SlideShare una empresa de Scribd logo
1 de 31
Sunset clauses and
quantification of damages
When may a Vendor rescind a contract?
When is it appropriate to assess damages at a date other than the date of
breach?
Legalwise Second Annual Property Law Seminar
9 March 2016
Laina Chan
Barrister at Ninth Floor Wentworth Chambers
laina chan
barrister
S 66ZL Conveyancing Act 1919
(3) A vendor may rescind an off the plan contract under a
sunset clause if the subject lot has not been created by the
sunset date, but only if:
(a) each purchaser under the contract, at any time after
being served with the notice under subsection (4), consents
in writing to the rescission, or
(b) the vendor has obtained an order of the Supreme Court
under this section permitting the vendor to rescind the
contract under the sunset clause, or
(c) the regulations otherwise permit the vendor to rescind
the contract under the sunset clause.
S 66ZL Conveyancing Act 1919
(6) The Supreme Court may on the application of a
vendor under an off the plan contract make an order
permitting the vendor to rescind the contract under a
sunset clause but only if the vendor satisfies the Court
that making the order is just and equitable in all the
circumstances.
S 66ZL Conveyancing Act 1919
(7) In determining whether it is just and equitable in all the circumstances the
Court is to take the following into account:
(a) the terms of the off the plan contract,
(b) whether the vendor has acted unreasonably or in bad faith,
(c) the reason for the delay in creating the subject lot,
(d) the likely date on which the subject lot will be created,
(e) whether the subject lot has increased in value,
(f) the effect of the rescission on each purchaser,
(g) any other matter that the Court considers to be relevant,
(h) any other matter prescribed by the regulations.
S 66ZL Conveyancing Act 1919
• Regulations are currently silent
• Ss 66ZL(7) is prescriptive.
• In determining whether it is just and equitable for the
developer to rescind the contract and to illuminate
the likely approach of the courts in relation to ss
66ZL, the following cases are instructive.
Godfrey Constructions Pty Ltd v Kanangra Park Pty
Ltd (1972) 128 CLR 529
• ‘if the V shall be unable or unwilling to comply with
or remove any objection or requisition which the
purchaser has made and shall not waive within 14
days after the V has given him notice of intention to
rescind this agreement, the V, whether he has or
has not attempted to remove or comply with such
objection or requisition, and notwithstanding any
negotiation or litigation in respect thereof, and
whether the P has or has not taken possession shall
be entitled by notice in writing to rescind this
agreement.’
laina chan
barrister
Godfrey Constructions Pty Ltd v Kanangra Park Pty
Ltd (1972) 128 CLR 529
• original purpose - improper and extraneous
purposes
• bona fides
• reasonableness
• not an arbitrary power
laina chan
barrister
Woolcott v Peggie (1889) 15 App Cas 42
• The vendor was entitled to rescind the contract,
provided he acted in good faith.
laina chan
barrister
In re Jackson and Haden’s Contract [1906] 1 Ch 412
• something on the part of the vendor less than the
law requires of him in such cases.
• may stop short of fraud
• for example, a reckless disregard by the vendor of
his duty as to accuracy of statement when he is
making a statement with a view to other people
acting on it as correct
• look at circumstances as a whole
Selkirk v Romar Investments Ltd [1963] 3 All ER 994
• Clause 3(3) of the agreement conferred power on
the vendor, if any requisition should be insisted on
with which he should be unable or unwilling to
comply, to rescind the contract by notice in writing.
Selkirk v Romar Investments Ltd [1963] 3 All ER 994
• A vendor's position, for this purpose, has to be
ascertained as at the date when he enters into his
contract
• not to be arbitrary or without reason
• a vendor has to be reasonable: he does not have to
be beyond criticism before he can exercise his right
to recission
laina chan
barrister
Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575
• cl 14 contained the usual provision allowing the
vendors to give notice of intention to rescind if
‘unable or unwilling to comply with or remove any
objection or requisition’ and to rescind if the
purchaser did not waive the objection or requisition
within fourteen days of the notice
laina chan
barrister
Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575
• begin with a contractual right to rescind, all the
circumstances covered by clause 14 being present.
• onus on the P to convince the V that V may not use
its contractual right
• take the circumstances of the case as a whole
laina chan
barrister
Burger King Corporation v Hungry Jack’s Pty Ltd
(2001 69 NSWLR 558
• An action by Hungry Jack’s (franchisee) against
Burger King (franchisor) for the latter’s alleged
wrongful termination of an agreement made
between them and its breach of certain terms
alleged to have been implied in that agreement.
laina chan
barrister
Burger King Corporation v Hungry Jack’s Pty Ltd
(2001 69 NSWLR 558
• general rescission clauses may not be used ‘for
improper and extraneous purposes: Godfrey
Constructions Pty Ltd v Kanangra Park Pty Ltd
• the Contract Review Act 1980, the Credit Act 1984
and s 51A of the Trade Practices Act 1974 (Cth)
• implied obligation of good faith and reasonableness
• disentitling conduct of vendor
laina chan
barrister
Tanwar v Cauchi (2003) 217 CLR 315
• The purchaser was unable to complete the contracts
because of a delay in obtaining finance.
• Finance became available the following day.
• The vendors were aware that the purchaser then
wished to complete the contracts but issued notices
of termination.
• Proceedings for specific performance.
laina chan
barrister
Tanwar v Cauchi (2003) 217 CLR 315
• the vendors had not caused or contributed in any
significant way to the purchaser’s breach
• it was not unconscientious for them to exercise their
contractual right to terminate the contracts.
• relief on the ground of accident was not available
