The offer must be explicit.
For an offer to constitute a valid contract there must be the communication of an offer
from one party to the other, and the intent of the agreement must be explicit (definite).
A valid contact is one that meets all the requirements of a binding agreement. A void
contract is one that does not meet all the requirements of a binding agreement.
Revoking an offer
In a bilateral contract you may revoke an offer anytime before the offer is accepted. In a
unilateral offer you cannot revoke the offer for a reasonable amount of time once the
party has begun to work or perform on the contract.
An offer can be revoked if a lengthy amount of time has passed, or if the contract says
“time is of the essence” and provides a date certain when the offer will be revoked. If the
offer is rejected then the offer is revoked. If a counter offer is made, then the offer was
revoked or terminated.
Statute of Frauds
The Statute of Frauds says that certain types of contracts must be in writing in order to
minimize corruption or fraud. For our purposes these contracts include promises to
answer for the duty of another, contracts that cannot be performed within one year, and
the transfer of real property.
The Statute of Frauds requires the following:
• define the parties to the contract or agreement
• specify the subject mater and terms of the contract or agreement
• must be signed by all parties to the contract or agreement.
Brevard Contractors School
32
Prepare To Pass
Copyright 2004 – 2006 ©
AIA – Summary of Forms:
A-101 or short form A-107 is the stipulated sum agreement.
A-10-111/CM is stipulated sum agreement for construction management.
A-111 is the cost of work plus a fee agreement.
A-401 is the contractor – subcontractor agreement.
A-701 is instructions to bidders
A-201 General conditions for construction contract.
G-701 is a change order
G-706 A is a release of liens form
G-702 application and certificate for payment
The primary forms reviewed on the exam are A201, A401, and A701.
The AIA form A-201 has 14 articles as defined in Walkers 1.09-1.18
1: defines the documents, the work, the project, execution, correlation, intent an
interpretations of the contract…
2: defines the architect as the "administrator" of the contract
3: Defines the owner, his rights and responsibilities
4: defines the contractor, his duties, in supervision, and construction of all labor and
materials, defines the warranty, as well as taxes, permits, fees, notices, cash allowances,
the progress schedule, draws to be kept on job site, drawings, samples…
5: defines subcontractors
6: sets forth owners rights
7: miscellaneous provisions
8: defines contract time
9: discusses payments and completion sum
10: covers protection of persons and property
11: insurance requirements
12: includes change orders
13: acceptance of defective and non-conforming work
14: termination of the contract.
Brevard Contractors School
33
Prepare To Pass
Copyright 2004 – 2006 ©
AIA 201 owner-contractor agreement calls for the successful bidder to submit a list
of subcontractors for approval. If the owner rejects a subcontractor after the contract is
bid, then any change in price caused by rejecting the subcontractor constitutes a change
order and the owner must pay the difference. 1:12 Walker
Section 1.1 define the basic definitions of the document. The contract documents consist
of the agreement between Owner and Contractor, Conditions of the Contract, drawings,
specifications, and addenda issued prior to execution of the contract. A modification is
(1) a written amendment to the Contract signed by both parties, (2) a change order, (3)
construction change Directive or (4) a written order for a minor change in the work.
Section 1.6 Ownership and use of the drawings, specifications and other instruments of
service. The contractor may keep one set of drawings for his records. The Architect shall
retain all rights to the drawings, all other copies of the instruments (drawings and
specifications) shall be returned to the architect.
2.2.3 The owner shall furnish surveys describing the physical characterizes, legal
limitations and utility locations for the site of the project, and a legal description of the
site.
2.4.1 Owners rights to carry out work: If the contractor defaults or neglects to carry out
the work in accordance with the contract documents and fails within a seven-day period
after receipt of written notice from the owner to commence and continue correction of
such default or neglect within diligence and promptness, the owner may after such seven-
day period give the contractor a second written notice to correct such deficiencies within
a three-day period. If the contractor within a three day period after receipt of such second
notice fails to commence and continue to correct any deficiencies, the owner may,
without prejudice to other remedies the owner may have, correct such deficiencies.
3.2.1 If the contractor discovers any errors, inconsistencies or omissions discovered by
the contractor shall be reported promptly to the architect as a request for information in
such a form as the architect may require.
3.3.2 The contractor shall be responsible to the owner for acts and omissions of the
contractor’s employees, subcontractors and their agents and employees, and other persons
or entities performing portions of the work for or on behalf of the contractor or any of its
subcontractors.
3.4.3 The contactor shall enforce strict discipline and good order among the contractors
employees and subcontractors.
3.7.1 Permits and fees: the contractor shall secure and pay for the building permit and
other permits and governmental fees, licenses, and inspections necessary for proper
execution and completion of the work which are customarily secured after execution of
the contract.
3.7.3 It is not the contractor’s responsibility to ascertain that the contract documents are
in accordance with applicable laws, statures, ordinances, building codes, and rules and
regulations.
Brevard Contractors School
34
Prepare To Pass
Copyright 2004 – 2006 ©
3.8.1 Allowances: The contractor shall include in the contract sum all allowances stated
in the contact documents. Items covered by allowances shall be supplied for such
amounts and by such persons or entities as the owner may direct.
3.11.1 Documents and samples at the site: The contractor shall maintain at the site for the
owner one record copy of the Drawings, specifications, addenda, change orders and other
modifications in good order and marked currently to record field changes and selections
made during construction, one record copy of approved shop drawings, product data,
samples and similar requires submittals.
3.12.1 Shop Drawing: Shop Drawings are drawings, diagrams, schedules and other data
specially prepared for the work by the contractor or a subcontractor, sub-subcontractor,
manufacturer, supplier or distributor to illustrate some portion of the work.
3.12.7 The contractor shall perform no portion of the work for which the contract
documents require submittal and review of shop drawings, product data, samples or
similar submittals until the respective submittal has been approved by the architect.
3.12.8 the work shall be in accordance with approved submittals except that the
contractor shall not be relieved of responsibility for deviations form requirements of the
contract documents by the architect’s approval of shop drawings, product data, samples
or similar submittals unless the contractor has specifically informed the architect in
writing of such deviation at the time of submittal.
3.13.1 The contractor shall confine operations at the site to areas permitted by law,
ordinances, permits and the contract documents and shall not unreasonably encumber the
site with materials or equipment.
9.3.2 Unless otherwise provided in the contract documents, payments shall be made on
account of materials and equipment delivered and suitably stored at the site for
subsequent incorporation in the work.
9.3.3 the contractor warrants that title to all work covered by an application for payment
will pass to the owner no later than the time of payment. The work…will be free and
clear of liens, claims, security interests or encumbrances in favor of the contractor,
subcontractors, material suppliers, or other persons…
Applications for getting paid are usually made monthly on form G-702
Definitions – which are provided in Walkers 1.18 are included with a contract to make
certain there is a "meeting of the minds" relating to understanding the terms of the
contract.
Glossary of Construction terms in the contract can be helpful as a source for information.;
These are good to know, but the glossary in the Contractors Manual should be
memorized if you can, as a number of questions come from the glossary in the
Contractors Manual.
Brevard Contractors School
35
Prepare To Pass
Copyright 2004 – 2006 ©
AIA – 401 documents which is the contractor sub-contractor contract agreement
The important element is that the final payment shall be due when the work is completed
satisfactorily to the architect and owner.
The sub-contractor shall not assign or sub-contract the work without written consent of
the contractor.
The sub-contractor shall report to the contractor within 3 days any injury to any of the
sub-contractors employees on the site.
If the sub-contractor is not paid by the contractor, through no fault of the sub-contractor,
within 7 days of the time in which payment should have been made the sub-contractor
may given 7 days written notice to the contractor stop work until the amount has been
paid.
Unless otherwise provided in the contract documents, the contractor shall pay the sub-
contractor each progress payment and the final payment under the sub-contract within 3
working days after the contractor receives any payments from the owner.
Back Charges: If the sub-contractor defaults or neglects to carry out the work in
accordance with the agreement, or fails within 7 days of receiving written notice from the
contractor to commence and continue corrections of such default or neglect with
diligence and promptness the contractor may after giving 7 from receipt by the sub-
contractor of any written notice, and without prejudice to any other remedy he may have
such deficiency made good, and may deduct the cost from the money owed to the sub-
contractor.
Time is considered to be of the essence in this contract. This means it is a timing specific
document.
Within 30 days of the architect issuing a certificate for payment covering such
substantially complete work the contractor shall within the extent of the documents make
payments to the sub-contractor the entire unpaid balance of the contract sum, or of that
portion of the contract sum contributable to the substantially completed work.
After a payment is due the sub-contractor the sub-contractor is entitled to the payment
plus interest.
Before issuance of payment to the sub-contractor by the contractor the sub-contractor
shall be required to submit evidence of all bills being paid.
Sub-contractors ability to assign his portion of the sub-contract is permissible with
written consent of the contractor.
Permits for sub-contractors shall be the responsibility of the sub-contractor for payment.
The contractor shall provide the sub-contractor with a copy of the estimated progress
schedule of the contractor's entire job.
Contractor shall notify the sub-contractor of all modifications of the contract promptly.
If the work is stopped for a period of 60 days through no fault of the sub-contractor
because the contractor has not made payment to the sub-contractor may, in writing, give
7 additional days notice and then terminate the contract.
The sub-contractor agrees that all esthetic work shall be done subject to the final approval
of the architect.
Brevard Contractors School
36
Prepare To Pass
Copyright 2004 – 2006 ©
The sub-contractor shall notify the contractor in writing 5 days in advance of
commencement of the work that is scheduled to begin; unless a notice to proceed
precedes the date of commencement issued by the contractor.
A contractor may terminate employment of a sub-contractor that repeatedly fails to
supply enough workers or materials if the contractor gives the subcontractor 2 written
notices over a 14 day period.
AIA Document 701
Instructions to bidders
Any changes to the bidding document must be made by addendum. AIA bids are received
in a sealed envelope.
The owner must prove financial testing no later than 7 days prior to the expiration of the
withdrawal of bids.
The bidder shall deliver the required bonds to the owner no later than 3 days following
the date of the execution of the contract.
By making a bid on the project the contractor represents all of the following to be true;
the bidder has visited the site; the bidder has used the provided documents to make a bid;
bidder understands local conditions.
No addenda will be issued later than 4 days prior to the final date of the receipt of bids.
If bonds are required the bidder must deliver them to the owner no later than 3 days
following the date of contract execution.
Brevard Contractors School
37
Prepare To Pass
Copyright 2004 – 2006 ©
Mechanics' Lien Law
Time Line for Filing and Serving Documents According to the Mechanics' Lien Law
Document Type – section Who serves or files notice Time to serve or file
Notice of Commencement
(713.135)
Owner or owners agent Record in County Clerks
office prior to obtaining
building permits
Notice to Owner
(713.06)
All suppliers of goods or
services in privity with
owners, except laborers
Post on site or send notice
by registered mail to
owners prior to
commencing work – but
not later than 45 days
after commencing work.
Notice of Claim
(713.08)
Every lienor including
laborers and persons in
privity with the owners.
File in the County Clerk's
office not later than 90
days after completion of
work
Notice of Delivery
(713.09)
Seller and purchaser of
materials delivered to a
location other than the
job site.
Serve on owner a notice
signed by both the seller
and the purchaser of
goods.
Waiver of Release
(713.20)
Any lienor other than a
laborer: laborer may
waive to the extent of
labor previously
performed
At anytime
Notice of Contest of Lien
(713.22)
Owner, agent, attorney of
owner, this accelerates
the time for filing a suit to
60 days.
Record in County Clerk's
office
Payment Bond
(713.23)
Contractor Before commencing the
construction
If the claim of lien is for $5,000 or less it is filed with the County Clerk's office.
If the amount of the claim of lien is in excess of $5,000 then it is filed with the Circuit
Clerk's Office.
Brevard Contractors School
38
Prepare To Pass
Copyright 2004 – 2006 ©
Summary of Construction Lien Law;
Liens for professional services: 713.03
Any person who performs services as architect, landscape architect, interior designer,
engineer, or surveyor and mapper, subject to compliance with the limitations imposed by
this part, has a lien of the real property improved for any money that is owing to him for
his services used in connection with improving the real property or for his services in
supervising any portion of the work of improving the real property, rendered in
accordance with this contract and with the direct contract. No lienor under this section
shall be required to serve a notice to owner. You must file a claim of lien.
Subdivision improvements: 713.04
Any lienor who, regardless of privity, performs services or furnishes material to real
property for the purpose of making it suitable as the site for the construction of an
improvement or improvements shall be entitled to a lien on the real property. Site
improvement shall include but not be limited to grading, leveling, excavating, and filling
of land, including the furnishing of fill soil; the grading and paving of streets, curbs, and
sidewalks; the construction of ditches and other area drainage facilities; the laying of
pipes and conduits for water, gas, electric, sewage and drainage proposes. No notice of
commencement shall have to have been filed to file a lien under this section. No lienor
shall be required to serve a notice to owner for liens under this section. You must file a
claim of lien.
Liens of Persons in privity: 713.05
A material man or laborer, either of whom is in privity with the owner and provides
labor, services, materials, or other items required by, or furnished in accordance with, the
direct contract and also for unpaid finance charges due under the lienors contract, shall
have a right to lien the property. No lienor under this section shall be required to serve a
notice to owner as provided in section 713.06.
Liens of Persons NOT in privity; proper payments:
713.06
All lienors under this section, except laborers, as a prerequisite to perfecting a lien under
this chapter and owner setting forth the lienors name and address, a description sufficient
for identification of the real property, and the nature of the services or materials furnished
or to be furnished. A notice must be served before commencing, or not later than 45 days
after commencing, to furnish his services or materials, but in any event, before the date of
the owner's disbursement of the final payment after the contractor has furnished the
affidavit under subparagraph 3-d 1.
Brevard Contractors School
39
Prepare To Pass
Copyright 2004 – 2006 ©
The notice to owner must be substantially the following form;
WARNING TO OWNER: UNDER FLORIDA LAW, YOUR FAILURE TO MAKE
SURE THAT WE ARE PAID MAY RESULT IN A LIEN AGAINST YOUR
PROPERTY AND YOUR PAYING TWICE.
TO AVOID A LIEN AND PAYING TWICE, YOU MUST OBTAIN A WRITTEN
RELEASE FROM US EVERY TIME YOU PAY YOUR CONTRACTOR.
NOTICE TO OWNER
To Owners name and address:
Liens for improving real property under contract with husband or wife on
property of the other or of both: 713.12
The spouse who contracts shall be deemed to be the agent of the other, unless such other
shall, within 10 days after learning of such contract, give the contractor and record in the
clerk's office, notice of his or her objection thereto.
Manner of serving notices and other instruments: 713.18
1: by actual delivery to the person to be served, or one partner, or an officer of the
corporation, director or managing agent.
2: by mailing the same, postage prepaid, by registered or certified mail to the person and
at the address listed on the notice of commencement, or shown on the building permit
application.
3: If neither of the above methods can be accomplished, then by posting the notice on the
premises.
Duration of a Lien: 713.22 (must renew lien each year to remain active)
No lien provide by part I shall continue for a longer period than 1 year after the claim of
lien has been recorded, unless within that timer an action to enforce the lien is
commenced in a court of competent jurisdiction.
Brevard Contractors School
40
Prepare To Pass
Copyright 2004 – 2006 ©
An owner or his agent or attorney may elect to shorten the time prescribed in subsection 1
within which to commence an action to enforce any claim of lien or claim against a bond
or other security under s. 713.23 or 713.24 by recording in the clerk's office a notice in
substantially the following form:
Notice of Contest of Lien
To (name of lienor)
You are notified that the undersigned contests the claim of lien filed by you on (date),
and recorded in _______Book, _____Page, of the public records of Brevard County,
Florida, and that the time within which you may file suit to enforce your lien is limited to
60 days from the date of service of this notice. This (date)
Signed (owner or attorney)
Moneys received for real property improvements; penalty for misapplication: 713.345
A person, firm, or corporation, or an agent, officer, or employee thereof, who receives
any payment on account of improving real property must apply such portion of any
payment to the payment of all amount then due and owing for services and labor which
were performed on, or materials which were furnished for, such improvement prior to
receipt of the payment.
Any person who knowingly and intentionally fails to comply with paragraph A is
guilty of misapplication of construction funds, punishable as follows;
1: $100,000 or more is a first degree felony.
2: Less than $100,000 but more than $20,000 is a second degree felony.
3: Less than $20,000 is a third degree felony.
Brevard Contractors School
41
Prepare To Pass
Copyright 2004 – 2006 ©
Florida Construction Industry Licensing Board
Summary Chapter 489
It is important to understand that Chapter 489 of the Florida Statutes gives the
construction board the power to regulate the construction industry, and to discipline
contractors or persons who hold themselves out as contractors. One of the questions on
your exam is likely to be what law or statute gives the Bureau of Professional Regulation
the authority to govern the construction industry; the answer is Chapter 489.
The regulation of professions by government has two major
objectives: (2-6)
• To protect the public and ensure safety by preventing unqualified individuals
from practicing a given profession; and
• To establish standards of practice for those who engage in a particular profession.
The professional boards provide a valuable service to the public by determining who is
eligible to be licensed to practice of profession, investigating complaints against
licensees, and taking disciplinary action against licensees when professional standards
have been violated.
They serve two important functions: (2-6)
• (1) protection of the public by identifying and taking action against incompetent
or unethical practitioners and;
• (2) serving notice of professional standards on members of the profession and
those seeking to become members of the profession.
Chapter 489 Florida Statutes provide for the licensure and regulation of all types of
contractors in Florida.
Who Needs to be Licensed?
Generally, any person who, for compensation, undertakes to, submits a bid to, or does
himself or by others construct, repair, alter, remodel, add to, demolish, subtract from, or
improve any building or structure, including related improvements to real estate for
others or for resale to others, must be licensed. (2-7)
Brevard Contractors School
42
Prepare To Pass
Copyright 2004 – 2006 ©
Licensing Exemptions:
The following are exempted from licensure;
• Highway, street, road, bridge, and railway contractors;
• Employees of licensed contractors acting within the scope of the contractor's
license and with the knowledge and permission of the licensed contractor;
• Federal, state, and local government employees (except school boards, the board
of regents, and community colleges, unless for the purpose of performing routine
maintenance or repair or construction not exceeding $200,000 to existing
installations) who do not hold themselves out for hire or otherwise engage in
contracting except in accordance with government employment;
• Court appointed officers;
• Public utilities;
• Persons who sell or install finished products, materials, or merchandise which are
not fabricated into and do not become a permanent fixed part of the structure.
• Property owners acting as their own contractor;
• Any construction on United States property;
• With certain exceptions, persons performing work of a casual or
inconsequential nature, with a contract price of less than $1,000,
unless the person represents that he or she is a qualified contractor.
• Any construction or operation of irrigation and drainage ditches;
• Registered architects or engineers acting within the scope of their practice;
• Persons who only supply materials or supplies;
• Liquefied petroleum gas dealers;
• Heating and AC dealers and installers which AC's have a capacity of 3 tons or
less.
• Architects, landscape architects, and engineers who offer design-build services.
Brevard Contractors School
43
Prepare To Pass
Copyright 2004 – 2006 ©
Subcontractor Requirements:
A construction contractor must subcontract the electrical, mechanical, plumbing,
roofing, sheet metal, swimming pool, and air conditioning work when a local
examination for certificate of competency or license is required in these areas,
unless the contractor himself holds a State certificate of competency or license in that
area.
Not required to sub-contract the following:
• General, Building, and Residential contractors are NOT required to
subcontract the following; wood shingles, wood shakes, or asphalt or
fiberglass shingle roofing materials on NEW building they are constructing.
• General contractors can build swimming pools.
• General Contractors can build sanitary sewer collections systems, storm water
systems, or the water distribution system on new site development work, site
redevelopment work, mobile home parks or commercial properties;
• General Contractors can connect utility lines from the mains on mobile home
parks.
Sub-Contractors – Independent Contractors or Employees?
An independent contractors allow you to considerably lower payroll tax savings
(no FICA, FUTA or state unemployment tax) there are fewer administrative costs,
no withholding income, no payroll taxes, no workers' compensation costs, no age
discrimination problems, no Americans with Disabilities Act as both acts apply
only to employees, also no retirement costs, and fringe benefits.
BUT if the independent contractor violates any laws, then the person who holds
the contractors license and pulled the building permits will be held responsible, just as
if the individuals had been employees of the contractor.
Brevard Contractors School
44
Prepare To Pass
Copyright 2004 – 2006 ©
If the independent contractor:
• Does not have liability insurance
• Does not have workman's compensation insurance
• Does not pay FICA and FUTA matching funds
• Does not train employees to use tools properly
• Does not meet OSHA safety requirements
• Does not have the proper licensing
• Hires illegal aliens (non-nationals)
• Hires persons under the age of 16
• Causes or allows employee(s) to be hurt or killed
Then the licensed contractor of record on the job in question will be responsible for the
above listed expenses.
IRS test for Independent Contractor Status:
Independent if:
• Control, - contractor does not define when, where, and how the job is to be
done.
• Training, - if the contractor does not train workers or pays to train workers.
• Services, - If the contractor does not allow the independent contractor to
determine who and how the work is to be done, requiring only a finished
product.
• Integration, - the operations of the contractors business must not depend upon
the services of the independent contractor.
