SlideShare una empresa de Scribd logo
1 de 6
Descargar para leer sin conexión
Order’s Physical Process Flow
What do your excel results tell you?
The graphs on the last pages represent the time per order and time per board based on the
standard process flow information in exhibit 2. The order sizes used are 1, 10, 100, 500, and 1000.
In graph 1 there is positive correlation between order size and the time it takes to complete the
order. As the order size increases more time is needed to complete the order.
In graph 2 there correlation between time spent per board and order size is negative. The larger
the order, the less time spent per board is due to avoiding extra setup time along with using the CNC Drill
and CNC Router for the fastest production time.
Donner Company currently promises delivery in three weeks for order less than 1000 boards and
five weeks for larger orders. Graph 1 shows an order of 1000 boards taking approximately 6000 minutes,
(or 100 hours) to complete production. Donner does not consider the time spent per board when
estimating delivery dates and taking large orders. Graph 2 shows for orders larger than 100 the time spent
per board is greatly reduced. Orders greater than 500 boards take less than 7 minutes per board while
orders of 10 boards can take over 380 minutes due to setup time. While Donner Company considers the
number of board per order when estimating the delivery date they also need to consider what other orders
the currently have, the size of their other current orders, and what machinery is being used for the current
productions. Donner Company needs to improve its order scheduling and sync it with the production
process. They need to focus on eliminating idle time and having orders on schedule, ready to be shipped
by the customer delivery date.
Utilization of Operations
To asses a process’s utilization, one must first figure out the amount of time the facility is
available for operations. Second, the amount of time the process is used must be present. In the Donner
Case study we are given data for the total process of manufactured printed circuit boards in September of
1987. In that month there were a total of 30 days, but only 22 were part of the typical work week. Of
those 22 days one was a federal holiday, the 7th was “Labor Day”, leaving 21 days of operations for the
facility.
As per the case study, it is mentioned that there are 22 production employees. With these 22
employees operating in 3 departments with a total of 13 subset process’ it can be assumed that this
company is only operating on a 1 shift schedule, approximately 8 hours a day. The case study explicitly
states that many of employees are “crossed-trained” in multiple departments, so we can also assume that
there are supplement employees to cover during break times. This leads us to conclude that they are fully
functioning the whole 8 hours of each available work day. As previously stated, there were 21 work days
in September of 1987 and with 8 hours of a functioning facility we can calculate that there were 168
hours of availability (21days x 8hr/day).
The usage time of each processes is stated in Exhibit 2 Standard Process Flow of the case study.
To find the utilization of the artwork generation we would simply take the total hours of usage (24.2hrs)
and divide it by the total hours available for the facility (168), [24.2/168=.14404 or about 14.4%]. Now
finding the utilization of the CNC Drill might prove to be a little harder. Since the setup time is “almost
entirely made up of required computer control” we can’t actually uses the total hours figure given to us,
instead we must take the Run Time (9,650mins) and translate it into hours. This gives us a look at the
actual time excluding the initial computer setup [9,650/60 = 160.83 hours]. To find its utilization one
must take the time of use (160.83hrs) and divide it by the total available hours for the month (168hrs). We
can conclude that the CNC Drill operates at a utilization rate of 95.7% [160.83/168]. Similarly, to find the
utilization of the CNC Router we ignore the initial computer setup time (for the same reason) and
translate the actual setup time into hours [2,166mins/60 = 36.1hrs]. With the new accurate number of
usage hours (36.1hrs) we can find the utilization rate by dividing that by the total hours of operations in
September of 1987 (168) to find the rate of 21.5% [36.1/168].
For an ideal performance a company should be using whichever process is best suited for each
specific type of order. In this process there are 2 steps that allow us to choose a process to fit an order’s
needs, they are CNC Drill versus the Manual process and CNC Router versus the Punch Press. To be
most effective Donner should be picking the best option from each group, respectively. So we must figure
out at what order sizes the company should choose to use the newer CNC technology. To compare we
need to set up an equation using fixed and variable times.
For the Manual drill, there is a setup of 15min and a run time per hole of .080 (.08 x 500 holes/per
board = 40mins/per board). For the CNC Drill there is a set up time of 240min and run time of .004 per
hole (.004 x 500 holes/per board = 2mins/per board). Next we set the two equations together leaving the
variable of order size(x) [240 + 2*x = 15 + 40*x] → [225 = 38*x] → [225/38 = x] → 5.921 = x. This tells
us that if the order size is about 5.921 or ≈ 6 Donner should use the CNC Drill. But, they are only using it
on orders with sizes over 140 boards totaling 4,825 boards. This leaves a range of order sizes 6-136
totaling 26 orders and 871 boards that would be better suited using the CNC Drill process. Unfortunately,
