SlideShare una empresa de Scribd logo
1 de 11
Descargar para leer sin conexión
10/15/04 1
Schedule Forecasting Methodology
Measurement of Potential Risks on High
Technology Projects
John Isom
Gray Research, Inc.
10/15/04 2
Contents
• Objective and Approach 3
• Schedule Reserve vs Liens & Threats Comparison 4
• Project Assessment Model 5
• Threats and Liens Schedule 6
• Vehicle Delivery Status Plot 7
• Events (Historical) 8-9
• Forecast Schedule Accuracy 10-11
PageSlide
10/15/04 3
Objective and Approach
• Approach developed by the Gravity Probe B business team and
applied to X-37.
• Identifies threats and liens above and beyond project risks.
These threats and liens could result in new project risks.
• Apply threats and liens to current contractor forecasts, based on
past contract performance and assessment by gov’t technical and
business experts.
• Method enables evaluation of the day-to-day project issues that
may impact critical path.
• As key technical risk and liens are “burned down” they are
removed from the forecast and retired. Forecast dates are
improved (if applicable).
10/15/04 4
Schedule Reserve vs Liens Threat Comparison
• Identify project liens and threats
• Durations not in the baselined plan (liens)
• Durations approved by Program Control Board (PCB) and in baselined schedule
plan (threats)
• Quantify unplanned durations in time (weeks, days, hours)
• Develop a realization factor (subjective assessment)
• Compute the total unplanned durations into a lien and threat amount.
• Develop schedule reserve
• Weekends are used for schedule reserve. Other methods can be used to develop
schedule reserve.
• Compare the actual schedule reserve plot to the liens and threats.
• Provides advance planning techniques by using quantifiable measures
of schedule risk.
10/15/04 5
Project Assessment Model
• Contractor realizes effects of plan
risks resulting in poor
performance.
• Contractor establishes new
forecast based on poor
performance driving schedule
logic.
• During performance, liens and
threats are identified outside of
the planned risk. Identified on a
daily basis and assessed.
• Govt. establishes new forecast
based on identified liens and
threats.
• Govt. tracks reserve plan vs.
actual reserve usage. In addition,
liens and threats plot is provided.
• Contractor realizes effects of plan
risks resulting in poor
performance.
• Contractor establishes new
forecast based on poor
performance driving schedule
logic.
• During performance, liens and
threats are identified outside of
the planned risk. Identified on a
daily basis and assessed.
• Govt. establishes new forecast
based on identified liens and
threats.
• Govt. tracks reserve plan vs.
actual reserve usage. In addition,
liens and threats plot is provided.
• Task in place with resources
• Contractor identified risks
monitored with Continuous Risk
Management (CRM)
• Budget reserve provided
• Task in place with resources
• Contractor identified risks
monitored with Continuous Risk
Management (CRM)
• Budget reserve provided
-80
-60
-40
-20
0
20
40
60
80
100
11/28
12/12
12/26
1/9
1/23
2/6
2/20
3/5
3/19
4/2
4/16
4/30
5/14
5/28
6/11
6/25
7/9
7/23
8/6
8/20
9/3
9/17
10/1
10/15
10/29
11/12
Days
Rollout Reserve
Rollout Reserve Remaining
Cont Slack
Rollout Threat and Liens
Exp. Finish
Baseline Plan Plan Risk
Early Finish
Planning
Exp.
Finish
Contractor
Est.
Risk Liens
Forecast
Finish Govt.
Est.
Actual Performance
Early Finish
Execution
FY04 FY05 FY06
J J A S O N D J F M A M J J A S O N
11 8/21
Sys Test 2 Start
Sys Test 3 Start
22 2
TRR
11/15
Contractor
Est.
VOP
11/25 2/9 Govt. Est VOP 33 3
FRR 44 4
1C TRR
FOCC Del
to Range
FCA/PCA AFSRB 55 5
11/15 11/25 2/9
11 22 33 44 55
1 2 3 4 5
Vehicle Assembly
System Test 1
Mechanical Installations
System Test 2
Thermal Systems Integration
System Test 3
Vehicle Prep
Vehicle Out of Plant
Ground Testing
Captive Carry Tests
Contractor Forecast
Govt. Forecast
Subcomponent CKT Testing
FY04 FY05 FY06
J J A S O N D J F M A M J J A S O N
11 8/21
Sys Test 2 Start
Sys Test 3 Start
22 2
TRR
11/15
Contractor
Est.
VOP
11/25 2/9 Govt. Est VOP 33 3
FRR 44 4
1C TRR
FOCC Del
to Range
FCA/PCA AFSRB 55 5
11/15 11/25 2/9
11 22 33 44 55
1 2 3 4 5
Vehicle Assembly
System Test 1
Mechanical Installations
System Test 2
Thermal Systems Integration
System Test 3
Vehicle Prep
Vehicle Out of Plant
Ground Testing
Captive Carry Tests
Contractor Forecast
Govt. Forecast
Subcomponent CKT Testing
10/15/04 6
Threats and Liens Schedule
FY04 FY05 FY06
J J A S O N D J F M A M J J A S O N
11 8/21
Sys Test 2 Start
Sys Test 3 Start
22 2
TRR
11/15
Contractor
Est.
VOP
11/25 2/9 Govt. Est VOP 33 3
FRR 44 4
1C TRR
FOCC Del
to Range
FCA/PCA AFSRB 55 5
11/15 11/25 2/9
11 22 33 44 55
1 2 3 4 5
Vehicle Assembly
System Test 1
Mechanical Installations
System Test 2
Thermal Systems Integration
System Test 3
Vehicle Prep
Vehicle Out of Plant
Ground Testing
Captive Carry Tests
Contractor Forecast
Govt. Forecast
