TACTICAL RAPID IMPROVEMENT
          EVENT
        FIELDBOOK




 How to conduct a successful Rapid Improvement
Event as part of the Air Force Smart Operations for
         the 21st Century (AFSO21) Effort


                  January 2006
                   Beta Version
PREFACE

A paradox of documenting a Tactical Rapid Improvement Event (RIE)
Field Book is that though the body of knowledge is continually
improving and changing, the core concepts remain consistent. The Air
Force is continually learning new applications for improvement in the
wide range of situations they face daily. Thus, this Field Book strikes a
balance between documenting the core or must-do principles and the
tailorable tools that may not all be implemented in every area. Care was
taken to provide examples in most cases, with good use of graphics.

The purpose of this Field Book is to serve as a reference for any Air
Force team member who will Facilitate or participate in an AFSO21
Rapid Improvement Event or initiative – usually one work week in
duration. It is meant to be a guide, but not necessarily a recipe to be
followed without thought about the operation. Further reference and
detail is provided in the wider-scoped CONOPS and Implementation
Plan for Air Force Smart Operations (AFSO21).

This Field Book focuses exclusively on the Rapid Improvement Event.
It does not take the place of the wider-scoped CONOPS and
Implementation Plan for Air Force Smart Operations that provide the
plans and framework for full enterprise transformation.

Any Air Force team member who wishes to lead Rapid Improvement
Events should work for a time with a learned expert who has
successfully led transformations with other organizations before. This is
not because the toolkit is so mysterious that it cannot be learned but
simply because it is a “learn through doing” system. This Field Book
will show the user key steps in conducting a successful RIE – a key step
for an organization on its journey toward a culture of continuous
transformation.


                                     1
2
PERSONAL JOURNEY RECORD:

(Record your RIE’s on this page; get your RIE Facilitator to sign)


     Event Title              Event Type                   Dates




Event Types described on next page.


                                    3
PERSONAL JOURNEY RECORD – PAGE 2:

(Have your RIE Facilitator sign this page next to the CPI Tools you
learned and used)

        Improvement Tool                Trained      Applied          Cert
VSM:
     Current State Map
     Future State Map
     Annual Action Plan
     Communication Plan
Basics:
      Flow & Pull
     7 Wastes
     Standard Work
     6S
     5 Why’s
Advanced:
     Total Productive Maintenance
     QCO/Setup Reduction
     Cell/Workplace Design
     Kanban
     Level Production
Quality:
      Problem Solving
      Error Proofing
      Six Sigma (belt/training)
      Six Sigma (project)
Training – 8 Hr Basic Instruction




                                    4
KEYS TO AFSO21 TRANSFORMATION IN THE
AIR FORCE:

  •   AFSO21 requires Leadership at all levels

  •   Leaders must engage and actively PARTICIPATE

  •   All employees learn by doing: Get expert help, but you must do
      it yourself

  •   Educate the ENTIRE workforce: Knowledge transfer

  •   Operationalize AFSO21: Involve everyone

  •   Tie all actions to key metrics: Customer Value & Combat
      Readiness

  •   Change your Metrics to change behavior for desired results

  •   Manage your Operation with a focus on improvement

  •   It is not easy and will not happen overnight

  •   The only constant is change; be sure the changes in your area are
      true improvements!
Three aspects must change to transform an organization:

  •   Physical

  •   Operational

  •   Cultural

                                   5
Air Force Hanger (modeled after the Toyota House):



                                           AFSO21 Operating System
                   JOINT CDRS                         AIRMEN                    AIR FORCE
 Desired      Air/Space/Cyberspace         Deployment Predictability, Safe    Combat Capability,
             Capability for Joint Fight—    Work Place, Involvement &        Flexibility, Efficiency,
 Results       When/Where Needed                   Satisfaction                 & Sustainability




                   AF Smart Ops for 21st Century – AFSO21
              CONTINUOUS IMPROVEMENT: Lean—Six Sigma—Reengineering
                    SUPERIOR                         VALUED                      COMBAT
 Pillars           PROCESSES                         AIRMEN                     CAPABILITY
              •   Core Mission Focus          •   Innovative Airmen          Asymmetric:
              •   Responsive                  •   Knowledge                  - Global Strike
              •   Right the First Time            Enabled                    - Global Mobility
Elements      •   Waste Removed               •   Accountable                - Intell/Surve/Recon/
                                              •   Recognized/                  C2
                                                  Rewarded


Foundation                        Performance Standards & Measurement

 Bedrock            Integrity                        Service                   Excellence

                                  Integrity - Service - Excellence                                      1




The AFSO21 Operating System diagram above illustrates the bedrock,
foundation, key pillars and results needed to move your operations along
on its transformation journey. It portrays a holistic approach that
focuses on Superior Processes, Valued Airmen, and Synchronized
Combat Capability in order to provide lasting Results for our customers
(Joint Commanders), Airmen and the Air Force.

The Air Force method for continuous improvement will blend Lean, Six
Sigma, and other recognized techniques with our Airmen culture
focused on combat capability, innovative Airmen, and responsive
processes with minimal waste.

                                                          6
Principles, Tools & Systems in the Hanger Model:

The AFSO21 journey applies key, unchanging Principles and tools. The
principles are “must do’s” that guide transformation, interwoven
throughout the improvement process from planning through
sustainment. These principles also apply well in “Above Shop floor”
and support areas. Air Force operations are already operating on a strong
Base of our core values, our adherence to standards, and measuring
results. The three “Pillars” represent delivery of war-winning,
asymmetric combat capability and effects (why we exist as Airmen), the
attributes of our workforce we must develop, and the ever improving
processes that deliver results for our customers (Joint Commanders), our
people, and our Air Force as an enduring and continuously improving
institution.

Primary tools and methods we will use in our AFSO21 operating system
will include Lean, Six Sigma, Theory of Constraint, Business Process
Reengineering, and other methods. We will adapt these techniques to
our culture. They will be used in our relentless pursuit to improve the
capability we provide to the joint fight and homeland security. Our aim
is to deliver that capability with less non-value added work and
resources—to reduce the cycle times in our processes similar to our
efforts to reduce the kill chain in time critical targeting.




                                   7
Model for AFSO21 CPI:

                                       1

       5                         Leading Change
                                 Leading Change                     2

Measure, Assess
Measure, Assess                                                 Organize &
                                                                Organize &
   & Sustain
   & Sustain                                                     Prioritize
                                                                 Prioritize

                        Continuous
                       Improvement
                                              Cultural
                        Centered on
                                           Transformation
                          Combat
                         Capability
               4                                            3
                                                        Process
                                                        Process
            Improve
             Improve                                    Redesign
                                                        Redesign



This model is followed from Step 1 – Leading Change through Step 5 –
Measure, Assess & Sustain. We will use this model to describe the steps
taken to complete a successful RIE. Some loop-backs can happen
during an event. Please note that each AFSO21 event often kicks off
several more iterations of this cycle as more Redesign, Improve and
Sustain actions open up new avenues to improve the operations.
It is the multiple passes (whether in a project area or larger Air Force
end-to-end processes) that result in the greatest gains. A single pass is
equivalent to an action workout. It is the continuous pursuit of
improvement and revisiting areas to see and take the opportunities for
greater waste removal, variability reduction, and improvements to
combat capability delivered. A net effect is a cultural change in how we
do and think about the work we do.