• Hiring, supervision, paying assistants, - The contractor must not hire,
supervise nor pay assistants for the independent contractor.
• The contractor must not hire the independent contractor on a regular (weekly
basis).
• Hours of work, the contractor must not set the hours of work the independent
contractor must work, but rather define a finished product.
• The contractor must not require the independent contractor to work for
him/her on a full time basis.
• Working on the employers premises, the contractor must not require the
independent contractor to perform work at the contractors shop.
• The contractor must not set the order or sequence of work, (this is a difficult
test to pass for the construction industry).
• Oral or written reports by the contractor suggests that the independent
contractor is an employee.
• Hourly, weekly, or monthly pay suggests a continuing relationship, which
argues against independent contractor status.
Brevard Contractors School
45
Prepare To Pass
Copyright 2004 – 2006 ©
• Payment of business/travel expenses argues against an independent contractor
status.
• Furnishing of tools and materials, once again the nature of the construction
industry makes it difficult to pass this test unless the independent contractor is
responsible for buying the materials to perform the work on his/her bid.
• The contractor must not have the right to discharge the independent
contractor before his contract bid is finished. In this case it is wise to construct
a contract around the AIA contractor – sub-contractor form A-401.
The independent contractor can help by doing the following:
• Have his/her own business cards
• Have a city and county business license
• Have liability insurance, pay workman's comp on employees
• Bids on jobs, and works by the job
• Buying all his/her own tools and materials.
• Renting a separate office or construction barn at a separate location.
• Runs a risk of making a profit or loss if his bid is inaccurate, or if the job goes
badly.
• If he/she works for more than one firm on a regular basis.
• Makes his/her services available to other licensed contractors or the general
public.
• Receives no bonuses, tools, or travel expenses
• The contractor files a 1099-MISC on the independent contractor.
• REMEMBER this from the Circular E. Backup Withholding: If you are
required to file a 1099 on an independent contractor or materials supplier, or
persons to whom you paid "interest, dividends, rents, royalties, commissions, non-
employee compensation in the course of your trade or business" and the payee
fails to furnish you with a Taxpayer Identification Number (TIN) then generally
you must withhold 31% of taxable payments.
• Have a written contract, signed by both parties, that makes it clear that the
company doesn't have the right to control the methods or procedures for the
worker to accomplish the work contracted for (2-13).
• The Independent contractor hires his/her own workers as necessary.
• Compensation based on work finished, not hours worked.
• Never give an independent contractor a bonus.
Brevard Contractors School
46
Prepare To Pass
Copyright 2004 – 2006 ©
Note:
If the IRS determines that the independent contractor is an employee you will be
responsible for the entire 15.3% due for FICA plus the 6.2% on the first $,7000 due
FUTA, as well as penalties which will likely exceed the payment amount due. This
applies to the independent contractor, for the last 4 years he worked for you, as well
as all his/her employees! Be certain that the individuals you are hiring are truly
independent contractors, and that they are collecting FICA and FUTA, as well as
paying workman's comp insurance on their employees. If they are not, you are taking
a huge risk. In this type situation, the contractor stands to lose more than he/she
stands to gain. Any miscalculation, or accident could land the contractor in
bankruptcy court. When you bid your jobs, include all the real expenses of doing
business; let some other poor fool take the low-ball jobs.
If you have to, bid only city, county, state, or federally funded projects where every
bidder is required to incur the same cost structures.
Rules of Thumb:
• Real property (land) 20% to 50% of project costs
• Real estate agent 3% of project costs
• Materials (improvements) 33% of project costs
• Labor 33% to 50% of project costs
• Insurance 2% to 10% of project costs
• Capital costs (interest rates) 7% to 12% of project costs
• Machinery, tools, 5% to 15% of project costs
• Overhead, office, and other fixed expenses 3% to 12%
According to Dunn and Bradstreet Standard Industrial Code (SIC) business
summaries, the average contractor makes 24% profit.
The elements listed above are all you have available to manipulate in order to realize a
profit. If you can realize only 10% savings in each one of these categories you will
realize about a 30% to 35% profit on your overall project.
Brevard Contractors School
47
Prepare To Pass
Copyright 2004 – 2006 ©
Penalties for Unlicensed Activity:
Engaging in or holding oneself out to be a contractor without first obtaining a
license is a violation of Florida Law. Any person who falsely holds himself out to be a
licensed contractor or who engages in contracting without first obtaining a license is
guilty of a first-degree misdemeanor. The DBPR or a county, municipal, or local
licensing board may issue a cease and desist order to prohibit any person from engaging
in the business without a valid license.
Any contract entered into by a contractor not licensed pursuant to Part I or Part II of
Chapter 489, Florida Statutes, is legally unenforceable. Any contract entered into by an
unlicensed repairperson or handyman for more than $1,000 dollars is unenforceable.
In addition if the person holds themselves out to be a contractor and causes injures to a
person due to negligence, malfeasance, or misfeasance, and is not certified by the state
nor licensed pursuant to the laws of the city or county in which he does business, the
consumer is entitled to three times the actual damages sustained and costs and attorney's
fees.
Licensing Requirements:
Certified Contractor is a contractor who successfully passes a state-administered
examination and obtains a certificate of competency issued by the DBPR. Certified
contractors are allowed to contract in ay city, county, or district in the state without being
required to fulfill the competency requirements of that jurisdiction.
Registered Contractor is any contractor who has registered with the DBPR and has
fulfilled the competency requirements in the city, county, or district for which the
registration is issued. Registered contractors can only contract in the jurisdiction that
issued the license.
Financial Responsibility Requirements – NET WORTH REPORTING
• Net Worth of $10,000 in cash or a line of credit or any combination of the two.
(Letter from your bank attesting to the fact that you have $10,000, a letter of
bond-ability, or compliance bond issued for $10,000).
• A credit report that checks to see if the contractor has any construction related
judgments on his/her record (the usual credit report will not work).
• Public Liability Insurance 50,000 property/ 300,000 personal injury
Brevard Contractors School
48
Prepare To Pass
Copyright 2004 – 2006 ©
• Workers compensation coverage or a personal exemption
• A financial statement, not more than 12 months old, containing information
indicating the current assets and liabilities, total assets and total liabilities, and
total Net Worth of the applicant
• Must answer questions pertaining to unpaid or past-due bills or claims for labor,
materials, services, liens, suits or judgments or record or pending against the
applicant or his firm.
The Financial statement needs to look like something out of Builders Guide to
Accounting. As much as seeing how much money you have, they DBPR wants to see if
you can put together financial statements. All you have to provide is a Profit and Loss
Statement, and ratio analysis, but you can include an Income Statement. Almost no one
provides a Sources and Uses of Funds Statement.
Brevard Contractors School
49
Prepare To Pass
Copyright 2004 – 2006 ©
Davy Jones
320 N. Atlantic Ave #1A
Cocoa Beach, Fl. 32931
Balance Sheet
December 31, 2001
Assets
Current Assets
Cash in bank 10,000
Stocks and bonds 2,000
IRA account** 12,000
Savings 2,450
Accounts receivable (business accounts) 0
Notes receivable (include all mortgages and leases) 0
Materials held for trade purposes 1,200
Total Current Assets 27,650
Long Term Assets
Long Terms notes receivable (mortgages) 0
Tools 8,560
Machinery and tractors, trailers 2,300
Trucks, cars, motorcycles, boats *** 14,800
Real Property (house and commercial) 62,500
House Hold belongings 15,000
Total Long Term Assets 103,160
Total Assets 130,810
Current Liabilities
Credit Cards 2,300
Line of Credit at bank 850
Trade accounts payable 0
Rent due before Dec. 31 (optional) 0
Mortgages payable due before Dec. 31 (optional) 3,456
Auto loans due before Dec. 31 6,000
Total Current Liabilities 12,606
Long Term Liabilities
Auto and truck loans due more than one year 3,200
Home equity loans 19,000
Equipment mortgages 0
Revolving loans – Sears – Rooms to Go 0
House and real property mortgages 10,500
Total Long Term Liabilities 32,700
Total Liabilities 45,306
NET WORTH 85,504
Net Worth = Total Assets – Total Liabilities
Brevard Contractors School
50
Prepare To Pass
Copyright 2004 – 2006 ©
All financial documents should carry notes at the bottom of the document detailing the
conventions used by the preparer of the documents. These notes are used to explain the
choices you used in making the statement. e.g.;
** IRA can not be withdrawn until 59 years old
*** Market value of assets – not book value
Term of License
The license is good for 2 years. It must be renewed every two years, and the contractor is
required to take 14 hours of continuing education every two years to be able to renew the
license.
Continuing Education
The contractor must take 14 credit hours of continuing education every two years to
be able to renew the license.
Business Records
Business records and complete financial statements for the business must be kept at
the place of business for the preceding three years. NOTE from Circular-E that the IRS
requires you to keep your records for four years.
Qualifying Agents
If a joint venture, partnership, corporation, trust, or other business organization wishes to
do business and engage in contracting the applicant must apply through a qualifying
agent.
• The applicant must state the name of the business
• List its directors, partners, or officers, or trustees
• Show compliance with the fictitious name statute
• The qualifying agent is legally qualified to act for the business organization
• The qualifying agent has the authority to supervise construction
• The qualifying agent must be either a certified or registered contractor
Brevard Contractors School
51
Prepare To Pass
Copyright 2004 – 2006 ©
In addition, if the qualifying agent is the only licensed contractor affiliated with the
business organization, the business organization must notify DBPR of the termination of
the qualifying agent and obtain another qualifying agent within sixty days (60).
The qualifying agent is responsible for supervision of all operations of the business, for
all fieldwork at all sites, and unless a financially responsible officer is designated. A
sole primary qualifying agent is jointly and equally responsible with secondary qualifying
agents for fieldwork supervision.
A secondary qualifying agent is responsible only for supervision of filed work at
sites where his license was used o obtain the building permit, and any other work for
which he accepts responsibility. A secondary qualifying agent is not responsible for
supervision of financial matters.
A change in the status of a qualifying agent is effective form the date of the change
forward, and will not relieve the qualifying agent of responsibility for projects or actions
that took place during the time he was acting as a qualifying agent.
Florida courts have held that Chapter 489 imposes a professional duty upon the sole
qualifying agent of record for a general contractor to supervise all of the general
contractor's projects. Failure to carry out this duty may serve as grounds for revocation of
a qualifying agent's contractor's license.
A qualifying agent's claim that he had no personal knowledge of activities of the business
entity or of its employees that result in violations of Chapter 489 will not absolve the
qualifying agent.
Definitions:
Primary qualifying agent means a person who possesses the requisite skill,
knowledge, and experience, and has the responsibility, to supervise, direct, manage, and
control the contracting activities of the business organization with which he is connected.
Professional Responsibility – Liability
Changes in Licensure information:
business organization must inform the DBPR by mail of any change in the information
required to be submitted on the application for qualification of a business organization
within forty-five days following the change.
Brevard Contractors School
52
Prepare To Pass
Copyright 2004 – 2006 ©
Grounds for disciplinary action against a contractor:
• Obtaining a license by fraud or misrepresentation
• Being convicted and found guilty of a crime related to contracting
• Knowingly violating applicable building codes
• Assisting a person in unlicensed practice of contracting, or evading licensing
• Acting as a contractor in another name other than on the license
• Committing mismanagement or misconduct causing financial harm to a customer
• Abandoning a construction project (abandoned after 90 days)
• Being disciplined by any city or county for violation of licensing law
• Failing in any material respect to comply with the licensing law or rule
• Signing a statement that a job is bonded, falsely stating subcontracted work has
been paid for, labor or materials have been paid for, falsely indicating that
workers' comp and public liability insurance are provided
• Committing fraud or deceit in the practice of contracting
• Committing incompetence or misconduct
• Committing gross negligence
• Proceeding on any job without building permits
• Intimidating, threatening, coercing or otherwise discouraging the service of a
notice to owner or a notice to contractor under the mechanic's lien laws;
• Failing to satisfy a civil judgment obtained against a licensee or a business within
a reasonable time.
Brevard Contractors School
53
Prepare To Pass
Copyright 2004 – 2006 ©
Circular E
Employer's Tax Guide
Purpose: To Calculate withholding taxes using Circular E.
You need to have a working knowledge of Circular E. You will use the tables in Circular
E weekly or bi-weekly when paying employee wages. It is important that you are familiar
with the process, and with the filing dates associated with Circular E. The deductions
computed in Circular E are Federal Income Tax Withholding, Social Security
(FICA), Medicare, and Federal Unemployment Tax (FUTA).
Summary of Circular E:
Employees are to file Form W-4 before December 1 of each year. The W-4 defines their
address, social security number, martial filing status, and their number of withholding
allowances.
Backup Withholding. If you are required to file a 1099 on an independent
contractor or materials supplier, or persons to whom you paid "interest, dividends, rents,
royalties, commissions, non-employee compensation in the course of your trade or
business" and the payee fails to furnish you with a Taxpayer Identification Number
(TIN) then generally you must withhold 31% of taxable payments.
Federal Unemployment Tax, FUTA is filed on Form 940 or 940 EZ by January 31.
All employers must file Form 941 on a quarterly basis and deposit any income tax,
Social Security, and Medicare taxes. You pay these taxes on Form 941 if your total tax
liability for the quarter is less than $1000 dollars. If all taxes were deposited on time, you
are given a 10 day extension for filing.
Brevard Contractors School
54
Prepare To Pass
Copyright 2004 – 2006 ©
Quarters Ending Due Date last deposit date
January – March March 31 April 30 May 10
April – June June 31 July 31 Aug 10
July – September Sept 30 Oct. 31 Nov 10
Oct – Dec Dec 31 Jan 31 Feb 10
Record Keeping:
Keep all records of employment taxes for at least 4 years.
Who must have an Employer Identification Number?
If you are required to report employment taxes or give tax statements to employees or
annuitants, you need an EIN. Request an EIN on Form SS-4.
Wages and Compensation:
Wages subject to Federal employment taxes include all you pay an employee in salaries,
vacation allowances, bonuses, commissions, and fringe benefits.
Wages not paid in money but "in kind" such as lodging, food, clothing, and services, are
generally subject to income tax Withholding and Social Security, Medicare and FUTA
taxes.
Meals and lodging: The value of meals is not taxable income and is not subject to income
tax withholding and if they are furnished for the employer's convenience and on the
employer's premises. The same holds true for lodging if it is furnished for the employer's
convenience, on the employer's premises, and as a condition of employment.
Fringe Benefits:
You must include fringe benefits in an employee's gross income. Fringe benefits include
cars you provide, flights on aircraft you provide, free or discounted commercial flights,
vacations, discounts on property or services, membership in county clubs, or social clubs,
and tickets to entertainment or sporting events. You must include an amount equal to fair
market value of the benefits, less any amount the employee paid.
Supplemental Wages:
These wages are wages paid in addition to regular wages, and they include bonuses,
commissions, overtime pay, payments for sick leave, severance pay, awards, prizes, back
pay and retroactive pay increases, as well as nondeductible moving expenses.
Brevard Contractors School
55
Prepare To Pass
Copyright 2004 – 2006 ©
Calculating Supplemental Withholding:
If you have been withholding income tax from an employees regular wages, then use 1 of
the following methods for supplemental wages.
1: Withhold a flat 28% (no other percentage is allowed).
2: Add the supplemental and regular wages for the most recent payroll period this year.
Then figure the income tax withholding as if the total were a single payment. Subtract the
tax already withheld from the regular wages. Withhold the remaining tax from the
supplemental wages.
Payroll Period:
A payroll period is a period of service for which you usually pay wages.
Social Security and Medicare Taxes:
The Federal Insurance Contributions Act (FICA) provides for a Federal system of old-
age, survivors, disability and hospital insurance.
Tax rates:
The employee tax rates for social security is 6.2% (amount withheld) . The employer tax
rate for social security is 6.2% (12.4% TOTAL). The wage limit base is 87,900
The employee tax rate for Medicare is 1.45% (amount withheld). The employer tax
rate for Medicare is 1.45% (2.9% TOTAL). There is no wage base limit for Medicare
tax; all covered wages are subject to Medicare tax.
Advanced Earned Income Credit (EIC):
An employee who is eligible for the EIC and has a qualifying child is entitled to receive
EIC payments with his or her pay during the year. To get these payments the employee
must give you a properly completed FORM W-5.
Depositing Taxes:
Income tax withheld, social security, and Medicare taxes are to be filed on Form 941
at a local Federal Reserve Bank or electronically.
Form 945 is for filing non-payroll tax liabilities and payroll and non-payroll may not be
filled on the same form.
Brevard Contractors School
56
Prepare To Pass
Copyright 2004 – 2006 ©
Depositing on Time:
To be considered timely, the funds must be available to the depositary or FRB on the
deposit due date before the institution's daily cutoff deadline (usually 2:00 P.M.).
HOWEVER, a deposit received by the authorized depository or FRB after the due date
will be considered timely if the taxpayer establishes that is was mailed in the USA at
least 2 days before the due date.
Deposit Penalties:
2% late fee on Deposits made 1 to 5 days late.
5% late fee on Deposits made 6 to 15 days late.
10% late fee on Deposits made 16 or more days late.
Filing Form 941:
Form 941 must be filed each quarter.
Penalties for late payment:
For each whole or part month a return is not filed when required, there is a penalty of 5%
of the unpaid tax due with that return. The maximum penalty is 25%. Also, for each
whole or part of a month the tax is paid late, a penalty of .5% of the amount of the tax
generally applies. The maximum penalty is also 25%.
Federal Unemployment Tax (FUTA):
Only the employer pays FUTA tax, it is not deducted from the employee's wages.
Test for FUTA:
1: You paid wages of $1,500 or more a year for any calendar quarter for the present year
and the previous year.
2: You paid $1,000 or more to household employees in the previous year.
3: You paid farm workers more than $20,000 in any calendar quarter, or employed 10 or
more farm workers for 20 or more weeks.
Brevard Contractors School
57
Prepare To Pass
Copyright 2004 – 2006 ©
Computing FUTA Tax:
The FUTA tax rate is 6.2%. The tax applies to the first $7,000 you pay each
employee as wages during the year. FUTA is only paid by the employer.
Florida does not have any SUTA tax:
Florida does not have any SDI tax:
Calculating Tax liabilities:
1: From the Form W-4, obtain employees filing status, either married or single, and
number of withholding allowances claimed. From the time card obtain the employees
gross wages subject to income taxes. With this information you are ready to go to the
Circular E wage and tax tables and calculate the income tax to be withheld on a weekly
or bi-weekly basis. Write down the amount from the tables.
2: Calculate Social Security, FICA; - refer to Circular E for current rates.
• 6.2% (.062) * wage rate up to annual maximum of 87,900
• .145% (.0145) * wage for Medicare – on total wages -no maximum
• 7.65% (.0765) total FICA and Medicare deducted from employees check.
The employer must match each of the FICA and Medicare deductions made by
the employee. These are matching funds of 7.65% which are contributed by the
employer making the total payment due 15.3% of gross wages.
3: Calculate FUTA, Federal Unemployment Tax, this amount is paid completely
by the employer. The FUTA tax rate is 6.2% (.062) on the first $7,000 of annual
wages.
If you pay SUTA to the state up to 5.4% maybe deducted from the 6.2% paid to
the FUTA leaving a balance of .8% or (.008) to be paid on Form 940. Florida has
no SUTA.
Brevard Contractors School
58
Prepare To Pass
Copyright 2004 – 2006 ©
Some abbreviations:
FICA Social Security Tax
FUTA Federal Unemployment Tax
EIC Earned Income Credit
FRB Federal Reserve Bank
SSA Social Security Administration
FIT Federal Income Tax
To obtain a current copy of Publication 15: Circular E, Employer's Tax Guide: go
to the IRS website listed below and type in "Publication 15." To obtain 940, 941,
W2's, and W4's you may go to the same website and type in the desired
publication and then download it in Adobe format.
http://www.irs.ustreas.gov/formspubs/index.html
Brevard Contractors School
59
Prepare To Pass
Copyright 2004 – 2006 ©
%
% of Completion · 16
1
1099 · 45, 53
9
940 EZ · 53
A
Accounts Payable · 3, 4, 10, 21
accrual accounting method · 14
Advanced Earned Income Credit · 55
AIA · 28
AIA – 401 · 35
AIA – Summary of Forms · 32
AIA 201 · 33
AIA Document 701 · 36
Averages Days Receivables · 9
B
Backup Withholding · 53
Bad Debt Ratio · 8
Balance Sheet · 1, 3, 4, 5, 6, 7, 21, 25, 49
bilateral contract · 30
breach of contract · 29
Business Records · 50
C
Calculating Tax liabilities · 57
cash accounting method · 14
Cash Movement Method · 7
Cash Receipts Daily Journal · 18
Certified Contractor · 47
Changes in Licensure · 51
Changes in Licensure information · 51
Chapter 489 · 41, 47, 51
Chart of Accounts · 1, 2, 3
Circular E · 45, 53, 57, 58
Closing Adjustments · 26
Combined Ratios · 7
Completed Contract · 14, 15
Continuing Education · 50
contract · 14, 15, 26, 27, 28, 29, 30, 31, 32, 33, 34,
35, 36, 38, 39, 42, 43, 45, 47
credit · 3, 4, 6, 8, 12, 47, 50
Credit Balance · 1
Current Assets · 2, 6, 7, 21, 49
Current Liabilities · 10
Current Ratio · 6, 7
D
debit · 3, 4, 12
Debit Balance · 1
Declining Balance Depreciation · 10, 11
Deferred Assets · 10
Deposit Penalties · 56
Depositing Taxes · 55
Depreciation Methods · 10
E
Elements of a Contract · 29
Equity Account · 22
Essentials of an offer · 31
F
FICA · 43, 44, 46, 53, 55, 57, 58
Fixed Assets · 4, 21
Form 940 · 53, 57
Form W-4 · 53, 57
Fringe Benefits · 54
Funds Flow Analysis · 24
FUTA · 43, 44, 46, 53, 54, 56, 57, 58
G
Grounds for disciplinary · 52
I
Income Statement · 3, 5, 6, 7, 15, 19, 20, 25, 48
Brevard Contractors School
60
Prepare To Pass
Copyright 2004 – 2006 ©
independent contractor · 44
Intangible Assets · 2, 10
IRS · 15, 44, 46, 50, 58
L
last deposit date · 54
Lenders Ratios · 26
Liabilities · 1, 3, 4, 6, 7, 10, 21, 22, 49
Licensing · 41, 42, 47
Licensing Exemptions · 42
Licensing Requirements · 47
Long Term Receivables · 9
Long-Term Assets · 9
M
MACRS · 10, 12, 13
Management Ratios: · 25
Markup from Cost · 27
Markup on Selling Price · 27
Markup Profit · 27
Mechanics' Lien Law · 37
N
Net Profit · 20, 22
Net Worth · 1, 3, 4, 7, 21, 47, 48, 49
NET WORTH REPORTING · 47
Notes Receivable · 2, 9
Notice of Contest of Lien · 40
notice to owner · 38, 39, 52
O
Owners Ratios · 25
P
Penalties for Unlicensed Activity · 47
Percentage of Completion · 14, 15
Petty Cash Fund · 16, 17, 18
Prepaid Assets · 10
Q
Qualifying Agent · 50
Quick Ratio · 6
R
Receivables · 8, 9
Reconciling the Checkbook · 19
Record Keeping · 54
Registered Contractor · 47
Reserve for Bad Debts · 2, 8
Retainage · 2, 9
Retained Earnings · 3, 4, 21, 22
S
secondary qualifying agent · 51
Sources and Application of Funds Method · 7
Sources and Uses of Funds Statement · 3, 5, 48
Sources and Uses of Funds Statement. · 3, 48
Sources of Capital · 23
Statute of Frauds · 31
Step by Step Bookkeeping · 14
Straight Line Depreciation for Real Estate · 13
Sub-Contractors · 43
Summary of Contract Law · 29
Summary of Operations · 5
Supplemental Wages · 54
T
Tax rates · 55
Term of License · 50
The Balance Sheet · 21
The Builder's Guide to Accounting · 5
The Income Statement · 5, 19
The Law of Contracts · 29
The Statement of Cash Flows · 5, 23, 25
The Trial Balance · 26
U
unilateral contract · 30
Uses or (applications) of Capital · 23
V
Voucher · 16
W
Working Capital · 7, 26
Brevard Contractors School
61
Prepare To Pass
Copyright 2004 – 2006 ©