Subcomponent CKT Testing
FY04 FY05 FY06
J J A S O N D J F M A M J J A S O N
11 8/21
Sys Test 2 Start
Sys Test 3 Start
22 2
TRR
11/15
Contractor
Est.
VOP
11/25 2/9 Govt. Est VOP 33 3
FRR 44 4
1C TRR
FOCC Del
to Range
FCA/PCA AFSRB 55 5
11/15 11/25 2/9
11 22 33 44 55
1 2 3 4 5
Vehicle Assembly
System Test 1
Mechanical Installations
System Test 2
Thermal Systems Integration
System Test 3
Vehicle Prep
Vehicle Out of Plant
Ground Testing
Captive Carry Tests
Contractor Forecast
Govt. Forecast
Subcomponent CKT Testing
10/15/04 7
Vehicle Delivery Status Plot
(Historical)
-62d Total
Slack
-80
100
11/28
12/12
12/26
1/9
1/23
2/6
2/20
3/5
3/19
4/2
4/16
4/30
5/14
5/28
6/11
6/25
7/9
7/23
8/6
8/20
9/3
9/17
10/1
10/15
10/2911/12
Rollout Reserve
Rollout Reserve Remaining
Cont. Slack
Rollout Threat and Liens
-61d Reserve
Remain
88d project risk
and liens
possible
Contractor to 6 day week
schedule available reserve 1 day
per week
Cont.
VOP
Est
8/26/04
Govt.
VOP Est
11/23/04
5 6 7
1
1
2 3
4
-60
-40
-20
0
20
40
60
80
Days
9 10
11
13
12
8
Definitions
Rollout Reserve – The weekly
burndown of planned reserve in days
(weekends).
Rollout Reserve Remaining – The
difference in reserve and contractor
calculated slack
Cont. Slack – The total number of
days of slack reported in the
Contractor Integrated Master
Schedule (IMS) (monthly input)
Rollout Threats and Liens – The
govt. calculated threats and liens
compiled during project meetings and
from other information sources.
Definitions
Rollout Reserve – The weekly
burndown of planned reserve in days
(weekends).
Rollout Reserve Remaining – The
difference in reserve and contractor
calculated slack
Cont. Slack – The total number of
days of slack reported in the
Contractor Integrated Master
Schedule (IMS) (monthly input)
Rollout Threats and Liens – The
govt. calculated threats and liens
compiled during project meetings and
from other information sources.
10/15/04 8
Events
(Historical)
Delays in Pallet and Cabling Fabrication
Delays in Completing Wirebird Testing, electrical component delivery delays
Electrical component delivery, Control Surfaces Fabrication, Flight Actuator/Controller, TPS
Fabrication and Installation delays. Improvement in Slack based on resolution of Testing
starting earlier using 3.0 S/W.
Delays in Flight Controllers delivery, TCS and TPS Installation fab and installation delays.
Improvement in slack status due to contractor going to 6 day work week. Greater
improvement if First flight slack and date than in the Rollout date. Rollout slack remains the
same but since more work days are involved, improved rollout date is the result.
Delays in the completion of pallet integration for testing. Component 1 the primary driver.
TPS installation could be the looming problem in the future. Contractor lacks the resources to
stay on plan.
Delay in start of test pushes out both rollout and FF by 5 days.
Delay in S/W Delivery.
Improved Threats and Liens due to completion of testing, Ruddervator lien added.
1
2
3
4
5
6
7
8
9
10/15/04 9
Events
(Historical)
Ruddervator Actuator Lien changed to a threat (within the Contractor schedule) increased to
effect 10 days due to contractor forecast of 7/15 completion of installation of LH Ruddervator
(Constraint to testing) and Pneumatic tubing lien added due to cleaning facility breakdown at
plant, may result in up to a week slip (Contractor working to resolve ASAP).
Cleaning facility back in action; realized 1 day slip in pneumatic tubing installation.
CKT Adapter procurements may delay testing up to a month.
CKT Adapter procurements will delay testing for one month, expected testing start to be now
7/15.
10
11
12
13
10/15/04 10
Forecast Accuracy
(Completed Activities)
• This schedule approach was implemented and forecasting of Test 1 validated this
approach.
• The following table summarizes the comparison of the contractor forecast to the
Govt. forecast.
Govt. Schedule
Update (Weekly)
Forecast
Date
Cont. DR
Submission
Forecast
Date
3/24/04 6/7/04 March-04 5/11/04
3/31/04 6/7/04
4/6/04 6/7/04 April-04 5/27/04
4/13/04 6/7/04
4/21/04 6/15/04
4/28/04 6/9/04
5/5/04 6/14/04 May-04 5/27/04
5/12/04 6/17/04
5/19/04 6/8/04
5/26/04 6/8/04
Test 1 Complete The Govt. generated
Threats and Lien’s not
included in the Contractor
plan correctly predicted
the completion of testing 3
months prior to the
contractor estimate. The
Contractor schedule did
not forecast the correct
end date until June 04.
Test1 was completed on 6/7/04
10/15/04 11
Forecast Accuracy
(Future Activities)
Contractor
provided a new
proposed baseline
schedule in July
2004. The new
dates coincide
more correctly with
the Govt. risk
schedule predicted
in June 2004.
Cont. Baseline
Cont. Forecast
Govt. Forecast
Cont. Proposed New
Baseline
FY04 FY05
N D J F M A M J J A S O N D J F M A M J J
Task
Test 1 Complete
Thermal Installation Comp.
Test 2 Complete
Test 3 Complete
Vehicle Out of Plant
Ground Operations
Captive Carry Complete
First Flight

