517619-LLP-1-2011-1-GR-GRUNDTVIG-GMP
13-14 December 2011| Athens – Greece
Dimitris Raftopoulos
Strategic Leadership Unit
Day 1 - Presentation Outline
2
 Presentation of partners and their activity
 Presentation of the Project
 Concept of the Project: Background, Aims and Objectives
 Project Management
 Administrative Rules, Reporting, Filling System
 Financial Management
 Projects’ Action Plan
 Implementation Methodology, Presentation of the Work Packages,
Projects’ activities and deadlines, Analysis of Activities per Work
Package and PP
 Lunch
 Presentation of the Project (cont.)
 Dinner
Presentation of PPs and their activity
 3L Research Institute, Greece
 University of Strathclyde, UK
 Folkuniversitetet, Sweden
 University of Social Sciences, Poland
 Documenta, Spain
4
Framework
 Aim of GRUNDTVIG Multilateral projects
 Achieving concrete and innovative results/products with
indisputable European value. In many cases, this will involve
piloting experiences in strategic areas and producing
teaching products of high quality (strengthen the European
dimension in the field of adult learning)
5
Background
 Lisbon Strategy stated that Europe should “become the most competitive and
dynamic knowledge-based economy in the world, capable of sustainable
economic growth with more and better jobs and greater social cohesion”
 The inclusion of the ageing workforce which is an important priority of the European
social agenda
 Directive 2000/78/EC, which aims at combating discrimination on the grounds of
age as regards employment and occupation
 Many enterprises, particularly in a time of economic crisis, adopt strategies which
adversely affect older workers, through, for example, early retirement or
redundancy programmes
 Concretely the challenge consists in making the workplace more suitable for the
ageing workforce who owns the knowledge and offer them well adapted jobs or
actions and training to take advantage of their skills, while putting in place
capitalisation processes and train new comers
6
Presentation of the Project
Aims
7
Main Objective
 Study how innovative management approaches,
based on ICT, can generate concepts to answer the
urgent European situation made out of low
employment of older workers, shortage of critical
skills and decline of birth rate
8
Objectives
 Improve existing age management methods
 Introduce new organizational business concepts
for the improvement of the employability of the
aged workforce within the operational
framework of the enterprise
 Develop all the necessary tools in order to
minimise the impact of age barriers and age
discriminatory approaches in job recruitment
and training with the development of new
business concepts
 Identify the most appropriate fields of
employment for the aged workforce in order to
promote the employability of the aged
workforce
 Promote the activation and better use of the
capacities of aged personnel
 Identify new business-oriented qualifications for
the aged personnel in order to improve their
skills and capacities
 Elaborate a Strategy Plan in order to meet
future demographic needs
 Explore existing practices being used to
encourage older worker participation in
lifelong learning
 Develop innovative ways of encouraging
older adult participation and understanding
of VET/CVET
 Create training programmes that encourages
older worker participation and breaks down
barriers to learning
 Create training programmes for age
management concept
 Work closely with employers across a range of
industry sectors to educate and inform them on
age management concept and vocational
training for older workers
9
Project Management
10
 Administrative Rules
 Project Handbook (included in the Booklet)
 Project and Financial Officers
 Meeting in Brussels for the Coordinators (19-20/01/2012)
 Reporting system
 Two part process for claiming: Completion of Financial
Claim and Progress Report
 Quality assurance – will help with providing data for
Interim/Final reports
 Filling System
Financial Management & Reporting
 Bilateral agreements sent out – first payment on
return of signed copy
*** Project must have demonstrated spend >70% of initial 40% pre-financing to trigger
further grant payment ***
 Every 6 Month Financial & Progress Report
 Financial Tool
 Connected through ICT
 Excel Files
11
Impact 1/2
 During the project the following group categories, in each of the
participating countries, will be targeted:
 Aged workers and aged unemployed (over the age of 50)
 Employers, SMEs
 National agencies involved in (VET/CVET)
 Employment services
 Social partners
 Policy makers at a local, regional, national and European level
 Training providers, Educational institutions and Lifelong Learning Institutes
 Aged workers, aged unemployed and employers will be involved in the
project directly by participating in training programmes
 The training will be organized in pilot applications, in all participating areas
 The results will be used for improvement of the methodology and preparing
exploitation path
 A conference will be organised to introduce to enterprises concepts on age
management, training personnel and business organisation
12
Impact 2/2
13
 Five (5) workshops will be held about the benefits of age
management concepts addressing to employees, customers, suppliers
 Organisation of five study tours aiming at sensitising entrepreneurs
and introducing them to good applied practices, but also at
identifying and exchanging good practices between partners
 A dissemination conference and awareness-raising seminars will be
organised as well in each country to reached
 The overall promotion of the project will contribute to reach and
inform relevant agencies, policy-makers, education and training
providers and any other relevant stakeholder
 The success of the involvement of the above mentioned target groups
will be assessed by evaluating the participation rate of each group
category in the organised event and the dissemination rate of all
project outputs and results
Projects’ Action Plan
 Implementation Methodology – PMI Project Life Cycle
 WP1 - Project Management | Lead: 3LRI
 WP2 - Defining Ageing and Employment Trends in EU |
Lead: Academy of Management
 WP3 - Developing Business Concepts for Age Management
& Investment in the HR sector | Lead: UoS
 WP4 - Pilot Projects | Lead: FU-Uppsala
 WP5 - Quality Assurance | Lead: 3LRI
 WP6 - Awareness raising activities | Lead: Documenta
 WP7 - Dissemination of Results | Lead: 3LRI
 WP8 - Mainstreaming and results exploitation | Lead: 3LRI
14
Work Packages Analysis WP.1-2
Work Package / Deliverables
Type
Number Title
WP1 Project Management
1.1 Consortium Agreement Other
1.2 Web-based system Service/Product
1.3 Project Partners Meetings Event
1.4 Progress Reports Report
WP2 Defining Ageing and Employment Trends in EU
2.1 Analysing the demographic trends Report
2.2 Analysis of the aged workforce employability Report
2.3 Survey on the aged employed / unemployed workforce Report
2.4 Strategy plan to meet future demographic needs Report
2.5 Exchange information and know-how Report
15
WP.1-Act.1.1
Activity 1.1: Consortium Agreement
 The Consortium Agreement will contain at least the
following:
 rules defining decision-making process at project level
 obligations of the LP towards the partners and the Programme
 obligations of the partners towards the LP and the Programme
 principles for conflict resolutions
 rules for protecting Intellectual Property Rights
 schedule of reporting (technical & financial)
16
WP.1-Act.1.2
Activity 1.2: Web-based system
 The Web based system will be used to manage information flow, which
will be implemented on the LP’s server and accessible for all partners’
team, with specific personnel accounts. This collaborative web tool will
help partners working in common and will be used for project
management, for implementation of activities, researches, reports, etc.
 Through this tool, partners will share working documents, drafts, ideas,
methodologies and comments useful for the writing of reports, the
organisation of events, and the implementation of all project activities
 This will help as well in project management, in order to define dates for
meetings or web-conferences, for reminding deadlines and obligations
to partners, for exchanging comments on progress reports, for giving
advices to partners on project implementation and programme rules
17
WP.1-Act.1.3
Activity 1.3: PPs’ meetings
 In sum, 6 meetings will take place, kick-off and closing meetings will be
organised by the LP, the other meetings will be hosted each time by a
different partner:
 Month 2, kick-off meeting
 Month 9, next Meeting M9 (June 2012) – Sweden – 27th – 30th Travelling
 28th – 29th
 Month 15, 3rd meeting December
 Month 21, 4th meeting May 2013 Poland
 Month 27, 5th meeting December
 Month 34, Closing meeting (in Brussels)
18
WP.1-Act.1.4
Activity 1.4: Progress Reports
 Each partner will have to deliver to the Lead Partner progress reports
on activities and finances every six months (6 reports in total) in order to
ensure a qualitative and smooth project implementation, in time and to
budget and to be pro-active in case of problems arising or delays in
implementation or budget spending.
 These reports will give detailed information of the activities
implemented within each Work Package, the objectives achieved, the
targets and indicators reached, for each semester, according to the
Application Form and the project timetable. Furthermore, the reports will
contain information on financial activities and budget reporting by work
package and budget line.
19
WP.2-Act.2.1-2.2
Activity 2.1: Analysing the demographic trends
 Will attempt to analyze the demographic trends regarding ageing workforce at European
level. Using the statistics provided by Eurostat and other sources of data, the report will reveal
the situation as it is currently in EU and it will evaluate the impact those trends will have in
different economic sectors. The specific report will be used as a basis for the further
implementation of the project.
 Duration: M2-M3, 2 months
 Budget: 3.888,00€
Activity 2.2 : Analysis of the aged workforce employability
 Analysis of the employability of the aged workforce in correlation to specific social
characteristics, such as religion and origin. Through that analysis, the report will demonstrate the
differences existing due to social characteristics and how those are affecting performance and
perception of work issues both in terms of employee as well as employer.
 Duration: Μ4-Μ5, 2 months
 Budget: 7.797,00€
 The 40 pages reports will be available in English
20
WP.2-Act.2.3-2.4
Activity 2.3: Survey on the aged employed / unemployed workforce
 It will be a survey, for the aged employed and unemployed workforce, mainly concerning the
analysis of attitudes, the arisen difficulties, and their awareness on age discrimination issues. The
main issue deriving from the specific report will be how we should examine the above issues in
order to define strong points of aged personnel and how they can be used as an asset within
their companies.
 Duration: M7, 1 month
 Budget: 6.944,00€
Activity 2.4: Strategy plan to meet future demographic needs
 The current strategy plan will be examined and worked in combination with the analysis of
demographic trends, in order to see how companies could meet the future demographic. The
focal point will be how to increase the positive aspects of ageing workforce, while decreasing
the negative ones. That plan will define the steps needed to be followed and will be used as the
basis on which the workshops will be conducted as well as the pilot actions. The analytical
content of the report will be decided by the Consortium, setting up the methodology for
conducting the research as well as quantitative and qualitative standards.
 Duration: M9, 1 month
 Budget: 7.480,00€
 The 40 pages report will be available in English
21
WP.2-Act.2.5
Activity 2.5: Exchange information and know-how
 The report will support the exchange of information and Know-How on
building upon innovative processes in the sector of age management
towards developing and testing alternative working conditions in
enterprises. This will be based on the findings of the reports already
conducted in the specific work package.
 Duration: M10, 1 month
 Budget: 4.985,00€
22
Work Packages Analysis WP.3-4
WP3
Developing Business Concepts for Age Management &
Investment in the HR sector
3.1 Designing model for enterprises on age management Report
3.2 Guide for management optimisation performance Report
3.3 Development of measurable performance indicators Report
3.4 Analysis of older workforce work traits Report
3.5 Employment opportunities for older workers Report
WP4 Pilot Projects
4.1 Developing training modules for skills upgrading Demonstrator / Prototype
4.2 Training seminars for the employers aged 50+ Demonstrator / Prototype
4.3 Evaluation of the age management concept Demonstrator / Prototype