Más contenido relacionado

La actualidad más candente

Financial Report Literacy Fall 2011
Financial Report Literacy Fall 2011Financial Report Literacy Fall 2011
Financial Report Literacy Fall 2011Miriam Smith
 
Balance sheet analysis
Balance sheet analysisBalance sheet analysis
Balance sheet analysisBachir Jamali
 
Financial Reports and Ratios
Financial Reports and RatiosFinancial Reports and Ratios
Financial Reports and RatiosMiriam Smith
 
Understanding Financial Statement / Report
Understanding Financial Statement / ReportUnderstanding Financial Statement / Report
Understanding Financial Statement / ReportMayur Khatri
 
Income statement & balance sheet
Income statement & balance sheetIncome statement & balance sheet
Income statement & balance sheetKashmira_180
 
Income Statement Slideshow
Income  Statement SlideshowIncome  Statement Slideshow
Income Statement Slideshowmjones59
 
Financial Statement Analysis and Financial Models
Financial Statement Analysis and Financial ModelsFinancial Statement Analysis and Financial Models
Financial Statement Analysis and Financial ModelsMaksudul Huq Chowdhury
 
Fundamental of accounting
Fundamental of accountingFundamental of accounting
Fundamental of accountingRahul Kumar
 
preparation of financial statements
preparation of financial statementspreparation of financial statements
preparation of financial statementsJyothi P
 
Block2 1understanding the_balance_sheet
Block2 1understanding the_balance_sheetBlock2 1understanding the_balance_sheet
Block2 1understanding the_balance_sheetÁngel Martín Soto
 
Understanding Balance Sheets, Cash Flow, Income Statements Farm Economics
Understanding Balance Sheets, Cash Flow, Income Statements Farm EconomicsUnderstanding Balance Sheets, Cash Flow, Income Statements Farm Economics
Understanding Balance Sheets, Cash Flow, Income Statements Farm EconomicseAfghanAg
 
Full balance sheet_&_profit_&_loss_analysis
Full balance sheet_&_profit_&_loss_analysisFull balance sheet_&_profit_&_loss_analysis
Full balance sheet_&_profit_&_loss_analysisAdil Shaikh
 
Block1 1 why does accounting matter
Block1 1 why does accounting matterBlock1 1 why does accounting matter
Block1 1 why does accounting matterÁngel Martín Soto
 

La actualidad más candente (20)

Financial Report Literacy Fall 2011
Financial Report Literacy Fall 2011Financial Report Literacy Fall 2011
Financial Report Literacy Fall 2011
 
Balance sheet analysis
Balance sheet analysisBalance sheet analysis
Balance sheet analysis
 
Financial Reports and Ratios
Financial Reports and RatiosFinancial Reports and Ratios
Financial Reports and Ratios
 
Understanding Financial Statement / Report
Understanding Financial Statement / ReportUnderstanding Financial Statement / Report
Understanding Financial Statement / Report
 
Block2 5dupontandotherratios
Block2 5dupontandotherratiosBlock2 5dupontandotherratios
Block2 5dupontandotherratios
 
Income statement & balance sheet
Income statement & balance sheetIncome statement & balance sheet
Income statement & balance sheet
 
Income Statement Slideshow
Income  Statement SlideshowIncome  Statement Slideshow
Income Statement Slideshow
 
The balancesheet
The balancesheetThe balancesheet
The balancesheet
 
Financial Statement Analysis and Financial Models
Financial Statement Analysis and Financial ModelsFinancial Statement Analysis and Financial Models
Financial Statement Analysis and Financial Models
 
Fundamental of accounting
Fundamental of accountingFundamental of accounting
Fundamental of accounting
 
preparation of financial statements
preparation of financial statementspreparation of financial statements
preparation of financial statements
 
Understanding the Balance Sheet.
Understanding the Balance Sheet.Understanding the Balance Sheet.
Understanding the Balance Sheet.
 
Types of financial statement
Types of financial statementTypes of financial statement
Types of financial statement
 
Block2 1understanding the_balance_sheet
Block2 1understanding the_balance_sheetBlock2 1understanding the_balance_sheet
Block2 1understanding the_balance_sheet
 
Lecture 1
Lecture 1Lecture 1
Lecture 1
 
Understanding Balance Sheets, Cash Flow, Income Statements Farm Economics
Understanding Balance Sheets, Cash Flow, Income Statements Farm EconomicsUnderstanding Balance Sheets, Cash Flow, Income Statements Farm Economics
Understanding Balance Sheets, Cash Flow, Income Statements Farm Economics
 
Balance sheet analysis
Balance sheet analysisBalance sheet analysis
Balance sheet analysis
 
Full balance sheet_&_profit_&_loss_analysis
Full balance sheet_&_profit_&_loss_analysisFull balance sheet_&_profit_&_loss_analysis
Full balance sheet_&_profit_&_loss_analysis
 
Balance sheet analysis
Balance sheet analysisBalance sheet analysis
Balance sheet analysis
 
Block1 1 why does accounting matter
Block1 1 why does accounting matterBlock1 1 why does accounting matter
Block1 1 why does accounting matter
 

Destacado

Desarrollo de ejemplo
Desarrollo de ejemploDesarrollo de ejemplo
Desarrollo de ejemplodiann_a_e
 
Dica para contratar equipe
Dica para contratar equipeDica para contratar equipe
Dica para contratar equipeDouglas Jesus
 
Русское искусство второй половины XVIII века
Русское искусство второй половины XVIII векаРусское искусство второй половины XVIII века
Русское искусство второй половины XVIII векаgalinakap
 
Cuadro explicativo tasas
Cuadro explicativo  tasasCuadro explicativo  tasas
Cuadro explicativo tasasIlario Gavidia
 
2017 1-14教學連繫
2017 1-14教學連繫2017 1-14教學連繫
2017 1-14教學連繫Jocelyn Ho
 
Jumbo j-1800-report
Jumbo j-1800-report Jumbo j-1800-report
Jumbo j-1800-report John Beasley
 
ESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMOR
ESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMORESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMOR
ESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMORartenaprensa
 
Finance class outline-2012
Finance   class outline-2012Finance   class outline-2012
Finance class outline-2012John Beasley
 

Destacado (12)

Thesis 5-31-11
Thesis 5-31-11Thesis 5-31-11
Thesis 5-31-11
 
Desarrollo de ejemplo
Desarrollo de ejemploDesarrollo de ejemplo
Desarrollo de ejemplo
 
Dica para contratar equipe
Dica para contratar equipeDica para contratar equipe
Dica para contratar equipe
 
Русское искусство второй половины XVIII века
Русское искусство второй половины XVIII векаРусское искусство второй половины XVIII века
Русское искусство второй половины XVIII века
 
What is Goal GPS?
What is Goal GPS?What is Goal GPS?
What is Goal GPS?
 