                                       8
Typical Rapid Improvement Event (RIE) Timeline:

Please note the importance of leadership involvement in the setup and
scoping of each RIE. A Strategic VSM session with Strategic
Alignment and Deployment is needed in advance to avoid losing the
impact of each RIE and to help prioritize which RIE’s will yield the
“biggest bang for the buck”.



                                        AFSO21 RIE Schedule

                            Process Owners
  (Commanders




                             Identify Secure
  Executive




                                                 Exploration



                                                                   Chartering
                            Potential Services
  & Staff)




                                                                                                                                                  Follow-up
  Council




                                                   Project



                                                                    Project


                             Project of Coach




                                                                                                                      Out-brief and Celebration
                                                                                Preparation
                                                                                 Pre-event
                            Team Leader



                                                                                              Event Kickoff
  (MBB’s, BB’s,
             Consultants)
  Core Team




                                                  Project                                                                                          Publish
                                                 Evaluation                                                                                        Results
                                                                                                              Event
 Implementation

    Members
      Team




                             - 4 Wks   - 3 Wks            - 2 Wks               - 1 Wk                                                            + 1 Wk
                                                                                                   Event
                                    Integrity - Service - Excellence                                                                                         65




This key session, along with strategic planning by the leaders in your
area, align all of the various improvement efforts.




                                                               9
Preliminary Step: Total Process Value Stream Map –
The Big Picture:
[Leaders in your area should conduct this VSM “visioning” session
before your RIE. Refer to this overall vision and plan when you start
setting up your RIE.]

  •    Select a Product or Key Process in our area (what we deliver to
       the Customer)

  •    Form a Team that create the “Vision” for this process

  •    Understand Customer Demand

  •    Map the total process at the “50,000 foot” level with minimum
       detail

  •    Identify the total time for each step the process (80% of the time,
       it takes less than …)

         −    Note: If the Total end-to-end time (TAT or Lead Time)
              does not make sense, you have missed something in the
              process.

  •    Identify the Minimum Cycle Time (MCT) for each step in the
       process

  •    Use the comparison of MCT and TAT to identify Waste
       Elimination opportunities in the high-level Value Stream

  •    Select a target area for more detailed analysis. Criteria
       considerations:

         −    Close to Customer
                                    10
−   Opportunity to improve total Lead Time for the Customer

          −   Ability to deliver waste reduction results on a timely basis

  •    Develop a detailed Action Plan to close the gap between your
       Current and Future states; integrate all other transformation and
       improvement initiatives into the overall plan. The overall plan
       will include follow-on RIE’s (like yours), “just do it” tasks and
       somewhat larger “projects”.


  •    Start the setup steps for your RIE (see next pages); NOTE: the
       supervisor or key leader in each target area should be the Team
       Leader for the RIE and should help implement and sustain all
       changes brought forward by the team.



Example of the AFSO21 Support Request Worksheet Form:

An RIE that is well-scoped with buy-in by leaders and stakeholders will
likely be a success. These are two of the most critical success factors for
RIE’s. All of the fields need to be filled out completely with great
attention to the “expected improvements” goals. These goals should be
measurable, numerical and integrate into the goals of the unit. They
need to align with the overall Air Force goals. The goals should
“stretch” the team toward even greater success. Blank and completed
examples of this Form can be downloaded from the Air Force Smart Ops
for the 21st Century – AFSO21 Community of Practice (CoP).

In addition to a clear objective and scope, other critical fields include:

            Point of Contact (POC) Information. Someone who
understands the objectives MUST lead the team. This person will be
                                 11
Leading the event, working closely with the facilitator and coordinating
the identification, attendance, and expectations of the team members.

           Sponsor: Each RIE must have a sponsor with the availability
and authority to approve and support the changes the team decides to
make during the event week.

          Team participants: RIEs are only successful when they have
knowledgeable participants who have embraced the idea of change and
who are willing and capable of being the driving force behind such an
effort.

            Requested Date and Location for the Event: The sponsor,
team participants, critical stakeholders, process to be studied, and
facilitator must all be available simultaneously during the RIE week.
This requires some coordination and can drive when and where the event
should take place.




                                   12
Example of an AFSO21 Support Request Worksheet. This
sheet can serve as a team charter.



                                       AFSO21 Support Request Worksheet

RIE (Process targeted for Improvement):           F-15 Acceptance Inspection (AI) Process
MAJCOMPriority:             __________
W ing/Directorate Priority: __________                                                             Date of submission: ______
Impact of Event on Overall AF Goals               Impact: defined and documented process for AF and Guard to accept a plane being
 - Increased Aircraft Availability                returned from PDMin W     arner Robins AFB. This process will reduce redundancy , waste
 - Reduced total cost                             and damage caused by unneeded disassembly and inspection and i ncrease aircraft
                                                  availability. Overall impact : increase in aircraft availability in the near termand future.
Unit:                                             154th W  ing
Base:                                             Hickam AFB
Sponsor: - Owns all processes under study ;       Colonel Ronald P. Han, Jr.
  Group/CC or higher (name, title)                Commander, 154 th Maintenance Group, 154 th W            ing
POC: (name, phone, e -mail)                       Lt Col Bill Petti, (808)448 -8429 or DSN 448 -8429, W      illiam.Petti@  hihick.ang.af.mil
Current Mission Sh ortfall:                       Complex acceptance procedure delays availability of plane and increases costs
 (schedule, cost, quality)
Current Measures of Effectiveness:                Current time and cost to performacceptance in spection in terms of flow days and
 (name, description, st d, FY04/current value)    manhours, accuracy of part serial numbers.
Brief description of current process:             An Acceptance I nspection will be accomplished on all newly assigned, tra nsferred,
  (include boundaries by highlighting start and   loaned or returning aircraft from Program Depot Maintenance (PDM); to include
    stop of process)                              modification and TCTO's accomplished by CFT's or depot away from home station
                                                  before placing into service at home station. In conjunction with a periodic/ isochronical
                                                  inspection when possible. If no periodic inspection is due.. . QA will review the PDM
                                                  work package and Form 103…The check sheet will be placed in th e aircraft forms and
                                                  routed to PS& after all items have been initialed/signed by appropriate work area.
                                                                 D
Description of expected improvements:             Faster availability of aircraft after returning form PDM, reduced cost, and no reduction
                                                  of accuracy of seri al number data
  - Schedule                                      Acceptance flowdays reduced
  - Cost                                          Cost to receive aircraft from PDM reduced
  - Quality                                       No change expected in the short term; could be if FOD issues are resolved
Implementation TeamMembers:                       Lt Col Bill Petti, 154 th MXG, (at Lean Executive Training at W  arner -Robins-Feb 05)
 (name, unit, training/experience in Lean)        Lt Col Jan Sue Heverly, 154 MXS, no Lean training yet …(others)
                                                  CMSgt Irvin Yoshino, 154 MXG, attended L ean training at Hurlburt Field
Personnel Responsible for Sustainment of          SMSgt Douglas Awana, 154 AMXS, Production Superintendent
Gains:                                            SMSgt Dominador Molina, 154 MXS, F -15 Inspection Docks Chief
Other Potentially Affected Groups or              PACAF/LGMand 15 th AMXS (will be sending representatives to Lean Event)
Parties (Other MAJCOM’s, bases, cross -
functional teams, prog rams, initiatives, etc)