4.4 Evaluation of the training seminars for the employers aged 50+ Report
4.5 Consultation of the unemployed Demonstrator / Prototype
4.6 Training seminar for the unemployed aged 50+ Demonstrator / Prototype
4.7
Evaluation of the training seminars for the unemployed aged
50+
Report
23
WP.3-Act.3.1-3.2
Activity 3.1: Designing model for enterprises on age management
 Focus on the development of innovative business concepts related to age management processes.
To this end, a study will be conducted to design a model for enterprises on introducing age
management concepts, flexible working arrangements and succession management, using the
finding of the report already elaborated in WP2.
 Duration: M15, 1 month
 Budget: 13.627,00€
 The 40 pages report will be firstly available in English and in electronic version and then
translated in Greek, Spanish, Polish and Swedish
Activity 3.2: Guide for management optimisation performance
 The above guide will cross examine the management systems currently deployed in the
companies of the EU with those suggested in the first action of WP3 and will lead to the
development of a methodological guide which will point what actions need to be taken in order
to optimize the performance of management systems used in the EU market.
 Duration: M17, 1 month
 Budget: 2.674,00€
 The 40 pages report will be available in English
24
WP.3-Act.3.3-3.4
Activity 3.3: Development of measurable performance indicators
 In order to examine the effectiveness of the proposed systems, a guide will be elaborated
stating the measurable performance indicators that are needed in order to estimate the
effectiveness of the management concepts. This will offer the opportunity for perfective
maintenance actions as well as identification of further needed actions that need to be taken.
 Duration: M19, 1 month
 Budget: 7.797,00€
 The 40 pages report will be available in English
Activity 3.4: Analysis of older workforce work traits
 An analysis of the work traits of the aged workforce (strengths and weaknesses) will be
conducted in order to identify the EU labour market employment opportunities for the aged
workforce. The SWOT analysis will be conducted under the perspective of the “new skills for
new jobs report”, thus the findings of it will point the set of questions needed to be asked so to
start transforming older workers to become more productive again for their companies/
organizations.
 Duration: Μ20, 1 month
 Budget: 7.785,00€
 The 40 pages report will be available in English and then translated in Greek, Spanish, Polish
and Swedish
25
WP.3-Act.3.5
Activity 3.5: Employment opportunities for older workers
 Employment opportunities will be the results of the previous report and will be examined
in relation to the EQF system along with the national qualifications systems. The aim of the
report is to examine how to adapt the approach of potential employment opportunities
for aged personnel to the local labour market. The report will examine how the different
levels of the professional framework systems can become the starting point for changing
the perception towards aged personnel and their skills. It will also demonstrate the
required actions in terms of training issues for older workers.
 Duration: Μ22, 1 month
 Budget: 6.944,00€
 The 40 pages report will be available in English
26
WP.4-Act.4.1-4.2
Activity 4.1: Developing training modules for skills upgrading
 Those aim at applying and adapting the concept on HR development for improving employability of aged
personnel within the specific business practices. The training model will be based on the findings of the project,
the “new skills for new jobs reports” and the adults learning concepts of Life Long Learning. P3 will be
responsible for creating the training material, with the support and contribution of all partners.
 Duration: M26, 1 month
 Budget: 11.436,00€
 The training material will be available in English and then translated in Greek, Spanish, Polish and Swedish
Activity 4.2: Training seminars for the employers aged 50+
 Will explain how the training material was prepared and the benefits of it, along with its use within a company,
in order to become more attractive and viable. The employers aged 50+ will be targeted by the partners
through the general promotion of the project and directly by communicating with enterprises, chambers of
commerce and network of enterprises through emails and phone calls in order to catch a minimum of 20
participants per seminar.
 These seminars will last one day and will be organised by each partner in each participating country, adapting
the training modules to their language, their specific working conditions, market needs and specific enterprises
attending the seminars.
 Duration: M27, 1 month
 Budget: 25.118,00€
27
WP.4-Act.4.3-4.4
Activity 4.3: Evaluation of the age management concept
 After the full model has been applied on 2 companies in Poland, an evaluation will be conducted in
order to find the strong as well as the weak points of the proposed strategy. The evaluation will record
how the model has been tested, how it has been perceived and accepted both by employers and
employees, and will lead to include the necessary changes in it, and therefore to the creation of a
successful management concept for aged workforce, applicable in all EU member states.
 Duration: M28, 1 month
 Budget: (included in 4.2)
 The 20 pages report will be available in Polish and in English
Activity 4.4: Evaluation of the training seminars for the employers aged 50+
 It will examine the effectiveness of the seminars, the negative issues of them and finally the reasons of
success and failure. The Lead Partner of this Work Package will use each partner’s evaluation to draft
a common document summarising all findings and proposing one common approach.
 Duration: M29, 1 month
 Budget: (included in 4.1, 4.2)
 The 10 pages evaluations will be available in each partner’s language with a summary in English and
in electronic version, downloadable from the project website for a larger diffusion and use. The common
evaluation will be available in English.
28
WP.4-Act.4.5-4.6
Activity 4.5: Consultation of the unemployed
 Five different consultations, one in each participating country, which will focus on the unemployed of 50+. The
participants will discuss on the issues their unemployment creates, how they could gain skills in order to become
asset again and will try to explain how they should adopt to the changing needs of the labour market. Finally,
it will explain to them the benefits of 50+ personnel in terms of skills and in terms of the benefits for the
company.
 Catch a minimum of 20 participants per consultation.
 Duration: M29, 1 month
 Budget: (included in 4.1, 4.2)
Activity 4.6: Training seminar for the unemployed aged 50+
 Training seminars will be organized focusing on the unemployed 50+, which will use the findings of the previous
consultations. It will address the issues discussed in the consultations, and will suggest strategies for becoming
again competitive for their organizations. More in detail it will provide the participants with guidance on
gaining the new skills needed, as well the skills themselves, when and where it is possible.
 Catch a minimum of 20 participants per seminar.
 Duration: M30, 1 month
 Budget: 1.500,00 € (included in 4.1, 4.2)
 Will last half a day and will be organised by each partner in each participating country, directly into the premises
of employment services, adapting the content to their language, their specific working conditions, labour market
needs and specificities of the attendants.
29
WP.4-Act.4.7
Activity 4.7: Evaluation of the training seminars for the unemployed
aged 50+
 It will examine if the target group has been benefited from them, if the new knowledge
had made them more competitive, problems they had faced during the implementation of
the strategy and finally the gains of them from such knowledge. The Lead Partner of this
Work Package will use each partner’s evaluation to draft a common document
summarising all findings and proposing one common approach. Duration:
 The 10 pages evaluations will be available in each partner’s language with a summary in
English. The common evaluation will be available in English.
 Duration: M31, 1 month
 Budget: (included in 4.1, 4.2)
30
Work Packages Analysis WP.5-6
WP5 Quality Assurance
5.1
Methodological Guide for WP “Defining Ageing and Employment
Trends in EU”
Report
5.2
Methodological Guide for WP “Developing Business Concepts for
Age Management & Investment in the HR sector”
Report
5.3 Methodological Guide for Pilot Projects implementation Report
5.4
Methodological Guide for Awareness raising, Dissemination and
Exploitation of results activities
Report
5.5 Evaluation of the results of the project Report
WP6 Awareness raising activities
6.1 Workshops for the age management concept benefits Event
6.2 Sensitising entrepreneurs Event
6.3 Seminars addressing HR managers Event
6.4 Sensitising the aged workforce Event
31
WP.5-Act.5.1 - 5.5
 Activity 5.1: Methodological Guide for WP “Defining Ageing and Employment Trends in EU”
 Activity 5.2: Methodological Guide for WP “Developing Business Concepts for Age Management &
Investment in the HR sector”
 Activity 5.3: Methodological Guide for Pilot Projects implementation
 Activity 5.4: Methodological Guide for Awareness raising, Dissemination and Exploitation of results
activities
 Activity 5.5: Evaluation of the results of the project
 A methodological guide will be created that will have examine all factors that are crucial for the
successful organization and implementation of each WP. It will analyze each step and each activity
and will provide guidance not only for the project partners but for anyone that would like to use the
deliverables. It will be created on high quality standards and by following them, PPs will assure the
expected quality in their deliverables and activities.
 The guide will define the methodology to be used for each deliverable and the overall “philosophy” of
the WP and will define the exact role of each partner for the smooth implementation of the work
package. Milestones and detailed timetable will be also included in the guide.
 The 20 pages guide, after being validated by the Steering Committee, will be available in English and
in electronic version
 Duration: M2-M36, 35 months
 Budget: 29.723,00€
32
WP.6-Act.6.1
Activity 6.1: Awareness raising activities
 The five workshops (one per country) will involve local public and private actors,
enterprises employees, customers, suppliers, employers and the community and will discuss
as well as examine the benefits enterprises could have from the proposed strategies. It will
reveal the strengths of aged work force and at the same time will demonstrate how
enterprises can be prepared to face the “demographic bomb issue”. Invited speakers,
expert on their fields, will elaborate on Age management concepts.
 The target groups will be targeted by the partners through the general promotion of the
project and directly by communicating with national and local stakeholders, through
meetings, emails and phone calls in order to catch a minimum of 20 participants per
workshop.
 These workshops will last half a day and will be organised by each partner in each
participating country, adapting the content to their language, their specific working
conditions, labour market needs and specificities of the attendants.
 Duration: M10-M12, 3 months
 Budget: 29.706,00€
33
WP.6-Act.6.2-6.3
34
Activity 6.2: Sensitising entrepreneurs
 Project partners will visit each other’s area and will visit businesses that operate with aged work force and have
successful results, for exchanging experience. PPs will discuss with the personnel and owners, gaining valuable experience
and know–how that they could bring back to their organizations as well as countries. Local business people will be part
as well of the study tours.
 These study tours (5 in total, one per country), will last one day and will take place together with the project meetings, in
order to save time and money from travelling.
 Duration: M2, M9, M15, M21, M27, 5 months
 Budget: 2.500,00€ (included in 6.1)
Activity 6.3: Seminars addressing HR managers
 There will be organized 5 seminars, one in each different participating country, addressing to Human Resources
Managers for implementing decisions on staff recruitment, retention and redundancy in view of the formulated Age
Management Concepts. The proposed issues will be deriving from the reports already elaborated in the context of the
project.
 Catch a minimum of 20 participants per seminar.
 These seminars will last half a day and will be organised by each partner in each participating country, adapting the
content to their language, their specific labour market needs and conditions and specificities of the attendants.
 Duration: M18-M22, 5 months
 Budget: 1.700,00€ (included in 6.1)
WP.6-Act.6.4
35
Activity 6.4: Sensitising the aged workforce