Más contenido relacionado

La actualidad más candente

Mangold essential elements of risk assessment
Mangold essential elements of risk assessmentMangold essential elements of risk assessment
Mangold essential elements of risk assessment
LTDH2013
 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephen
NASAPMC
 
Resume Apr 2015
Resume Apr 2015Resume Apr 2015
Resume Apr 2015
Jim Reaves
 
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
MECConference
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPT
Euan Pirie
 
Devin Gavin Summer Intern
Devin Gavin Summer InternDevin Gavin Summer Intern
Devin Gavin Summer Intern
Devin Gavin
 
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape
 
HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15
Euan Pirie
 

La actualidad más candente (20)

Roberto Guevara-CV
Roberto Guevara-CVRoberto Guevara-CV
Roberto Guevara-CV
 
Final Proposal
Final ProposalFinal Proposal
Final Proposal
 
Mangold essential elements of risk assessment
Mangold essential elements of risk assessmentMangold essential elements of risk assessment
Mangold essential elements of risk assessment
 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephen
 
Resume Apr 2015
Resume Apr 2015Resume Apr 2015
Resume Apr 2015
 
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
 
Alaska LNG Project Update (10.30.2015)
Alaska LNG Project Update (10.30.2015)Alaska LNG Project Update (10.30.2015)
Alaska LNG Project Update (10.30.2015)
 
Improve Tollgate
Improve TollgateImprove Tollgate
Improve Tollgate
 
Define Tollgate
Define TollgateDefine Tollgate
Define Tollgate
 
Tpqma r5 to upload in slide share
Tpqma r5 to upload in slide shareTpqma r5 to upload in slide share
Tpqma r5 to upload in slide share
 
