SlideShare una empresa de Scribd logo
1 de 19
Earned Value
Management
What is Earned
Value
Management?
Earned Value Management (EVM) is comprised
of several formulas that provide an analysis of a
project and its current state regarding budget
and schedule.
EARNED VALUE
MANAGEMENT:
DEFINITION OF VALUES
Budget At
Completion
(BAC)
The Planned
Expected Costs to
Complete the Project
Actual Cost
(AC)
The actual amount of
money spent at a
given point
Planned
Value (PV)
The value of the work that should have
been completed at any given point for the
total project to remain on budget and
schedule
PV =
(Planned Percentage Completed)
Multiplied by the Budget At Completion
(BAC)
Planned
Value (PV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
15% X $20,000 = $3,000
Planned Value = $3,000
Earned
Value (EV)
The estimated value of the work
completed at any given point
EV = (Actual Percentage
Completed) X BAC
Earned Value
(EV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
12% X $20,000 = $2,400
Earned Value = $2,400
Cost
Variance
(CV)
The difference between the Earned Value
(EV) and the Actual Cost (AC) that shows
how much ahead or behind in the budget
the project is at any given point
A negative CV is the amount the project is
over budget
A positive CV is the amount the project is
under budget
Cost
Variance
(CV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
$2,400 - $3,000 = -$600
Cost Variance = -$600
This Project is over budget
Cost
Performance
Index (CPI)
An indicator into the speed or rate of spending compared
to the value being generated (Is the project budget on
track)
CPI less than 1 shows the project is spending too fast and is
over budget
CPI equal to 1 shows the project budget is on track
CPI greater than 1 shows the project is under budget
Cost Performance Index = Earned Value Divided by Actual
Cost
Cost
Performance
Index (CPI):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
•Cost Variance: -$600
$2,400/$3,000 = 0.8
Cost Performance Index = 0.8
This Project is over budget
Schedule
Variance
(SV)
The difference between the planned work
completed versus the amount of work that
was completed
A negative SV is an estimate of how much
the project is behind schedule
A positive SV is an estimate of how much
the project is ahead of schedule
Schedule Variance = Earned Value – Planned
Value
Schedule
Variance
(SV):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
•Cost Variance: -$600
•Cost Performance Index: 0.8
$2,400 - $3,000 = -$600
Schedule Variance = -$600
This Project is $600 worth of work
behind schedule
Schedule
Performance
Index (SPI)
The indicator into the speed or rate of the work being getting
completed compared to the work that was expected to be
completed
SPI less than 1 shows the project as being behind schedule
SPI equal to 1 shows the project as being on track
SPI greater than 1 shows that the project is ahead of
schedule
Schedule Performance Index = Earned Value divided by
Planned Value
Schedule
Performance
Index (SPI):
Example
•Budget At Completion: $20,000
•Planned Schedule Duration: 100 Days
•Current Day in the Project: 15 Days
•Actual Work Completed: 12%
•Actual Costs (AC): $3,000
•Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15%
•Planned Value: $3,000
•Earned Value: $2,400
•Cost Variance: -$600
•Cost Performance Index: 0.8
•Schedule Variance: -$600
$2,400/$3,000 = 0.8
Schedule Performance Index = 0.8
This Project is behind schedule
Other EVM Values
Estimate At Completion
(EAC)
• Based on the current
spending rate, EAC is
an estimate of how
much it will actually
cost to complete the
whole project
• EAC = BAC/CPI
Estimate To Completion
(ETC)
• Based on the current
spending rate, ETC is an
estimate of how much
it will actually cost
from a specified point
forward to complete
the project; it is simply
the EAC minus the
current actual costs
• ETC = EAC – AC
Variance At Completion
(VAC)
• The difference
between the planned
budget (BAC) and the
new forecast budget
(EAC)
• VAC = BAC – EAC
To-Complete
Performance Index
• An estimate of how
hard it would be to
meet the project’s
objectives
• TCPI (BAC – EV)/(BAC –
AC)
Earned Value
Management
Joshua Render
https://agile-mercurial.com
https://twentyfirstcenturyworkfor
ce.com/

Más contenido relacionado

La actualidad más candente

09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureCOEPD HR
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value AnalysisDavidMcLachlan1
 
Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and schedulingSulman Ahmed
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 

La actualidad más candente (20)

09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and scheduling
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Project quality management.ppt msm
Project quality management.ppt msmProject quality management.ppt msm
Project quality management.ppt msm
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 

Similar a Earned value management (EVM)

Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationGhassan Kabbara
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptAsBali1
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringNitish Kumar
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6HARDIK PARIKH
 

Similar a Earned value management (EVM) (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in Organization
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
 
Earned value management
Earned value managementEarned value management
Earned value management
 

Más de Joshua Render

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Joshua Render
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivationJoshua Render
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZJoshua Render
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelJoshua Render
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelJoshua Render
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of LeanJoshua Render
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story CreationJoshua Render
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaJoshua Render
 
Procurement Management Knowledge Area
Procurement Management Knowledge AreaProcurement Management Knowledge Area
Procurement Management Knowledge AreaJoshua Render
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge AreaJoshua Render
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge AreaJoshua Render
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge AreaJoshua Render
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge AreaJoshua Render
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?Joshua Render
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge AreaJoshua Render
 

Más de Joshua Render (20)

Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?Setting SMART Goals - What are SMART Goals?
Setting SMART Goals - What are SMART Goals?
 
