1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 4/14/2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
4/12/2010
Current Activities this Week:
Mass Excavation:
Remaining Mass Excavation Activities are ongoing
and are nearling completion. Removal of the Haul Road
to Area C is complete and restoration of the Speedway
Property is ongoing.
Site Utilities: Speedway Property – Sod and seeding
Installation of the new electrical ductbank is ongoing. installation has commenced.
Approximately 150 linear feet is installed. Awaiting
BPU resolution on manhole tie-in.
Boring of the service line and Sanitary Main Line
D is complete, installation of the steel casing is ongoing.
Foundations:
Area 1 Field Level – Column Pad placement in Area 1
is nearly complete. Installation of Field Walls has
started. Concourse Level Area 2 – Waterline
relocation piping is nearly complete and
Area 1 Mezzanine Level – E-Line Footing installation backfill of line has started.
is complete. E-Line Wall installation is ongoing.
Area 1 Concourse Level – E-Line Footing installation
Has started at Column Line 23.2.
Area 2 Field Level – Excavation for the footings has
started.
Field Level Area 2 – Soil nail wall installation
on remaining section (east of Column Line
14) has commenced.
Building the Future
2. Soil Nail Wall:
Area 2 – Shotcrete installation on the remaining sections
has begun.
Structural Steel Erection:
Field Bowl – 300 Ton Crane has been mobilized and
assembled (230’ Boom Length).
Projected Activities occurring next Week: Field Level Area 2 – Excavation for A-Line
footing has started.
Mass Excavation:
Removal of the ledges for soil nail wall installation will
continue to be removed.
Site Utilities:
Waterline relocation will be complete.
Installation of the Sanitary Manhole at the North end of
Area 1 will begin.
Field Level Bowl – Crane assembly
Installation of the Storm Line on the East Side (France underway.
Family Drive) of the site will begin.
Deep Underground Sanitary in Area 1/2 will continue.
Foundations:
Area 2 Field Level – Placement of footings around stage
will begin.
Area 1 Mezzanine Level – Drilled Pier installation at D-Line
will begin.
Field Level Area 1 – Shot looking north from
Area 1 Concourse Level – E-Line footing will be completed. Concourse Level showing column pads and
deep underground sanitary line installation.
Soil Nail Wall:
Area 2 – Shotcrete wall installation east of Column 13
will continue.
Structural Steel Erection:
Erection of Structural Steel Sequence 1-1 will begin.
Building the Future
3. Additional Photos:
Field Level Area 1 – Field Wall installation is
ongoing at the base of the north section of Field Level Area 1 – Placement of Elevator
on-grade seating. F1 Pit Walls.
Mezzanine Level Area 1 – Placement of
concrete for D-Line Wall and Rebar set in Concourse Level Area 1 – E-Line Footing
place for E-Line Wall at VIP Entrance. Placement at Column Line 23.2
Mezzanine Level Area 1 – Steel Casing
installation under Village West Parkway for Field Level Area 1/2 – Making the turn from
Sanitary Main Line. Area 1 into Area 2 with Foundations.
Building the Future