because the possibility of breach was reasonably
within the contemplation of the purchaser.
laina chan
barrister
Ginger Development Enterprises Pty Ltd v Crown
Developments (2003) 12 BPR 22,607
• special condition 30 referred to the ‘caveats’ that
were on the title of the property.
• in the draft contract, special condition 55 referred to
caveats the presence of which were to be
acknowledged by the purchaser. However, special
condition 55 had been deleted from the contract
before exchange.
laina chan
barrister
Ginger Development Enterprises Pty Ltd v Crown
Developments (2003) 12 BPR 22,607
• obligation on the part of the person giving the
transfer to do all that was reasonable to ensure that
the sale could proceed to completion.
• Vendor had issued lapsing notices.
• Vendor should have sought an order under s 74MA
of the RPA to prevent the lodgment of further
successive caveats.
laina chan
barrister
Actall Pty Ltd v Pacific Bay Development Pty Ltd
[2006] NSWCA 190
• Clauses 28.2 and 28.3 of the Contract provided:
• “28.2 The vendor must do everything reasonable to have
the plan registered within 6 months after the contract
date …
• 28.3 If the plan is not registered within that time and in
that manner –
• 28.3.1 the purchaser can rescind; and
• 28.3.2 the vendor can rescind, but only if the vendor has
complied with clause 28.2.”
laina chan
barrister
Actall Pty Ltd v Pacific Bay Development Pty Ltd
[2006] NSWCA 190
• Allegation that the Vendor had an ulterior motive
“as an excuse to enable themselves to get rid
of the contract for some ulterior purpose, such
as to obtain a higher price for the land from
some other purchaser”
• The condition precedent to the right to rescind
contained in cl 28.2 is a significant protection to the
purchaser
• No need for equity to intervene.
laina chan
barrister
Cordon Investments Pty Ltd v Lesdor Properties Pty
Ltd (2013) 29 BCL 329
• Lesdor owned certain property.
• It contracted with Cordon for Cordon to develop the
property. Cordon was responsible for obtaining all
necessary approvals and for all construction costs, and
was to be reimbursed its actual costs from a loan it had
obtained to fund the development.
• Cordon’s profit was to be derived from the sale of certain
units in the project to the extent the proceeds exceeded
the development costs. Lesdor was entitled to retain the
balance of the units.
• Works were allegedly defective and Lesdor refused to
sign the strata plan
laina chan
barrister
Cordon Investments Pty Ltd v Lesdor Properties Pty
Ltd (2013) 29 BCL 329
• Lesdor repaid the loan out of another loan and
purported to terminate the contract relying upon
Cordon’s alleged renunciation in insisting on other
than defect-free completion.
• Lesdor took possession of the units that would have
gone to Cordon
• Cordon sued for damages for breach of contract.
laina chan
barrister
Cordon Investments Pty Ltd v Lesdor Properties Pty
Ltd (2013) 29 BCL 329
• It was appropriate to imply into the contract an
obligation that the parties would act in good faith
towards each other.
• No breach.
• Obligation could not be inconsistent with the terms
of the contract.
laina chan
barrister
Johnson v Perez (1988) 166 CLR 351 at 355
• The normal measure is the contract price less the
market price at the contractual time fixed for
completion.
• If the market price at the time fixed for completion
exceeds the contract price the vendor has not
suffered any damage by the loss of the bargain:
Carpenter v McGrath (1996) 40 NSWLR 39 at 59.
laina chan
barrister
HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd
(2004) 217 CLR 640 at 667
• Where there is no readily available market a later
date may be appropriate.
laina chan
barrister
HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd
(2004) 217 CLR 640 at 657[36]
• A key qualification which prevents the ordinary rule
from being inflexible is that the test does not depend
upon the difference between price and market value
but instead depends on the difference between price
and real value or fair value or fair or real value or
intrinsic value or true value or actual value or what
the asset was truly worth or really worth or what
would have been a fair price to be paid in the
circumstances.
• The distinction is an old and fundamental one.
laina chan
barrister
HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd
(2004) 217 CLR 640 at 657-8 [37]
• Other reasons why the law does not limit recovery
by reference to market value is that subject to
mitigation issues, the plaintiff is ‘not bound to sell
them’.
• Another is that there may not be a market or if for
some other reason the plaintiff is “locked in” to
holding the asset. In each of these circumstances,
the plaintiff may not have acted unreasonably in
retaining the asset.
laina chan
barrister
HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd
(2004) 217 CLR 640 at 657-8 [37]
• market value may be disregarded if they are
‘delusive or fictitious’ because they are the result of
‘a fraudulent prospectus, manipulation of the market
or some other improper practice on the part of the
defendant’
laina chan
barrister
HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd
(2004) 217 CLR 640 at 668
• The comparison of price and value at the date of
acquisition (which was the date of loss in the instant
case) as a test may produce a fair result ‘if the asset
acquired is a readily marketable asset and there is
no special feature (such as a continuing
misrepresentation or the purchaser being locked into
a business that he has acquired)’
laina chan
barrister
Filmlock Pty Ltd v Nissi Investments Pty Ltd (No 2)
[2013] NSWSC 959
• Damages assessed at date of resale rather than date of
breach
• Ng v Filmlock Pty Ltd (2014) 88 NSWLR 146 – appeal on
quantum
• NSWSC erred in concluding that difference between
price payable under sale contract and price realised
under resale contract represented appropriate measure
of damages
• In an appropriate case, damages could be quantified at a
time other than the date of breach
laina chan
barrister