CV Shray Jain
CV Shray Jain CV Shray Jain
CV Shray Jain
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPT
 
Devin Gavin Summer Intern
Devin Gavin Summer InternDevin Gavin Summer Intern
Devin Gavin Summer Intern
 
DRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio ExampleDRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio Example
 
Cv's Nitinai_Ratchawat
Cv's Nitinai_RatchawatCv's Nitinai_Ratchawat
Cv's Nitinai_Ratchawat
 
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
 
Analyze Tollgate
Analyze TollgateAnalyze Tollgate
Analyze Tollgate
 
Maryland Register - Nov 14, 2016 - New Fracking Rules
Maryland Register - Nov 14, 2016 - New Fracking RulesMaryland Register - Nov 14, 2016 - New Fracking Rules
Maryland Register - Nov 14, 2016 - New Fracking Rules
 
RFP-Test-Design_Psychometrics-2011
RFP-Test-Design_Psychometrics-2011RFP-Test-Design_Psychometrics-2011
RFP-Test-Design_Psychometrics-2011
 
HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15HM hub and NPD first masterclass seminar 6.10.15
HM hub and NPD first masterclass seminar 6.10.15
 

Similar a 03-2004PDS_Technology_Isom

Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & Integration
Prachi Dikshit
 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7
Michael Cary
 
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhdGL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
nithinnick66
 
Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)
Dylan Gonsalves
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CV
Sajith Nair
 

Similar a 03-2004PDS_Technology_Isom (20)

PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & Integration
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7
 
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhdGL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
 
Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
(Technical paper) Cis utilization of earned value management for monitoring p...
(Technical paper) Cis utilization of earned value management for monitoring p...(Technical paper) Cis utilization of earned value management for monitoring p...
(Technical paper) Cis utilization of earned value management for monitoring p...
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
The construction programme - assurance and controls
The construction programme - assurance and controlsThe construction programme - assurance and controls
The construction programme - assurance and controls
 
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CV
 
MOHAMMAD Updated CV
MOHAMMAD Updated CV MOHAMMAD Updated CV
MOHAMMAD Updated CV
 
Essential program management views
Essential program management viewsEssential program management views
Essential program management views
 