as previously discussed the CNC drill is operating at a 95.7% utilization rate, since it is already the
bottleneck of the process, anymore activity would not be advantageous to the company. So due to the
bottleneck effect we can’t possibly functioning at the most efficient rate.
Next we can compare the CNC Router to the Punch Press method in a similar fashion. For the
CNC Router there is a set up time of 150mins and Run Time of .5min per board. The Punch Press
operates with a setup time of 50mins and a Run Time of 1min per board. We must compare these two
equations using the variable of order size (x) [150 +.5*x = 50 +1*x] → [100 = .5*x] → [100/.5 = x] →
200=x. This would imply that we should be using the CNC Router on orders larger than 200 to function at
the highest efficiency. Currently Donner is using the CNC Router process on 6 orders, the smallest at 229
boards, totaling 4,331 boards. It would not be advantageous for Donner to produces the next smallest
order size (200) using the CNC Router, since 200 isn’t greater than the point of indifference of 200 (as
solved previously).
What is your explanation for each of the problems mentioned by Plummer?
Operating Problems
Management had a hard time finding where the main bottleneck was specifically in their system
because there would be a different problem every day in a different operation. All these different setbacks
were happening at random places in the system because each circuit board order was different. Each
customer had special requirements that were different from other orders.
Because he had no way of predicting where the next bottleneck would happen, Flaherty, the shop
supervisor, moved his workers accordingly to the top priority of work. For example, if three works had
finished their manual drilling, he would move them to another task until there were more boards to be
drilled. So essentially if all three workers were busy working on a different task, boards that were waiting
to be drilled had to wait.
Productivity Problems
Plummer, the president of the company, had noticed that some machines were idle more than he
expected them to be. This shows that there is a bottleneck somewhere in production that causes machines
to be idle. Also the Donner Company wasn’t even using their own goals, or time standards for their
operations. This is not a good sign because they need to be using their own numbers and times to create
the company’s own goals.
Under the plating operation, the president noticed that a platter would be inspecting panels and
then would have to walk 18’ to place the panels in the tanks. Altmeyer, the design engineer, concluded
that the walk from her desk to the tanks took up 15% of her time. Plummer stressed his concern that he
thought job improvements would not be beneficial for the company. He thought it would just create more
pileups at other stations. This is not a positive way of thinking when wanting to grow and develop a
company.
Quality Problems
Inspecting the circuit boards is difficult because there is not a specific standard of what a board
should look like because each customer’s order is different. Treating the boards in a careful manner is one
problem, but not meeting the correct qualifications that the customer asked for is a bigger problem
because on the order sheet (which top management writes up along with a blueprint), it lists everything
that is needed for the order to be complete. About 90% the company’s returns are because the customer’s
requirements were not met. 10% of the returns are from damaged boards.
Delivery Problems
In august of 1987, shipments had average nine days late. Lloyd Searby, the sales manager, had
calculated that if The Donner Company had changed its small order deliveries from 3 weeks to 4 weeks,
the company would barely make $2 million, instead of $3 million if they keep the deliveries at 3 weeks.
Plummer had a goal of clearing all work possible out of the shop by the end of every month. This
created a pattern in which the beginning of the month had fewer orders to fulfill than that of the end of the
month, because the goal made people try to rush and get the shop cleared out.
What specific actions should Mr. Plummer take to solve these problems?
Mr. Plummer should focus on what his company does best. This is serving his customers with
exactly what they want, ranging from order size to special requirements for their orders. Mr. Plummer
needs to realize that if there are multiple orders in the system, small orders and big orders, the big orders
are the ones that will take up most of the time, pushing the time back for the small orders. If the size of
orders is substantially different, then there needs to be two separate productions lines so the lines keep
moving. This way each order will essentially take up the same time even if they do have different
qualifications because they will be the same size.
By having two productions lines, one for small orders and one for big orders, machines will rarely
be idle and workers will remain busy, because there will be no stop and start periods. By keeping the
main variable constant, order size, it will be easy for management to spot a bottleneck. Now that there are
two productions lines, running at their own speeds, Plummer needs to find time goals that are fit yet still
demanding for the process. He needs to base these goals from his own lines of production, not from
competing firms, because most likely they have a completely different way of doing things than the
Donner Company. This new way of creating the circuit boards can increase delivery time depending on
the order size. Also, now the company can begin to look for job improvements and workers can master
their own skill with this new layout.
0	
  