Más contenido relacionado

La actualidad más candente

Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction Projects
Laina Chan
 
Contract law & application
Contract law & applicationContract law & application
Contract law & application
Donna Kesot
 
Lecture 8 Exclusion and Limiting Clauses - Cases
Lecture 8   Exclusion and Limiting Clauses - CasesLecture 8   Exclusion and Limiting Clauses - Cases
Lecture 8 Exclusion and Limiting Clauses - Cases
Ramona Vansluytman
 
Lecture 2 formation of a contract
Lecture 2   formation of a contractLecture 2   formation of a contract
Lecture 2 formation of a contract
Ramona Vansluytman
 
Specific performance, can parties contract out
Specific performance, can parties contract outSpecific performance, can parties contract out
Specific performance, can parties contract out
joseph-omwenga
 
Lecture 14 undue influence - cases
Lecture 14   undue influence - casesLecture 14   undue influence - cases
Lecture 14 undue influence - cases
Ramona Vansluytman
 

La actualidad más candente (20)

Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction Projects
 
Rights of the Parties and Discharge; Remedies for Breach of Contract
Rights of the Parties and Discharge; Remedies for Breach of ContractRights of the Parties and Discharge; Remedies for Breach of Contract
Rights of the Parties and Discharge; Remedies for Breach of Contract
 