Cuadro explicativo tasas
Cuadro explicativo  tasasCuadro explicativo  tasas
Cuadro explicativo tasas
 
2017 1-14教學連繫
2017 1-14教學連繫2017 1-14教學連繫
2017 1-14教學連繫
 
Jumbo j-1800-report
Jumbo j-1800-report Jumbo j-1800-report
Jumbo j-1800-report
 
Blue print-design
Blue print-designBlue print-design
Blue print-design
 
Ant. aura vladimir final
Ant. aura vladimir finalAnt. aura vladimir final
Ant. aura vladimir final
 
ESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMOR
ESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMORESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMOR
ESTAMPAS PARA SUBLIMAÇÃO - CANECAS AMOR
 
Finance class outline-2012
Finance   class outline-2012Finance   class outline-2012
Finance class outline-2012
 

Similar a Bcs day one_exam

accounting important regarding the importance of accounting in accounts
accounting important regarding the importance of accounting in accountsaccounting important regarding the importance of accounting in accounts
accounting important regarding the importance of accounting in accountsbalckstone358
 
Analysis of Financial Statements
Analysis of Financial StatementsAnalysis of Financial Statements
Analysis of Financial StatementsNEETHU S JAYAN
 
Account ratios 4unwjwjwjswuwjsjjsjsjwit.pdf
Account ratios 4unwjwjwjswuwjsjjsjsjwit.pdfAccount ratios 4unwjwjwjswuwjsjjsjsjwit.pdf
Account ratios 4unwjwjwjswuwjsjjsjsjwit.pdfmelegend647
 
Accounting Basics - Kevin Nott
Accounting Basics  - Kevin NottAccounting Basics  - Kevin Nott
Accounting Basics - Kevin NottKevin Nott
 
1. key financial terms
1. key financial terms1. key financial terms
1. key financial termsKaran Tikku
 
Accounting Lessons Day 2--Finalized
Accounting Lessons Day 2--FinalizedAccounting Lessons Day 2--Finalized
Accounting Lessons Day 2--FinalizedBarre Arale Mohamud
 
Ratios and Formulas in Customer Financial AnalysisFinancial stat.docx
Ratios and Formulas in Customer Financial AnalysisFinancial stat.docxRatios and Formulas in Customer Financial AnalysisFinancial stat.docx
Ratios and Formulas in Customer Financial AnalysisFinancial stat.docxcatheryncouper
 
Accounting chapter-3
Accounting chapter-3Accounting chapter-3
Accounting chapter-3Gyanbikash
 
Ecorl oer al-understanding-accounting-and-financial-statements-deepening
Ecorl oer al-understanding-accounting-and-financial-statements-deepeningEcorl oer al-understanding-accounting-and-financial-statements-deepening
Ecorl oer al-understanding-accounting-and-financial-statements-deepeningUniversità Popolare di Firenze
 
New accountingbasicspart3
New accountingbasicspart3New accountingbasicspart3
New accountingbasicspart3David Marshall
 
accountingbasics.ppt
accountingbasics.pptaccountingbasics.ppt
accountingbasics.pptDodong21
 
accountingbasics.ppt
accountingbasics.pptaccountingbasics.ppt
accountingbasics.pptKevin117905
 
Basic financial statements
Basic financial statements   Basic financial statements
Basic financial statements Vlad Philips
 
Power Point Accounts
Power Point AccountsPower Point Accounts
Power Point Accountsguestca543d
 
Chapter 2 Financial Statements.ppt
Chapter 2 Financial Statements.pptChapter 2 Financial Statements.ppt
Chapter 2 Financial Statements.pptMarsStudio
 

Similar a Bcs day one_exam (20)

accounting important regarding the importance of accounting in accounts
accounting important regarding the importance of accounting in accountsaccounting important regarding the importance of accounting in accounts
accounting important regarding the importance of accounting in accounts
 
Mkting Mgmt 2.03
Mkting Mgmt 2.03Mkting Mgmt 2.03
Mkting Mgmt 2.03
 
Analysis of Financial Statements
Analysis of Financial StatementsAnalysis of Financial Statements
Analysis of Financial Statements
 
Account ratios 4unwjwjwjswuwjsjjsjsjwit.pdf
Account ratios 4unwjwjwjswuwjsjjsjsjwit.pdfAccount ratios 4unwjwjwjswuwjsjjsjsjwit.pdf
Account ratios 4unwjwjwjswuwjsjjsjsjwit.pdf
 
Accounting Basics - Kevin Nott
Accounting Basics  - Kevin NottAccounting Basics  - Kevin Nott
Accounting Basics - Kevin Nott
 
Lecture-3.pdf
Lecture-3.pdfLecture-3.pdf
Lecture-3.pdf
 
1. key financial terms
1. key financial terms1. key financial terms
1. key financial terms
 
Accounting Lessons Day 2--Finalized
Accounting Lessons Day 2--FinalizedAccounting Lessons Day 2--Finalized
Accounting Lessons Day 2--Finalized
 
Ratios
RatiosRatios
Ratios
 
Ratios and Formulas in Customer Financial AnalysisFinancial stat.docx
Ratios and Formulas in Customer Financial AnalysisFinancial stat.docxRatios and Formulas in Customer Financial AnalysisFinancial stat.docx
Ratios and Formulas in Customer Financial AnalysisFinancial stat.docx
 
Accounting chapter-3
Accounting chapter-3Accounting chapter-3
Accounting chapter-3
 
AAUP 2017: "Finances for Everyone"
AAUP 2017: "Finances for Everyone"AAUP 2017: "Finances for Everyone"
AAUP 2017: "Finances for Everyone"
 
Ecorl oer al-understanding-accounting-and-financial-statements-deepening
Ecorl oer al-understanding-accounting-and-financial-statements-deepeningEcorl oer al-understanding-accounting-and-financial-statements-deepening
Ecorl oer al-understanding-accounting-and-financial-statements-deepening
 
New accountingbasicspart3
New accountingbasicspart3New accountingbasicspart3
New accountingbasicspart3
 
Ch16 introto business
Ch16 introto businessCh16 introto business
Ch16 introto business
 
accountingbasics.ppt
accountingbasics.pptaccountingbasics.ppt
accountingbasics.ppt
 
accountingbasics.ppt
accountingbasics.pptaccountingbasics.ppt
accountingbasics.ppt
 
Basic financial statements
Basic financial statements   Basic financial statements
Basic financial statements
 
Power Point Accounts
Power Point AccountsPower Point Accounts
Power Point Accounts
 
Chapter 2 Financial Statements.ppt
Chapter 2 Financial Statements.pptChapter 2 Financial Statements.ppt
Chapter 2 Financial Statements.ppt
 

Más de John Beasley

Masters thesis outline - word format
Masters thesis  outline - word formatMasters thesis  outline - word format
Masters thesis outline - word formatJohn Beasley
 
Utility of christianity june 18-print
Utility of christianity june 18-printUtility of christianity june 18-print
Utility of christianity june 18-printJohn Beasley
 
Beasley mba-marketing sheet
Beasley  mba-marketing sheetBeasley  mba-marketing sheet
Beasley mba-marketing sheetJohn Beasley
 
Tm 7300--final-edit Transportation Management
Tm 7300--final-edit Transportation Management Tm 7300--final-edit Transportation Management
Tm 7300--final-edit Transportation Management John Beasley
 

Más de John Beasley (8)

Masters thesis outline - word format
Masters thesis  outline - word formatMasters thesis  outline - word format
Masters thesis outline - word format
 
Utility of christianity june 18-print
Utility of christianity june 18-printUtility of christianity june 18-print
Utility of christianity june 18-print
 
Beasley mba-marketing sheet
Beasley  mba-marketing sheetBeasley  mba-marketing sheet
Beasley mba-marketing sheet
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
 
Oupv intro 1
Oupv intro 1Oupv intro 1
Oupv intro 1
 
Tm 7300--final-edit Transportation Management
Tm 7300--final-edit Transportation Management Tm 7300--final-edit Transportation Management
Tm 7300--final-edit Transportation Management
 
Port management
Port management Port management
Port management
 
Export 7500
Export 7500Export 7500
Export 7500
 

Último

Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified Binance Account
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdflaloo_007
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challengeshemanthkumar470700
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecZurliaSoop
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...NadhimTaha
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateCannaBusinessPlans
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSpanmisemningshen123
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareWorkforce Group
 

Último (20)

Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial Wings
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' Slideshare
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
 