03-2004PDS_Technology_Isom

  • 1. 10/15/04 1 Schedule Forecasting Methodology Measurement of Potential Risks on High Technology Projects John Isom Gray Research, Inc.
  • 2. 10/15/04 2 Contents • Objective and Approach 3 • Schedule Reserve vs Liens & Threats Comparison 4 • Project Assessment Model 5 • Threats and Liens Schedule 6 • Vehicle Delivery Status Plot 7 • Events (Historical) 8-9 • Forecast Schedule Accuracy 10-11 PageSlide
  • 3. 10/15/04 3 Objective and Approach • Approach developed by the Gravity Probe B business team and applied to X-37. • Identifies threats and liens above and beyond project risks. These threats and liens could result in new project risks. • Apply threats and liens to current contractor forecasts, based on past contract performance and assessment by gov’t technical and business experts. • Method enables evaluation of the day-to-day project issues that may impact critical path. • As key technical risk and liens are “burned down” they are removed from the forecast and retired. Forecast dates are improved (if applicable).
  • 4. 10/15/04 4 Schedule Reserve vs Liens Threat Comparison • Identify project liens and threats • Durations not in the baselined plan (liens) • Durations approved by Program Control Board (PCB) and in baselined schedule plan (threats) • Quantify unplanned durations in time (weeks, days, hours) • Develop a realization factor (subjective assessment) • Compute the total unplanned durations into a lien and threat amount. • Develop schedule reserve • Weekends are used for schedule reserve. Other methods can be used to develop schedule reserve. • Compare the actual schedule reserve plot to the liens and threats. • Provides advance planning techniques by using quantifiable measures of schedule risk.
  • 5. 10/15/04 5 Project Assessment Model • Contractor realizes effects of plan risks resulting in poor performance. • Contractor establishes new forecast based on poor performance driving schedule logic. • During performance, liens and threats are identified outside of the planned risk. Identified on a daily basis and assessed. • Govt. establishes new forecast based on identified liens and threats. • Govt. tracks reserve plan vs. actual reserve usage. In addition, liens and threats plot is provided. • Contractor realizes effects of plan risks resulting in poor performance. • Contractor establishes new forecast based on poor performance driving schedule logic. • During performance, liens and threats are identified outside of the planned risk. Identified on a daily basis and assessed. • Govt. establishes new forecast based on identified liens and threats. • Govt. tracks reserve plan vs. actual reserve usage. In addition, liens and threats plot is provided. • Task in place with resources • Contractor identified risks monitored with Continuous Risk Management (CRM) • Budget reserve provided • Task in place with resources • Contractor identified risks monitored with Continuous Risk Management (CRM) • Budget reserve provided -80 -60 -40 -20 0 20 40 60 80 100 11/28 12/12 12/26 1/9 1/23 2/6 2/20 3/5 3/19 4/2 4/16 4/30 5/14 5/28 6/11 6/25 7/9 7/23 8/6 8/20 9/3 9/17 10/1 10/15 10/29 11/12 Days Rollout Reserve Rollout Reserve Remaining Cont Slack Rollout Threat and Liens Exp. Finish Baseline Plan Plan Risk Early Finish Planning Exp. Finish Contractor Est. Risk Liens Forecast Finish Govt. Est. Actual Performance Early Finish Execution FY04 FY05 FY06 J J A S O N D J F M A M J J A S O N 11 8/21 Sys Test 2 Start Sys Test 3 Start 22 2 TRR 11/15 Contractor Est. VOP 11/25 2/9 Govt. Est VOP 33 3 FRR 44 4 1C TRR FOCC Del to Range FCA/PCA AFSRB 55 5 11/15 11/25 2/9 11 22 33 44 55 1 2 3 4 5 Vehicle Assembly System Test 1 Mechanical Installations System Test 2 Thermal Systems Integration System Test 3 Vehicle Prep Vehicle Out of Plant Ground Testing Captive Carry Tests Contractor Forecast Govt. Forecast Subcomponent CKT Testing FY04 FY05 FY06 J J A S O N D J F M A M J J A S O N 11 8/21 Sys Test 2 Start Sys Test 3 Start 22 2 TRR 11/15 Contractor Est. VOP 11/25 2/9 Govt. Est VOP 33 3 FRR 44 4 1C TRR FOCC Del to Range FCA/PCA AFSRB 55 5 11/15 11/25 2/9 11 22 33 44 55 1 2 3 4 5 Vehicle Assembly System Test 1 Mechanical Installations System Test 2 Thermal Systems Integration System Test 3 Vehicle Prep Vehicle Out of Plant Ground Testing Captive Carry Tests Contractor Forecast Govt. Forecast Subcomponent CKT Testing
  • 6. 10/15/04 6 Threats and Liens Schedule FY04 FY05 FY06 J J A S O N D J F M A M J J A S O N 11 8/21 Sys Test 2 Start Sys Test 3 Start 22 2 TRR 11/15 Contractor Est. VOP 11/25 2/9 Govt. Est VOP 33 3 FRR 44 4 1C TRR FOCC Del to Range FCA/PCA AFSRB 55 5 11/15 11/25 2/9 11 22 33 44 55 1 2 3 4 5 Vehicle Assembly System Test 1 Mechanical Installations System Test 2 Thermal Systems Integration System Test 3 Vehicle Prep Vehicle Out of Plant Ground Testing Captive Carry Tests Contractor Forecast Govt. Forecast Subcomponent CKT Testing FY04 FY05 FY06 J J A S O N D J F M A M J J A S O N 11 8/21 Sys Test 2 Start Sys Test 3 Start 22 2 TRR 11/15 Contractor Est. VOP 11/25 2/9 Govt. Est VOP 33 3 FRR 44 4 1C TRR FOCC Del to Range FCA/PCA AFSRB 55 5 11/15 11/25 2/9 11 22 33 44 55 1 2 3 4 5 Vehicle Assembly System Test 1 Mechanical Installations System Test 2 Thermal Systems Integration System Test 3 Vehicle Prep Vehicle Out of Plant Ground Testing Captive Carry Tests Contractor Forecast Govt. Forecast Subcomponent CKT Testing