 In parallel with the seminars organized focusing in HR managers, another 5 will be
organized, addressing to aged workforce and Unemployed aged 50+, with special focus
on sensitive social groups. It will explain the strengths they have as well as the skills that
they need to gain, in order to remain competitive in the labour market they operate and
even in the EU market.
 Catch a minimum of 20 participants per seminar
 These seminars will last half a day and will be organised by each partner in each
participating country, adapting the content to their language, their specific labour market
needs and conditions and specificities of the attendants.
 Duration: M18-M22, 5 months
 Budget: 1.700,00 € (included in 6.1)
Work Packages Analysis WP.7-8
WP7 Dissemination of Results
7.1 Developing a website Service/Product
7.2 Publicity campaign – Information and sensitisation brochures Other
7.3 Publicity campaign – Dissemination of events Other
7.4 Publicity campaign – Electronic Newsletters Other
7.5 Press campaign Other
7.6 Dissemination conference Event
WP8 Mainstreaming and results exploitation
8.1 Mainstreaming and results exploitation action plan Report
8.2 Developing a business manual Report
8.3 Policies assessment Report
36
WP.7-Act.7.1
37
Activity 7.1: Developing a website
 The website will give information on the project aims and objectives, the Programme LLL
and Grundtvig, all events organised by the project or by the partners and relevant to the
project theme, all project deliverables and other relevant documentation or research,
contact details of partners, general information on the project themes both for enterprises
and the aged workforce. Finally, it will have the communication and working infrastructure
(collaboration tools) as well as discussions forums to be used by the local societies.
 The website will be available firstly in English, with translations in each partners’ language
and will be continuously updating with new feeds by all partners. The website will be
maintained by the Lead Partner for at least three years after the project end.
 Duration: M3, 1 month
 Budget: 29.501,00€
Act.7.1: “website structure”
38
Structure
 Home
 Project overview
 Rationale
 EU added value
 Project objectives
 Deliverables
 Expected results & outcomes
 Project Meetings
 Project Calendar
 Media library
 Project Partners
 Documentation Center
 + Forum
 Online Questionnaire
 + Sitemap
WP.7-Act.7.2
39
Activity 7.2: Publicity campaign – Information and Sensitisation brochures
Four brochures of 4pages will be produced, in the following languages: EN, ES, EL, SE, PL
 one presenting the project
 one sensitising the aged workforce
 one sensitizing enterprises and
 one presenting the project results
 The Lead Partner of the Work Package will create a common layout (with the approbation of all
partners), including a project logo, to be used in all brochures and overall material, and a
common text, but each partner will adapt the text to local conditions, needs and specificities
 Each brochure (A5) will be printed in 1000 items per country
 Duration: M3, M7, M33, 3 months
 Budget: 11.300,00€
WP.7-Act.7.3-7.4
40
Activity 7.3: Publicity campaign – Dissemination of events
 For each event organised (workshops, seminars, conference), each partner will produce and diffuse flyers and posters to
disseminate the event in order to ensure the largest possible participation.
 This means that 6 different flyers and 6 different posters will be produced in each language. Each flyer (A5) will be
printed in 200 items, each poster (A3) in 20 items.
 The Lead Partner of the Work Package will create a common layout (with the approbation of all partners), to be used in
for flyers and posters, and a common text, but each partner will adapt the text to local conditions, needs and
specificities.
 This dissemination will be done in an electronic way as well.
 Duration: M9, M17, M26, M28-29, 5 months
 Budget: 1.900,00€ (included in 7.1)
Activity 7.4: Publicity campaign – Electronic Newsletters
 6 newsletters on the employability of the aged workforce and presenting the project evolution and outputs during the
project lifetime will be sent electronically, which will be used to promote the main Project initiatives, to inform the
operators of interested sectors on the project implementation, the activity phases still in progress, the possibilities and
modalities of participation, to sensitize the population towards the thematic at the focus of the debate, to spread the
results obtained by the Project.
 The Lead Partner will have the overall coordination of the activity, but all partners will participate in the drafting of the
newsletter and in its dissemination to all relevant EU, national, regional and local actors, not only within the 5
participating countries but also in other European countries, to ensure the largest possible dissemination.
 Duration: M3, M9, M15, M21, M27, M33, 6 months
 Budget: (included in 7.1)
WP.7-Act.7.5
41
Activity 7.5: Press campaign
 The project will be presented to local actors and local press by each partner during a
press-conference presenting the project and addressing specific issues relevant to the
project theme and the local conditions. Each partner will decide on when organising the
press-conference, in order to choose the most appropriate moment for a more effective
and positive event (e.g. before an important event).
 During the press-conferences, folders will be distributed to the journalists with information
about the project, the programme, the transnational actions and the local actions and
added value of the project.
 Regional press-releases will inform target groups about the project and the organised
events and will be issued after the press-conference and more often if possible.
 Project partners will launch a press and radio campaign trying to sensitise as many actors
and target groups as possible.
 Duration: M1-M36, 36 months
 Budget: 250,00 € (included in 7.1)
WP.7-Act.7.6
42
Activity 7.6: Dissemination Conference
 A dissemination conference of the project will be organized in Brussels to present the project results and
disseminate all project products and outputs and to open the ground to new collaborations and partnerships
for the continuity of the project activities. This conference will have as general objectives:
 To assure the largest information and raising awareness for the project by EU actors;
 To inform the public opinion on the role developed by local institutions, European Union and Project partners
in the realization of the Project;
 To inform about the project’s outputs and results, the impact of the Project’s interventions, the findings of it.
 To communicate about age management concept, training of the aged workers and business organization
issues
 The target groups (EU stakeholders, representatives of regions, lobbies, think tanks, representatives of
enterprises, unions of enterprises, unions of employees, policy makers, social partners, training and
education providers and agencies…) will be targeted by the partners through the promotion of the project
and through direct communication via the events organised, meetings, emails and phone calls in order to
catch a minimum of 80 participants.
 The conference will last half a day and will be organised by P1 in Brussels, for acceding EU decision-makers
and for ensuring an easy access to attendants from all over Europe. Each partner will participate in it and
bring about 10 national and local stakeholders in order to ensure transnationality to the event.
 Duration: M33, 1 month
 Budget: 37.800,00€
WP.8-Act.8.1
43
Activity 8.1: Mainstreaming and results exploitation action plan
 This action is one of the most important actions since the choice of adequate promotional
channels is of fundamental importance for the success of the whole project and its afterlife.
The specific report will be divided in two parts, one stating the action plan needed to be
followed for mainstreaming the results of the project and another plan with the necessary
actions for the project to be exploited after its end by PPs local and national societies. The
analytical content of the report will be decided by the Consortium, setting up the methodology
for conducting the research as well as quantitative and qualitative standards.
 The Lead Partner will coordinate this action, with the active participation of all partners from
the choice of the content to the draft of each part.
 The 40 pages report, after being validated by the Steering Committee, will be available in
English and in electronic version, firstly sent to all partners for direct use, but also
downloadable from the project website for a larger diffusion and use. The existence of this
material will be largely diffused by all partners to their professional networks as well as to
national and EU stakeholders.
 Duration: M27, 1 month
 Budget: 14.962,00€
WP.8-Act.8.2
44
Activity 8.2: Developing a business manual
 At the end of the project activities, a business manual will be produced, introducing
perceptions and practices in managing an ageing workforce, as they have been produced by
the project, while at the same time will reveal the experiences gained by the realization of the
different actions in terms of the ageing workforce. The analytical content of the report will be
decided by the Consortium, setting up the methodology for conducting the research as well as
quantitative and qualitative standards.
 Partner 3 will coordinate this action, with the active participation of all partners from the
choice of the content to the draft of each part.
 The 40 pages report, after being validated by the Steering Committee, will be available in
English and in electronic version, downloadable from the project website for a larger diffusion
and use. The existence of this material will be largely diffused by all partners to their
professional networks, as well as to national and EU stakeholders.
 Duration: M30, 1 month
 Budget: 5.512,00€
WP.8-Act.8.3
45
Activity 8.3: Policies assessment
 The specific report will make a comparison of the EU strategies and the findings of the project,
as they have been transformed with the feedback of all the foreseen actions. This will reveal
the crucial points needed to be taken into consideration when designing a policy aiming at the
workforce of 50+. It will include as well perceptions and practices in managing an ageing
workforce and could be used as a point of reference. The analytical content of the report will
be decided by the Consortium, setting up the methodology for conducting the research as well
as quantitative and qualitative standards.
 Partner 4 will coordinate this action, with the active participation of all partners from the
choice of the content to the draft of each part.
 The 40 pages report, after being validated by the Steering Committee, will be available in
English and in electronic version, downloadable from the project website for a larger diffusion
and use. The existence of this material will be largely diffused by all partners to their
professional networks, as well as to national and EU stakeholders.
 Duration: M34, 1 month
 Budget: 5.838,00€
Dissemination & Valorisation
WP 6, Awareness raising activities
 As in most cases aged persons are unaware of the fact that they are being discriminated, special activities
aim at sensitizing both employers and aged workforce are planned to be implemented, such as workshops
on age management concept benefits, study tours for sensitising entrepreneurs, seminars for HR managers
and for aged workforce.
WP7, Dissemination of results
 Following a methodology to be defined by the consortium, a communication plan will accompany the project
all over its duration, that will include: a publicity campaign (website and discussion forum, brochures, flyers,
posters, electronic newsletters, electronic dissemination of outputs) for paper and electronic dissemination of
the project, a press campaign (press-conferences, press-releases, radio spots) and a Dissemination
Conference. The Discussion Forum will be used as a tool for transferring outputs at regional, national and
European level.
WP8, Mainstreaming and results exploitation
 This work package will last one year, to prepare the project for its exploitation even after the end of the
project life time. The mainstreaming of the project results and outputs is designed to limit early retirement
and encourage the recruitment and retention of older workers. A Mainstreaming Action Plan is planned
within the framework of the project in order to support the transfer of practices and methodologies
experimented to different systems. Furthermore, a Results Exploitation Action Plan will be delivered in order
to identify results to be utilised and transferred. The mainstreaming and exploitation strategy will be
multilevel (from local to European) and multi-actor oriented.
46
Time Table
47
Indicators
 To Be Defined
48
 Thank you for your attention
49