Lecture 12 privity - notes
Lecture 12   privity - notesLecture 12   privity - notes
Lecture 12 privity - notes
 
Lecture 13 duress - notes
Lecture 13   duress - notesLecture 13   duress - notes
Lecture 13 duress - notes
 
Contracts terms - express, implied, incorporation
Contracts terms - express, implied, incorporationContracts terms - express, implied, incorporation
Contracts terms - express, implied, incorporation
 
Liquidated damages and penalty clause
Liquidated damages and penalty clauseLiquidated damages and penalty clause
Liquidated damages and penalty clause
 
Contract assignment
Contract assignmentContract assignment
Contract assignment
 
Powerpoint for New York State Bar Lecture
Powerpoint for New York State Bar LecturePowerpoint for New York State Bar Lecture
Powerpoint for New York State Bar Lecture
 
Evergreen Clause Fundamentals
Evergreen Clause FundamentalsEvergreen Clause Fundamentals
Evergreen Clause Fundamentals
 
Lecture 8 Collateral Contracts - Notes
Lecture 8   Collateral Contracts - NotesLecture 8   Collateral Contracts - Notes
Lecture 8 Collateral Contracts - Notes
 
Parties 2014
Parties 2014Parties 2014
Parties 2014
 
Remedies
RemediesRemedies
Remedies
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Contract law & application
Contract law & applicationContract law & application
Contract law & application
 
Lecture 8 Exclusion and Limiting Clauses - Cases
Lecture 8   Exclusion and Limiting Clauses - CasesLecture 8   Exclusion and Limiting Clauses - Cases
Lecture 8 Exclusion and Limiting Clauses - Cases
 
Reicon14 session 3 final ppt
Reicon14 session 3 final pptReicon14 session 3 final ppt
Reicon14 session 3 final ppt
 
Lecture 2 formation of a contract
Lecture 2   formation of a contractLecture 2   formation of a contract
Lecture 2 formation of a contract
 
Specific performance, can parties contract out
Specific performance, can parties contract outSpecific performance, can parties contract out
Specific performance, can parties contract out
 
Lecture 14 undue influence - cases
Lecture 14   undue influence - casesLecture 14   undue influence - cases
Lecture 14 undue influence - cases
 
Lecture 13 duress - cases
Lecture 13   duress - casesLecture 13   duress - cases
Lecture 13 duress - cases
 

Similar a Powerpoint for Legalwise Annual Property Seminar March 2016

Revstone sale transaction support agreement summary
Revstone sale transaction support agreement summaryRevstone sale transaction support agreement summary
Revstone sale transaction support agreement summary
Randall Reese
 
3차시 제2장 국제매매협약 매도인의 의무
3차시   제2장 국제매매협약 매도인의 의무3차시   제2장 국제매매협약 매도인의 의무
3차시 제2장 국제매매협약 매도인의 의무
Kunseo Park
 
How to Get Out of Your Timeshare
How to Get Out of Your TimeshareHow to Get Out of Your Timeshare
How to Get Out of Your Timeshare
PotomacLegalGroup
 
BUS 115 Chap011 written contracts
BUS 115 Chap011   written contractsBUS 115 Chap011   written contracts
BUS 115 Chap011 written contracts
neogenesis6
 
Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...
Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...
Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...
Tara Kissel, M.Ed
 
Opposition.Final
Opposition.FinalOpposition.Final
Opposition.Final
Mark Sharf
 
Chapter 18 – Performance and Remedies
Chapter 18 – Performance and RemediesChapter 18 – Performance and Remedies
Chapter 18 – Performance and Remedies
UAF_BA330
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
Ryan Hatton
 

Similar a Powerpoint for Legalwise Annual Property Seminar March 2016 (20)

WORKSHOP 2 FIRM B1 MORTGAGES.pptx
WORKSHOP 2 FIRM B1 MORTGAGES.pptxWORKSHOP 2 FIRM B1 MORTGAGES.pptx
WORKSHOP 2 FIRM B1 MORTGAGES.pptx
 
Rescission for Breach
Rescission for BreachRescission for Breach
Rescission for Breach
 