1000	
  
2000	
  
3000	
  
4000	
  
5000	
  
6000	
  
7000	
  
0	
   100	
   200	
   300	
   400	
   500	
   600	
   700	
   800	
   900	
   1000	
  
Time	
  Per	
  Order	
  
(Minutes)	
  
Order	
  Size	
  
Donner	
  Company-­‐	
  Graph	
  1	
  
0	
  
50	
  
100	
  
150	
  
200	
  
250	
  
300	
  
350	
  
400	
  
0	
   100	
   200	
   300	
   400	
   500	
   600	
   700	
   800	
   900	
   1000	
  
Time	
  Per	
  Board	
  
(minutes)	
  
Order	
  Size	
  
Donner	
  Company-­‐	
  Graph	
  2	
  
Order Process Flow Optimization

Más contenido relacionado

La actualidad más candente

Shouldice Hospital
Shouldice HospitalShouldice Hospital
Shouldice Hospitaltarunkdl
 
National cranberry case study
National cranberry case studyNational cranberry case study
National cranberry case studyRanjeet Singh
 
Kristen Cookie case study
Kristen Cookie case studyKristen Cookie case study
Kristen Cookie case studyAmit Walawalkar
 
HP Supply Chain Optimization
HP Supply Chain OptimizationHP Supply Chain Optimization
HP Supply Chain OptimizationSwapnil Pillai
 
Wal-Mart Stores in 2003 (HBS Case 9-704-430)
Wal-Mart Stores in 2003 (HBS Case 9-704-430)Wal-Mart Stores in 2003 (HBS Case 9-704-430)
Wal-Mart Stores in 2003 (HBS Case 9-704-430)Aditya Jhunjhunuwala
 
Wal-Mart Stores’ Discount operations
Wal-Mart Stores’ Discount operationsWal-Mart Stores’ Discount operations
Wal-Mart Stores’ Discount operationsAJAL A J
 
Bayonne packaging Case Study Analysis
Bayonne packaging Case Study AnalysisBayonne packaging Case Study Analysis
Bayonne packaging Case Study AnalysisPrashanth Sridhar
 
American Connector Company
American Connector CompanyAmerican Connector Company
American Connector CompanySubhradeep Mitra
 
House of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global FootprintHouse of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global FootprintAbhigyan Singh
 
Clique Pens Pricing: The Writing Implements Division of U.S. Home
Clique Pens Pricing: The Writing Implements Division of U.S. Home Clique Pens Pricing: The Writing Implements Division of U.S. Home
Clique Pens Pricing: The Writing Implements Division of U.S. Home Demin Wang
 
Sports Obermeyer Case
Sports Obermeyer CaseSports Obermeyer Case
Sports Obermeyer CaseGeeta Hansdah
 
Seven- Eleven Japan Co. Case Analysis
Seven- Eleven Japan Co. Case AnalysisSeven- Eleven Japan Co. Case Analysis
Seven- Eleven Japan Co. Case AnalysisGeeta Hansdah
 
Goodyear: The Aquatred Launch : Harvard Case Analysis
Goodyear: The Aquatred Launch : Harvard Case AnalysisGoodyear: The Aquatred Launch : Harvard Case Analysis
Goodyear: The Aquatred Launch : Harvard Case AnalysisSameer Mathur
 

La actualidad más candente (20)

Shouldice Hospital
Shouldice HospitalShouldice Hospital
Shouldice Hospital
 
The Cranberry Case
The Cranberry CaseThe Cranberry Case
The Cranberry Case
 
Shouldice case study
Shouldice case studyShouldice case study
Shouldice case study
 
Toyota- HBS case
Toyota- HBS caseToyota- HBS case
Toyota- HBS case
 
National cranberry case study
National cranberry case studyNational cranberry case study
National cranberry case study
 
Kristen Cookie case study
Kristen Cookie case studyKristen Cookie case study
Kristen Cookie case study
 
HP Supply Chain Optimization
HP Supply Chain OptimizationHP Supply Chain Optimization
HP Supply Chain Optimization
 