Alderfer's ERG theory of motivation
Alderfer's ERG theory of motivationAlderfer's ERG theory of motivation
Alderfer's ERG theory of motivation
 
MacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory ZMacGregor’s XY Theory and Ouchi’s Theory Z
MacGregor’s XY Theory and Ouchi’s Theory Z
 
Big Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor ModelBig Five Personality Traits: The Five Factor Model
Big Five Personality Traits: The Five Factor Model
 
Drexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance ModelDrexler-Sibbet Team Performance Model
Drexler-Sibbet Team Performance Model
 
What is Kanban?
What is Kanban?What is Kanban?
What is Kanban?
 
7 Core Concepts of Lean
7 Core Concepts of Lean7 Core Concepts of Lean
7 Core Concepts of Lean
 
Guide to User Story Creation
Guide to User Story CreationGuide to User Story Creation
Guide to User Story Creation
 
Tuckman's Model
Tuckman's ModelTuckman's Model
Tuckman's Model
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Stakeholder Management Knowledge Area
Stakeholder Management Knowledge AreaStakeholder Management Knowledge Area
Stakeholder Management Knowledge Area
 
Procurement Management Knowledge Area
Procurement Management Knowledge AreaProcurement Management Knowledge Area
Procurement Management Knowledge Area
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge Area
 
Communication Management Knowledge Area
Communication Management Knowledge AreaCommunication Management Knowledge Area
Communication Management Knowledge Area
 
Resource Management Knowledge Area
Resource Management Knowledge AreaResource Management Knowledge Area
Resource Management Knowledge Area
 
Quality Management Knowledge Area
Quality Management Knowledge AreaQuality Management Knowledge Area
Quality Management Knowledge Area
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
What is Osmotic Communication?
What is Osmotic Communication?What is Osmotic Communication?
What is Osmotic Communication?
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 

Último

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 

Último (20)

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 

Earned value management (EVM)

  • 2. What is Earned Value Management? Earned Value Management (EVM) is comprised of several formulas that provide an analysis of a project and its current state regarding budget and schedule.
  • 4. Budget At Completion (BAC) The Planned Expected Costs to Complete the Project
  • 5. Actual Cost (AC) The actual amount of money spent at a given point
  • 6. Planned Value (PV) The value of the work that should have been completed at any given point for the total project to remain on budget and schedule PV = (Planned Percentage Completed) Multiplied by the Budget At Completion (BAC)
  • 7. Planned Value (PV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% 15% X $20,000 = $3,000 Planned Value = $3,000
  • 8. Earned Value (EV) The estimated value of the work completed at any given point EV = (Actual Percentage Completed) X BAC
  • 9. Earned Value (EV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 12% X $20,000 = $2,400 Earned Value = $2,400
  • 10. Cost Variance (CV) The difference between the Earned Value (EV) and the Actual Cost (AC) that shows how much ahead or behind in the budget the project is at any given point A negative CV is the amount the project is over budget A positive CV is the amount the project is under budget
  • 11. Cost Variance (CV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 $2,400 - $3,000 = -$600 Cost Variance = -$600 This Project is over budget
  • 12. Cost Performance Index (CPI) An indicator into the speed or rate of spending compared to the value being generated (Is the project budget on track) CPI less than 1 shows the project is spending too fast and is over budget CPI equal to 1 shows the project budget is on track CPI greater than 1 shows the project is under budget Cost Performance Index = Earned Value Divided by Actual Cost
  • 13. Cost Performance Index (CPI): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 •Cost Variance: -$600 $2,400/$3,000 = 0.8 Cost Performance Index = 0.8 This Project is over budget
  • 14. Schedule Variance (SV) The difference between the planned work completed versus the amount of work that was completed A negative SV is an estimate of how much the project is behind schedule A positive SV is an estimate of how much the project is ahead of schedule Schedule Variance = Earned Value – Planned Value
  • 15. Schedule Variance (SV): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 •Cost Variance: -$600 •Cost Performance Index: 0.8 $2,400 - $3,000 = -$600 Schedule Variance = -$600 This Project is $600 worth of work behind schedule
  • 16. Schedule Performance Index (SPI) The indicator into the speed or rate of the work being getting completed compared to the work that was expected to be completed SPI less than 1 shows the project as being behind schedule SPI equal to 1 shows the project as being on track SPI greater than 1 shows that the project is ahead of schedule Schedule Performance Index = Earned Value divided by Planned Value
  • 17. Schedule Performance Index (SPI): Example •Budget At Completion: $20,000 •Planned Schedule Duration: 100 Days •Current Day in the Project: 15 Days •Actual Work Completed: 12% •Actual Costs (AC): $3,000 •Planned Percent Completed: 15 Days / 100 Days = 0.15 = 15% •Planned Value: $3,000 •Earned Value: $2,400 •Cost Variance: -$600 •Cost Performance Index: 0.8 •Schedule Variance: -$600 $2,400/$3,000 = 0.8 Schedule Performance Index = 0.8 This Project is behind schedule
  • 18. Other EVM Values Estimate At Completion (EAC) • Based on the current spending rate, EAC is an estimate of how much it will actually cost to complete the whole project • EAC = BAC/CPI Estimate To Completion (ETC) • Based on the current spending rate, ETC is an estimate of how much it will actually cost from a specified point forward to complete the project; it is simply the EAC minus the current actual costs • ETC = EAC – AC Variance At Completion (VAC) • The difference between the planned budget (BAC) and the new forecast budget (EAC) • VAC = BAC – EAC To-Complete Performance Index • An estimate of how hard it would be to meet the project’s objectives • TCPI (BAC – EV)/(BAC – AC)