Focus on Retail
Focus on RetailFocus on Retail
Focus on Retail
 
Remedies for Breach of Contract
Remedies for Breach of ContractRemedies for Breach of Contract
Remedies for Breach of Contract
 
Specific performance
Specific performanceSpecific performance
Specific performance
 
Revstone sale transaction support agreement summary
Revstone sale transaction support agreement summaryRevstone sale transaction support agreement summary
Revstone sale transaction support agreement summary
 
Businesslawnotes
BusinesslawnotesBusinesslawnotes
Businesslawnotes
 
3차시 제2장 국제매매협약 매도인의 의무
3차시   제2장 국제매매협약 매도인의 의무3차시   제2장 국제매매협약 매도인의 의무
3차시 제2장 국제매매협약 매도인의 의무
 
How to Get Out of Your Timeshare
How to Get Out of Your TimeshareHow to Get Out of Your Timeshare
How to Get Out of Your Timeshare
 
BUS 115 Chap011 written contracts
BUS 115 Chap011   written contractsBUS 115 Chap011   written contracts
BUS 115 Chap011 written contracts
 
Business Law lect 7 & 8.pptx
Business Law lect 7 & 8.pptxBusiness Law lect 7 & 8.pptx
Business Law lect 7 & 8.pptx
 
Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...
Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...
Chapter 22: Sales Contracts: Domestic & Global Aspects of Preformace, Breach,...
 
Business law notes of module 1 (sem 2)
Business law notes of module 1 (sem 2)Business law notes of module 1 (sem 2)
Business law notes of module 1 (sem 2)
 
Opposition.Final
Opposition.FinalOpposition.Final
Opposition.Final
 
Contract of formation of sales
Contract of formation of sales Contract of formation of sales
Contract of formation of sales
 
Contract Interpretation - SP21
Contract Interpretation - SP21Contract Interpretation - SP21
Contract Interpretation - SP21
 
Prohibitory orders
Prohibitory ordersProhibitory orders
Prohibitory orders
 
Chapter 18 – Performance and Remedies
Chapter 18 – Performance and RemediesChapter 18 – Performance and Remedies
Chapter 18 – Performance and Remedies
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptx
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 

Más de Laina Chan

When Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
When Conveyances Go Wrong - Purchaser’s Remedies for Vendor BreachesWhen Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
When Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
Laina Chan
 

Más de Laina Chan (6)

Construction Law Intensive - UNSW Edge
Construction Law Intensive - UNSW EdgeConstruction Law Intensive - UNSW Edge
Construction Law Intensive - UNSW Edge
 
Handout pillar 1 regulatory reforms - laina chan bar cpd 9 march 2021
Handout   pillar 1 regulatory reforms - laina chan bar cpd 9 march 2021Handout   pillar 1 regulatory reforms - laina chan bar cpd 9 march 2021
Handout pillar 1 regulatory reforms - laina chan bar cpd 9 march 2021
 
Mediation, Adjudication and Arbitration - What gets the job done?
Mediation, Adjudication and Arbitration  - What gets the job done?Mediation, Adjudication and Arbitration  - What gets the job done?
Mediation, Adjudication and Arbitration - What gets the job done?
 
Doing deals and avoiding squeals
Doing deals and avoiding squealsDoing deals and avoiding squeals
Doing deals and avoiding squeals
 
Rob Harper SC & Laina Chan How to brief counsel and Why
Rob Harper SC & Laina Chan   How to brief counsel and WhyRob Harper SC & Laina Chan   How to brief counsel and Why
Rob Harper SC & Laina Chan How to brief counsel and Why
 
When Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
When Conveyances Go Wrong - Purchaser’s Remedies for Vendor BreachesWhen Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
When Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
 

Último

Types of Agricultural markets LLB- SEM I
Types of Agricultural markets LLB- SEM ITypes of Agricultural markets LLB- SEM I
Types of Agricultural markets LLB- SEM I
yogita9398
 
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSSASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
CssSpamx
 
一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理
e9733fc35af6
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
trryfxkn
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
e9733fc35af6
 
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
ss
 
一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书
irst
 
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
ss
 
一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理
一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理
一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理
e9733fc35af6
 