Wal-Mart Stores in 2003 (HBS Case 9-704-430)
Wal-Mart Stores in 2003 (HBS Case 9-704-430)Wal-Mart Stores in 2003 (HBS Case 9-704-430)
Wal-Mart Stores in 2003 (HBS Case 9-704-430)
 
Wal-Mart Stores’ Discount operations
Wal-Mart Stores’ Discount operationsWal-Mart Stores’ Discount operations
Wal-Mart Stores’ Discount operations
 
Bayonne packaging Case Study Analysis
Bayonne packaging Case Study AnalysisBayonne packaging Case Study Analysis
Bayonne packaging Case Study Analysis
 
Brunswick motors, inc
Brunswick motors, incBrunswick motors, inc
Brunswick motors, inc
 
Xerox & Fuji Xerox
Xerox & Fuji XeroxXerox & Fuji Xerox
Xerox & Fuji Xerox
 
INGERSOLL RAND-Harvard Case Study
INGERSOLL RAND-Harvard Case StudyINGERSOLL RAND-Harvard Case Study
INGERSOLL RAND-Harvard Case Study
 
American Connector Company
American Connector CompanyAmerican Connector Company
American Connector Company
 
House of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global FootprintHouse of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global Footprint
 
Clique Pens Pricing: The Writing Implements Division of U.S. Home
Clique Pens Pricing: The Writing Implements Division of U.S. Home Clique Pens Pricing: The Writing Implements Division of U.S. Home
Clique Pens Pricing: The Writing Implements Division of U.S. Home
 
Sports Obermeyer Case
Sports Obermeyer CaseSports Obermeyer Case
Sports Obermeyer Case
 
Seven- Eleven Japan Co. Case Analysis
Seven- Eleven Japan Co. Case AnalysisSeven- Eleven Japan Co. Case Analysis
Seven- Eleven Japan Co. Case Analysis
 
Goodyear: The Aquatred Launch : Harvard Case Analysis
Goodyear: The Aquatred Launch : Harvard Case AnalysisGoodyear: The Aquatred Launch : Harvard Case Analysis
Goodyear: The Aquatred Launch : Harvard Case Analysis
 
Manzana insurance
Manzana insuranceManzana insurance
Manzana insurance
 

Destacado

McCombs Fall Case Competition 2014 - Dropbox
McCombs Fall Case Competition 2014 - DropboxMcCombs Fall Case Competition 2014 - Dropbox
McCombs Fall Case Competition 2014 - DropboxJonathan Ong
 
Deloitte qualifyingprompt
Deloitte qualifyingpromptDeloitte qualifyingprompt
Deloitte qualifyingpromptJonathan Ong
 
INFORMS annual meeting case study competition presentation pmg
INFORMS annual meeting case study competition presentation pmgINFORMS annual meeting case study competition presentation pmg
INFORMS annual meeting case study competition presentation pmgPolly Mitchell-Guthrie
 
Cobbs Mad Hats Case Competition
Cobbs Mad Hats Case CompetitionCobbs Mad Hats Case Competition
Cobbs Mad Hats Case CompetitionHenry Cobbs
 
Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011
Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011
Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011CBS Case Competition
 
Presentation by National University of Singapore - Winners of CBS Case Compet...
Presentation by National University of Singapore - Winners of CBS Case Compet...Presentation by National University of Singapore - Winners of CBS Case Compet...
Presentation by National University of Singapore - Winners of CBS Case Compet...CBS Case Competition
 
Deloitte Undergraduate Case Competition 2015 Final Presentation
Deloitte Undergraduate Case Competition 2015 Final PresentationDeloitte Undergraduate Case Competition 2015 Final Presentation
Deloitte Undergraduate Case Competition 2015 Final PresentationJonathan Ong
 
Deloitte Case Competition 2013
Deloitte Case Competition 2013Deloitte Case Competition 2013
Deloitte Case Competition 2013ryanamenges
 
MBA case study presentation template
MBA case study presentation templateMBA case study presentation template
MBA case study presentation templategorvis
 

Destacado (9)

McCombs Fall Case Competition 2014 - Dropbox
McCombs Fall Case Competition 2014 - DropboxMcCombs Fall Case Competition 2014 - Dropbox
McCombs Fall Case Competition 2014 - Dropbox
 
Deloitte qualifyingprompt
Deloitte qualifyingpromptDeloitte qualifyingprompt
Deloitte qualifyingprompt
 