Bcs day one_exam

  • 1. Brevard Contractors School 1 Prepare To Pass Copyright 2004 – 2006 © Day 1 Exam Review Accounting Review: The Chart of Accounts is used to catalog all Sources and Uses of Funds. The Chart of Accounts is a list of all categories of a company's Assets, Liabilities and Equities. The Chart of Accounts are numbered to provide a shorthand method to apply costs and income. The Chart of Accounts is basically a list of places (accounts). These accounts can either be sources of money or uses of money. Asset accounts typically carry what is called a Debit Balance and are located on the left side of the Balance Sheet, while Liabilities and Equity typically carry what is called a Credit Balance, and they are located on the right side of the Balance Sheet. An asset is anything a business owns that has a money value. Anything a business owes is a liability. The difference between what a business owns and what it owes is called equity or capital. Equity can also be called Net Worth. Net Worth is the amount of equity or money that would remain if all the debts of the business were paid and the business were liquidated. This is the portion of the business that belongs to the owner(s). The summary document that lists assets, liabilities, and equity is called a Balance Sheet. It is called the Balance Sheet because the left Asset side of the spreadsheet must equal the right Liability + Equity side of the spreadsheet. Assets = Liabilities + Net Worth.
  • 2. Brevard Contractors School 2 Prepare To Pass Copyright 2004 – 2006 © Chart of Accounts Assets Current Assets Petty Cash Funds Cash in Banks Cash in Escrow Accounts Notes Receivable Accounts Receivable Reserve for Bad Debts Retainage Inventories Long-term Assets Land Building Furniture and Fixtures Autos and Trucks Equipment Machinery Small Tools Improvements Accumulated Depreciation Furniture and Fixtures Accumulated Depreciation - Autos and Trucks Accumulated Depreciation - Equipment Accumulated Depreciation - Improvements Suspense Account Accrued Construction-In-Progress Debits (Income) Deferred Construction-in-Progress Debits (expenses) Intangible Assets Covenants Not to Compete Goodwill
  • 3. Brevard Contractors School 3 Prepare To Pass Copyright 2004 – 2006 © Liabilities Current Liabilities Accounts Payable Payroll Taxes Payable Sales Taxes Payable Income Taxes Payable Other Taxes Payable Accrued Expenses Payable Notes Payable - Current Portion Long-term Liabilities Notes Payable - Long-term Portion Other Credits Deferred Construction-in-Progress Credits Suspense Account Net Worth Net Worth Accounts (for corporations) Capital Stock Retained Earnings Profit and Loss - Corporations Net Worth Accounts (for partnerships) Owners' Equity Accounts Owners' Drawing Accounts Profit and Loss - Partnerships Net Worth Accounts (for sale owners) Financial data is entered into a database that uses The Chart of Accounts for the category headings. This allows the accounts or "fields" to be summarized. These summaries of financial data are called Financial Statements. The three primary financial statements are the Balance Sheet, the Income Statement (Profit and Loss Statement) and the Sources and Uses of Funds Statement. The classic accounting equation is: Assets = Liabilities + Net Worth. Type of account to decrease to increase typical balance Asset credit debit debit Liability debit credit credit Capital debit credit credit Income debit credit credit Expense credit debit debit
  • 4. Brevard Contractors School 4 Prepare To Pass Copyright 2004 – 2006 © This relationship between assets and liabilities plus net worth is evident in the classic presentation of the Balance Sheet. Assets: Debit Credit Debit Credit Assets Cash xxx Accounts Receivable xxx Bad Debt Reserves xxx Fixed Assets xxx Depreciation Reserve xxx Liabilities xxx Accounts Payable xxx Taxes Payable xxx Notes Payable xxx Net Worth xxx Capital Stock xxx Retained Earnings xxx Look at the Balance Sheet, it has 3 accounts, Assets on the left side, and Liabilities and Net Worth on the right side of the page. The two sides allow for a debit or credit balance for each account. The left column is called the debit side and the right side column is called the credit side. Assets usually carry a debit balance, which means there is a positive number located on the left side of the equation. Liabilities and Net Worth usually carry a credit balance. The two sides of the balance sheet must always balance or equal each other. The two sides of the account are like a mirror image of each other. Debit Credit Debit Credit X = X Assets = Liabilities + Net Worth Anytime the Asset side of the equation increases or decreases the Liabilities or Net Worth side of the equation must also increase or decrease in an equal amount. In double entry bookkeeping, any change will affect a minimum of 2 accounts. In asset accounts a debit increases the account, and a credit decreases an account. In the Liabilities and Net Worth
  • 5. Brevard Contractors School 5 Prepare To Pass Copyright 2004 – 2006 © account a debit decreases the account and a credit increases the account. In this way the double entry accounting system is maintained in balance. The Income Statement is a snap shot of the business on a given day in time. Since a business can make money or lose money the Income Statement is also called a Profit and Loss Statement or the Summary of Operations. The Income Statement lists income, direct costs, operating expenses and profits. Construction Company Income Statement For the year 2002 Eared Income xxx Returns and Allowances xxx Net Sales xxx Cost of Goods Sold xxx Gross Profit xxx Selling Expenses xxx Profit before fixed Overhead xxx Fixed Overhead xxx Net Income xxx Sources and Uses of Funds Statement also called The Statement of Cash Flows summaries the management of cash during a specified period. The Statement of Cash Flows is in many ways the most valuable report you can have. The Builder's Guide to Accounting begins by asking how are you going to manage asset and liability accounts in your company. The decisions you make have cash consequences as well as tax consequences. Look again at the Balance Sheet; each of these accounts can be managed. The cash category, called the cash account can and must be monitored to insure that enough cash is available to run the business. It is normal to keep a cash journal to make it easier to do sales tax reports. Charge sales are kept in a separate journal from cash sales so they can be monitored as accounts receivable. Cash flow problems are common to builders because the construction business requires large investments.
  • 6. Brevard Contractors School 6 Prepare To Pass Copyright 2004 – 2006 © A cash budget should accomplish the following; • Make cash available for day-to-day operations. • Plan for the use of excess funds. • Time operations for seasonal business changes. • Provide for levels of inventory. • Prepare for tax liabilities. • Control the purchase of materials and help prevent over or under buying. • Help you maintain a good credit rating. Ratio Test for Cash The Current Ratio compares current assets (cash, receivables and inventories) to current liabilities (current notes payable, accounts payable, accrued taxes). Current Ratio = Current Assets / Current Liabilities A good current ratio is 2:1 or higher, which means current assets are double current liabilities. A 1:1 ratio is weak. A negative ratio is cause for concern, not only is the company low on cash, but growth potential is negative as well. It is common to try and obtain more cash to increase the ratio, instead try to reduce your current liabilities. The current ratio is the most popular and widely used test for a cash position. The Quick Ratio compares current assets (not including inventories) to current liabilities. An acceptable ratio rate is 1:1 or better. This quick ratio is also called the Acid Test because it tests the ability of a company to pay its current debts from its current cash and near cash assets. The acid test is a more consistent test as inventories are variable. Quick Ratio = (Current Assets – Inventories) / Current Liabilities Ratio analysis: Using the Balance Sheet and Income Statement it is possible to do analysis on a business. Ratios are a quick and easy way to understand how well a business is performing. Also, one can obtain a SIC – Standard Industrial Classification for a comparable class of industry and compare this companies ratios with the industry standard. The analysis takes the form of ratio analysis. Certain accounts in the Balance Statement or Income Statement are divided by other accounts to obtain ratios.
  • 7. Brevard Contractors School 7 Prepare To Pass Copyright 2004 – 2006 © Balance Sheet Ratios: Both parts of the ratio are found on the balance sheet. Current Ratio = current assets / current liabilities. Quick Assets Ratio (acid test) = Current Assets-Inventories / Current Liabilities. Owner's Investment vs. Creditors Investment = Capital / Current Liabilities. Ability to Meet Obligations = Working Capital / Funded Debt. Working Capital = Current Assets – Current Liabilities. Owner Financing vs. Debt Financing = Net Worth / Assets. Income Statement Account Ratios: Both parts of the ratio are found on the income statement. Percentage of Gross Profit = Gross Profit / Sales. Expense Control Ratio = Operating Expenses / Sales Volume. Margin of Profit = Net Income / Sales. Combined Ratios: One part is found on the income statement and one part is from the balance sheet. Trend in Charge Sales = Sales / Accounts Receivable. Real Turnover = Cost of Sales / Inventory at Cost. Day’s of Inventory Available = Total Working Days Per Year / Turnover. True Investment Yield = Net Income / Net Worth. There are two ways to prepare a cash budget. One is the Cash Movement Method and the other is the Sources and Application of Funds Method. The Cash Movement Method involves budgeting for the flow of actual cash in and out of your business. The Sources and Application of Funds Method assumes an operating budget and then subtracts expenses from cash flow to calculate the level of available working capital.
  • 8. Brevard Contractors School 8 Prepare To Pass Copyright 2004 – 2006 © It is important to obtain a line of credit to insure that the construction company has available cash for emergences. A manager must be careful not to rely upon 30 day and 90 days materials revolving accounts in the event a customer does not pay. A contractor must be careful not to take on more jobs than he/she has cash to buy materials and pay labors until the contracts are completed. Reserve for Bad Debts A company needs a policy for collecting debts and for dealing with un-collectable debts. Recognizing when a customer is late paying, and holding the customer to a payment schedule can greatly reduce bad debts. Debts can only be written off the books when; • A debtor abandons his/her business. • The debtor cannot be contacted. • The debtor dies and leaves a worthless estate. It is important to monitor bad debts to make sure the ratio of charge sales to bad debts are not increasing. If they are, the company's policy or process used in evaluating charge sales must be reevaluated. Bad Debt Ratio: Total Credit Sales / Actual Bad Debt Losses. Since the contractor knows that some percentage of receivables will never be collected he/she makes an account for bad debts. The objective is to make sure the company does not come to depend on cash that will never materialize. Receivables: The next account that can be managed is receivables. Receivables are short-term debts (for a period of less than one year) that must be monitored and managed to make sure as much as possible turns into cash. Also, a company will commonly set a dollar limit on receivables, to make sure the company does not run out of cash. A second option is to sell or pledge receivables at a bank against a revolving line of credit. It is important to track your receivables trend as; if customers begin to take longer to pay, it is more likely that bad debts will increase. This is particularly important in a declining economy.
  • 9. Brevard Contractors School 9 Prepare To Pass Copyright 2004 – 2006 © Average Days Receivables = (Average Receivables / (12 Month's Charges)) x 365 When a receivable is assigned to a collection agency or considered a bad debt it should be listed in a separate column in your accounts receivable and these amounts should be excluded from monthly totals. The next asset account is Long Term Receivables. These must also be managed to insure that they turn into cash at maturity. It is also important to know that it is possible to sell or pledge long term notes receivables to obtain financing. Banks, mortgage companies, and factors will buy long term receivables, often at a discount. Long-term receivables are often called Notes Receivable. Keep this in mind when agreeing to hold paper on a construction job. To qualify as a Notes Receivable the debt must be in writing in a formal legal document, signed by both parties. For this reason a signed lease for more than one year also qualifies as a note receivable. If you plan to sell off notes receivable your notes need to carry an interest rate premium of 2 to 3 percentage points above the market average or your notes will be severely discounted. Retainage: These are hold backs that customers kept, usually about 10% of the bid amount to insure that the contractor does the "punch list" items and resolves all the incidental problems which may exist after the project is "substantially complete" or has received a CO, "certificate of occupancy.” Retainages can't be considered past due receivables, and they must be separated from delinquent receivables. Long-Term Assets: Long-term assets are assets that are expected to remain on the books for more than one year before they are turned into cash. Some assets, such as trucks, front-end loaders, and barns are used in the course of business and there is no intention to turn such long-term assets into cash.
  • 10. Brevard Contractors School 10 Prepare To Pass Copyright 2004 – 2006 © Prepaid Assets and Deferred Assets: Prepaid assets are sometimes called deferred assets. Some debts are paid for in advance, such as insurance, deposits on real estate, utilities deposits, office supplies, and loan interest: These prepaid assets should be listed on the books as assets. The distinction between prepaid assets and deferred assets is that deferred assets are not put on the books until the item is available for use, even though it has been paid for. Intangible Assets: Intangible assets are typically non-physical assets such as the "goodwill" that a businessperson's reputation will earn, as well as non-competition clauses. Anytime you pay more for an asset than it's appraised or "fair market" value the difference is classified as "goodwill." Such non-tangible assets are listed on the books and amortized over a period of years. Current Liabilities: These are debts the company must pay within 12 months. Notes payable, current: these are accounts, which are due and payable before the end of the fiscal year, usually December 31. Long Term Notes Payable: These are debts that are due and payable at a future date beyond the current year. Accounts Payable: are typically vendor accounts for materials and rentals, but they can be truck and equipment loans, electric bills, and current real estate taxes. Taxes: taxes of all sorts, employee taxes, sales taxes, income taxes, are collected for the state and federal government and must be deposited at the bank or mailed out on a periodic basis. Depreciation Methods • Straight Line Depreciation • S/L -For Residential Real Estate • S/L -For Commercial Real Estate • 200% Declining Balance Depreciation • 150% Declining Balance Depreciation • MACRS
  • 11. Brevard Contractors School 11 Prepare To Pass Copyright 2004 – 2006 © In Declining Balance Depreciation you always use the asset life as the depreciation factor. Do not use the remaining years as the depreciation factor. Two ways to solve the problem: Straight Line Depreciation rate = 1 / life of asset 1/life of asset = constant factor constant rate = constant factor x depreciation factor (2 or 1.5 or 1.25) yearly amount due = constant rate x book value The yearly depreciation schedule for double declining with a 10 year life would be: Year Depreciation Expense Accumulated Depreciation Book Value 1 .10 x 2 x 60000 12,000 $48,000 2 .10 x 2 x 48000 9,600 $38,400 Year Depreciation Expense Accumulated Depreciation Book Value 1 60,000 /10 years = 6000 * 2 = 12,000 $48,000 2 48,000 / 10 years = 4800 * 2 = 9,600 $38,400 Double Declining Balance Depreciation Method The double declining balance (DDB) method is an accelerated depreciation method in which more depreciation expense is recognized in earlier years and less is recognized in later years. This method gets its name from the fact that it uses a rate twice the straight- line rate. To compute depreciation expense using the DDB method, the following steps are used. 1) Determine the straight-line rate per year. For instance, if the useful life of an asset is ten years, The straight-line rate is 1/10 or 10%. If the useful life is five years, the straight line rate is 1/5 or 20%. 2) Determine the DDB rate. This is simply double the straight-line rate. A straight-line rate of 10% becomes 20% and a straight-line rate of 20% becomes 40%.
  • 12. Brevard Contractors School 12 Prepare To Pass Copyright 2004 – 2006 © 3) Compute the current year's DDB depreciation. Assume that Mythical purchased a machine costing $100,000 with an estimated useful life of five years and an estimated salvage value of $10,000. The straight-line rate would be 20%. The DDB rate would be 40%. Depreciation for year one is $100,000 X 40% = $40,000. NOTE: Under the DDB method, any salvage value is ignored in computing depreciation expense. Remember, you never depreciate an asset below its salvage value. As is true with all depreciation problems, you should prepare a depreciation schedule. The depreciation schedule for this asset is shown below. The journal entry to record depreciation expense is exactly the same regardless of the method used. For any accounting period you would debit depreciation expense and credit accumulated depreciation. Calculator for MACRS: http://www.pine-grove.com/depreciation/MACRS_Screen.htm Calculator for Declining Balance depreciation: http://www.acsu.buffalo.edu/~thill/programs/JavaScript/financial/dbc.html
  • 13. Brevard Contractors School 13 Prepare To Pass Copyright 2004 – 2006 © MACRS: Modified Accelerated Cost Recovery System has 3,5,7, 10 year categories and uses the following conventions. • 3, 5, 7, 10 year assets are depreciated at 200% declining balance. • 15 and 20 year assets are depreciated at 150% declining balance. • Autos and trucks are depreciated for 5 years at 200% • Office equipment such as computers are depreciated for 5 years at 200% • Commercial Real Estate 39 years straight line only • Residential real estate 27.5 years straight line only Generally all property put in place under the MACRS system uses the mid-year conversion. It is assumed that all assets are put in service at the middle of the year, and the first year you are entitled to 1/2 the annual deduction. Straight Line Depreciation for Real Estate: It is currently required that you use straight line (SL) depreciation on all real estate. Chapter 3 of the Contractors Manual details depreciation. Commercial Real Estate placed in service after May 12, 1993 must be depreciated for 39 years. Residential rental property is depreciated for 27.5 years. Straight line depreciation rate = 1 / life of asset (either 27.5 or 39 years) 1/life of asset = constant factor (1/39 = .02564 or 1/27.5 = .03636) yearly amount due = constant rate x book value Depreciation has two functions. On the one hand you want to depreciate the assets so you know how much has been used up and how much useful life the asset has remaining. A secondary or tax objective is to match depreciation schedules with income flows to shield the maximum amount of income from taxation. For this reason many companies maintain two depreciation schedules on long term and real assets.
  • 14. Brevard Contractors School 14 Prepare To Pass Copyright 2004 – 2006 © Types of Business Entities: • Proprietorship • Partnership • Corporation Proprietorship is simply an individual in business for him or herself. The proprietorship lacks a distinct legal form; there is no legal difference between the business and the owner of the business. Partnership is two or more individuals in business for the common good. A Corporation is a legal entity separate and distinct from the people who own and manage the corporation. Accounting Methods: The Builders Guide to Accounting is not a great introduction to accounting; a better booklet is "Step by Step Bookkeeping, the complete handbook for the small business" by Robert C. Ragan, C.P.A. The Builders Guide to Accounting takes the approach of asking the reader to consider their options in handling various accounting conventions. You are asked to consider whether your company will use Percentage of Completion or Completed Contract method for recording income and expenses. This relates directly to a primary accounting question; will your company use the cash accounting method or the accrual accounting method? What method will your company use for depreciation? Do you know how to match income with depreciation schedules? The Builders Guide then tells you how to handle a number of journals, such as payables journal, receivables journal, materials journal, petty cash journal, and how to reconcile your checkbook. Cash Accounting Method Vs Accrual Accounting Method: A cash based accounting system records income and expenses only when the CASH actually changes hands. For construction this would equate to completed contract method. In an accrual based system a transaction is entered on the books as soon as the transaction takes place, regardless of when cash is exchanged. Many companies use a modified cash basis. They may reflect income and materials expenses on an accrual basis, but do all other accounts on a cash basis to minimize bookkeeping. But remember that the
  • 15. Brevard Contractors School 15 Prepare To Pass Copyright 2004 – 2006 © IRS requires you to: • use a method that clearly reflects income and • requires that your company use this method consistently. The Income Statement lists income, direct costs, operating expenses and profits. Income Statement Earned Income xxx Returns and Allowances <xxx> Net Sales xxx Cost of Goods Sold <xxx> Gross Profit xxx Selling Expenses <xxx> Profit before fixed Overhead xxx Fixed Overhead <xxx> Net Income xxx Percentage of Completion VS Completed Contract Method: Under the Completed Contract Method the income and the costs of a given project are shown on the income statement only when the project is 100% complete. Both the income from the project and any cost associated with the project are recorded at the same time. Periodic payments, costs, and profits, are not recorded while the project is under construction. Usually, completed contract method is limited to small jobs of short duration. The IRS will not allow companies with revenues in excess of 10 million annually to use completed contract method for tax purposes. The Percentage of Completion Method is the most desirable method for contract accounting. It requires you to start with an estimate of the total cost to construct the entire project in advance. The percentage of completion method of accounting will allow you to recognize the amount of money you have earned on a project at any given time. This is then compared to how much you have invoiced the owner at the same particular time. The result may be that you are under billed, or accrued income. (You have not billed as much as you have earned). Or over billed, have unearned or deferred income (you have billed more than you have earned). The formula for percentage of completion accounting is performed in the following steps;