Último (20)

Common Legal Risks in Hiring and Firing Practices.pdf
Common Legal Risks in Hiring and Firing Practices.pdfCommon Legal Risks in Hiring and Firing Practices.pdf
Common Legal Risks in Hiring and Firing Practices.pdf
 
judicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxjudicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptx
 
Elective Course on Forensic Science in Law
Elective Course on Forensic Science  in LawElective Course on Forensic Science  in Law
Elective Course on Forensic Science in Law
 
Chambers Global Practice Guide - Canada M&A
Chambers Global Practice Guide - Canada M&AChambers Global Practice Guide - Canada M&A
Chambers Global Practice Guide - Canada M&A
 
Types of Agricultural markets LLB- SEM I
Types of Agricultural markets LLB- SEM ITypes of Agricultural markets LLB- SEM I
Types of Agricultural markets LLB- SEM I
 
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSSASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
 
一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
一比一原版(McMaster毕业证书)麦克马斯特大学毕业证学历认证可查认证
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
Reason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in IndiaReason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in India
 
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证书)皇家墨尔本理工大学毕业证如何办理
 
一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书一比一原版(USC毕业证书)南加州大学毕业证学位证书
一比一原版(USC毕业证书)南加州大学毕业证学位证书
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
 
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
一比一原版(UNSW毕业证书)新南威尔士大学毕业证如何办理
 
一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理
一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理
一比一原版(AUT毕业证书)新西兰奥克兰理工大学毕业证如何办理
 
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam TakersPhilippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
 