Más contenido relacionado

La actualidad más candente

CV_BN_ Oct 2016
CV_BN_ Oct 2016CV_BN_ Oct 2016
CV_BN_ Oct 2016
Negash Et
 
Colm McClements - How can more effective project identification, prioritizati...
Colm McClements - How can more effective project identification, prioritizati...Colm McClements - How can more effective project identification, prioritizati...
Colm McClements - How can more effective project identification, prioritizati...
GIZ Moldova
 
baf_bim_education_report_2015
baf_bim_education_report_2015baf_bim_education_report_2015
baf_bim_education_report_2015
Dr. Anas Bataw
 

La actualidad más candente (20)

IFAD IOE: Evaluation of non-lending activities in IFAD’s operations
IFAD IOE: Evaluation of non-lending activities in IFAD’s operationsIFAD IOE: Evaluation of non-lending activities in IFAD’s operations
IFAD IOE: Evaluation of non-lending activities in IFAD’s operations
 
Montenegro: Workshop 2 Building a National Partnership (Nov 2015)
Montenegro: Workshop 2 Building a National Partnership (Nov 2015)Montenegro: Workshop 2 Building a National Partnership (Nov 2015)
Montenegro: Workshop 2 Building a National Partnership (Nov 2015)
 
OECD Skills Strategy Luxembourg
OECD Skills Strategy LuxembourgOECD Skills Strategy Luxembourg
OECD Skills Strategy Luxembourg
 
Luxembourg National Research Fund
Luxembourg National Research FundLuxembourg National Research Fund
Luxembourg National Research Fund
 
Exemplar Evaluation Report
Exemplar Evaluation ReportExemplar Evaluation Report
Exemplar Evaluation Report
 
Systemic M&E Concept Note
Systemic M&E Concept NoteSystemic M&E Concept Note
Systemic M&E Concept Note
 
Erasmus+ Strategic Partnership
Erasmus+ Strategic PartnershipErasmus+ Strategic Partnership
Erasmus+ Strategic Partnership
 
Concept Note for Local Learning Groups - Second Pilot
Concept Note for Local Learning Groups - Second PilotConcept Note for Local Learning Groups - Second Pilot
Concept Note for Local Learning Groups - Second Pilot
 
Erasmus+ Capacity Building
Erasmus+ Capacity Building Erasmus+ Capacity Building
Erasmus+ Capacity Building
 
2015 03 Local supplier and workforce participation optimization
2015 03 Local supplier and workforce participation optimization2015 03 Local supplier and workforce participation optimization
2015 03 Local supplier and workforce participation optimization
 
E-SLP stakeholder events 20 and 21 May 2021 by George Ubachs (EADTU)
E-SLP stakeholder events 20 and 21 May 2021 by George Ubachs (EADTU) E-SLP stakeholder events 20 and 21 May 2021 by George Ubachs (EADTU)
E-SLP stakeholder events 20 and 21 May 2021 by George Ubachs (EADTU)
 
Kd present public sector productivity
Kd present public sector productivityKd present public sector productivity
Kd present public sector productivity
 
CV_BN_ Oct 2016
CV_BN_ Oct 2016CV_BN_ Oct 2016
CV_BN_ Oct 2016
 
E-SLP teaching stakholder event 20 May 2021 by Marcelo Maina
E-SLP teaching stakholder event 20 May 2021 by Marcelo MainaE-SLP teaching stakholder event 20 May 2021 by Marcelo Maina
E-SLP teaching stakholder event 20 May 2021 by Marcelo Maina
 
Colm McClements - How can more effective project identification, prioritizati...
Colm McClements - How can more effective project identification, prioritizati...Colm McClements - How can more effective project identification, prioritizati...
Colm McClements - How can more effective project identification, prioritizati...
 
Dr Inmaculada Higueras, Social Sciences and Humanities Thematic Lead/ Norther...
Dr Inmaculada Higueras, Social Sciences and Humanities Thematic Lead/ Norther...Dr Inmaculada Higueras, Social Sciences and Humanities Thematic Lead/ Norther...
Dr Inmaculada Higueras, Social Sciences and Humanities Thematic Lead/ Norther...
 