INFORMS annual meeting case study competition presentation pmg
INFORMS annual meeting case study competition presentation pmgINFORMS annual meeting case study competition presentation pmg
INFORMS annual meeting case study competition presentation pmg
 
Cobbs Mad Hats Case Competition
Cobbs Mad Hats Case CompetitionCobbs Mad Hats Case Competition
Cobbs Mad Hats Case Competition
 
Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011
Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011
Presentation by Larsson, Ögren, Troll and Jäger - Winners of Beat The Elite 2011
 
Presentation by National University of Singapore - Winners of CBS Case Compet...
Presentation by National University of Singapore - Winners of CBS Case Compet...Presentation by National University of Singapore - Winners of CBS Case Compet...
Presentation by National University of Singapore - Winners of CBS Case Compet...
 
Deloitte Undergraduate Case Competition 2015 Final Presentation
Deloitte Undergraduate Case Competition 2015 Final PresentationDeloitte Undergraduate Case Competition 2015 Final Presentation
Deloitte Undergraduate Case Competition 2015 Final Presentation
 
Deloitte Case Competition 2013
Deloitte Case Competition 2013Deloitte Case Competition 2013
Deloitte Case Competition 2013
 
MBA case study presentation template
MBA case study presentation templateMBA case study presentation template
MBA case study presentation template
 

Similar a Order Process Flow Optimization

Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industryGanesh TN
 
Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]Gagan306
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materialspikuoec
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materialspikuoec
 
What is cycle time in the manufacturing process
What is cycle time in the manufacturing processWhat is cycle time in the manufacturing process
What is cycle time in the manufacturing processMRPeasy
 
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
 CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docxarnit1
 
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sMba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sChainon
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningRaju Pegada
 
customer relation management presentation roadmap what is known and
customer relation management presentation roadmap  what is known andcustomer relation management presentation roadmap  what is known and
customer relation management presentation roadmap what is known andMohamadIbrahim86
 
Takt Time with Matt Hansen at StatStuff
Takt Time with Matt Hansen at StatStuffTakt Time with Matt Hansen at StatStuff
Takt Time with Matt Hansen at StatStuffMatt Hansen
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineLaukik Raut
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaainfinitepestcontrol
 
C0362015022
C0362015022C0362015022
C0362015022theijes
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Hariharan Ponnusamy
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
Thango© : Extrusion cost savings and die making improvement
Thango© : Extrusion cost savings and die making improvementThango© : Extrusion cost savings and die making improvement
Thango© : Extrusion cost savings and die making improvementThango
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPmeijjournal
 
Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018ramuaa124
 

Similar a Order Process Flow Optimization (20)

Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
 
Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
What is cycle time in the manufacturing process
What is cycle time in the manufacturing processWhat is cycle time in the manufacturing process
What is cycle time in the manufacturing process
 
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
 CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
CENTRE FOR CONTINUING EDUCATION EXECUTIVE MBA (OIL & .docx
 
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sMba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity Planning
 
customer relation management presentation roadmap what is known and
customer relation management presentation roadmap  what is known andcustomer relation management presentation roadmap  what is known and
customer relation management presentation roadmap what is known and
 
Takt Time with Matt Hansen at StatStuff
Takt Time with Matt Hansen at StatStuffTakt Time with Matt Hansen at StatStuff
Takt Time with Matt Hansen at StatStuff
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
 
C0362015022
C0362015022C0362015022
C0362015022
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
Process design
Process designProcess design
Process design
 
Thango© : Extrusion cost savings and die making improvement
Thango© : Extrusion cost savings and die making improvementThango© : Extrusion cost savings and die making improvement
Thango© : Extrusion cost savings and die making improvement
 
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMPPRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
PRODUCTION PROCESS ANALYSIS ON MANUFACTURING OF HYDRAULIC GEAR PUMP
 
Pmm
PmmPmm
Pmm
 
Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018Ops 571 final exam guide (new, 2018
Ops 571 final exam guide (new, 2018
 