  • 16. Brevard Contractors School 16 Prepare To Pass Copyright 2004 – 2006 © Cost to Date = % of Completion (Cost to Date + Estimated Cost to Complete) % of Completion * Contract Amount = Revenue Earned Revenue Earned – Amount Invoiced = Deferred OR Accrued Income Petty Cash Fund: The Petty Cash Fund is a fixed amount of money that is set aside for purchases that are too small to warrant writing a check. The fund must be controlled if the petty cash fund is to work. The major control in the petty cash system is the voucher slip. Anytime money is taken from the petty cash box a voucher must be presented to the person who keeps the petty cash box. The controller of the cash fund then issues cash for voucher ticket. This is called the voucher system. The petty cash fund should be replenished by writing a check to petty cash which is supported by source documents (receipts) for the money that has been spent out of the fund. Do not write a check to CASH as this is difficult to document. Petty Cash Voucher: No: Date _________ RECEIVED OF PETTY CASH Amount $________ For _________________________________________________________ Charge to:____________________________________________________ Received by: Approved by: ________________________ ________________________
  • 17. Brevard Contractors School 17 Prepare To Pass Copyright 2004 – 2006 © Reconciling the Petty Cash Fund is done as follows; 1: add all expenses on vouchers 2: add cash remaining in fund 3: determine shortage or overage 4: calculate petty cash remaining balance 5: Check amount = Fund limit – actual cash balance eg: Office Supplies 60.32 Postage 28.80 Parking 22.00 Delivery exp 28.15 Coffee 9.47 Printing expense 42.18 Expenses: 109.92 Calculating Shortage Cash on hand = $300 – 190.92 = 109.08 Actual cash on hand 107.45 Shortage 1.63 Check to replenish fund $300 – 107.45 = 192.55 Cash Receipts Daily Journal
  • 18. Brevard Contractors School 18 Prepare To Pass Copyright 2004 – 2006 © Daily Summary of Sales and Cash Receipts 1: Cash Sales Materials __________ Services __________ 2: Misc. Sales __________ 3: Collection of accounts receivable __________ 4: TOTAL DAILY RECEIPTS __________ 5: Cash in Petty Cash Box __________ 6: Petty Cash vouchers and receipts __________ 7: Total in Petty Cash Box __________ 8: Petty Cash fund Limit = $300.00 9: Line 8 – line 5 = ________ 10: Cash short / over ________ 11: Total Cash and Daily Receipts (add lines 1-7) ========= Deduct Petty Cash Fund limit from deposit <__________> 12: Total Deposit __________ Sales Summary 13: Cash Sales ___________ 14: Charge Sales ___________ 15: Total Daily Sales ___________ Check Writing: When you write a check there must be enough information on the check and the check stub to readily allow you to reconstruct the expense and assign it to a ledger account. Every check should have a source document to support the reason the check was written. The supporting document can be a bill, a time card, a petty cash summary voucher. Every check should have the date, payee, amount, purpose and job number or name, and purpose of the payment.
  • 19. Brevard Contractors School 19 Prepare To Pass Copyright 2004 – 2006 © Reconciling the Checkbook: There are two parts of reconciling the checkbook. You must first reconcile the bank statement and then reconcile the check book. To Reconcile the Bank Statement: 1: List balance as shown on statement balance 2: ADD checks in transit (not cleared) 3: DEDUCT checks outstanding 4: ADD/DEDUCT incorrect charges 5: The net amount is the reconciled bank statement To Reconcile the Checkbook to the Bank Statement: 1: List balance as shown in checkbook 2: Deduct service charges 3: Deduct bad check charges 4: The net amount is the reconciled checkbook statement These two numbers should be the same, at least on the test! Review: The Income Statement: The Income Statement summarizes business operations within a time period. The Income Statement lists income, direct costs, operating expenses and profit.
  • 20. Brevard Contractors School 20 Prepare To Pass Copyright 2004 – 2006 © The Income Statement's standard divisions are; Gross Sales Less direct costs Equals gross profit Gross Profit Less operating expenses Equals income from operations Income from operations Less provision for taxes Equals Net Profit Construction Company Income Statement For the year 2002 Earned Income xxx -Returns and Allowances xxx =Net Sales xxx -Cost of Goods Sold xxx =Gross Profit xxx -Selling Expenses xxx =Profit before fixed Overhead xxx -Fixed Overhead xxx =Net Income xxx
  • 21. Brevard Contractors School 21 Prepare To Pass Copyright 2004 – 2006 © Review: The Balance Sheet: The Balance Sheet is a summary of existing conditions of the business. The Balance Sheet lists Assets, Liabilities, and Net Worth. The Balance Sheet Assets: Debit Credit Debit Credit Assets Cash xxx Accounts Receivable xxx Bad Debt Reserves xxx Fixed Assets xxx Depreciation Reserve xxx Liabilities xxx Accounts Payable xxx Taxes Payable xxx Notes Payable xxx Net Worth xxx Capital Stock xxx Retained Earnings xxx The Balance Sheet: (has the following major categories) Current Assets Current assets are liquid and near liquid assets. These assets include cash, accounts receivable, inventories and other current assets. Fixed Assets Fixed Assets includes the gross value of equipment and machinery, small tools, improvements, furniture, fixtures, structures, and land. Other Assets Intangible assets include such as covenant not to compete, and Goodwill of a business.
  • 22. Brevard Contractors School 22 Prepare To Pass Copyright 2004 – 2006 © Current Liabilities Include such accounts as accounts payable, taxes payable, notes, contracts, ad deposits to be refunded. Long Term Liabilities Some liabilities exist on the books for more than one year. If a liability is not paid off inside of one year keep the remaining portion of the assets value separate from current liabilities. Contingent Liabilities These are debts that have not occurred now, but are pending, such as pending lawsuits. Equity Account Capital stock or owners equity represents the original investment of the owners of the business. Capital stock accounts are only changed by the addition of new capital or the removal of old capital. Retained Earnings Each year’s profit and losses Net Profit Each year’s net profit or loss is recorded and placed into an earnings account when the books are closed at the end of the year. This account may be called a retained earnings account or equity account.
  • 23. Brevard Contractors School 23 Prepare To Pass Copyright 2004 – 2006 © Statement of Cash Flows Is a summary of the sources and uses of cash. The Statement of Cash Flows shows changes in long-term assets and liabilities and capital accounts. The Statement of Cash Flows is often called the most important financial statement, even though it is often the least used financial statement. The Statement of Cash Flows has two sections: • Fixed or long-term provisions of funds. • Change in current assets and liabilities. Sources of Capital Net profit on a cash basis Funds received from the sale of capital assets Funds received in the form of a loan proceeds Investments of capital by stockholders Increases in long-term liabilities Uses or (applications) of Capital Funds paid for the acquisition of capital assets Reduction in long-term liabilities Dividends paid or payments to stockholders Decreases in long-term liability accounts The net difference between these two accounts, long term assets, and long term liability and capital accounts result in a net increase or decrease in funds for the period.
  • 24. Brevard Contractors School 24 Prepare To Pass Copyright 2004 – 2006 © Funds Flow Analysis Sources of Funds Profit from operations __________________________ Depreciation __________________________ Decrease in cash __________________________ Decrease in receivables __________________________ Decrease in Inventories __________________________ Decrease in other assets __________________________ Increase in payables __________________________ Increase in notes __________________________ Increase in common stock __________________________ Increase in accrued expenses __________________________ Increase in deferred taxes __________________________ Gain form sale of asset __________________________ Other __________________________ TOTAL ======================= Uses of Funds Increase in accounts receivable __________________________ Increase in notes receivable __________________________ Increase in inventory __________________________ Increase in plant and equipment __________________________ Increase in prepaids __________________________ Decrease in notes payable __________________________ Decrease in secured notes __________________________ Dividends __________________________ Decrease in mortgage __________________________ Increase in Cash __________________________ TOTAL =======================
  • 25. Brevard Contractors School 25 Prepare To Pass Copyright 2004 – 2006 © Summary: The Balance Sheet is a general indicator of the strength of your operation. The Income Statement shows how well you're controlling costs and expenses. The yield on your operations, and the volume of business you're doing. The Statement of Cash Flows tells you whether your operation is handling cash properly. Management Ratios: Cost of goods sold = cost of goods sold / net sales Goss margin = net sales – cost of goods sold / net sales Profit margin = net profit / net sales Profit margin = net profit before taxes $ interest / net sales Profit margin = net profit after taxes, before interest / net sales Expense radio = various expense items / net sales Contribution to fixed cost and profit = net sales – direct costs (variable costs) / net sales Net sales / gross assets Gross assets / net sales Net sales / net assets Average inventory / net sales Average inventory / cost of goods sold Net sales / average inventory Cost of goods sold / average inventory Net sales / days of the year Accounts receivable / sales per day Net profit / assets Net profit / net assets (capitalization) Net profit before interest and taxes / net assets (capitalization) Net profit after taxes, before interest / assets Net profit after taxes, before interest / net assets (capitalization) Owners Ratios: Net profit / net worth Net profit to common / common equity Earnings per share = net income / average number of sales outstanding
  • 26. Brevard Contractors School 26 Prepare To Pass Copyright 2004 – 2006 © Lenders Ratios: Current assets / current liabilities Cash + marketable securities + receivables / current liabilities Total debt / total assets Long term debt / capitalization (net assets) Total debt / net worth (equity) Long term debt / capitalization – long term debt Working Capital refers to the net difference between current assets and current liabilities. The Trial Balance: This worksheet proves that the general ledger is in balance. In all cases debits should equal credits. Closing Adjustments: This is much like reconciling the bank statement that we did last week, except there are more accounts to reconcile. 1: debits to expense accounts 2: adjustments for coding errors in your books 3: Bank reconciliation adjustments 4: write-offs for bad debts 5: Changes in inventory based on your year-end physical 6: Recording of depreciation and amortization 7: Adjustments to the notes payable liability for the years interest 8: Corrections to liability and expense accounts for tax liabilities 9: Adjustments to percentage of completion report 10: adjustment for completed contract accounting
  • 27. Brevard Contractors School 27 Prepare To Pass Copyright 2004 – 2006 © Markup Profit There are two methods for calculating Markup Profit, which are detailed in BGA, Walker's and the Contractors Manual. • Markup from Cost • Markup from Selling Price Markup from Cost: Take (the percentage allocated to overhead + the required profit margin)= % Direct cost of job * (1+ %) = bid 24% (.24) percent for overhead + 18% (.18) percent required profit = 42% or .42 54,000 * 1.42 = $76,680 Markup on Selling Price: 100 – (overhead + profit margin) = multiplier Job cost / multiplier = bid 100 – 24% (.24) + 18% (.18%) = 58% or .58 54,000 / .58 = $93,103 What BGA wants you to see is how you calculate profit can make a big difference in how much money your company earns. The exam board does not tell you to use Markup on Selling Price, but it stands to reason that if you are a construction manager, and you agree to do a job for cost plus a percentage, you want to use Markup on Selling Price. Always use markup on selling price unless the contract specifically requires you to use Markup from Cost. On the exam they will probably ask questions to test your knowledge of the difference between these two methods.
  • 28. Brevard Contractors School 28 Prepare To Pass Copyright 2004 – 2006 © AIA AIA documents are very structured construction contracts. • They make the architect the arbitrator or mediator between the owner and the contractor. The architect will charge extra for this service. • In so precisely spelling out the contractor's duties and obligations these contracts place a lot of pressure on the contractor to perform. • This is a good contract if you are certain you can meet the building schedule requirements, or if the other party to the contract is in a superior position. In Florida, the following contractual rules apply; • Written text supercedes typed text • Typed text supercedes printed text • Florida courts tend to rule against the writer of the contract in the event of disagreement. • A valid contract has to have the following elements; • An offer (the bid is an offer) • Acceptance • Consideration by both parties. So when you make a bid, determine how much time and money it cost to calculate the bid – and include a preliminary invoice. Ok, if the owner accepts your offer you have already supplied consideration when you prepared the bid, therefore you have a contract. Sometimes people will change their mind, and they will get their lawyer to write and say the contract did not exist because you have not begun work, i.e. you have not provided consideration. You circumvent this problem by including an invoice with the bid that details the amount of time and expense it took to create the bid and working drawings to demonstrate that you have provided consideration. This invoice needs to be for $101.00 or more to have a binding contract.
  • 29. Brevard Contractors School 29 Prepare To Pass Copyright 2004 – 2006 © INVOICE: TO: Beasley's Construction 320 N. Atlantic Ave 1A Cocoa Beach, Fl. 32931 Bob Hansen estimating $250 Tom Richards – working drawings $175 (5) Copies blue prints - Architect $100 8 hours (John Beasley) Site Inspection Summary of Contract Law The courts generally rule that a contract exists whenever the parties manifest the intention to be bound by an agreement. Courts generally allow a party to be excused from a contract by reason of fraud, duress, undue influence, a mistake, unconscionability, or impossibility of intent. Fraud = cheated, lied, misrepresented intent Duress = made you do it, not a free will choice Undue influence, if you were tricked or suckered or manipulated Mistake = clearly did not understand the intent of the agreement or facts Unconscionability = asked to do something that no average sane person would do Impossibility = looked good on paper, but simply can not be done The Law of Contracts is generally covered by each states common law. Another type of law is the Federal Uniform Commercial Code. Personal Property is any type of property other than real property. Most personal property sold around the United States is covered under Article 2 of the Uniform Commercial Code. The exception to items covered under the U.C.C. is real property (land) or land with improvements such as buildings, as well as employment contracts, service contracts, and insurance contracts. A sale is a contact (or agreement) involving the transfer of title to goods from a seller to a buyer for a price (for consideration). A contract is a collection of promises the courts will enforce. A breach of contract is a failure to perform on those promises. The Essential Elements of a Contract 1: Mutual consent or assent. The parties to a contract must show by word or deed that they have agreed to enter into a contract. This usually constitutes an offer and acceptance of the offer.
  • 30. Brevard Contractors School 30 Prepare To Pass Copyright 2004 – 2006 © 2: Consideration. Each party to a contract must intentionally exchange something of value as an incentive to get the other party to the contract to return the exchange. 3: Legality. The objectives of the contract (to be enforceable by the courts) must be for a legal activity. 4: Capacity. Each party to the contract must have contractual capacity. The person must not have been declared incompetent by a court, must be of legal age, and not intoxicated. If all of these four elements of a contract are available, then in most cases an oral contract is a binding and enforceable agreement by the courts. Contracts for the sale of real estate must be in writing; as well contracts for more than $500 dollars generally must be in writing. Types and Classification of Contracts Express contracts are contracts where the parties have manifested their agreement by oral or written agreement. An implied contract is one which can be discerned from the conduct of both parties, but is not totally spoken or written. A bilateral contract is one in which both parties exchange promises to do something. Typically think of these as (AND) contracts. You do this AND I will do that. Each party is obligated to perform under a bilateral contract. A bilateral contract is accepted by way of an agreement. A unilateral contract is one where one party makes an offer to the other party, but the second party is not obligated to take the offer. IF – THEN contracts. IF you do this, THEN I will do that. Rather of a take it or leave it offer. Only the offering party is obligated to perform on the contract IF the offer is accepted. A unilateral contract is accepted by performance. The contract is a done deal when the performance is completed. Example: I will pay you 1,000 dollars to put up the sheetrock. If the person responds by starting to put up sheetrock what you have is acceptance of a unilateral contract. If the person puts up half the sheetrock and quits, no contract exists. If the person responds by handing the offeror a work order and says, sign this and we will get started next Tuesday, then the contract has become a bilateral contract. An executed contract is one where all the parties to the contract have fully performed on their promises. An executory contract is one that is yet to be performed. One or more parties to the contract have one or more promises as yet to perform.
  • 31. Brevard Contractors School 31 Prepare To Pass Copyright 2004 – 2006 © Essentials of an offer 1: An offer must be communicated to the offeree. 2: Both parties must manifest intent to agreement. 3: The offer must be explicit. For an offer to constitute a valid contract there must be the communication of an offer from one party to the other, and the intent of the agreement must be explicit (definite). A valid contact is one that meets all the requirements of a binding agreement. A void contract is one that does not meet all the requirements of a binding agreement. Revoking an offer In a bilateral contract you may revoke an offer anytime before the offer is accepted. In a unilateral offer you cannot revoke the offer for a reasonable amount of time once the party has begun to work or perform on the contract. An offer can be revoked if a lengthy amount of time has passed, or if the contract says “time is of the essence” and provides a date certain when the offer will be revoked. If the offer is rejected then the offer is revoked. If a counter offer is made, then the offer was revoked or terminated. Statute of Frauds The Statute of Frauds says that certain types of contracts must be in writing in order to minimize corruption or fraud. For our purposes these contracts include promises to answer for the duty of another, contracts that cannot be performed within one year, and the transfer of real property. The Statute of Frauds requires the following: • define the parties to the contract or agreement • specify the subject mater and terms of the contract or agreement • must be signed by all parties to the contract or agreement.
  • 32. Brevard Contractors School 32 Prepare To Pass Copyright 2004 – 2006 © AIA – Summary of Forms: A-101 or short form A-107 is the stipulated sum agreement. A-10-111/CM is stipulated sum agreement for construction management. A-111 is the cost of work plus a fee agreement. A-401 is the contractor – subcontractor agreement. A-701 is instructions to bidders A-201 General conditions for construction contract. G-701 is a change order G-706 A is a release of liens form G-702 application and certificate for payment The primary forms reviewed on the exam are A201, A401, and A701. The AIA form A-201 has 14 articles as defined in Walkers 1.09-1.18 1: defines the documents, the work, the project, execution, correlation, intent an interpretations of the contract… 2: defines the architect as the "administrator" of the contract 3: Defines the owner, his rights and responsibilities 4: defines the contractor, his duties, in supervision, and construction of all labor and materials, defines the warranty, as well as taxes, permits, fees, notices, cash allowances, the progress schedule, draws to be kept on job site, drawings, samples… 5: defines subcontractors 6: sets forth owners rights 7: miscellaneous provisions 8: defines contract time 9: discusses payments and completion sum 10: covers protection of persons and property 11: insurance requirements 12: includes change orders 13: acceptance of defective and non-conforming work 14: termination of the contract.
  • 33. Brevard Contractors School 33 Prepare To Pass Copyright 2004 – 2006 © AIA 201 owner-contractor agreement calls for the successful bidder to submit a list of subcontractors for approval. If the owner rejects a subcontractor after the contract is bid, then any change in price caused by rejecting the subcontractor constitutes a change order and the owner must pay the difference. 1:12 Walker Section 1.1 define the basic definitions of the document. The contract documents consist of the agreement between Owner and Contractor, Conditions of the Contract, drawings, specifications, and addenda issued prior to execution of the contract. A modification is (1) a written amendment to the Contract signed by both parties, (2) a change order, (3) construction change Directive or (4) a written order for a minor change in the work. Section 1.6 Ownership and use of the drawings, specifications and other instruments of service. The contractor may keep one set of drawings for his records. The Architect shall retain all rights to the drawings, all other copies of the instruments (drawings and specifications) shall be returned to the architect. 2.2.3 The owner shall furnish surveys describing the physical characterizes, legal limitations and utility locations for the site of the project, and a legal description of the site. 2.4.1 Owners rights to carry out work: If the contractor defaults or neglects to carry out the work in accordance with the contract documents and fails within a seven-day period after receipt of written notice from the owner to commence and continue correction of such default or neglect within diligence and promptness, the owner may after such seven- day period give the contractor a second written notice to correct such deficiencies within a three-day period. If the contractor within a three day period after receipt of such second notice fails to commence and continue to correct any deficiencies, the owner may, without prejudice to other remedies the owner may have, correct such deficiencies. 3.2.1 If the contractor discovers any errors, inconsistencies or omissions discovered by the contractor shall be reported promptly to the architect as a request for information in such a form as the architect may require. 3.3.2 The contractor shall be responsible to the owner for acts and omissions of the contractor’s employees, subcontractors and their agents and employees, and other persons or entities performing portions of the work for or on behalf of the contractor or any of its subcontractors. 3.4.3 The contactor shall enforce strict discipline and good order among the contractors employees and subcontractors. 3.7.1 Permits and fees: the contractor shall secure and pay for the building permit and other permits and governmental fees, licenses, and inspections necessary for proper execution and completion of the work which are customarily secured after execution of the contract. 3.7.3 It is not the contractor’s responsibility to ascertain that the contract documents are in accordance with applicable laws, statures, ordinances, building codes, and rules and regulations.
