Construction Update 3-31-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 3/31/2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
3/29/2010
Current Activities this Week:
Mass Excavation:
Mass Excavation Activities in the Main Bowl continues
In Areas 2 and 3.
.
Site Utilities:
Installation of the new electrical ductbank has started.
Area 3 – Excavation continues at south end
Excavation for the manhole on sanitary line D is of Area 3.
complete. Boring for the service line for Sanitary Line
D is ongoing.
Foundations:
Area 1 Field Level – Column Pads excavation and
Concrete placement is ongoing.
Area 1 Field Level – D-Line wall placement is complete.
Soil Nail Wall:
Area 1 – Shotcrete installation on the 4th lift is ongoing.
Concourse Level Area 2 – Electrical Duct
nd
Area 2 – Shotcrete installation is ongoing on the 2 and bank re-location .
3rd lifts.
Field Level Area 1 – D-Line Foundation Wall
tie in at Soil Nail Shoring Wall.
Building the Future
2. Projected Activities occurring next Week:
Mass Excavation:
Remaining mass excavation activities will be nearing
completion. Removal of the haul road will begin.
Site Utilities:
Field Level Area 1 – Concrete placement for
Installation of the new electrical ductback will continue.
elevator 2/3 slab.
Boring under the Field Level D-Line Wall
for the Sanitary Main Line D will begin.
Foundations:
Area 1 Concourse Level – Backfilling of D-Line
wall will continue for section placed this week.
Area 1 Field Level – A-Line footing placement will
continue south towards 19.5 Line.
Field Level Area 1 – Formwork in place for
Soil Nail Wall: north vomitory wall at Player Field Entrance.
Area 2 – Shotcrete placement on the 2nd and 3rd lifts will
continue.
Area 2 – Shotcrete wall installation
continues on 2nd and 3rd lifts.
Building the Future
3. Additional Photos:
A shot of Area 1 from the Main Concourse Field Level Area 1 – Backfill, compaction and
Level. insulation behind D/SSB-Line Walls.
Area 1 – Column pad rebar cages pre-tied. Field Level Area 1 – Column pad excavation
at C-Line.
Field Level Area 1 – Column pad ready for Area 2 – Preparation for the soil nail pull
concrete. test.