Order Process Flow Optimization

  • 2. What do your excel results tell you? The graphs on the last pages represent the time per order and time per board based on the standard process flow information in exhibit 2. The order sizes used are 1, 10, 100, 500, and 1000. In graph 1 there is positive correlation between order size and the time it takes to complete the order. As the order size increases more time is needed to complete the order. In graph 2 there correlation between time spent per board and order size is negative. The larger the order, the less time spent per board is due to avoiding extra setup time along with using the CNC Drill and CNC Router for the fastest production time. Donner Company currently promises delivery in three weeks for order less than 1000 boards and five weeks for larger orders. Graph 1 shows an order of 1000 boards taking approximately 6000 minutes, (or 100 hours) to complete production. Donner does not consider the time spent per board when estimating delivery dates and taking large orders. Graph 2 shows for orders larger than 100 the time spent per board is greatly reduced. Orders greater than 500 boards take less than 7 minutes per board while orders of 10 boards can take over 380 minutes due to setup time. While Donner Company considers the number of board per order when estimating the delivery date they also need to consider what other orders the currently have, the size of their other current orders, and what machinery is being used for the current productions. Donner Company needs to improve its order scheduling and sync it with the production process. They need to focus on eliminating idle time and having orders on schedule, ready to be shipped by the customer delivery date. Utilization of Operations To asses a process’s utilization, one must first figure out the amount of time the facility is available for operations. Second, the amount of time the process is used must be present. In the Donner Case study we are given data for the total process of manufactured printed circuit boards in September of 1987. In that month there were a total of 30 days, but only 22 were part of the typical work week. Of those 22 days one was a federal holiday, the 7th was “Labor Day”, leaving 21 days of operations for the facility. As per the case study, it is mentioned that there are 22 production employees. With these 22 employees operating in 3 departments with a total of 13 subset process’ it can be assumed that this company is only operating on a 1 shift schedule, approximately 8 hours a day. The case study explicitly states that many of employees are “crossed-trained” in multiple departments, so we can also assume that there are supplement employees to cover during break times. This leads us to conclude that they are fully functioning the whole 8 hours of each available work day. As previously stated, there were 21 work days in September of 1987 and with 8 hours of a functioning facility we can calculate that there were 168 hours of availability (21days x 8hr/day). The usage time of each processes is stated in Exhibit 2 Standard Process Flow of the case study. To find the utilization of the artwork generation we would simply take the total hours of usage (24.2hrs) and divide it by the total hours available for the facility (168), [24.2/168=.14404 or about 14.4%]. Now finding the utilization of the CNC Drill might prove to be a little harder. Since the setup time is “almost entirely made up of required computer control” we can’t actually uses the total hours figure given to us, instead we must take the Run Time (9,650mins) and translate it into hours. This gives us a look at the actual time excluding the initial computer setup [9,650/60 = 160.83 hours]. To find its utilization one must take the time of use (160.83hrs) and divide it by the total available hours for the month (168hrs). We can conclude that the CNC Drill operates at a utilization rate of 95.7% [160.83/168]. Similarly, to find the
  • 3. utilization of the CNC Router we ignore the initial computer setup time (for the same reason) and translate the actual setup time into hours [2,166mins/60 = 36.1hrs]. With the new accurate number of usage hours (36.1hrs) we can find the utilization rate by dividing that by the total hours of operations in September of 1987 (168) to find the rate of 21.5% [36.1/168]. For an ideal performance a company should be using whichever process is best suited for each specific type of order. In this process there are 2 steps that allow us to choose a process to fit an order’s needs, they are CNC Drill versus the Manual process and CNC Router versus the Punch Press. To be most effective Donner should be picking the best option from each group, respectively. So we must figure out at what order sizes the company should choose to use the newer CNC technology. To compare we need to set up an equation using fixed and variable times. For the Manual drill, there is a setup of 15min and a run time per hole of .080 (.08 x 500 holes/per board = 40mins/per board). For the CNC Drill there is a set up time of 240min and run time of .004 per hole (.004 x 500 holes/per board = 2mins/per board). Next we set the two equations together leaving the variable of order size(x) [240 + 2*x = 15 + 40*x] → [225 = 38*x] → [225/38 = x] → 5.921 = x. This tells us that if the order size is about 5.921 or ≈ 6 Donner should use the CNC Drill. But, they are only using it on orders with sizes over 140 boards totaling 4,825 boards. This leaves a range of order sizes 6-136 totaling 26 orders and 871 boards that would be better suited using the CNC Drill process. Unfortunately, as previously discussed the CNC drill is operating at a 95.7% utilization rate, since it is already the bottleneck of the process, anymore activity would not be advantageous to the company. So due to the bottleneck effect we can’t possibly functioning