  • 7. 10/15/04 7 Vehicle Delivery Status Plot (Historical) -62d Total Slack -80 100 11/28 12/12 12/26 1/9 1/23 2/6 2/20 3/5 3/19 4/2 4/16 4/30 5/14 5/28 6/11 6/25 7/9 7/23 8/6 8/20 9/3 9/17 10/1 10/15 10/2911/12 Rollout Reserve Rollout Reserve Remaining Cont. Slack Rollout Threat and Liens -61d Reserve Remain 88d project risk and liens possible Contractor to 6 day week schedule available reserve 1 day per week Cont. VOP Est 8/26/04 Govt. VOP Est 11/23/04 5 6 7 1 1 2 3 4 -60 -40 -20 0 20 40 60 80 Days 9 10 11 13 12 8 Definitions Rollout Reserve – The weekly burndown of planned reserve in days (weekends). Rollout Reserve Remaining – The difference in reserve and contractor calculated slack Cont. Slack – The total number of days of slack reported in the Contractor Integrated Master Schedule (IMS) (monthly input) Rollout Threats and Liens – The govt. calculated threats and liens compiled during project meetings and from other information sources. Definitions Rollout Reserve – The weekly burndown of planned reserve in days (weekends). Rollout Reserve Remaining – The difference in reserve and contractor calculated slack Cont. Slack – The total number of days of slack reported in the Contractor Integrated Master Schedule (IMS) (monthly input) Rollout Threats and Liens – The govt. calculated threats and liens compiled during project meetings and from other information sources.
  • 8. 10/15/04 8 Events (Historical) Delays in Pallet and Cabling Fabrication Delays in Completing Wirebird Testing, electrical component delivery delays Electrical component delivery, Control Surfaces Fabrication, Flight Actuator/Controller, TPS Fabrication and Installation delays. Improvement in Slack based on resolution of Testing starting earlier using 3.0 S/W. Delays in Flight Controllers delivery, TCS and TPS Installation fab and installation delays. Improvement in slack status due to contractor going to 6 day work week. Greater improvement if First flight slack and date than in the Rollout date. Rollout slack remains the same but since more work days are involved, improved rollout date is the result. Delays in the completion of pallet integration for testing. Component 1 the primary driver. TPS installation could be the looming problem in the future. Contractor lacks the resources to stay on plan. Delay in start of test pushes out both rollout and FF by 5 days. Delay in S/W Delivery. Improved Threats and Liens due to completion of testing, Ruddervator lien added. 1 2 3 4 5 6 7 8 9
  • 9. 10/15/04 9 Events (Historical) Ruddervator Actuator Lien changed to a threat (within the Contractor schedule) increased to effect 10 days due to contractor forecast of 7/15 completion of installation of LH Ruddervator (Constraint to testing) and Pneumatic tubing lien added due to cleaning facility breakdown at plant, may result in up to a week slip (Contractor working to resolve ASAP). Cleaning facility back in action; realized 1 day slip in pneumatic tubing installation. CKT Adapter procurements may delay testing up to a month. CKT Adapter procurements will delay testing for one month, expected testing start to be now 7/15. 10 11 12 13
  • 10. 10/15/04 10 Forecast Accuracy (Completed Activities) • This schedule approach was implemented and forecasting of Test 1 validated this approach. • The following table summarizes the comparison of the contractor forecast to the Govt. forecast. Govt. Schedule Update (Weekly) Forecast Date Cont. DR Submission Forecast Date 3/24/04 6/7/04 March-04 5/11/04 3/31/04 6/7/04 4/6/04 6/7/04 April-04 5/27/04 4/13/04 6/7/04 4/21/04 6/15/04 4/28/04 6/9/04 5/5/04 6/14/04 May-04 5/27/04 5/12/04 6/17/04 5/19/04 6/8/04 5/26/04 6/8/04 Test 1 Complete The Govt. generated Threats and Lien’s not included in the Contractor plan correctly predicted the completion of testing 3 months prior to the contractor estimate. The Contractor schedule did not forecast the correct end date until June 04. Test1 was completed on 6/7/04
  • 11. 10/15/04 11 Forecast Accuracy (Future Activities) Contractor provided a new proposed baseline schedule in July 2004. The new dates coincide more correctly with the Govt. risk schedule predicted in June 2004. Cont. Baseline Cont. Forecast Govt. Forecast Cont. Proposed New Baseline FY04 FY05 N D J F M A M J J A S O N D J F M A M J J Task Test 1 Complete Thermal Installation Comp. Test 2 Complete Test 3 Complete Vehicle Out of Plant Ground Operations Captive Carry Complete First Flight