                                                             13
Step 2 – Organize and Prioritize:

An RIE needs to be set up properly. Please use the setup checklist
from the Air Force Smart Ops for the 21st Century -- AFSO21
CoP. In preparation for the event, meetings or conference calls
should be held with the team participants, critical stakeholders,
sponsor and facilitator. Here are some key questions you can ask
during your meetings/calls starting 3 weeks in advance of the
event:

Answer all Questions with your Leadership Team

1.    Are all participants and affected parties aware of and in
      agreement with the objectives, scope and expectations for
      this event? (Do this at least twice in advance of each RIE
      event)

2.    Who will officially kick off the workshop (sponsors and
      process champions are good candidates)?

3.    How will views of nonparticipating associates be brought
      into the process (before/during, will they be available for
      daily outbriefs)?

4.    When will the workshop sponsor need to be present at the
      event?

5.    How will progress be reported out during the RIE; who will
      do this (the team leader / POC may be the presenter or may
      share the presentation responsibilities)?



                                14
6.     How will results be reported out at the end of the workshop
       (there are standard report forms, but to whom should they be
       sent)?

7.     When and how will follow-up activity progress be
       communicated to the sponsor and management team? By
       whom?

           Event – 4         Event – 3         Event – 2              Event – 1
            Weeks             Weeks             Weeks                  Week

                                                        Organize &
     Leading                                             Prioritize
     Change

                                            Team Leader
                                            • Confirms avail.of
                                                                  Team Leader
      •Event focus area                       personnel/resourc
                                                                  •Prepare data
       identified                           •Reminds leaders,      packets,
      •Consultant                             and sponsors to      employee
       Assigned             Tm Ldr            be available for
                            Forwards                               suggestions,
      •Team Leader                            Inbrief and Day 5    supplies, tool
       assigned             team roster,      Outbrief
                            preliminary                            kits, forms,
      Team Leader                           •Ensures affected      meeting spaces
                            data, and
      •Begins collecting    event goals
                                              parties in the       for event
       primary data         to Facilitat.
                                              event focus are     •Confirms event
      •Determines some                        aware of pending     agenda and
       opportunities                          event                schedule with all
      •Defines goals                        •Ensures affected      affected parties
      •Selects team                           partied have a
       members                                method to
      •Identifies                             forward
       resources required                     observations



                                       15
Step 3 – Process Redesign

Actions during the week of the actual RIE. Focus on your team
members and make sure they stay focused on the goals. Use flip
chart paper and capture any ideas or thoughts as you go. Ask lots
of questions to see if they are tracking. Be a good time manager to
ensure the group stays on task through the course of a day and the
week. This includes setting clear expectations on what will be
accomplished each day and setting expectations on the day, which
typically could run longer than an 8 hour duty day. So all should
plan for it. As the event is conducted, capture portions that will be
part of the outbrief in an organized and chronological order. The
order includes the problem the team is addressing, current state
process and performance, problem identification, and
improvements recommended, with associated measures. In the
best events (especially in a “shop” area project), improvements
should be implemented and validated during the one-week RIE.
The following steps need to be followed closely. The appropriate
day is noted.

Typical Event Week – Agenda:

1.    [Day 1] Present the Charter/Worksheet; clarify the
      boundaries
2.    Review the RIE “Current State” and/or the RIE “Tools”
      Briefing/Training slides on the tools & principles.
3.    Do a ‘Group Waste Walk’ – physically (if possible) or
      virtually (if not possible to go where the process occurs)
      walk as a team through the entire process.



                                 16
4.    Capture the Current State (map or list of steps); mark steps
      as Value-Added (VA) or Non-Value-Added (NVA) (See
      section below: Describe the current state)
5.    Identify Current problems and issues
6.    [Day 2] Present the RIE “Future State” and/or “Think out of
      the box” Briefing -- Leave behind any frustration that was
      created as you closely examined of your current state and
      think about improvement for a while.
7.    The team may (or may not) develop an “ideal state” vision.
      Depending on the experience and culture of the team, it may
      be helpful to draw a vision of the process if it could exist
      perfectly with no waste.
8.    Develop a “future state” vision – either by removing as
      much NVA work from your current state as you can or by
      adding back to your ideal state (if the team created one) the
      NVA work that you cannot yet (during this RIE) eliminate
9.    Identify Root Causes and constraints in the current state to
      be sure that you eliminate as much waste as possible in your
      future state.
10.   Develop the detailed Lean Action Plan (how to get from the
      current to the future state)
11.   Prioritize the Action Items. Secure the approval of the
      sponsor and other leaders to move ahead.
12.   [Day 3-4] Capture, Post and Train all affected people on
      future Standard Work and process changes
13.   [Day 5] Present the RIE Final Results briefing



                                17
Typical Event Week – Bill of Materials:

  •   Laptop with latest Training Briefings and sample results
      Briefings

  •   Powerpoint projector to show your files on a screen or wall

  •   Flip Chart and Easel (tape to wall; apply post-its)

  •   Large roll of butcher block paper

  •   Post-it notes (to capture the Current State)

  •   Red and Green stickers (3/4”, AVET #5466, 5463, to mark
      value added steps)

  •   Copy of Training slides (1 each, black and white, 2
      handouts per page, double sided)

  •   Waste Walk Form or 7 Waste Checklist

  •   Digital camera (secure permission from your site first; use
      to capture all Before and After pictures, team pictures, and
      pictures of the whiteboards before erasing)




                                18
Step 3 – Process Redesign

A. Describe the Current State

It is important to capture the Current State in as much detail as
possible. When documenting current state of any process or
operation, you can also use the following tools. These are
described in detail in the AFSO21 CONOPS and Implementation
Plan on the Air Force Smart Ops for the 21st Century -- AFSO21
CoP.


  •   Value Stream Mapping (picture pg 23)

  •   Current Standard Work (picture pg 37)

  •   Affinity Diagrams (left center, pg 31)

  •   Spaghetti Diagrams

  •   Current Cycle Times of each process step

  •   Department Metrics (if tracked)




                               19
Here is an example of a format used to display Current State data
collected during your VSM. The metrics tracked will depend on
your process, so change them so they make sense to your team.