  • 34. Brevard Contractors School 34 Prepare To Pass Copyright 2004 – 2006 © 3.8.1 Allowances: The contractor shall include in the contract sum all allowances stated in the contact documents. Items covered by allowances shall be supplied for such amounts and by such persons or entities as the owner may direct. 3.11.1 Documents and samples at the site: The contractor shall maintain at the site for the owner one record copy of the Drawings, specifications, addenda, change orders and other modifications in good order and marked currently to record field changes and selections made during construction, one record copy of approved shop drawings, product data, samples and similar requires submittals. 3.12.1 Shop Drawing: Shop Drawings are drawings, diagrams, schedules and other data specially prepared for the work by the contractor or a subcontractor, sub-subcontractor, manufacturer, supplier or distributor to illustrate some portion of the work. 3.12.7 The contractor shall perform no portion of the work for which the contract documents require submittal and review of shop drawings, product data, samples or similar submittals until the respective submittal has been approved by the architect. 3.12.8 the work shall be in accordance with approved submittals except that the contractor shall not be relieved of responsibility for deviations form requirements of the contract documents by the architect’s approval of shop drawings, product data, samples or similar submittals unless the contractor has specifically informed the architect in writing of such deviation at the time of submittal. 3.13.1 The contractor shall confine operations at the site to areas permitted by law, ordinances, permits and the contract documents and shall not unreasonably encumber the site with materials or equipment. 9.3.2 Unless otherwise provided in the contract documents, payments shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation in the work. 9.3.3 the contractor warrants that title to all work covered by an application for payment will pass to the owner no later than the time of payment. The work…will be free and clear of liens, claims, security interests or encumbrances in favor of the contractor, subcontractors, material suppliers, or other persons… Applications for getting paid are usually made monthly on form G-702 Definitions – which are provided in Walkers 1.18 are included with a contract to make certain there is a "meeting of the minds" relating to understanding the terms of the contract. Glossary of Construction terms in the contract can be helpful as a source for information.; These are good to know, but the glossary in the Contractors Manual should be memorized if you can, as a number of questions come from the glossary in the Contractors Manual.
  • 35. Brevard Contractors School 35 Prepare To Pass Copyright 2004 – 2006 © AIA – 401 documents which is the contractor sub-contractor contract agreement The important element is that the final payment shall be due when the work is completed satisfactorily to the architect and owner. The sub-contractor shall not assign or sub-contract the work without written consent of the contractor. The sub-contractor shall report to the contractor within 3 days any injury to any of the sub-contractors employees on the site. If the sub-contractor is not paid by the contractor, through no fault of the sub-contractor, within 7 days of the time in which payment should have been made the sub-contractor may given 7 days written notice to the contractor stop work until the amount has been paid. Unless otherwise provided in the contract documents, the contractor shall pay the sub- contractor each progress payment and the final payment under the sub-contract within 3 working days after the contractor receives any payments from the owner. Back Charges: If the sub-contractor defaults or neglects to carry out the work in accordance with the agreement, or fails within 7 days of receiving written notice from the contractor to commence and continue corrections of such default or neglect with diligence and promptness the contractor may after giving 7 from receipt by the sub- contractor of any written notice, and without prejudice to any other remedy he may have such deficiency made good, and may deduct the cost from the money owed to the sub- contractor. Time is considered to be of the essence in this contract. This means it is a timing specific document. Within 30 days of the architect issuing a certificate for payment covering such substantially complete work the contractor shall within the extent of the documents make payments to the sub-contractor the entire unpaid balance of the contract sum, or of that portion of the contract sum contributable to the substantially completed work. After a payment is due the sub-contractor the sub-contractor is entitled to the payment plus interest. Before issuance of payment to the sub-contractor by the contractor the sub-contractor shall be required to submit evidence of all bills being paid. Sub-contractors ability to assign his portion of the sub-contract is permissible with written consent of the contractor. Permits for sub-contractors shall be the responsibility of the sub-contractor for payment. The contractor shall provide the sub-contractor with a copy of the estimated progress schedule of the contractor's entire job. Contractor shall notify the sub-contractor of all modifications of the contract promptly. If the work is stopped for a period of 60 days through no fault of the sub-contractor because the contractor has not made payment to the sub-contractor may, in writing, give 7 additional days notice and then terminate the contract. The sub-contractor agrees that all esthetic work shall be done subject to the final approval of the architect.
  • 36. Brevard Contractors School 36 Prepare To Pass Copyright 2004 – 2006 © The sub-contractor shall notify the contractor in writing 5 days in advance of commencement of the work that is scheduled to begin; unless a notice to proceed precedes the date of commencement issued by the contractor. A contractor may terminate employment of a sub-contractor that repeatedly fails to supply enough workers or materials if the contractor gives the subcontractor 2 written notices over a 14 day period. AIA Document 701 Instructions to bidders Any changes to the bidding document must be made by addendum. AIA bids are received in a sealed envelope. The owner must prove financial testing no later than 7 days prior to the expiration of the withdrawal of bids. The bidder shall deliver the required bonds to the owner no later than 3 days following the date of the execution of the contract. By making a bid on the project the contractor represents all of the following to be true; the bidder has visited the site; the bidder has used the provided documents to make a bid; bidder understands local conditions. No addenda will be issued later than 4 days prior to the final date of the receipt of bids. If bonds are required the bidder must deliver them to the owner no later than 3 days following the date of contract execution.
  • 37. Brevard Contractors School 37 Prepare To Pass Copyright 2004 – 2006 © Mechanics' Lien Law Time Line for Filing and Serving Documents According to the Mechanics' Lien Law Document Type – section Who serves or files notice Time to serve or file Notice of Commencement (713.135) Owner or owners agent Record in County Clerks office prior to obtaining building permits Notice to Owner (713.06) All suppliers of goods or services in privity with owners, except laborers Post on site or send notice by registered mail to owners prior to commencing work – but not later than 45 days after commencing work. Notice of Claim (713.08) Every lienor including laborers and persons in privity with the owners. File in the County Clerk's office not later than 90 days after completion of work Notice of Delivery (713.09) Seller and purchaser of materials delivered to a location other than the job site. Serve on owner a notice signed by both the seller and the purchaser of goods. Waiver of Release (713.20) Any lienor other than a laborer: laborer may waive to the extent of labor previously performed At anytime Notice of Contest of Lien (713.22) Owner, agent, attorney of owner, this accelerates the time for filing a suit to 60 days. Record in County Clerk's office Payment Bond (713.23) Contractor Before commencing the construction If the claim of lien is for $5,000 or less it is filed with the County Clerk's office. If the amount of the claim of lien is in excess of $5,000 then it is filed with the Circuit Clerk's Office.
  • 38. Brevard Contractors School 38 Prepare To Pass Copyright 2004 – 2006 © Summary of Construction Lien Law; Liens for professional services: 713.03 Any person who performs services as architect, landscape architect, interior designer, engineer, or surveyor and mapper, subject to compliance with the limitations imposed by this part, has a lien of the real property improved for any money that is owing to him for his services used in connection with improving the real property or for his services in supervising any portion of the work of improving the real property, rendered in accordance with this contract and with the direct contract. No lienor under this section shall be required to serve a notice to owner. You must file a claim of lien. Subdivision improvements: 713.04 Any lienor who, regardless of privity, performs services or furnishes material to real property for the purpose of making it suitable as the site for the construction of an improvement or improvements shall be entitled to a lien on the real property. Site improvement shall include but not be limited to grading, leveling, excavating, and filling of land, including the furnishing of fill soil; the grading and paving of streets, curbs, and sidewalks; the construction of ditches and other area drainage facilities; the laying of pipes and conduits for water, gas, electric, sewage and drainage proposes. No notice of commencement shall have to have been filed to file a lien under this section. No lienor shall be required to serve a notice to owner for liens under this section. You must file a claim of lien. Liens of Persons in privity: 713.05 A material man or laborer, either of whom is in privity with the owner and provides labor, services, materials, or other items required by, or furnished in accordance with, the direct contract and also for unpaid finance charges due under the lienors contract, shall have a right to lien the property. No lienor under this section shall be required to serve a notice to owner as provided in section 713.06. Liens of Persons NOT in privity; proper payments: 713.06 All lienors under this section, except laborers, as a prerequisite to perfecting a lien under this chapter and owner setting forth the lienors name and address, a description sufficient for identification of the real property, and the nature of the services or materials furnished or to be furnished. A notice must be served before commencing, or not later than 45 days after commencing, to furnish his services or materials, but in any event, before the date of the owner's disbursement of the final payment after the contractor has furnished the affidavit under subparagraph 3-d 1.
  • 39. Brevard Contractors School 39 Prepare To Pass Copyright 2004 – 2006 © The notice to owner must be substantially the following form; WARNING TO OWNER: UNDER FLORIDA LAW, YOUR FAILURE TO MAKE SURE THAT WE ARE PAID MAY RESULT IN A LIEN AGAINST YOUR PROPERTY AND YOUR PAYING TWICE. TO AVOID A LIEN AND PAYING TWICE, YOU MUST OBTAIN A WRITTEN RELEASE FROM US EVERY TIME YOU PAY YOUR CONTRACTOR. NOTICE TO OWNER To Owners name and address: Liens for improving real property under contract with husband or wife on property of the other or of both: 713.12 The spouse who contracts shall be deemed to be the agent of the other, unless such other shall, within 10 days after learning of such contract, give the contractor and record in the clerk's office, notice of his or her objection thereto. Manner of serving notices and other instruments: 713.18 1: by actual delivery to the person to be served, or one partner, or an officer of the corporation, director or managing agent. 2: by mailing the same, postage prepaid, by registered or certified mail to the person and at the address listed on the notice of commencement, or shown on the building permit application. 3: If neither of the above methods can be accomplished, then by posting the notice on the premises. Duration of a Lien: 713.22 (must renew lien each year to remain active) No lien provide by part I shall continue for a longer period than 1 year after the claim of lien has been recorded, unless within that timer an action to enforce the lien is commenced in a court of competent jurisdiction.
  • 40. Brevard Contractors School 40 Prepare To Pass Copyright 2004 – 2006 © An owner or his agent or attorney may elect to shorten the time prescribed in subsection 1 within which to commence an action to enforce any claim of lien or claim against a bond or other security under s. 713.23 or 713.24 by recording in the clerk's office a notice in substantially the following form: Notice of Contest of Lien To (name of lienor) You are notified that the undersigned contests the claim of lien filed by you on (date), and recorded in _______Book, _____Page, of the public records of Brevard County, Florida, and that the time within which you may file suit to enforce your lien is limited to 60 days from the date of service of this notice. This (date) Signed (owner or attorney) Moneys received for real property improvements; penalty for misapplication: 713.345 A person, firm, or corporation, or an agent, officer, or employee thereof, who receives any payment on account of improving real property must apply such portion of any payment to the payment of all amount then due and owing for services and labor which were performed on, or materials which were furnished for, such improvement prior to receipt of the payment. Any person who knowingly and intentionally fails to comply with paragraph A is guilty of misapplication of construction funds, punishable as follows; 1: $100,000 or more is a first degree felony. 2: Less than $100,000 but more than $20,000 is a second degree felony. 3: Less than $20,000 is a third degree felony.
  • 41. Brevard Contractors School 41 Prepare To Pass Copyright 2004 – 2006 © Florida Construction Industry Licensing Board Summary Chapter 489 It is important to understand that Chapter 489 of the Florida Statutes gives the construction board the power to regulate the construction industry, and to discipline contractors or persons who hold themselves out as contractors. One of the questions on your exam is likely to be what law or statute gives the Bureau of Professional Regulation the authority to govern the construction industry; the answer is Chapter 489. The regulation of professions by government has two major objectives: (2-6) • To protect the public and ensure safety by preventing unqualified individuals from practicing a given profession; and • To establish standards of practice for those who engage in a particular profession. The professional boards provide a valuable service to the public by determining who is eligible to be licensed to practice of profession, investigating complaints against licensees, and taking disciplinary action against licensees when professional standards have been violated. They serve two important functions: (2-6) • (1) protection of the public by identifying and taking action against incompetent or unethical practitioners and; • (2) serving notice of professional standards on members of the profession and those seeking to become members of the profession. Chapter 489 Florida Statutes provide for the licensure and regulation of all types of contractors in Florida. Who Needs to be Licensed? Generally, any person who, for compensation, undertakes to, submits a bid to, or does himself or by others construct, repair, alter, remodel, add to, demolish, subtract from, or improve any building or structure, including related improvements to real estate for others or for resale to others, must be licensed. (2-7)
  • 42. Brevard Contractors School 42 Prepare To Pass Copyright 2004 – 2006 © Licensing Exemptions: The following are exempted from licensure; • Highway, street, road, bridge, and railway contractors; • Employees of licensed contractors acting within the scope of the contractor's license and with the knowledge and permission of the licensed contractor; • Federal, state, and local government employees (except school boards, the board of regents, and community colleges, unless for the purpose of performing routine maintenance or repair or construction not exceeding $200,000 to existing installations) who do not hold themselves out for hire or otherwise engage in contracting except in accordance with government employment; • Court appointed officers; • Public utilities; • Persons who sell or install finished products, materials, or merchandise which are not fabricated into and do not become a permanent fixed part of the structure. • Property owners acting as their own contractor; • Any construction on United States property; • With certain exceptions, persons performing work of a casual or inconsequential nature, with a contract price of less than $1,000, unless the person represents that he or she is a qualified contractor. • Any construction or operation of irrigation and drainage ditches; • Registered architects or engineers acting within the scope of their practice; • Persons who only supply materials or supplies; • Liquefied petroleum gas dealers; • Heating and AC dealers and installers which AC's have a capacity of 3 tons or less. • Architects, landscape architects, and engineers who offer design-build services.
  • 43. Brevard Contractors School 43 Prepare To Pass Copyright 2004 – 2006 © Subcontractor Requirements: A construction contractor must subcontract the electrical, mechanical, plumbing, roofing, sheet metal, swimming pool, and air conditioning work when a local examination for certificate of competency or license is required in these areas, unless the contractor himself holds a State certificate of competency or license in that area. Not required to sub-contract the following: • General, Building, and Residential contractors are NOT required to subcontract the following; wood shingles, wood shakes, or asphalt or fiberglass shingle roofing materials on NEW building they are constructing. • General contractors can build swimming pools. • General Contractors can build sanitary sewer collections systems, storm water systems, or the water distribution system on new site development work, site redevelopment work, mobile home parks or commercial properties; • General Contractors can connect utility lines from the mains on mobile home parks. Sub-Contractors – Independent Contractors or Employees? An independent contractors allow you to considerably lower payroll tax savings (no FICA, FUTA or state unemployment tax) there are fewer administrative costs, no withholding income, no payroll taxes, no workers' compensation costs, no age discrimination problems, no Americans with Disabilities Act as both acts apply only to employees, also no retirement costs, and fringe benefits. BUT if the independent contractor violates any laws, then the person who holds the contractors license and pulled the building permits will be held responsible, just as if the individuals had been employees of the contractor.
  • 44. Brevard Contractors School 44 Prepare To Pass Copyright 2004 – 2006 © If the independent contractor: • Does not have liability insurance • Does not have workman's compensation insurance • Does not pay FICA and FUTA matching funds • Does not train employees to use tools properly • Does not meet OSHA safety requirements • Does not have the proper licensing • Hires illegal aliens (non-nationals) • Hires persons under the age of 16 • Causes or allows employee(s) to be hurt or killed Then the licensed contractor of record on the job in question will be responsible for the above listed expenses. IRS test for Independent Contractor Status: Independent if: • Control, - contractor does not define when, where, and how the job is to be done. • Training, - if the contractor does not train workers or pays to train workers. • Services, - If the contractor does not allow the independent contractor to determine who and how the work is to be done, requiring only a finished product. • Integration, - the operations of the contractors business must not depend upon the services of the independent contractor. • Hiring, supervision, paying assistants, - The contractor must not hire, supervise nor pay assistants for the independent contractor. • The contractor must not hire the independent contractor on a regular (weekly basis). • Hours of work, the contractor must not set the hours of work the independent contractor must work, but rather define a finished product. • The contractor must not require the independent contractor to work for him/her on a full time basis. • Working on the employers premises, the contractor must not require the independent contractor to perform work at the contractors shop. • The contractor must not set the order or sequence of work, (this is a difficult test to pass for the construction industry). • Oral or written reports by the contractor suggests that the independent contractor is an employee. • Hourly, weekly, or monthly pay suggests a continuing relationship, which argues against independent contractor status.
  • 45. Brevard Contractors School 45 Prepare To Pass Copyright 2004 – 2006 © • Payment of business/travel expenses argues against an independent contractor status. • Furnishing of tools and materials, once again the nature of the construction industry makes it difficult to pass this test unless the independent contractor is responsible for buying the materials to perform the work on his/her bid. • The contractor must not have the right to discharge the independent contractor before his contract bid is finished. In this case it is wise to construct a contract around the AIA contractor – sub-contractor form A-401. The independent contractor can help by doing the following: • Have his/her own business cards • Have a city and county business license • Have liability insurance, pay workman's comp on employees • Bids on jobs, and works by the job • Buying all his/her own tools and materials. • Renting a separate office or construction barn at a separate location. • Runs a risk of making a profit or loss if his bid is inaccurate, or if the job goes badly. • If he/she works for more than one firm on a regular basis. • Makes his/her services available to other licensed contractors or the general public. • Receives no bonuses, tools, or travel expenses • The contractor files a 1099-MISC on the independent contractor. • REMEMBER this from the Circular E. Backup Withholding: If you are required to file a 1099 on an independent contractor or materials supplier, or persons to whom you paid "interest, dividends, rents, royalties, commissions, non- employee compensation in the course of your trade or business" and the payee fails to furnish you with a Taxpayer Identification Number (TIN) then generally you must withhold 31% of taxable payments. • Have a written contract, signed by both parties, that makes it clear that the company doesn't have the right to control the methods or procedures for the worker to accomplish the work contracted for (2-13). • The Independent contractor hires his/her own workers as necessary. • Compensation based on work finished, not hours worked. • Never give an independent contractor a bonus.