Breakthrough competences in the development of public administration
Breakthrough competences in the development of public administrationBreakthrough competences in the development of public administration
Breakthrough competences in the development of public administration
 
Grant Scheme
Grant  SchemeGrant  Scheme
Grant Scheme
 
IFAD Seahub presentation ioe workshop july2016 achievements-benoit
IFAD Seahub presentation ioe workshop july2016  achievements-benoitIFAD Seahub presentation ioe workshop july2016  achievements-benoit
IFAD Seahub presentation ioe workshop july2016 achievements-benoit
 
baf_bim_education_report_2015
baf_bim_education_report_2015baf_bim_education_report_2015
baf_bim_education_report_2015
 

Destacado (9)

History of HRM
History of HRMHistory of HRM
History of HRM
 
Hrp
HrpHrp
Hrp
 
Development of personnel management
Development of personnel managementDevelopment of personnel management
Development of personnel management
 
Evolution of human resources management
Evolution of human resources managementEvolution of human resources management
Evolution of human resources management
 
Module 1 HRM vs. Personnel Management
Module 1 HRM vs. Personnel ManagementModule 1 HRM vs. Personnel Management
Module 1 HRM vs. Personnel Management
 
Evolution of hrm
Evolution of hrmEvolution of hrm
Evolution of hrm
 
Evolution of Human Resource Management (HRM)
Evolution of Human Resource Management (HRM)Evolution of Human Resource Management (HRM)
Evolution of Human Resource Management (HRM)
 
Human Resource Planning and Recruitment
Human Resource Planning and RecruitmentHuman Resource Planning and Recruitment
Human Resource Planning and Recruitment
 
Privileges of Teaching Personnel in Public and Private schools
Privileges of Teaching Personnel in Public and Private schoolsPrivileges of Teaching Personnel in Public and Private schools
Privileges of Teaching Personnel in Public and Private schools
 

Similar a {LIKE} kick off PPT

{LIKE} 2nd PM PPT
{LIKE} 2nd PM PPT{LIKE} 2nd PM PPT
{LIKE} 2nd PM PPT
LIKE
 
Dialogos+ Project Presentation
Dialogos+ Project PresentationDialogos+ Project Presentation
Dialogos+ Project Presentation
Aristoteles Lakkas
 
10 management issues-20130221
10 management issues-2013022110 management issues-20130221
10 management issues-20130221
fruitbreedomics
 
Ia4 si caps concertation presentation
Ia4 si caps concertation presentationIa4 si caps concertation presentation
Ia4 si caps concertation presentation
CAPS2020
 
Copie 110119 deutschland bettina reuter
Copie 110119 deutschland   bettina reuterCopie 110119 deutschland   bettina reuter
Copie 110119 deutschland bettina reuter
Toby Johnson
 
Helath mangement in business
Helath mangement in business Helath mangement in business
Helath mangement in business
Hélder Silva
 
FP7 Specific Programme Capacities (March 2007)
FP7 Specific  Programme  Capacities (March 2007)FP7 Specific  Programme  Capacities (March 2007)
FP7 Specific Programme Capacities (March 2007)
CPN_Africa
 

Similar a {LIKE} kick off PPT (20)

{LIKE} 2nd PM PPT
{LIKE} 2nd PM PPT{LIKE} 2nd PM PPT
{LIKE} 2nd PM PPT
 
Dialogos+ Project Presentation
Dialogos+ Project PresentationDialogos+ Project Presentation
Dialogos+ Project Presentation
 
Mobilise sme guide-for-participants_
Mobilise sme guide-for-participants_Mobilise sme guide-for-participants_
Mobilise sme guide-for-participants_
 
10 management issues-20130221
10 management issues-2013022110 management issues-20130221
10 management issues-20130221
 
ETM kick off
ETM kick offETM kick off
ETM kick off
 
Erasmus + Knowledge Alliances 2020 call EAC/A02/2019 open
Erasmus + Knowledge Alliances 2020 call EAC/A02/2019 open Erasmus + Knowledge Alliances 2020 call EAC/A02/2019 open
Erasmus + Knowledge Alliances 2020 call EAC/A02/2019 open
 
HoCare Interreg Europe project
HoCare Interreg Europe projectHoCare Interreg Europe project
HoCare Interreg Europe project
 
OECD Work Based Learning
OECD Work Based LearningOECD Work Based Learning
OECD Work Based Learning
 
Transfer of Innovation project VOW+IPLM- The Value of Work for Individual Pos...
Transfer of Innovation project VOW+IPLM- The Value of Work for Individual Pos...Transfer of Innovation project VOW+IPLM- The Value of Work for Individual Pos...
Transfer of Innovation project VOW+IPLM- The Value of Work for Individual Pos...
 
Tables syndicate 1
Tables syndicate 1Tables syndicate 1
Tables syndicate 1
 
Ia4 si caps concertation presentation
Ia4 si caps concertation presentationIa4 si caps concertation presentation
Ia4 si caps concertation presentation
 
Career education for South-Eastern Europe, 08th Nov 2011, Part 1
Career education for South-Eastern Europe, 08th Nov 2011, Part 1Career education for South-Eastern Europe, 08th Nov 2011, Part 1
Career education for South-Eastern Europe, 08th Nov 2011, Part 1
 
Monitoring the process using the PEG M&E Tool
Monitoring the process using the PEG M&E ToolMonitoring the process using the PEG M&E Tool
Monitoring the process using the PEG M&E Tool
 
Ifad west africa hub knowledge and case studies practical guide 2019 en
Ifad west africa hub  knowledge and case studies practical guide 2019 enIfad west africa hub  knowledge and case studies practical guide 2019 en
Ifad west africa hub knowledge and case studies practical guide 2019 en
 
Copie 110119 deutschland bettina reuter
Copie 110119 deutschland   bettina reuterCopie 110119 deutschland   bettina reuter
Copie 110119 deutschland bettina reuter
 
OECD/DAC - Results Community October 2018 Workshop - Results approaches for t...
OECD/DAC - Results Community October 2018 Workshop - Results approaches for t...OECD/DAC - Results Community October 2018 Workshop - Results approaches for t...
OECD/DAC - Results Community October 2018 Workshop - Results approaches for t...
 
Health ncp information lesotho
Health ncp information lesothoHealth ncp information lesotho
Health ncp information lesotho
 
Programme guide en
Programme guide enProgramme guide en
Programme guide en
 
Helath mangement in business
Helath mangement in business Helath mangement in business
Helath mangement in business
 
FP7 Specific Programme Capacities (March 2007)
FP7 Specific  Programme  Capacities (March 2007)FP7 Specific  Programme  Capacities (March 2007)
FP7 Specific Programme Capacities (March 2007)
 

Último

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
fonyou31
 

Último (20)