                                20
Here are some additional data collection elements and tips for
documenting current state:

  •    Customer requirements (units/day, quality specs, min
       delivery time)

  •    SIPOC (for each Process we are studying, identify several
       Inputs and Outputs, and then Suppliers and Customers for
       each Input and Output)

  •    Other Selected Process Metrics (e.g. overall end-to-end
       time, Available Time, defects, etc.)

  •    Complete a quick walk through the target area to validate
       the main processes.


Step 3 – Process Redesign

B: Analyze the Current State

Now that you made documented each step in your Current State
and made them visible (on a chart, wall, projected file, etc.), mark
which steps add value in the eyes of the customer (Recommended:
use green stickers for value added and red for non-value added if
you are using post-it note to capture each process step as in the
picture below).




                                 21
Valuable:

 •   Is the output of the process what the customer wants and
     needs?

 •   Are there items missing that can add value to the customer
     in the current process?

 •   Steps that do not add value should be eliminated


                              22
•   Time spent on Non-value-added steps that are required
     should be reduced.

Capable:

 •   Can each step be performed the same way with the same
     result every time?

 •   Is the result satisfactory from the standpoint of the
     customer?

 •   Can the steps be executed in similar locations with the same
     output every time?

Adequate:

 •   Can each step be performed every time it needs to be
     performed?

 •   Can each step be performed in the cycle time required?

 •   Is there enough capacity to perform each step without
     waiting?

 •   Is there too much capacity due to the need to add capacity
     in large increments?

 •   Can the process accommodate changes to operating
     conditions and still meet customer requirements?

 •   Can the process produce similar quality outputs across a
     range of operating conditions?

                               23
Step 3 – Process Redesign

          C. Identify Current Problems & Issues

                        Human                     Method                               Machine

         Im proper                                               N preventive
                                                                  o
                                No Standard
           loading                                               M aintenance
                                      W ork
    Lack of
    Training
             Lack of                                                   O M
                                                                        ld odel
        docum   entation             N Training
                                      o
             M anual                                                     Poor Design
       Interuption of
                 Job
                                                                                                                                Paper Jams
                                                                                                                                  in the
         Paper fill                                                                                                               Copier
         level not
                                                     Poor quality                            Copier
           clearly
                                                          Paper                           overheats
          m arked                                                                                                         Paper gets
   Num of
       ber                                            Paper                                                               wet
jam per day
    s                                             wrinkled in                              R not air
                                                                                            oom
 not captured                                      shipm ent                               conditioned

                                                  Supplier not                                                  R leaks
                                                                                                                 oof
                                                   aw of
                                                     are
                                                   problem
                 Measurement                                        Materials                         Environment



          Fishbone or Cause & Effect diagrams are used to brainstorm
          potential root causes to a problem. The “5 Why’s” is method
          developed by Toyota for analyzing and solving problems by asking
          “Why?” five times or until no other reasons can be brainstormed.
          These “root” causes are what need to be addressed to eliminate
          failure. The first few brainstormed causes were likely just
          symptoms of the more underlying root issues.




                                                                       24
Steps 3 & 4 – Process Redesign & Improve

D. Identify Waste for Elimination

The team and key stakeholders then develop a “waste free” Future
State vision for the process. Once you have as waste free of a
picture or vision as possible (given your time, resources and buy-in
by the team), it is time to start developing an action plan and
implement it. An example Future State Map is below. Again, it is
recommended that you use your original post-it note process steps
(with green stickers for value added) to do this step. Make sure
that you do NOT move any red-stickered (non value added) steps
over to the Future State unless there is no other solution.




                                25
Step 4 –Improve

During this step, the team will plan out then implement the
solutions selected in the previous step. The team should
communicate all potential changes to the people in the affected
area before, during and after the RIE. After implementing each
item, the team will then evaluate solutions against targeted goals to
determine effectiveness. New process cycle times and Standard
Work will be updated as well. The team will verify their results
from the previous step and measure the impact of their changes
against the goals. Results should be documented. Note: always
take a “before” picture before you move some major objects.

A good example of these steps through Future State Map and
Action Plan is included on the next page. A good way to prioritize
the Action Items that were brainstormed in the prior steps is to
rank them based on Difficulty (how easy and cheap it would be to
implement this step) and Impact (progress toward the goals of the
RIE). An example of this follows. The cutoffs for these factors
should be defined before prioritizing the tasks. For more
examples, see the Air Force Smart Ops for the 21st Century --
AFSO21 CoP at link.




                                 26
Potential Action Items are placed in one of the four quadrants.
         Those items that can be implemented with minimal effort but have
         a large impact should become “just do its”. Others may be future
         RIEs or projects which require more investment – but may be just
         as worthwhile to pursue.




Impact




                                Difficulty




                                        27
Step 5 – Measure, Assess, & Sustain

The team will do a practice debriefing within the group before
presenting to leaders. During this meeting the group will:

  •   Document areas where further examination (and follow-up
      – may be another RIE) may be necessary

  •   Identify who will monitor (and audit) changes, and who will
      update the action register with future results

  •   Identify areas for future RIE events

  •   The team should also recognize the efforts of those in the
      area being improved
It is important to present your RIE results to leaders and
stakeholders on the final day of your RIE. Do not wait until a
fancy briefing can be drawn up and approved. Present what you
have, even if it is just hand-drawn flip charts. These sometimes
make the most effective communication devices for busy leaders.
Note: make sure you discuss the importance of thanking the team
with your leaders in advance. Nightly outbriefs to these leaders
can prevent a negative reaction in front of your team.

The Team Leaders, Champions & Sponsors need to check on all
major improvements in the days, weeks, and months following the
RIE (especially Monday after)! The final briefing action plan
should be used to prevent backsliding. Follow-up must continue
until the plan has been implemented, stability has been achieved on
the new process, and/or the next improvement effort on the process
has begun.
                                28
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE
AFSO21 RIE

Más contenido relacionado

La actualidad más candente

Deploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive WeaponDeploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive Weapon
Grant Crow
 
Lean Key Performance Metrics
Lean Key Performance MetricsLean Key Performance Metrics
Lean Key Performance Metrics
Hank Czarnecki
 

La actualidad más candente (20)

5-S Methodology - ADDVALUE - Nilesh Arora
5-S Methodology - ADDVALUE - Nilesh Arora5-S Methodology - ADDVALUE - Nilesh Arora
5-S Methodology - ADDVALUE - Nilesh Arora
 
5S Audit Checklists for Manufacturing & Office
5S Audit Checklists for Manufacturing & Office5S Audit Checklists for Manufacturing & Office
5S Audit Checklists for Manufacturing & Office
 
Standard work for leaders
Standard work for leadersStandard work for leaders
Standard work for leaders
 
Lean Management System
Lean Management SystemLean Management System
Lean Management System
 
5s basic principle
5s basic principle5s basic principle
5s basic principle
 
5s audit template ver2
5s audit template ver25s audit template ver2
5s audit template ver2
 
Deploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive WeaponDeploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive Weapon
 