at the most efficient rate. Next we can compare the CNC Router to the Punch Press method in a similar fashion. For the CNC Router there is a set up time of 150mins and Run Time of .5min per board. The Punch Press operates with a setup time of 50mins and a Run Time of 1min per board. We must compare these two equations using the variable of order size (x) [150 +.5*x = 50 +1*x] → [100 = .5*x] → [100/.5 = x] → 200=x. This would imply that we should be using the CNC Router on orders larger than 200 to function at the highest efficiency. Currently Donner is using the CNC Router process on 6 orders, the smallest at 229 boards, totaling 4,331 boards. It would not be advantageous for Donner to produces the next smallest order size (200) using the CNC Router, since 200 isn’t greater than the point of indifference of 200 (as solved previously). What is your explanation for each of the problems mentioned by Plummer? Operating Problems Management had a hard time finding where the main bottleneck was specifically in their system because there would be a different problem every day in a different operation. All these different setbacks were happening at random places in the system because each circuit board order was different. Each customer had special requirements that were different from other orders. Because he had no way of predicting where the next bottleneck would happen, Flaherty, the shop supervisor, moved his workers accordingly to the top priority of work. For example, if three works had finished their manual drilling, he would move them to another task until there were more boards to be drilled. So essentially if all three workers were busy working on a different task, boards that were waiting to be drilled had to wait. Productivity Problems
  • 4. Plummer, the president of the company, had noticed that some machines were idle more than he expected them to be. This shows that there is a bottleneck somewhere in production that causes machines to be idle. Also the Donner Company wasn’t even using their own goals, or time standards for their operations. This is not a good sign because they need to be using their own numbers and times to create the company’s own goals. Under the plating operation, the president noticed that a platter would be inspecting panels and then would have to walk 18’ to place the panels in the tanks. Altmeyer, the design engineer, concluded that the walk from her desk to the tanks took up 15% of her time. Plummer stressed his concern that he thought job improvements would not be beneficial for the company. He thought it would just create more pileups at other stations. This is not a positive way of thinking when wanting to grow and develop a company. Quality Problems Inspecting the circuit boards is difficult because there is not a specific standard of what a board should look like because each customer’s order is different. Treating the boards in a careful manner is one problem, but not meeting the correct qualifications that the customer asked for is a bigger problem because on the order sheet (which top management writes up along with a blueprint), it lists everything that is needed for the order to be complete. About 90% the company’s returns are because the customer’s requirements were not met. 10% of the returns are from damaged boards. Delivery Problems In august of 1987, shipments had average nine days late. Lloyd Searby, the sales manager, had calculated that if The Donner Company had changed its small order deliveries from 3 weeks to 4 weeks, the company would barely make $2 million, instead of $3 million if they keep the deliveries at 3 weeks. Plummer had a goal of clearing all work possible out of the shop by the end of every month. This created a pattern in which the beginning of the month had fewer orders to fulfill than that of the end of the month, because the goal made people try to rush and get the shop cleared out. What specific actions should Mr. Plummer take to solve these problems? Mr. Plummer should focus on what his company does best. This is serving his customers with exactly what they want, ranging from order size to special requirements for their orders. Mr. Plummer needs to realize that if there are multiple orders in the system, small orders and big orders, the big orders are the ones that will take up most of the time, pushing the time back for the small orders. If the size of orders is substantially different, then there needs to be two separate productions lines so the lines keep moving. This way each order will essentially take up the same time even if they do have different qualifications because they will be the same size. By having two productions lines, one for small orders and one for big orders, machines will rarely be idle and workers will remain busy, because there will be no stop and start periods. By keeping the main variable constant, order size, it will be easy for management to spot a bottleneck. Now that there are two productions lines, running at their own speeds, Plummer needs to find time goals that are fit yet still demanding for the process. He needs to base these goals from his own lines of production, not from competing firms, because most likely they have a completely different way of doing things than the Donner Company. This new way of creating the circuit boards can increase delivery time depending on the order size. Also, now the company can begin to look for job improvements and workers can master their own skill with this new layout.
  • 5. 0   1000   2000   3000   4000   5000   6000   7000   0   100   200   300   400   500   600   700   800   900   1000   Time  Per  Order   (Minutes)   Order  Size   Donner  Company-­‐  Graph  1   0   50   100   150   200   250   300   350   400   0   100   200   300   400   500   600   700   800   900   1000   Time  Per  Board   (minutes)   Order  Size   Donner  Company-­‐  Graph  2