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 

{LIKE} kick off PPT

  • 1. 517619-LLP-1-2011-1-GR-GRUNDTVIG-GMP 13-14 December 2011| Athens – Greece Dimitris Raftopoulos Strategic Leadership Unit
  • 2. Day 1 - Presentation Outline 2  Presentation of partners and their activity  Presentation of the Project  Concept of the Project: Background, Aims and Objectives  Project Management  Administrative Rules, Reporting, Filling System  Financial Management  Projects’ Action Plan  Implementation Methodology, Presentation of the Work Packages, Projects’ activities and deadlines, Analysis of Activities per Work Package and PP  Lunch  Presentation of the Project (cont.)  Dinner
  • 3. Presentation of PPs and their activity  3L Research Institute, Greece  University of Strathclyde, UK  Folkuniversitetet, Sweden  University of Social Sciences, Poland  Documenta, Spain 4
  • 4. Framework  Aim of GRUNDTVIG Multilateral projects  Achieving concrete and innovative results/products with indisputable European value. In many cases, this will involve piloting experiences in strategic areas and producing teaching products of high quality (strengthen the European dimension in the field of adult learning) 5
  • 5. Background  Lisbon Strategy stated that Europe should “become the most competitive and dynamic knowledge-based economy in the world, capable of sustainable economic growth with more and better jobs and greater social cohesion”  The inclusion of the ageing workforce which is an important priority of the European social agenda  Directive 2000/78/EC, which aims at combating discrimination on the grounds of age as regards employment and occupation  Many enterprises, particularly in a time of economic crisis, adopt strategies which adversely affect older workers, through, for example, early retirement or redundancy programmes  Concretely the challenge consists in making the workplace more suitable for the ageing workforce who owns the knowledge and offer them well adapted jobs or actions and training to take advantage of their skills, while putting in place capitalisation processes and train new comers 6
  • 6. Presentation of the Project Aims 7
  • 7. Main Objective  Study how innovative management approaches, based on ICT, can generate concepts to answer the urgent European situation made out of low employment of older workers, shortage of critical skills and decline of birth rate 8
  • 8. Objectives  Improve existing age management methods  Introduce new organizational business concepts for the improvement of the employability of the aged workforce within the operational framework of the enterprise  Develop all the necessary tools in order to minimise the impact of age barriers and age discriminatory approaches in job recruitment and training with the development of new business concepts  Identify the most appropriate fields of employment for the aged workforce in order to promote the employability of the aged workforce  Promote the activation and better use of the capacities of aged personnel  Identify new business-oriented qualifications for the aged personnel in order to improve their skills and capacities  Elaborate a Strategy Plan in order to meet future demographic needs  Explore existing practices being used to encourage older worker participation in lifelong learning  Develop innovative ways of encouraging older adult participation and understanding of VET/CVET  Create training programmes that encourages older worker participation and breaks down barriers to learning  Create training programmes for age management concept  Work closely with employers across a range of industry sectors to educate and inform them on age management concept and vocational training for older workers 9
  • 9. Project Management 10  Administrative Rules  Project Handbook (included in the Booklet)  Project and Financial Officers  Meeting in Brussels for the Coordinators (19-20/01/2012)  Reporting system  Two part process for claiming: Completion of Financial Claim and Progress Report  Quality assurance – will help with providing data for Interim/Final reports  Filling System
  • 10. Financial Management & Reporting  Bilateral agreements sent out – first payment on return of signed copy *** Project must have demonstrated spend >70% of initial 40% pre-financing to trigger further grant payment ***  Every 6 Month Financial & Progress Report  Financial Tool  Connected through ICT  Excel Files 11
  • 11. Impact 1/2  During the project the following group categories, in each of the participating countries, will be targeted:  Aged workers and aged unemployed (over the age of 50)  Employers, SMEs  National agencies involved in (VET/CVET)  Employment services  Social partners  Policy makers at a local, regional, national and European level  Training providers, Educational institutions and Lifelong Learning Institutes  Aged workers, aged unemployed and employers will be involved in the project directly by participating in training programmes  The training will be organized in pilot applications, in all participating areas  The results will be used for improvement of the methodology and preparing exploitation path  A conference will be organised to introduce to enterprises concepts on age management, training personnel and business organisation 12
  • 12. Impact 2/2 13  Five (5) workshops will be held about the benefits of age management concepts addressing to employees, customers, suppliers  Organisation of five study tours aiming at sensitising entrepreneurs and introducing them to good applied practices, but also at identifying and exchanging good practices between partners  A dissemination conference and awareness-raising seminars will be organised as well in each country to reached  The overall promotion of the project will contribute to reach and inform relevant agencies, policy-makers, education and training providers and any other relevant stakeholder  The success of the involvement of the above mentioned target groups will be assessed by evaluating the participation rate of each group category in the organised event and the dissemination rate of all project outputs and results
  • 13. Projects’ Action Plan  Implementation Methodology – PMI Project Life Cycle  WP1 - Project Management | Lead: 3LRI  WP2 - Defining Ageing and Employment Trends in EU | Lead: Academy of Management  WP3 - Developing Business Concepts for Age Management & Investment in the HR sector | Lead: UoS  WP4 - Pilot Projects | Lead: FU-Uppsala  WP5 - Quality Assurance | Lead: 3LRI  WP6 - Awareness raising activities | Lead: Documenta  WP7 - Dissemination of Results | Lead: 3LRI  WP8 - Mainstreaming and results exploitation | Lead: 3LRI 14
  • 14. Work Packages Analysis WP.1-2 Work Package / Deliverables Type Number Title WP1 Project Management 1.1 Consortium Agreement Other 1.2 Web-based system Service/Product 1.3 Project Partners Meetings Event 1.4 Progress Reports Report WP2 Defining Ageing and Employment Trends in EU 2.1 Analysing the demographic trends Report 2.2 Analysis of the aged workforce employability Report 2.3 Survey on the aged employed / unemployed workforce Report 2.4 Strategy plan to meet future demographic needs Report 2.5 Exchange information and know-how Report 15
  • 15. WP.1-Act.1.1 Activity 1.1: Consortium Agreement  The Consortium Agreement will contain at least the following:  rules defining decision-making process at project level  obligations of the LP towards the partners and the Programme  obligations of the partners towards the LP and the Programme  principles for conflict resolutions  rules for protecting Intellectual Property Rights  schedule of reporting (technical & financial) 16
  • 16. WP.1-Act.1.2 Activity 1.2: Web-based system  The Web based system will be used to manage information flow, which will be implemented on the LP’s server and accessible for all partners’ team, with specific personnel accounts. This collaborative web tool will help partners working in common and will be used for project management, for implementation of activities, researches, reports, etc.  Through this tool, partners will share working documents, drafts, ideas, methodologies and comments useful for the writing of reports, the organisation of events, and the implementation of all project activities  This will help as well in project management, in order to define dates for meetings or web-conferences, for reminding deadlines and obligations to partners, for exchanging comments on progress reports, for giving advices to partners on project implementation and programme rules 17
  • 17. WP.1-Act.1.3 Activity 1.3: PPs’ meetings  In sum, 6 meetings will take place, kick-off and closing meetings will be organised by the LP, the other meetings will be hosted each time by a different partner:  Month 2, kick-off meeting  Month 9, next Meeting M9 (June 2012) – Sweden – 27th – 30th Travelling  28th – 29th  Month 15, 3rd meeting December  Month 21, 4th meeting May 2013 Poland  Month 27, 5th meeting December  Month 34, Closing meeting (in Brussels) 18
  • 18. WP.1-Act.1.4 Activity 1.4: Progress Reports  Each partner will have to deliver to the Lead Partner progress reports on activities and finances every six months (6 reports in total) in order to ensure a qualitative and smooth project implementation, in time and to budget and to be pro-active in case of problems arising or delays in implementation or budget spending.  These reports will give detailed information of the activities implemented within each Work Package, the objectives achieved, the targets and indicators reached, for each semester, according to the Application Form and the project timetable. Furthermore, the reports will contain information on financial activities and budget reporting by work package and budget line. 19
  • 19. WP.2-Act.2.1-2.2 Activity 2.1: Analysing the demographic trends  Will attempt to analyze the demographic trends regarding ageing workforce at European level. Using the statistics provided by Eurostat and other sources of data, the report will reveal the situation as it is currently in EU and it will evaluate the impact those trends will have in different economic sectors. The specific report will be used as a basis for the further implementation of the project.  Duration: M2-M3, 2 months  Budget: 3.888,00€ Activity 2.2 : Analysis of the aged workforce employability  Analysis of the employability of the aged workforce in correlation to specific social characteristics, such as religion and origin. Through that analysis, the report will demonstrate the differences existing due to social characteristics and how those are affecting performance and perception of work issues both in terms of employee as well as employer.  Duration: Μ4-Μ5, 2 months  Budget: 7.797,00€  The 40 pages reports will be available in English 20
  • 20. WP.2-Act.2.3-2.4 Activity 2.3: Survey on the aged employed / unemployed workforce  It will be a survey, for the aged employed and unemployed workforce, mainly concerning the analysis of attitudes, the arisen difficulties, and their awareness on age discrimination issues. The main issue deriving from the specific report will be how we should examine the above issues in order to define strong points of aged personnel and how they can be used as an asset within their companies.  Duration: M7, 1 month  Budget: 6.944,00€ Activity 2.4: Strategy plan to meet future demographic needs  The current strategy plan will be examined and worked in combination with the analysis of demographic trends, in order to see how companies could meet the future demographic. The focal point will be how to increase the positive aspects of ageing workforce, while decreasing the negative ones. That plan will define the steps needed to be followed and will be used as the basis on which the workshops will be conducted as well as the pilot actions. The analytical content of the report will be decided by the Consortium, setting up the methodology for conducting the research as well as quantitative and qualitative standards.  Duration: M9, 1 month  Budget: 7.480,00€  The 40 pages report will be available in English 21
  • 21. WP.2-Act.2.5 Activity 2.5: Exchange information and know-how  The report will support the exchange of information and Know-How on building upon innovative processes in the sector of age management towards developing and testing alternative working conditions in enterprises. This will be based on the findings of the reports already conducted in the specific work package.  Duration: M10, 1 month  Budget: 4.985,00€ 22
  • 22. Work Packages Analysis WP.3-4 WP3 Developing Business Concepts for Age Management & Investment in the HR sector 3.1 Designing model for enterprises on age management Report 3.2 Guide for management optimisation performance Report 3.3 Development of measurable performance indicators Report 3.4 Analysis of older workforce work traits Report 3.5 Employment opportunities for older workers Report WP4 Pilot Projects 4.1 Developing training modules for skills upgrading Demonstrator / Prototype 4.2 Training seminars for the employers aged 50+ Demonstrator / Prototype 4.3 Evaluation of the age management concept Demonstrator / Prototype 4.4 Evaluation of the training seminars for the employers aged 50+ Report 4.5 Consultation of the unemployed Demonstrator / Prototype 4.6 Training seminar for the unemployed aged 50+ Demonstrator / Prototype 4.7 Evaluation of the training seminars for the unemployed aged 50+ Report 23