Powerpoint for Legalwise Annual Property Seminar March 2016

  • 1. Sunset clauses and quantification of damages When may a Vendor rescind a contract? When is it appropriate to assess damages at a date other than the date of breach? Legalwise Second Annual Property Law Seminar 9 March 2016 Laina Chan Barrister at Ninth Floor Wentworth Chambers laina chan barrister
  • 2. S 66ZL Conveyancing Act 1919 (3) A vendor may rescind an off the plan contract under a sunset clause if the subject lot has not been created by the sunset date, but only if: (a) each purchaser under the contract, at any time after being served with the notice under subsection (4), consents in writing to the rescission, or (b) the vendor has obtained an order of the Supreme Court under this section permitting the vendor to rescind the contract under the sunset clause, or (c) the regulations otherwise permit the vendor to rescind the contract under the sunset clause.
  • 3. S 66ZL Conveyancing Act 1919 (6) The Supreme Court may on the application of a vendor under an off the plan contract make an order permitting the vendor to rescind the contract under a sunset clause but only if the vendor satisfies the Court that making the order is just and equitable in all the circumstances.
  • 4. S 66ZL Conveyancing Act 1919 (7) In determining whether it is just and equitable in all the circumstances the Court is to take the following into account: (a) the terms of the off the plan contract, (b) whether the vendor has acted unreasonably or in bad faith, (c) the reason for the delay in creating the subject lot, (d) the likely date on which the subject lot will be created, (e) whether the subject lot has increased in value, (f) the effect of the rescission on each purchaser, (g) any other matter that the Court considers to be relevant, (h) any other matter prescribed by the regulations.
  • 5. S 66ZL Conveyancing Act 1919 • Regulations are currently silent • Ss 66ZL(7) is prescriptive. • In determining whether it is just and equitable for the developer to rescind the contract and to illuminate the likely approach of the courts in relation to ss 66ZL, the following cases are instructive.
  • 6. Godfrey Constructions Pty Ltd v Kanangra Park Pty Ltd (1972) 128 CLR 529 • ‘if the V shall be unable or unwilling to comply with or remove any objection or requisition which the purchaser has made and shall not waive within 14 days after the V has given him notice of intention to rescind this agreement, the V, whether he has or has not attempted to remove or comply with such objection or requisition, and notwithstanding any negotiation or litigation in respect thereof, and whether the P has or has not taken possession shall be entitled by notice in writing to rescind this agreement.’ laina chan barrister
  • 7. Godfrey Constructions Pty Ltd v Kanangra Park Pty Ltd (1972) 128 CLR 529 • original purpose - improper and extraneous purposes • bona fides • reasonableness • not an arbitrary power laina chan barrister
  • 8. Woolcott v Peggie (1889) 15 App Cas 42 • The vendor was entitled to rescind the contract, provided he acted in good faith. laina chan barrister
  • 9. In re Jackson and Haden’s Contract [1906] 1 Ch 412 • something on the part of the vendor less than the law requires of him in such cases. • may stop short of fraud • for example, a reckless disregard by the vendor of his duty as to accuracy of statement when he is making a statement with a view to other people acting on it as correct • look at circumstances as a whole
  • 10. Selkirk v Romar Investments Ltd [1963] 3 All ER 994 • Clause 3(3) of the agreement conferred power on the vendor, if any requisition should be insisted on with which he should be unable or unwilling to comply, to rescind the contract by notice in writing.
  • 11. Selkirk v Romar Investments Ltd [1963] 3 All ER 994 • A vendor's position, for this purpose, has to be ascertained as at the date when he enters into his contract • not to be arbitrary or without reason • a vendor has to be reasonable: he does not have to be beyond criticism before he can exercise his right to recission laina chan barrister
  • 12. Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575 • cl 14 contained the usual provision allowing the vendors to give notice of intention to rescind if ‘unable or unwilling to comply with or remove any objection or requisition’ and to rescind if the purchaser did not waive the objection or requisition within fourteen days of the notice laina chan barrister
  • 13. Pierce Bell Sales Pty Ltd v Frazer (1973) 130 CLR 575 • begin with a contractual right to rescind, all the circumstances covered by clause 14 being present. • onus on the P to convince the V that V may not use its contractual right • take the circumstances of the case as a whole laina chan barrister
  • 14. Burger King Corporation v Hungry Jack’s Pty Ltd (2001 69 NSWLR 558 • An action by Hungry Jack’s (franchisee) against Burger King (franchisor) for the latter’s alleged wrongful termination of an agreement made between them and its breach of certain terms alleged to have been implied in that agreement. laina chan barrister
  • 15. Burger King Corporation v Hungry Jack’s Pty Ltd (2001 69 NSWLR 558 • general rescission clauses may not be used ‘for improper and extraneous purposes: Godfrey Constructions Pty Ltd v Kanangra Park Pty Ltd • the Contract Review Act 1980, the Credit Act 1984 and s 51A of the Trade Practices Act 1974 (Cth) • implied obligation of good faith and reasonableness • disentitling conduct of vendor laina chan barrister
  • 16. Tanwar v Cauchi (2003) 217 CLR 315 • The purchaser was unable to complete the contracts because of a delay in obtaining finance. • Finance became available the following day. • The vendors were aware that the purchaser then wished to complete the contracts but issued notices of termination. • Proceedings for specific performance. laina chan barrister
  • 17. Tanwar v Cauchi (2003) 217 CLR 315 • the vendors had not caused or contributed in any significant way to the purchaser’s breach • it was not unconscientious for them to exercise their contractual right to terminate the contracts. • relief on the ground of accident was not available because the possibility of breach was reasonably within the contemplation of the purchaser. laina chan barrister
