1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 6.16.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
6.14.2010
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 1,
Area 2 and Area 3.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on Field Level Area 1 – Shallow Underground
east side of France Family Drive. plumbing pipe installation ongoing at Aux
Locker Rooms.
Sanitary Sewer Line E installation is ongoing on east
side of France Family Dive.
Foundations:
Area 2 Concourse Level – E-Line footing installation is
complete to column line 14.
Area 3 Field Level – A-Line wall (to column line 1) is
complete.
Area 3 Field Level – Isolated footing installation is Field Level Area 3 – A-Line wall installation is
ongoing. complete to Column Line 1.
Concrete Flatwork:
Area 1 – Mezzanine slab-on deck is complete, Main
Concourse structural slab is complete, Suite Level slab
on deck is complete from column line 23-32.
Area 1 – Underslab MEP rough-in is ongoing on Press
Level.
Suite Level – Concrete Slab on Metal Deck is
complete from Column Line 23 - 32.
Building the Future
2. Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-5 complete. Steel
Erection in sequence 1-3 is ongoing.
Decking/Detailing/Studs/Edge Angle is nearly complete in
Sequence 1-5.
Underground MEP:
Deep Sanitary installation is ongoing in Area 3. Area 1 – Structural Steel Erection Sequence
1-3 in underway (outdoor terrace area).
Electrical Secondary is ongoing in Area 2.
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks are
ongoing at Press Level. Shallow plumbing rough-in is
ongoing at Area 1 Field Level.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3. Rough grading of field will continue. Area 1 – Structural Steel Erection at West
Building is complete from Column Line 33 –
Site Utilities: 23. Decking is ongoing on the Press Level.
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 5000 and
4000 will begin. Installation of Sanitary Line E will continue.
Deep Underground Plumbing:
Deep Sanitary installation in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Area 4 Mezzanine Level – Foundation Wall installation will Concourse Level Area 2 – Backfill of E-Line
begin. walls are ongoing. This area is where
southwest concourse restrooms and
Concrete Flatwork: concessions are located.
Area 1 Press Level – Concrete placement will begin.
Building the Future
3. Structural Steel Erection:
Erection of Structural Steel in Sequence 1-3 will
continue.
Delivery of Roof Trusses for sequence 1-7 will begin to
arrive on site.
Structural Precast: Field Level Area 2 – Shot looking south (from
Erection of the precast risers and tubs will begin. Suite Level Column Line 32) of south
foundation walls.
Underground MEP:
Deep Sanitary installation will continue in Area 3.
Electrical Secondary will continue in Area 2
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks will
continue at Press Level. Shallow plumbing rough-in will
continue at Area 1 Field Level. Shallow electrical will
begin at Area 1 Field Level. Suite Level Area 1 – Steel edge plate
installation ongoing at Roof Level.
Building the Future
4. Additional Photos:
Area 1 – Shot looking at East Elevation of Suite Level – Concrete placed at exterior
the West Building. walkway outside of Lower Suite Lounge.
Press Level – Underslab MEP rough-in
ongoing prior to reinforcing steel Mezzanine Level Area 4 – Wall form
installation. installation is ongoing.
Concourse Level Area 1 – Ironworkers Field Level Area 1 – Electrical conduits
installing one of the numerous pieces of penetrating D-Line wall into electrical room
steel in Sequence 1-3. between Column Line 30 – 30.5.