  • 46. Brevard Contractors School 46 Prepare To Pass Copyright 2004 – 2006 © Note: If the IRS determines that the independent contractor is an employee you will be responsible for the entire 15.3% due for FICA plus the 6.2% on the first $,7000 due FUTA, as well as penalties which will likely exceed the payment amount due. This applies to the independent contractor, for the last 4 years he worked for you, as well as all his/her employees! Be certain that the individuals you are hiring are truly independent contractors, and that they are collecting FICA and FUTA, as well as paying workman's comp insurance on their employees. If they are not, you are taking a huge risk. In this type situation, the contractor stands to lose more than he/she stands to gain. Any miscalculation, or accident could land the contractor in bankruptcy court. When you bid your jobs, include all the real expenses of doing business; let some other poor fool take the low-ball jobs. If you have to, bid only city, county, state, or federally funded projects where every bidder is required to incur the same cost structures. Rules of Thumb: • Real property (land) 20% to 50% of project costs • Real estate agent 3% of project costs • Materials (improvements) 33% of project costs • Labor 33% to 50% of project costs • Insurance 2% to 10% of project costs • Capital costs (interest rates) 7% to 12% of project costs • Machinery, tools, 5% to 15% of project costs • Overhead, office, and other fixed expenses 3% to 12% According to Dunn and Bradstreet Standard Industrial Code (SIC) business summaries, the average contractor makes 24% profit. The elements listed above are all you have available to manipulate in order to realize a profit. If you can realize only 10% savings in each one of these categories you will realize about a 30% to 35% profit on your overall project.
  • 47. Brevard Contractors School 47 Prepare To Pass Copyright 2004 – 2006 © Penalties for Unlicensed Activity: Engaging in or holding oneself out to be a contractor without first obtaining a license is a violation of Florida Law. Any person who falsely holds himself out to be a licensed contractor or who engages in contracting without first obtaining a license is guilty of a first-degree misdemeanor. The DBPR or a county, municipal, or local licensing board may issue a cease and desist order to prohibit any person from engaging in the business without a valid license. Any contract entered into by a contractor not licensed pursuant to Part I or Part II of Chapter 489, Florida Statutes, is legally unenforceable. Any contract entered into by an unlicensed repairperson or handyman for more than $1,000 dollars is unenforceable. In addition if the person holds themselves out to be a contractor and causes injures to a person due to negligence, malfeasance, or misfeasance, and is not certified by the state nor licensed pursuant to the laws of the city or county in which he does business, the consumer is entitled to three times the actual damages sustained and costs and attorney's fees. Licensing Requirements: Certified Contractor is a contractor who successfully passes a state-administered examination and obtains a certificate of competency issued by the DBPR. Certified contractors are allowed to contract in ay city, county, or district in the state without being required to fulfill the competency requirements of that jurisdiction. Registered Contractor is any contractor who has registered with the DBPR and has fulfilled the competency requirements in the city, county, or district for which the registration is issued. Registered contractors can only contract in the jurisdiction that issued the license. Financial Responsibility Requirements – NET WORTH REPORTING • Net Worth of $10,000 in cash or a line of credit or any combination of the two. (Letter from your bank attesting to the fact that you have $10,000, a letter of bond-ability, or compliance bond issued for $10,000). • A credit report that checks to see if the contractor has any construction related judgments on his/her record (the usual credit report will not work). • Public Liability Insurance 50,000 property/ 300,000 personal injury
  • 48. Brevard Contractors School 48 Prepare To Pass Copyright 2004 – 2006 © • Workers compensation coverage or a personal exemption • A financial statement, not more than 12 months old, containing information indicating the current assets and liabilities, total assets and total liabilities, and total Net Worth of the applicant • Must answer questions pertaining to unpaid or past-due bills or claims for labor, materials, services, liens, suits or judgments or record or pending against the applicant or his firm. The Financial statement needs to look like something out of Builders Guide to Accounting. As much as seeing how much money you have, they DBPR wants to see if you can put together financial statements. All you have to provide is a Profit and Loss Statement, and ratio analysis, but you can include an Income Statement. Almost no one provides a Sources and Uses of Funds Statement.
  • 49. Brevard Contractors School 49 Prepare To Pass Copyright 2004 – 2006 © Davy Jones 320 N. Atlantic Ave #1A Cocoa Beach, Fl. 32931 Balance Sheet December 31, 2001 Assets Current Assets Cash in bank 10,000 Stocks and bonds 2,000 IRA account** 12,000 Savings 2,450 Accounts receivable (business accounts) 0 Notes receivable (include all mortgages and leases) 0 Materials held for trade purposes 1,200 Total Current Assets 27,650 Long Term Assets Long Terms notes receivable (mortgages) 0 Tools 8,560 Machinery and tractors, trailers 2,300 Trucks, cars, motorcycles, boats *** 14,800 Real Property (house and commercial) 62,500 House Hold belongings 15,000 Total Long Term Assets 103,160 Total Assets 130,810 Current Liabilities Credit Cards 2,300 Line of Credit at bank 850 Trade accounts payable 0 Rent due before Dec. 31 (optional) 0 Mortgages payable due before Dec. 31 (optional) 3,456 Auto loans due before Dec. 31 6,000 Total Current Liabilities 12,606 Long Term Liabilities Auto and truck loans due more than one year 3,200 Home equity loans 19,000 Equipment mortgages 0 Revolving loans – Sears – Rooms to Go 0 House and real property mortgages 10,500 Total Long Term Liabilities 32,700 Total Liabilities 45,306 NET WORTH 85,504 Net Worth = Total Assets – Total Liabilities
  • 50. Brevard Contractors School 50 Prepare To Pass Copyright 2004 – 2006 © All financial documents should carry notes at the bottom of the document detailing the conventions used by the preparer of the documents. These notes are used to explain the choices you used in making the statement. e.g.; ** IRA can not be withdrawn until 59 years old *** Market value of assets – not book value Term of License The license is good for 2 years. It must be renewed every two years, and the contractor is required to take 14 hours of continuing education every two years to be able to renew the license. Continuing Education The contractor must take 14 credit hours of continuing education every two years to be able to renew the license. Business Records Business records and complete financial statements for the business must be kept at the place of business for the preceding three years. NOTE from Circular-E that the IRS requires you to keep your records for four years. Qualifying Agents If a joint venture, partnership, corporation, trust, or other business organization wishes to do business and engage in contracting the applicant must apply through a qualifying agent. • The applicant must state the name of the business • List its directors, partners, or officers, or trustees • Show compliance with the fictitious name statute • The qualifying agent is legally qualified to act for the business organization • The qualifying agent has the authority to supervise construction • The qualifying agent must be either a certified or registered contractor
  • 51. Brevard Contractors School 51 Prepare To Pass Copyright 2004 – 2006 © In addition, if the qualifying agent is the only licensed contractor affiliated with the business organization, the business organization must notify DBPR of the termination of the qualifying agent and obtain another qualifying agent within sixty days (60). The qualifying agent is responsible for supervision of all operations of the business, for all fieldwork at all sites, and unless a financially responsible officer is designated. A sole primary qualifying agent is jointly and equally responsible with secondary qualifying agents for fieldwork supervision. A secondary qualifying agent is responsible only for supervision of filed work at sites where his license was used o obtain the building permit, and any other work for which he accepts responsibility. A secondary qualifying agent is not responsible for supervision of financial matters. A change in the status of a qualifying agent is effective form the date of the change forward, and will not relieve the qualifying agent of responsibility for projects or actions that took place during the time he was acting as a qualifying agent. Florida courts have held that Chapter 489 imposes a professional duty upon the sole qualifying agent of record for a general contractor to supervise all of the general contractor's projects. Failure to carry out this duty may serve as grounds for revocation of a qualifying agent's contractor's license. A qualifying agent's claim that he had no personal knowledge of activities of the business entity or of its employees that result in violations of Chapter 489 will not absolve the qualifying agent. Definitions: Primary qualifying agent means a person who possesses the requisite skill, knowledge, and experience, and has the responsibility, to supervise, direct, manage, and control the contracting activities of the business organization with which he is connected. Professional Responsibility – Liability Changes in Licensure information: business organization must inform the DBPR by mail of any change in the information required to be submitted on the application for qualification of a business organization within forty-five days following the change.
  • 52. Brevard Contractors School 52 Prepare To Pass Copyright 2004 – 2006 © Grounds for disciplinary action against a contractor: • Obtaining a license by fraud or misrepresentation • Being convicted and found guilty of a crime related to contracting • Knowingly violating applicable building codes • Assisting a person in unlicensed practice of contracting, or evading licensing • Acting as a contractor in another name other than on the license • Committing mismanagement or misconduct causing financial harm to a customer • Abandoning a construction project (abandoned after 90 days) • Being disciplined by any city or county for violation of licensing law • Failing in any material respect to comply with the licensing law or rule • Signing a statement that a job is bonded, falsely stating subcontracted work has been paid for, labor or materials have been paid for, falsely indicating that workers' comp and public liability insurance are provided • Committing fraud or deceit in the practice of contracting • Committing incompetence or misconduct • Committing gross negligence • Proceeding on any job without building permits • Intimidating, threatening, coercing or otherwise discouraging the service of a notice to owner or a notice to contractor under the mechanic's lien laws; • Failing to satisfy a civil judgment obtained against a licensee or a business within a reasonable time.
  • 53. Brevard Contractors School 53 Prepare To Pass Copyright 2004 – 2006 © Circular E Employer's Tax Guide Purpose: To Calculate withholding taxes using Circular E. You need to have a working knowledge of Circular E. You will use the tables in Circular E weekly or bi-weekly when paying employee wages. It is important that you are familiar with the process, and with the filing dates associated with Circular E. The deductions computed in Circular E are Federal Income Tax Withholding, Social Security (FICA), Medicare, and Federal Unemployment Tax (FUTA). Summary of Circular E: Employees are to file Form W-4 before December 1 of each year. The W-4 defines their address, social security number, martial filing status, and their number of withholding allowances. Backup Withholding. If you are required to file a 1099 on an independent contractor or materials supplier, or persons to whom you paid "interest, dividends, rents, royalties, commissions, non-employee compensation in the course of your trade or business" and the payee fails to furnish you with a Taxpayer Identification Number (TIN) then generally you must withhold 31% of taxable payments. Federal Unemployment Tax, FUTA is filed on Form 940 or 940 EZ by January 31. All employers must file Form 941 on a quarterly basis and deposit any income tax, Social Security, and Medicare taxes. You pay these taxes on Form 941 if your total tax liability for the quarter is less than $1000 dollars. If all taxes were deposited on time, you are given a 10 day extension for filing.
  • 54. Brevard Contractors School 54 Prepare To Pass Copyright 2004 – 2006 © Quarters Ending Due Date last deposit date January – March March 31 April 30 May 10 April – June June 31 July 31 Aug 10 July – September Sept 30 Oct. 31 Nov 10 Oct – Dec Dec 31 Jan 31 Feb 10 Record Keeping: Keep all records of employment taxes for at least 4 years. Who must have an Employer Identification Number? If you are required to report employment taxes or give tax statements to employees or annuitants, you need an EIN. Request an EIN on Form SS-4. Wages and Compensation: Wages subject to Federal employment taxes include all you pay an employee in salaries, vacation allowances, bonuses, commissions, and fringe benefits. Wages not paid in money but "in kind" such as lodging, food, clothing, and services, are generally subject to income tax Withholding and Social Security, Medicare and FUTA taxes. Meals and lodging: The value of meals is not taxable income and is not subject to income tax withholding and if they are furnished for the employer's convenience and on the employer's premises. The same holds true for lodging if it is furnished for the employer's convenience, on the employer's premises, and as a condition of employment. Fringe Benefits: You must include fringe benefits in an employee's gross income. Fringe benefits include cars you provide, flights on aircraft you provide, free or discounted commercial flights, vacations, discounts on property or services, membership in county clubs, or social clubs, and tickets to entertainment or sporting events. You must include an amount equal to fair market value of the benefits, less any amount the employee paid. Supplemental Wages: These wages are wages paid in addition to regular wages, and they include bonuses, commissions, overtime pay, payments for sick leave, severance pay, awards, prizes, back pay and retroactive pay increases, as well as nondeductible moving expenses.
  • 55. Brevard Contractors School 55 Prepare To Pass Copyright 2004 – 2006 © Calculating Supplemental Withholding: If you have been withholding income tax from an employees regular wages, then use 1 of the following methods for supplemental wages. 1: Withhold a flat 28% (no other percentage is allowed). 2: Add the supplemental and regular wages for the most recent payroll period this year. Then figure the income tax withholding as if the total were a single payment. Subtract the tax already withheld from the regular wages. Withhold the remaining tax from the supplemental wages. Payroll Period: A payroll period is a period of service for which you usually pay wages. Social Security and Medicare Taxes: The Federal Insurance Contributions Act (FICA) provides for a Federal system of old- age, survivors, disability and hospital insurance. Tax rates: The employee tax rates for social security is 6.2% (amount withheld) . The employer tax rate for social security is 6.2% (12.4% TOTAL). The wage limit base is 87,900 The employee tax rate for Medicare is 1.45% (amount withheld). The employer tax rate for Medicare is 1.45% (2.9% TOTAL). There is no wage base limit for Medicare tax; all covered wages are subject to Medicare tax. Advanced Earned Income Credit (EIC): An employee who is eligible for the EIC and has a qualifying child is entitled to receive EIC payments with his or her pay during the year. To get these payments the employee must give you a properly completed FORM W-5. Depositing Taxes: Income tax withheld, social security, and Medicare taxes are to be filed on Form 941 at a local Federal Reserve Bank or electronically. Form 945 is for filing non-payroll tax liabilities and payroll and non-payroll may not be filled on the same form.
  • 56. Brevard Contractors School 56 Prepare To Pass Copyright 2004 – 2006 © Depositing on Time: To be considered timely, the funds must be available to the depositary or FRB on the deposit due date before the institution's daily cutoff deadline (usually 2:00 P.M.). HOWEVER, a deposit received by the authorized depository or FRB after the due date will be considered timely if the taxpayer establishes that is was mailed in the USA at least 2 days before the due date. Deposit Penalties: 2% late fee on Deposits made 1 to 5 days late. 5% late fee on Deposits made 6 to 15 days late. 10% late fee on Deposits made 16 or more days late. Filing Form 941: Form 941 must be filed each quarter. Penalties for late payment: For each whole or part month a return is not filed when required, there is a penalty of 5% of the unpaid tax due with that return. The maximum penalty is 25%. Also, for each whole or part of a month the tax is paid late, a penalty of .5% of the amount of the tax generally applies. The maximum penalty is also 25%. Federal Unemployment Tax (FUTA): Only the employer pays FUTA tax, it is not deducted from the employee's wages. Test for FUTA: 1: You paid wages of $1,500 or more a year for any calendar quarter for the present year and the previous year. 2: You paid $1,000 or more to household employees in the previous year. 3: You paid farm workers more than $20,000 in any calendar quarter, or employed 10 or more farm workers for 20 or more weeks.
  • 57. Brevard Contractors School 57 Prepare To Pass Copyright 2004 – 2006 © Computing FUTA Tax: The FUTA tax rate is 6.2%. The tax applies to the first $7,000 you pay each employee as wages during the year. FUTA is only paid by the employer. Florida does not have any SUTA tax: Florida does not have any SDI tax: Calculating Tax liabilities: 1: From the Form W-4, obtain employees filing status, either married or single, and number of withholding allowances claimed. From the time card obtain the employees gross wages subject to income taxes. With this information you are ready to go to the Circular E wage and tax tables and calculate the income tax to be withheld on a weekly or bi-weekly basis. Write down the amount from the tables. 2: Calculate Social Security, FICA; - refer to Circular E for current rates. • 6.2% (.062) * wage rate up to annual maximum of 87,900 • .145% (.0145) * wage for Medicare – on total wages -no maximum • 7.65% (.0765) total FICA and Medicare deducted from employees check. The employer must match each of the FICA and Medicare deductions made by the employee. These are matching funds of 7.65% which are contributed by the employer making the total payment due 15.3% of gross wages. 3: Calculate FUTA, Federal Unemployment Tax, this amount is paid completely by the employer. The FUTA tax rate is 6.2% (.062) on the first $7,000 of annual wages. If you pay SUTA to the state up to 5.4% maybe deducted from the 6.2% paid to the FUTA leaving a balance of .8% or (.008) to be paid on Form 940. Florida has no SUTA.
  • 58. Brevard Contractors School 58 Prepare To Pass Copyright 2004 – 2006 © Some abbreviations: FICA Social Security Tax FUTA Federal Unemployment Tax EIC Earned Income Credit FRB Federal Reserve Bank SSA Social Security Administration FIT Federal Income Tax To obtain a current copy of Publication 15: Circular E, Employer's Tax Guide: go to the IRS website listed below and type in "Publication 15." To obtain 940, 941, W2's, and W4's you may go to the same website and type in the desired publication and then download it in Adobe format. http://www.irs.ustreas.gov/formspubs/index.html
  • 59. Brevard Contractors School 59 Prepare To Pass Copyright 2004 – 2006 © % % of Completion · 16 1 1099 · 45, 53 9 940 EZ · 53 A Accounts Payable · 3, 4, 10, 21 accrual accounting method · 14 Advanced Earned Income Credit · 55 AIA · 28 AIA – 401 · 35 AIA – Summary of Forms · 32 AIA 201 · 33 AIA Document 701 · 36 Averages Days Receivables · 9 B Backup Withholding · 53 Bad Debt Ratio · 8 Balance Sheet · 1, 3, 4, 5, 6, 7, 21, 25, 49 bilateral contract · 30 breach of contract · 29 Business Records · 50 C Calculating Tax liabilities · 57 cash accounting method · 14 Cash Movement Method · 7 Cash Receipts Daily Journal · 18 Certified Contractor · 47 Changes in Licensure · 51 Changes in Licensure information · 51 Chapter 489 · 41, 47, 51 Chart of Accounts · 1, 2, 3 Circular E · 45, 53, 57, 58 Closing Adjustments · 26 Combined Ratios · 7 Completed Contract · 14, 15 Continuing Education · 50 contract · 14, 15, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 38, 39, 42, 43, 45, 47 credit · 3, 4, 6, 8, 12, 47, 50 Credit Balance · 1 Current Assets · 2, 6, 7, 21, 49 Current Liabilities · 10 Current Ratio · 6, 7 D debit · 3, 4, 12 Debit Balance · 1 Declining Balance Depreciation · 10, 11 Deferred Assets · 10 Deposit Penalties · 56 Depositing Taxes · 55 Depreciation Methods · 10 E Elements of a Contract · 29 Equity Account · 22 Essentials of an offer · 31 F FICA · 43, 44, 46, 53, 55, 57, 58 Fixed Assets · 4, 21 Form 940 · 53, 57 Form W-4 · 53, 57 Fringe Benefits · 54 Funds Flow Analysis · 24 FUTA · 43, 44, 46, 53, 54, 56, 57, 58 G Grounds for disciplinary · 52 I Income Statement · 3, 5, 6, 7, 15, 19, 20, 25, 48
  • 60. Brevard Contractors School 60 Prepare To Pass Copyright 2004 – 2006 © independent contractor · 44 Intangible Assets · 2, 10 IRS · 15, 44, 46, 50, 58 L last deposit date · 54 Lenders Ratios · 26 Liabilities · 1, 3, 4, 6, 7, 10, 21, 22, 49 Licensing · 41, 42, 47 Licensing Exemptions · 42 Licensing Requirements · 47 Long Term Receivables · 9 Long-Term Assets · 9 M MACRS · 10, 12, 13 Management Ratios: · 25 Markup from Cost · 27 Markup on Selling Price · 27 Markup Profit · 27 Mechanics' Lien Law · 37 N Net Profit · 20, 22 Net Worth · 1, 3, 4, 7, 21, 47, 48, 49 NET WORTH REPORTING · 47 Notes Receivable · 2, 9 Notice of Contest of Lien · 40 notice to owner · 38, 39, 52 O Owners Ratios · 25 P Penalties for Unlicensed Activity · 47 Percentage of Completion · 14, 15 Petty Cash Fund · 16, 17, 18 Prepaid Assets · 10 Q Qualifying Agent · 50 Quick Ratio · 6 R Receivables · 8, 9 Reconciling the Checkbook · 19 Record Keeping · 54 Registered Contractor · 47 Reserve for Bad Debts · 2, 8 Retainage · 2, 9 Retained Earnings · 3, 4, 21, 22 S secondary qualifying agent · 51 Sources and Application of Funds Method · 7 Sources and Uses of Funds Statement · 3, 5, 48 Sources and Uses of Funds Statement. · 3, 48 Sources of Capital · 23 Statute of Frauds · 31 Step by Step Bookkeeping · 14 Straight Line Depreciation for Real Estate · 13 Sub-Contractors · 43 Summary of Contract Law · 29 Summary of Operations · 5 Supplemental Wages · 54 T Tax rates · 55 Term of License · 50 The Balance Sheet · 21 The Builder's Guide to Accounting · 5 The Income Statement · 5, 19 The Law of Contracts · 29 The Statement of Cash Flows · 5, 23, 25 The Trial Balance · 26 U unilateral contract · 30 Uses or (applications) of Capital · 23 V Voucher · 16 W Working Capital · 7, 26
  • 61. Brevard Contractors School 61 Prepare To Pass Copyright 2004 – 2006 ©