  • 18. Ginger Development Enterprises Pty Ltd v Crown Developments (2003) 12 BPR 22,607 • special condition 30 referred to the ‘caveats’ that were on the title of the property. • in the draft contract, special condition 55 referred to caveats the presence of which were to be acknowledged by the purchaser. However, special condition 55 had been deleted from the contract before exchange. laina chan barrister
  • 19. Ginger Development Enterprises Pty Ltd v Crown Developments (2003) 12 BPR 22,607 • obligation on the part of the person giving the transfer to do all that was reasonable to ensure that the sale could proceed to completion. • Vendor had issued lapsing notices. • Vendor should have sought an order under s 74MA of the RPA to prevent the lodgment of further successive caveats. laina chan barrister
  • 20. Actall Pty Ltd v Pacific Bay Development Pty Ltd [2006] NSWCA 190 • Clauses 28.2 and 28.3 of the Contract provided: • “28.2 The vendor must do everything reasonable to have the plan registered within 6 months after the contract date … • 28.3 If the plan is not registered within that time and in that manner – • 28.3.1 the purchaser can rescind; and • 28.3.2 the vendor can rescind, but only if the vendor has complied with clause 28.2.” laina chan barrister
  • 21. Actall Pty Ltd v Pacific Bay Development Pty Ltd [2006] NSWCA 190 • Allegation that the Vendor had an ulterior motive “as an excuse to enable themselves to get rid of the contract for some ulterior purpose, such as to obtain a higher price for the land from some other purchaser” • The condition precedent to the right to rescind contained in cl 28.2 is a significant protection to the purchaser • No need for equity to intervene. laina chan barrister
  • 22. Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd (2013) 29 BCL 329 • Lesdor owned certain property. • It contracted with Cordon for Cordon to develop the property. Cordon was responsible for obtaining all necessary approvals and for all construction costs, and was to be reimbursed its actual costs from a loan it had obtained to fund the development. • Cordon’s profit was to be derived from the sale of certain units in the project to the extent the proceeds exceeded the development costs. Lesdor was entitled to retain the balance of the units. • Works were allegedly defective and Lesdor refused to sign the strata plan laina chan barrister
  • 23. Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd (2013) 29 BCL 329 • Lesdor repaid the loan out of another loan and purported to terminate the contract relying upon Cordon’s alleged renunciation in insisting on other than defect-free completion. • Lesdor took possession of the units that would have gone to Cordon • Cordon sued for damages for breach of contract. laina chan barrister
  • 24. Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd (2013) 29 BCL 329 • It was appropriate to imply into the contract an obligation that the parties would act in good faith towards each other. • No breach. • Obligation could not be inconsistent with the terms of the contract. laina chan barrister
  • 25. Johnson v Perez (1988) 166 CLR 351 at 355 • The normal measure is the contract price less the market price at the contractual time fixed for completion. • If the market price at the time fixed for completion exceeds the contract price the vendor has not suffered any damage by the loss of the bargain: Carpenter v McGrath (1996) 40 NSWLR 39 at 59. laina chan barrister
  • 26. HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd (2004) 217 CLR 640 at 667 • Where there is no readily available market a later date may be appropriate. laina chan barrister
  • 27. HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd (2004) 217 CLR 640 at 657[36] • A key qualification which prevents the ordinary rule from being inflexible is that the test does not depend upon the difference between price and market value but instead depends on the difference between price and real value or fair value or fair or real value or intrinsic value or true value or actual value or what the asset was truly worth or really worth or what would have been a fair price to be paid in the circumstances. • The distinction is an old and fundamental one. laina chan barrister
  • 28. HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd (2004) 217 CLR 640 at 657-8 [37] • Other reasons why the law does not limit recovery by reference to market value is that subject to mitigation issues, the plaintiff is ‘not bound to sell them’. • Another is that there may not be a market or if for some other reason the plaintiff is “locked in” to holding the asset. In each of these circumstances, the plaintiff may not have acted unreasonably in retaining the asset. laina chan barrister
  • 29. HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd (2004) 217 CLR 640 at 657-8 [37] • market value may be disregarded if they are ‘delusive or fictitious’ because they are the result of ‘a fraudulent prospectus, manipulation of the market or some other improper practice on the part of the defendant’ laina chan barrister
  • 30. HTW Valuers (Central Qld) Pty Ltd v Astonland Pty Ltd (2004) 217 CLR 640 at 668 • The comparison of price and value at the date of acquisition (which was the date of loss in the instant case) as a test may produce a fair result ‘if the asset acquired is a readily marketable asset and there is no special feature (such as a continuing misrepresentation or the purchaser being locked into a business that he has acquired)’ laina chan barrister
  • 31. Filmlock Pty Ltd v Nissi Investments Pty Ltd (No 2) [2013] NSWSC 959 • Damages assessed at date of resale rather than date of breach • Ng v Filmlock Pty Ltd (2014) 88 NSWLR 146 – appeal on quantum • NSWSC erred in concluding that difference between price payable under sale contract and price realised under resale contract represented appropriate measure of damages • In an appropriate case, damages could be quantified at a time other than the date of breach laina chan barrister

Notas del editor

  1. In force since