Lean Key Performance Metrics
Lean Key Performance MetricsLean Key Performance Metrics
Lean Key Performance Metrics
 
Presentation 5 S workplace organization methodology
Presentation 5 S workplace organization methodologyPresentation 5 S workplace organization methodology
Presentation 5 S workplace organization methodology
 
5S in 5 minutes
5S in 5 minutes5S in 5 minutes
5S in 5 minutes
 
07 5 s committee
07 5 s committee07 5 s committee
07 5 s committee
 
The Lean Transformation
The Lean Transformation The Lean Transformation
The Lean Transformation
 
Visual Management by Operational Excellence Consulting
Visual Management by Operational Excellence ConsultingVisual Management by Operational Excellence Consulting
Visual Management by Operational Excellence Consulting
 
Clarity First: Process & Performance
Clarity First: Process & PerformanceClarity First: Process & Performance
Clarity First: Process & Performance
 
8 Wastes In Lean Manufacturing PowerPoint Presentation Slides
8 Wastes In Lean Manufacturing PowerPoint Presentation Slides 8 Wastes In Lean Manufacturing PowerPoint Presentation Slides
8 Wastes In Lean Manufacturing PowerPoint Presentation Slides
 
5S Overview
5S Overview5S Overview
5S Overview
 
Daily 15 minute office 5S
Daily 15 minute office 5SDaily 15 minute office 5S
Daily 15 minute office 5S
 
Yalin Üretim
Yalin ÜretimYalin Üretim
Yalin Üretim
 
Triz
TrizTriz
Triz
 
Toyotas 8 Steps To Problem Solving
Toyotas 8 Steps To Problem SolvingToyotas 8 Steps To Problem Solving
Toyotas 8 Steps To Problem Solving
 

Similar a AFSO21 RIE

Lima visit Oct 20 2016
Lima visit Oct 20 2016Lima visit Oct 20 2016
Lima visit Oct 20 2016
Paul Monus
 
Skills Portfolio 2010
Skills Portfolio 2010Skills Portfolio 2010
Skills Portfolio 2010
helenbiuk
 
Skills Portfolio 2010
Skills Portfolio 2010Skills Portfolio 2010
Skills Portfolio 2010
JacquiBIUK
 
Skills Portfolio 2010
Skills Portfolio 2010Skills Portfolio 2010
Skills Portfolio 2010
JacquiBIUK
 

Similar a AFSO21 RIE (20)

Agile network India | Scaling Agile Day @Gurugram | Agile Operating Model & ...
Agile network India | Scaling Agile Day @Gurugram |  Agile Operating Model & ...Agile network India | Scaling Agile Day @Gurugram |  Agile Operating Model & ...
Agile network India | Scaling Agile Day @Gurugram | Agile Operating Model & ...
 
Transforming How We Deliver Value: Agility at Scale
Transforming How We Deliver Value: Agility at ScaleTransforming How We Deliver Value: Agility at Scale
Transforming How We Deliver Value: Agility at Scale
 
Scaling agile Principles and Practices
Scaling agile Principles and PracticesScaling agile Principles and Practices
Scaling agile Principles and Practices
 
Lima visit Oct 20 2016
Lima visit Oct 20 2016Lima visit Oct 20 2016
Lima visit Oct 20 2016
 
A New Perspective on Operational Excellence
A New Perspective on Operational ExcellenceA New Perspective on Operational Excellence
A New Perspective on Operational Excellence
 
Getting execs to let go of waterfall vs agile (mha 2019)
Getting execs to let go of waterfall vs agile (mha 2019)Getting execs to let go of waterfall vs agile (mha 2019)
Getting execs to let go of waterfall vs agile (mha 2019)
 
Electrical Department Maintenance Management Vision
Electrical Department Maintenance Management VisionElectrical Department Maintenance Management Vision
Electrical Department Maintenance Management Vision
 
Agile certified practitioner Exam Notes
Agile certified practitioner Exam NotesAgile certified practitioner Exam Notes
Agile certified practitioner Exam Notes
 
Asset Mnmt Std ISO 55001 Imp Benefits for 4PL.pptx
Asset Mnmt Std ISO 55001 Imp Benefits for 4PL.pptxAsset Mnmt Std ISO 55001 Imp Benefits for 4PL.pptx
Asset Mnmt Std ISO 55001 Imp Benefits for 4PL.pptx
 
Kaizen SW
Kaizen SWKaizen SW
Kaizen SW
 
Scrum Bangalore 14th MeetUp 05 September 2015 - Scaling Agile - Saikat Das - ...
Scrum Bangalore 14th MeetUp 05 September 2015 - Scaling Agile - Saikat Das - ...Scrum Bangalore 14th MeetUp 05 September 2015 - Scaling Agile - Saikat Das - ...
Scrum Bangalore 14th MeetUp 05 September 2015 - Scaling Agile - Saikat Das - ...
 
Agile transformationatscale
Agile transformationatscaleAgile transformationatscale
Agile transformationatscale
 
Agile Transformation at Scale
Agile Transformation at ScaleAgile Transformation at Scale
Agile Transformation at Scale
 
The Five Phases of Agile Maturity (Part 3): Phase 5
The Five Phases of Agile Maturity (Part 3): Phase 5The Five Phases of Agile Maturity (Part 3): Phase 5
The Five Phases of Agile Maturity (Part 3): Phase 5
 
Agile Capacity Management
Agile Capacity ManagementAgile Capacity Management
Agile Capacity Management
 
Session 2- Planning ).pptx
Session 2- Planning ).pptxSession 2- Planning ).pptx
Session 2- Planning ).pptx
 
Skills Portfolio 2010
Skills Portfolio 2010Skills Portfolio 2010
Skills Portfolio 2010
 
Skills Portfolio 2010
Skills Portfolio 2010Skills Portfolio 2010
Skills Portfolio 2010
 
Skills Portfolio 2010
Skills Portfolio 2010Skills Portfolio 2010
Skills Portfolio 2010
 
Productivity for BMS student
Productivity for BMS studentProductivity for BMS student
Productivity for BMS student
 

Más de Leanleaders.org (20)

Variation and mistake proofing
Variation and mistake proofingVariation and mistake proofing
Variation and mistake proofing
 
D11 Define Review
D11 Define ReviewD11 Define Review
D11 Define Review
 
Blankgage.MTW
Blankgage.MTWBlankgage.MTW
Blankgage.MTW
 
Chi-sq GOF Calculator.xls
Chi-sq GOF Calculator.xlsChi-sq GOF Calculator.xls
Chi-sq GOF Calculator.xls
 
D04 Why6Sigma
D04 Why6SigmaD04 Why6Sigma
D04 Why6Sigma
 
D10 Project Management
D10 Project ManagementD10 Project Management
D10 Project Management
 
Attrib R&R.xls
Attrib R&R.xlsAttrib R&R.xls
Attrib R&R.xls
 
Blank Logo LEAN template
Blank Logo LEAN templateBlank Logo LEAN template
Blank Logo LEAN template
 