  • 23. WP.3-Act.3.1-3.2 Activity 3.1: Designing model for enterprises on age management  Focus on the development of innovative business concepts related to age management processes. To this end, a study will be conducted to design a model for enterprises on introducing age management concepts, flexible working arrangements and succession management, using the finding of the report already elaborated in WP2.  Duration: M15, 1 month  Budget: 13.627,00€  The 40 pages report will be firstly available in English and in electronic version and then translated in Greek, Spanish, Polish and Swedish Activity 3.2: Guide for management optimisation performance  The above guide will cross examine the management systems currently deployed in the companies of the EU with those suggested in the first action of WP3 and will lead to the development of a methodological guide which will point what actions need to be taken in order to optimize the performance of management systems used in the EU market.  Duration: M17, 1 month  Budget: 2.674,00€  The 40 pages report will be available in English 24
  • 24. WP.3-Act.3.3-3.4 Activity 3.3: Development of measurable performance indicators  In order to examine the effectiveness of the proposed systems, a guide will be elaborated stating the measurable performance indicators that are needed in order to estimate the effectiveness of the management concepts. This will offer the opportunity for perfective maintenance actions as well as identification of further needed actions that need to be taken.  Duration: M19, 1 month  Budget: 7.797,00€  The 40 pages report will be available in English Activity 3.4: Analysis of older workforce work traits  An analysis of the work traits of the aged workforce (strengths and weaknesses) will be conducted in order to identify the EU labour market employment opportunities for the aged workforce. The SWOT analysis will be conducted under the perspective of the “new skills for new jobs report”, thus the findings of it will point the set of questions needed to be asked so to start transforming older workers to become more productive again for their companies/ organizations.  Duration: Μ20, 1 month  Budget: 7.785,00€  The 40 pages report will be available in English and then translated in Greek, Spanish, Polish and Swedish 25
  • 25. WP.3-Act.3.5 Activity 3.5: Employment opportunities for older workers  Employment opportunities will be the results of the previous report and will be examined in relation to the EQF system along with the national qualifications systems. The aim of the report is to examine how to adapt the approach of potential employment opportunities for aged personnel to the local labour market. The report will examine how the different levels of the professional framework systems can become the starting point for changing the perception towards aged personnel and their skills. It will also demonstrate the required actions in terms of training issues for older workers.  Duration: Μ22, 1 month  Budget: 6.944,00€  The 40 pages report will be available in English 26
  • 26. WP.4-Act.4.1-4.2 Activity 4.1: Developing training modules for skills upgrading  Those aim at applying and adapting the concept on HR development for improving employability of aged personnel within the specific business practices. The training model will be based on the findings of the project, the “new skills for new jobs reports” and the adults learning concepts of Life Long Learning. P3 will be responsible for creating the training material, with the support and contribution of all partners.  Duration: M26, 1 month  Budget: 11.436,00€  The training material will be available in English and then translated in Greek, Spanish, Polish and Swedish Activity 4.2: Training seminars for the employers aged 50+  Will explain how the training material was prepared and the benefits of it, along with its use within a company, in order to become more attractive and viable. The employers aged 50+ will be targeted by the partners through the general promotion of the project and directly by communicating with enterprises, chambers of commerce and network of enterprises through emails and phone calls in order to catch a minimum of 20 participants per seminar.  These seminars will last one day and will be organised by each partner in each participating country, adapting the training modules to their language, their specific working conditions, market needs and specific enterprises attending the seminars.  Duration: M27, 1 month  Budget: 25.118,00€ 27
  • 27. WP.4-Act.4.3-4.4 Activity 4.3: Evaluation of the age management concept  After the full model has been applied on 2 companies in Poland, an evaluation will be conducted in order to find the strong as well as the weak points of the proposed strategy. The evaluation will record how the model has been tested, how it has been perceived and accepted both by employers and employees, and will lead to include the necessary changes in it, and therefore to the creation of a successful management concept for aged workforce, applicable in all EU member states.  Duration: M28, 1 month  Budget: (included in 4.2)  The 20 pages report will be available in Polish and in English Activity 4.4: Evaluation of the training seminars for the employers aged 50+  It will examine the effectiveness of the seminars, the negative issues of them and finally the reasons of success and failure. The Lead Partner of this Work Package will use each partner’s evaluation to draft a common document summarising all findings and proposing one common approach.  Duration: M29, 1 month  Budget: (included in 4.1, 4.2)  The 10 pages evaluations will be available in each partner’s language with a summary in English and in electronic version, downloadable from the project website for a larger diffusion and use. The common evaluation will be available in English. 28
  • 28. WP.4-Act.4.5-4.6 Activity 4.5: Consultation of the unemployed  Five different consultations, one in each participating country, which will focus on the unemployed of 50+. The participants will discuss on the issues their unemployment creates, how they could gain skills in order to become asset again and will try to explain how they should adopt to the changing needs of the labour market. Finally, it will explain to them the benefits of 50+ personnel in terms of skills and in terms of the benefits for the company.  Catch a minimum of 20 participants per consultation.  Duration: M29, 1 month  Budget: (included in 4.1, 4.2) Activity 4.6: Training seminar for the unemployed aged 50+  Training seminars will be organized focusing on the unemployed 50+, which will use the findings of the previous consultations. It will address the issues discussed in the consultations, and will suggest strategies for becoming again competitive for their organizations. More in detail it will provide the participants with guidance on gaining the new skills needed, as well the skills themselves, when and where it is possible.  Catch a minimum of 20 participants per seminar.  Duration: M30, 1 month  Budget: 1.500,00 € (included in 4.1, 4.2)  Will last half a day and will be organised by each partner in each participating country, directly into the premises of employment services, adapting the content to their language, their specific working conditions, labour market needs and specificities of the attendants. 29
  • 29. WP.4-Act.4.7 Activity 4.7: Evaluation of the training seminars for the unemployed aged 50+  It will examine if the target group has been benefited from them, if the new knowledge had made them more competitive, problems they had faced during the implementation of the strategy and finally the gains of them from such knowledge. The Lead Partner of this Work Package will use each partner’s evaluation to draft a common document summarising all findings and proposing one common approach. Duration:  The 10 pages evaluations will be available in each partner’s language with a summary in English. The common evaluation will be available in English.  Duration: M31, 1 month  Budget: (included in 4.1, 4.2) 30
  • 30. Work Packages Analysis WP.5-6 WP5 Quality Assurance 5.1 Methodological Guide for WP “Defining Ageing and Employment Trends in EU” Report 5.2 Methodological Guide for WP “Developing Business Concepts for Age Management & Investment in the HR sector” Report 5.3 Methodological Guide for Pilot Projects implementation Report 5.4 Methodological Guide for Awareness raising, Dissemination and Exploitation of results activities Report 5.5 Evaluation of the results of the project Report WP6 Awareness raising activities 6.1 Workshops for the age management concept benefits Event 6.2 Sensitising entrepreneurs Event 6.3 Seminars addressing HR managers Event 6.4 Sensitising the aged workforce Event 31
  • 31. WP.5-Act.5.1 - 5.5  Activity 5.1: Methodological Guide for WP “Defining Ageing and Employment Trends in EU”  Activity 5.2: Methodological Guide for WP “Developing Business Concepts for Age Management & Investment in the HR sector”  Activity 5.3: Methodological Guide for Pilot Projects implementation  Activity 5.4: Methodological Guide for Awareness raising, Dissemination and Exploitation of results activities  Activity 5.5: Evaluation of the results of the project  A methodological guide will be created that will have examine all factors that are crucial for the successful organization and implementation of each WP. It will analyze each step and each activity and will provide guidance not only for the project partners but for anyone that would like to use the deliverables. It will be created on high quality standards and by following them, PPs will assure the expected quality in their deliverables and activities.  The guide will define the methodology to be used for each deliverable and the overall “philosophy” of the WP and will define the exact role of each partner for the smooth implementation of the work package. Milestones and detailed timetable will be also included in the guide.  The 20 pages guide, after being validated by the Steering Committee, will be available in English and in electronic version  Duration: M2-M36, 35 months  Budget: 29.723,00€ 32
  • 32. WP.6-Act.6.1 Activity 6.1: Awareness raising activities  The five workshops (one per country) will involve local public and private actors, enterprises employees, customers, suppliers, employers and the community and will discuss as well as examine the benefits enterprises could have from the proposed strategies. It will reveal the strengths of aged work force and at the same time will demonstrate how enterprises can be prepared to face the “demographic bomb issue”. Invited speakers, expert on their fields, will elaborate on Age management concepts.  The target groups will be targeted by the partners through the general promotion of the project and directly by communicating with national and local stakeholders, through meetings, emails and phone calls in order to catch a minimum of 20 participants per workshop.  These workshops will last half a day and will be organised by each partner in each participating country, adapting the content to their language, their specific working conditions, labour market needs and specificities of the attendants.  Duration: M10-M12, 3 months  Budget: 29.706,00€ 33
  • 33. WP.6-Act.6.2-6.3 34 Activity 6.2: Sensitising entrepreneurs  Project partners will visit each other’s area and will visit businesses that operate with aged work force and have successful results, for exchanging experience. PPs will discuss with the personnel and owners, gaining valuable experience and know–how that they could bring back to their organizations as well as countries. Local business people will be part as well of the study tours.  These study tours (5 in total, one per country), will last one day and will take place together with the project meetings, in order to save time and money from travelling.  Duration: M2, M9, M15, M21, M27, 5 months  Budget: 2.500,00€ (included in 6.1) Activity 6.3: Seminars addressing HR managers  There will be organized 5 seminars, one in each different participating country, addressing to Human Resources Managers for implementing decisions on staff recruitment, retention and redundancy in view of the formulated Age Management Concepts. The proposed issues will be deriving from the reports already elaborated in the context of the project.  Catch a minimum of 20 participants per seminar.  These seminars will last half a day and will be organised by each partner in each participating country, adapting the content to their language, their specific labour market needs and conditions and specificities of the attendants.  Duration: M18-M22, 5 months  Budget: 1.700,00€ (included in 6.1)