D07 Project Charter
D07 Project CharterD07 Project Charter
D07 Project Charter
 
NG BB 36 Simple Linear Regression
NG BB 36 Simple Linear RegressionNG BB 36 Simple Linear Regression
NG BB 36 Simple Linear Regression
 
ANG_AFSO21_Awareness_Training_(DULUTH)
ANG_AFSO21_Awareness_Training_(DULUTH)ANG_AFSO21_Awareness_Training_(DULUTH)
ANG_AFSO21_Awareness_Training_(DULUTH)
 
Cause and Effect Tree.vst
Cause and Effect Tree.vstCause and Effect Tree.vst
Cause and Effect Tree.vst
 
LEAN template
LEAN templateLEAN template
LEAN template
 
I07 Simulation
I07 SimulationI07 Simulation
I07 Simulation
 
NG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapNG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE Roadmap
 
D01 Define Spacer
D01 Define SpacerD01 Define Spacer
D01 Define Spacer
 
NG BB 45 Quick Change Over
NG BB 45 Quick Change OverNG BB 45 Quick Change Over
NG BB 45 Quick Change Over
 
Attribute Process Capability Calculator.xls
Attribute Process Capability Calculator.xlsAttribute Process Capability Calculator.xls
Attribute Process Capability Calculator.xls
 
A05 Continuous One Variable Stat Tests
A05 Continuous One Variable Stat TestsA05 Continuous One Variable Stat Tests
A05 Continuous One Variable Stat Tests
 
XY Matrix.xls
XY Matrix.xlsXY Matrix.xls
XY Matrix.xls
 

Último

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Último (20)

SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 

AFSO21 RIE

  • 1. TACTICAL RAPID IMPROVEMENT EVENT FIELDBOOK How to conduct a successful Rapid Improvement Event as part of the Air Force Smart Operations for the 21st Century (AFSO21) Effort January 2006 Beta Version
  • 2. PREFACE A paradox of documenting a Tactical Rapid Improvement Event (RIE) Field Book is that though the body of knowledge is continually improving and changing, the core concepts remain consistent. The Air Force is continually learning new applications for improvement in the wide range of situations they face daily. Thus, this Field Book strikes a balance between documenting the core or must-do principles and the tailorable tools that may not all be implemented in every area. Care was taken to provide examples in most cases, with good use of graphics. The purpose of this Field Book is to serve as a reference for any Air Force team member who will Facilitate or participate in an AFSO21 Rapid Improvement Event or initiative – usually one work week in duration. It is meant to be a guide, but not necessarily a recipe to be followed without thought about the operation. Further reference and detail is provided in the wider-scoped CONOPS and Implementation Plan for Air Force Smart Operations (AFSO21). This Field Book focuses exclusively on the Rapid Improvement Event. It does not take the place of the wider-scoped CONOPS and Implementation Plan for Air Force Smart Operations that provide the plans and framework for full enterprise transformation. Any Air Force team member who wishes to lead Rapid Improvement Events should work for a time with a learned expert who has successfully led transformations with other organizations before. This is not because the toolkit is so mysterious that it cannot be learned but simply because it is a “learn through doing” system. This Field Book will show the user key steps in conducting a successful RIE – a key step for an organization on its journey toward a culture of continuous transformation. 1
  • 3. 2
  • 4. PERSONAL JOURNEY RECORD: (Record your RIE’s on this page; get your RIE Facilitator to sign) Event Title Event Type Dates Event Types described on next page. 3
  • 5. PERSONAL JOURNEY RECORD – PAGE 2: (Have your RIE Facilitator sign this page next to the CPI Tools you learned and used) Improvement Tool Trained Applied Cert VSM: Current State Map Future State Map Annual Action Plan Communication Plan Basics: Flow & Pull 7 Wastes Standard Work 6S 5 Why’s Advanced: Total Productive Maintenance QCO/Setup Reduction Cell/Workplace Design Kanban Level Production Quality: Problem Solving Error Proofing Six Sigma (belt/training) Six Sigma (project) Training – 8 Hr Basic Instruction 4
  • 6. KEYS TO AFSO21 TRANSFORMATION IN THE AIR FORCE: • AFSO21 requires Leadership at all levels • Leaders must engage and actively PARTICIPATE • All employees learn by doing: Get expert help, but you must do it yourself • Educate the ENTIRE workforce: Knowledge transfer • Operationalize AFSO21: Involve everyone • Tie all actions to key metrics: Customer Value & Combat Readiness • Change your Metrics to change behavior for desired results • Manage your Operation with a focus on improvement • It is not easy and will not happen overnight • The only constant is change; be sure the changes in your area are true improvements! Three aspects must change to transform an organization: • Physical • Operational • Cultural 5
  • 7. Air Force Hanger (modeled after the Toyota House): AFSO21 Operating System JOINT CDRS AIRMEN AIR FORCE Desired Air/Space/Cyberspace Deployment Predictability, Safe Combat Capability, Capability for Joint Fight— Work Place, Involvement & Flexibility, Efficiency, Results When/Where Needed Satisfaction & Sustainability AF Smart Ops for 21st Century – AFSO21 CONTINUOUS IMPROVEMENT: Lean—Six Sigma—Reengineering SUPERIOR VALUED COMBAT Pillars PROCESSES AIRMEN CAPABILITY • Core Mission Focus • Innovative Airmen Asymmetric: • Responsive • Knowledge - Global Strike • Right the First Time Enabled - Global Mobility Elements • Waste Removed • Accountable - Intell/Surve/Recon/ • Recognized/ C2 Rewarded Foundation Performance Standards & Measurement Bedrock Integrity Service Excellence Integrity - Service - Excellence 1 The AFSO21 Operating System diagram above illustrates the bedrock, foundation, key pillars and results needed to move your operations along on its transformation journey. It portrays a holistic approach that focuses on Superior Processes, Valued Airmen, and Synchronized Combat Capability in order to provide lasting Results for our customers (Joint Commanders), Airmen and the Air Force. The Air Force method for continuous improvement will blend Lean, Six Sigma, and other recognized techniques with our Airmen culture focused on combat capability, innovative Airmen, and responsive processes with minimal waste. 6
  • 8. Principles, Tools & Systems in the Hanger Model: The AFSO21 journey applies key, unchanging Principles and tools. The principles are “must do’s” that guide transformation, interwoven throughout the improvement process from planning through sustainment. These principles also apply well in “Above Shop floor” and support areas. Air Force operations are already operating on a strong Base of our core values, our adherence to standards, and measuring results. The three “Pillars” represent delivery of war-winning, asymmetric combat capability and effects (why we exist as Airmen), the attributes of our workforce we must develop, and the ever improving processes that deliver results for our customers (Joint Commanders), our people, and our Air Force as an enduring and continuously improving institution. Primary tools and methods we will use in our AFSO21 operating system will include Lean, Six Sigma, Theory of Constraint, Business Process Reengineering, and other methods. We will adapt these techniques to our culture. They will be used in our relentless pursuit to improve the capability we provide to the joint fight and homeland security. Our aim is to deliver that capability with less non-value added work and resources—to reduce the cycle times in our processes similar to our efforts to reduce the kill chain in time critical targeting. 7
  • 9. Model for AFSO21 CPI: 1 5 Leading Change Leading Change 2 Measure, Assess Measure, Assess Organize & Organize & & Sustain & Sustain Prioritize Prioritize Continuous Improvement Cultural Centered on Transformation Combat Capability 4 3 Process Process Improve Improve Redesign Redesign This model is followed from Step 1 – Leading Change through Step 5 – Measure, Assess & Sustain. We will use this model to describe the steps taken to complete a successful RIE. Some loop-backs can happen during an event. Please note that each AFSO21 event often kicks off several more iterations of this cycle as more Redesign, Improve and Sustain actions open up new avenues to improve the operations. It is the multiple passes (whether in a project area or larger Air Force end-to-end processes) that result in the greatest gains. A single pass is equivalent to an action workout. It is the continuous pursuit of improvement and revisiting areas to see and take the opportunities for greater waste removal, variability reduction, and improvements to combat capability delivered. A net effect is a cultural change in how we do and think about the work we do. 8
  • 10. Typical Rapid Improvement Event (RIE) Timeline: Please note the importance of leadership involvement in the setup and scoping of each RIE. A Strategic VSM session with Strategic Alignment and Deployment is needed in advance to avoid losing the impact of each RIE and to help prioritize which RIE’s will yield the “biggest bang for the buck”. AFSO21 RIE Schedule Process Owners (Commanders Identify Secure Executive Exploration Chartering Potential Services & Staff) Follow-up Council Project Project Project of Coach Out-brief and Celebration Preparation Pre-event Team Leader Event Kickoff (MBB’s, BB’s, Consultants) Core Team Project Publish Evaluation Results Event Implementation Members Team - 4 Wks - 3 Wks - 2 Wks - 1 Wk + 1 Wk Event Integrity - Service - Excellence 65 This key session, along with strategic planning by the leaders in your area, align all of the various improvement efforts. 9
  • 11. Preliminary Step: Total Process Value Stream Map – The Big Picture: [Leaders in your area should conduct this VSM “visioning” session before your RIE. Refer to this overall vision and plan when you start setting up your RIE.] • Select a Product or Key Process in our area (what we deliver to the Customer) • Form a Team that create the “Vision” for this process • Understand Customer Demand • Map the total process at the “50,000 foot” level with minimum detail • Identify the total time for each step the process (80% of the time, it takes less than …) − Note: If the Total end-to-end time (TAT or Lead Time) does not make sense, you have missed something in the process. • Identify the Minimum Cycle Time (MCT) for each step in the process • Use the comparison of MCT and TAT to identify Waste Elimination opportunities in the high-level Value Stream • Select a target area for more detailed analysis. Criteria considerations: − Close to Customer 10
  • 12. Opportunity to improve total Lead Time for the Customer − Ability to deliver waste reduction results on a timely basis • Develop a detailed Action Plan to close the gap between your Current and Future states; integrate all other transformation and improvement initiatives into the overall plan. The overall plan will include follow-on RIE’s (like yours), “just do it” tasks and somewhat larger “projects”. • Start the setup steps for your RIE (see next pages); NOTE: the supervisor or key leader in each target area should be the Team Leader for the RIE and should help implement and sustain all changes brought forward by the team. Example of the AFSO21 Support Request Worksheet Form: An RIE that is well-scoped with buy-in by leaders and stakeholders will likely be a success. These are two of the most critical success factors for RIE’s. All of the fields need to be filled out completely with great attention to the “expected improvements” goals. These goals should be measurable, numerical and integrate into the goals of the unit. They need to align with the overall Air Force goals. The goals should “stretch” the team toward even greater success. Blank and completed examples of this Form can be downloaded from the Air Force Smart Ops for the 21st Century – AFSO21 Community of Practice (CoP). In addition to a clear objective and scope, other critical fields include: Point of Contact (POC) Information. Someone who understands the objectives MUST lead the team. This person will be 11