  • 34. WP.6-Act.6.4 35 Activity 6.4: Sensitising the aged workforce  In parallel with the seminars organized focusing in HR managers, another 5 will be organized, addressing to aged workforce and Unemployed aged 50+, with special focus on sensitive social groups. It will explain the strengths they have as well as the skills that they need to gain, in order to remain competitive in the labour market they operate and even in the EU market.  Catch a minimum of 20 participants per seminar  These seminars will last half a day and will be organised by each partner in each participating country, adapting the content to their language, their specific labour market needs and conditions and specificities of the attendants.  Duration: M18-M22, 5 months  Budget: 1.700,00 € (included in 6.1)
  • 35. Work Packages Analysis WP.7-8 WP7 Dissemination of Results 7.1 Developing a website Service/Product 7.2 Publicity campaign – Information and sensitisation brochures Other 7.3 Publicity campaign – Dissemination of events Other 7.4 Publicity campaign – Electronic Newsletters Other 7.5 Press campaign Other 7.6 Dissemination conference Event WP8 Mainstreaming and results exploitation 8.1 Mainstreaming and results exploitation action plan Report 8.2 Developing a business manual Report 8.3 Policies assessment Report 36
  • 36. WP.7-Act.7.1 37 Activity 7.1: Developing a website  The website will give information on the project aims and objectives, the Programme LLL and Grundtvig, all events organised by the project or by the partners and relevant to the project theme, all project deliverables and other relevant documentation or research, contact details of partners, general information on the project themes both for enterprises and the aged workforce. Finally, it will have the communication and working infrastructure (collaboration tools) as well as discussions forums to be used by the local societies.  The website will be available firstly in English, with translations in each partners’ language and will be continuously updating with new feeds by all partners. The website will be maintained by the Lead Partner for at least three years after the project end.  Duration: M3, 1 month  Budget: 29.501,00€
  • 37. Act.7.1: “website structure” 38 Structure  Home  Project overview  Rationale  EU added value  Project objectives  Deliverables  Expected results & outcomes  Project Meetings  Project Calendar  Media library  Project Partners  Documentation Center  + Forum  Online Questionnaire  + Sitemap
  • 38. WP.7-Act.7.2 39 Activity 7.2: Publicity campaign – Information and Sensitisation brochures Four brochures of 4pages will be produced, in the following languages: EN, ES, EL, SE, PL  one presenting the project  one sensitising the aged workforce  one sensitizing enterprises and  one presenting the project results  The Lead Partner of the Work Package will create a common layout (with the approbation of all partners), including a project logo, to be used in all brochures and overall material, and a common text, but each partner will adapt the text to local conditions, needs and specificities  Each brochure (A5) will be printed in 1000 items per country  Duration: M3, M7, M33, 3 months  Budget: 11.300,00€
  • 39. WP.7-Act.7.3-7.4 40 Activity 7.3: Publicity campaign – Dissemination of events  For each event organised (workshops, seminars, conference), each partner will produce and diffuse flyers and posters to disseminate the event in order to ensure the largest possible participation.  This means that 6 different flyers and 6 different posters will be produced in each language. Each flyer (A5) will be printed in 200 items, each poster (A3) in 20 items.  The Lead Partner of the Work Package will create a common layout (with the approbation of all partners), to be used in for flyers and posters, and a common text, but each partner will adapt the text to local conditions, needs and specificities.  This dissemination will be done in an electronic way as well.  Duration: M9, M17, M26, M28-29, 5 months  Budget: 1.900,00€ (included in 7.1) Activity 7.4: Publicity campaign – Electronic Newsletters  6 newsletters on the employability of the aged workforce and presenting the project evolution and outputs during the project lifetime will be sent electronically, which will be used to promote the main Project initiatives, to inform the operators of interested sectors on the project implementation, the activity phases still in progress, the possibilities and modalities of participation, to sensitize the population towards the thematic at the focus of the debate, to spread the results obtained by the Project.  The Lead Partner will have the overall coordination of the activity, but all partners will participate in the drafting of the newsletter and in its dissemination to all relevant EU, national, regional and local actors, not only within the 5 participating countries but also in other European countries, to ensure the largest possible dissemination.  Duration: M3, M9, M15, M21, M27, M33, 6 months  Budget: (included in 7.1)
  • 40. WP.7-Act.7.5 41 Activity 7.5: Press campaign  The project will be presented to local actors and local press by each partner during a press-conference presenting the project and addressing specific issues relevant to the project theme and the local conditions. Each partner will decide on when organising the press-conference, in order to choose the most appropriate moment for a more effective and positive event (e.g. before an important event).  During the press-conferences, folders will be distributed to the journalists with information about the project, the programme, the transnational actions and the local actions and added value of the project.  Regional press-releases will inform target groups about the project and the organised events and will be issued after the press-conference and more often if possible.  Project partners will launch a press and radio campaign trying to sensitise as many actors and target groups as possible.  Duration: M1-M36, 36 months  Budget: 250,00 € (included in 7.1)
  • 41. WP.7-Act.7.6 42 Activity 7.6: Dissemination Conference  A dissemination conference of the project will be organized in Brussels to present the project results and disseminate all project products and outputs and to open the ground to new collaborations and partnerships for the continuity of the project activities. This conference will have as general objectives:  To assure the largest information and raising awareness for the project by EU actors;  To inform the public opinion on the role developed by local institutions, European Union and Project partners in the realization of the Project;  To inform about the project’s outputs and results, the impact of the Project’s interventions, the findings of it.  To communicate about age management concept, training of the aged workers and business organization issues  The target groups (EU stakeholders, representatives of regions, lobbies, think tanks, representatives of enterprises, unions of enterprises, unions of employees, policy makers, social partners, training and education providers and agencies…) will be targeted by the partners through the promotion of the project and through direct communication via the events organised, meetings, emails and phone calls in order to catch a minimum of 80 participants.  The conference will last half a day and will be organised by P1 in Brussels, for acceding EU decision-makers and for ensuring an easy access to attendants from all over Europe. Each partner will participate in it and bring about 10 national and local stakeholders in order to ensure transnationality to the event.  Duration: M33, 1 month  Budget: 37.800,00€
  • 42. WP.8-Act.8.1 43 Activity 8.1: Mainstreaming and results exploitation action plan  This action is one of the most important actions since the choice of adequate promotional channels is of fundamental importance for the success of the whole project and its afterlife. The specific report will be divided in two parts, one stating the action plan needed to be followed for mainstreaming the results of the project and another plan with the necessary actions for the project to be exploited after its end by PPs local and national societies. The analytical content of the report will be decided by the Consortium, setting up the methodology for conducting the research as well as quantitative and qualitative standards.  The Lead Partner will coordinate this action, with the active participation of all partners from the choice of the content to the draft of each part.  The 40 pages report, after being validated by the Steering Committee, will be available in English and in electronic version, firstly sent to all partners for direct use, but also downloadable from the project website for a larger diffusion and use. The existence of this material will be largely diffused by all partners to their professional networks as well as to national and EU stakeholders.  Duration: M27, 1 month  Budget: 14.962,00€
  • 43. WP.8-Act.8.2 44 Activity 8.2: Developing a business manual  At the end of the project activities, a business manual will be produced, introducing perceptions and practices in managing an ageing workforce, as they have been produced by the project, while at the same time will reveal the experiences gained by the realization of the different actions in terms of the ageing workforce. The analytical content of the report will be decided by the Consortium, setting up the methodology for conducting the research as well as quantitative and qualitative standards.  Partner 3 will coordinate this action, with the active participation of all partners from the choice of the content to the draft of each part.  The 40 pages report, after being validated by the Steering Committee, will be available in English and in electronic version, downloadable from the project website for a larger diffusion and use. The existence of this material will be largely diffused by all partners to their professional networks, as well as to national and EU stakeholders.  Duration: M30, 1 month  Budget: 5.512,00€
  • 44. WP.8-Act.8.3 45 Activity 8.3: Policies assessment  The specific report will make a comparison of the EU strategies and the findings of the project, as they have been transformed with the feedback of all the foreseen actions. This will reveal the crucial points needed to be taken into consideration when designing a policy aiming at the workforce of 50+. It will include as well perceptions and practices in managing an ageing workforce and could be used as a point of reference. The analytical content of the report will be decided by the Consortium, setting up the methodology for conducting the research as well as quantitative and qualitative standards.  Partner 4 will coordinate this action, with the active participation of all partners from the choice of the content to the draft of each part.  The 40 pages report, after being validated by the Steering Committee, will be available in English and in electronic version, downloadable from the project website for a larger diffusion and use. The existence of this material will be largely diffused by all partners to their professional networks, as well as to national and EU stakeholders.  Duration: M34, 1 month  Budget: 5.838,00€
  • 45. Dissemination & Valorisation WP 6, Awareness raising activities  As in most cases aged persons are unaware of the fact that they are being discriminated, special activities aim at sensitizing both employers and aged workforce are planned to be implemented, such as workshops on age management concept benefits, study tours for sensitising entrepreneurs, seminars for HR managers and for aged workforce. WP7, Dissemination of results  Following a methodology to be defined by the consortium, a communication plan will accompany the project all over its duration, that will include: a publicity campaign (website and discussion forum, brochures, flyers, posters, electronic newsletters, electronic dissemination of outputs) for paper and electronic dissemination of the project, a press campaign (press-conferences, press-releases, radio spots) and a Dissemination Conference. The Discussion Forum will be used as a tool for transferring outputs at regional, national and European level. WP8, Mainstreaming and results exploitation  This work package will last one year, to prepare the project for its exploitation even after the end of the project life time. The mainstreaming of the project results and outputs is designed to limit early retirement and encourage the recruitment and retention of older workers. A Mainstreaming Action Plan is planned within the framework of the project in order to support the transfer of practices and methodologies experimented to different systems. Furthermore, a Results Exploitation Action Plan will be delivered in order to identify results to be utilised and transferred. The mainstreaming and exploitation strategy will be multilevel (from local to European) and multi-actor oriented. 46
  • 47. Indicators  To Be Defined 48