  • 13. Leading the event, working closely with the facilitator and coordinating the identification, attendance, and expectations of the team members. Sponsor: Each RIE must have a sponsor with the availability and authority to approve and support the changes the team decides to make during the event week. Team participants: RIEs are only successful when they have knowledgeable participants who have embraced the idea of change and who are willing and capable of being the driving force behind such an effort. Requested Date and Location for the Event: The sponsor, team participants, critical stakeholders, process to be studied, and facilitator must all be available simultaneously during the RIE week. This requires some coordination and can drive when and where the event should take place. 12
  • 14. Example of an AFSO21 Support Request Worksheet. This sheet can serve as a team charter. AFSO21 Support Request Worksheet RIE (Process targeted for Improvement): F-15 Acceptance Inspection (AI) Process MAJCOMPriority: __________ W ing/Directorate Priority: __________ Date of submission: ______ Impact of Event on Overall AF Goals Impact: defined and documented process for AF and Guard to accept a plane being - Increased Aircraft Availability returned from PDMin W arner Robins AFB. This process will reduce redundancy , waste - Reduced total cost and damage caused by unneeded disassembly and inspection and i ncrease aircraft availability. Overall impact : increase in aircraft availability in the near termand future. Unit: 154th W ing Base: Hickam AFB Sponsor: - Owns all processes under study ; Colonel Ronald P. Han, Jr. Group/CC or higher (name, title) Commander, 154 th Maintenance Group, 154 th W ing POC: (name, phone, e -mail) Lt Col Bill Petti, (808)448 -8429 or DSN 448 -8429, W illiam.Petti@ hihick.ang.af.mil Current Mission Sh ortfall: Complex acceptance procedure delays availability of plane and increases costs (schedule, cost, quality) Current Measures of Effectiveness: Current time and cost to performacceptance in spection in terms of flow days and (name, description, st d, FY04/current value) manhours, accuracy of part serial numbers. Brief description of current process: An Acceptance I nspection will be accomplished on all newly assigned, tra nsferred, (include boundaries by highlighting start and loaned or returning aircraft from Program Depot Maintenance (PDM); to include stop of process) modification and TCTO's accomplished by CFT's or depot away from home station before placing into service at home station. In conjunction with a periodic/ isochronical inspection when possible. If no periodic inspection is due.. . QA will review the PDM work package and Form 103…The check sheet will be placed in th e aircraft forms and routed to PS& after all items have been initialed/signed by appropriate work area. D Description of expected improvements: Faster availability of aircraft after returning form PDM, reduced cost, and no reduction of accuracy of seri al number data - Schedule Acceptance flowdays reduced - Cost Cost to receive aircraft from PDM reduced - Quality No change expected in the short term; could be if FOD issues are resolved Implementation TeamMembers: Lt Col Bill Petti, 154 th MXG, (at Lean Executive Training at W arner -Robins-Feb 05) (name, unit, training/experience in Lean) Lt Col Jan Sue Heverly, 154 MXS, no Lean training yet …(others) CMSgt Irvin Yoshino, 154 MXG, attended L ean training at Hurlburt Field Personnel Responsible for Sustainment of SMSgt Douglas Awana, 154 AMXS, Production Superintendent Gains: SMSgt Dominador Molina, 154 MXS, F -15 Inspection Docks Chief Other Potentially Affected Groups or PACAF/LGMand 15 th AMXS (will be sending representatives to Lean Event) Parties (Other MAJCOM’s, bases, cross - functional teams, prog rams, initiatives, etc) 13
  • 15. Step 2 – Organize and Prioritize: An RIE needs to be set up properly. Please use the setup checklist from the Air Force Smart Ops for the 21st Century -- AFSO21 CoP. In preparation for the event, meetings or conference calls should be held with the team participants, critical stakeholders, sponsor and facilitator. Here are some key questions you can ask during your meetings/calls starting 3 weeks in advance of the event: Answer all Questions with your Leadership Team 1. Are all participants and affected parties aware of and in agreement with the objectives, scope and expectations for this event? (Do this at least twice in advance of each RIE event) 2. Who will officially kick off the workshop (sponsors and process champions are good candidates)? 3. How will views of nonparticipating associates be brought into the process (before/during, will they be available for daily outbriefs)? 4. When will the workshop sponsor need to be present at the event? 5. How will progress be reported out during the RIE; who will do this (the team leader / POC may be the presenter or may share the presentation responsibilities)? 14
  • 16. 6. How will results be reported out at the end of the workshop (there are standard report forms, but to whom should they be sent)? 7. When and how will follow-up activity progress be communicated to the sponsor and management team? By whom? Event – 4 Event – 3 Event – 2 Event – 1 Weeks Weeks Weeks Week Organize & Leading Prioritize Change Team Leader • Confirms avail.of Team Leader •Event focus area personnel/resourc •Prepare data identified •Reminds leaders, packets, •Consultant and sponsors to employee Assigned Tm Ldr be available for Forwards suggestions, •Team Leader Inbrief and Day 5 supplies, tool assigned team roster, Outbrief preliminary kits, forms, Team Leader •Ensures affected meeting spaces data, and •Begins collecting event goals parties in the for event primary data to Facilitat. event focus are •Confirms event •Determines some aware of pending agenda and opportunities event schedule with all •Defines goals •Ensures affected affected parties •Selects team partied have a members method to •Identifies forward resources required observations 15
  • 17. Step 3 – Process Redesign Actions during the week of the actual RIE. Focus on your team members and make sure they stay focused on the goals. Use flip chart paper and capture any ideas or thoughts as you go. Ask lots of questions to see if they are tracking. Be a good time manager to ensure the group stays on task through the course of a day and the week. This includes setting clear expectations on what will be accomplished each day and setting expectations on the day, which typically could run longer than an 8 hour duty day. So all should plan for it. As the event is conducted, capture portions that will be part of the outbrief in an organized and chronological order. The order includes the problem the team is addressing, current state process and performance, problem identification, and improvements recommended, with associated measures. In the best events (especially in a “shop” area project), improvements should be implemented and validated during the one-week RIE. The following steps need to be followed closely. The appropriate day is noted. Typical Event Week – Agenda: 1. [Day 1] Present the Charter/Worksheet; clarify the boundaries 2. Review the RIE “Current State” and/or the RIE “Tools” Briefing/Training slides on the tools & principles. 3. Do a ‘Group Waste Walk’ – physically (if possible) or virtually (if not possible to go where the process occurs) walk as a team through the entire process. 16
  • 18. 4. Capture the Current State (map or list of steps); mark steps as Value-Added (VA) or Non-Value-Added (NVA) (See section below: Describe the current state) 5. Identify Current problems and issues 6. [Day 2] Present the RIE “Future State” and/or “Think out of the box” Briefing -- Leave behind any frustration that was created as you closely examined of your current state and think about improvement for a while. 7. The team may (or may not) develop an “ideal state” vision. Depending on the experience and culture of the team, it may be helpful to draw a vision of the process if it could exist perfectly with no waste. 8. Develop a “future state” vision – either by removing as much NVA work from your current state as you can or by adding back to your ideal state (if the team created one) the NVA work that you cannot yet (during this RIE) eliminate 9. Identify Root Causes and constraints in the current state to be sure that you eliminate as much waste as possible in your future state. 10. Develop the detailed Lean Action Plan (how to get from the current to the future state) 11. Prioritize the Action Items. Secure the approval of the sponsor and other leaders to move ahead. 12. [Day 3-4] Capture, Post and Train all affected people on future Standard Work and process changes 13. [Day 5] Present the RIE Final Results briefing 17
  • 19. Typical Event Week – Bill of Materials: • Laptop with latest Training Briefings and sample results Briefings • Powerpoint projector to show your files on a screen or wall • Flip Chart and Easel (tape to wall; apply post-its) • Large roll of butcher block paper • Post-it notes (to capture the Current State) • Red and Green stickers (3/4”, AVET #5466, 5463, to mark value added steps) • Copy of Training slides (1 each, black and white, 2 handouts per page, double sided) • Waste Walk Form or 7 Waste Checklist • Digital camera (secure permission from your site first; use to capture all Before and After pictures, team pictures, and pictures of the whiteboards before erasing) 18
  • 20. Step 3 – Process Redesign A. Describe the Current State It is important to capture the Current State in as much detail as possible. When documenting current state of any process or operation, you can also use the following tools. These are described in detail in the AFSO21 CONOPS and Implementation Plan on the Air Force Smart Ops for the 21st Century -- AFSO21 CoP. • Value Stream Mapping (picture pg 23) • Current Standard Work (picture pg 37) • Affinity Diagrams (left center, pg 31) • Spaghetti Diagrams • Current Cycle Times of each process step • Department Metrics (if tracked) 19
  • 21. Here is an example of a format used to display Current State data collected during your VSM. The metrics tracked will depend on your process, so change them so they make sense to your team. 20
  • 22. Here are some additional data collection elements and tips for documenting current state: • Customer requirements (units/day, quality specs, min delivery time) • SIPOC (for each Process we are studying, identify several Inputs and Outputs, and then Suppliers and Customers for each Input and Output) • Other Selected Process Metrics (e.g. overall end-to-end time, Available Time, defects, etc.) • Complete a quick walk through the target area to validate the main processes. Step 3 – Process Redesign B: Analyze the Current State Now that you made documented each step in your Current State and made them visible (on a chart, wall, projected file, etc.), mark which steps add value in the eyes of the customer (Recommended: use green stickers for value added and red for non-value added if you are using post-it note to capture each process step as in the picture below). 21
  • 23. Valuable: • Is the output of the process what the customer wants and needs? • Are there items missing that can add value to the customer in the current process? • Steps that do not add value should be eliminated 22
  • 24. Time spent on Non-value-added steps that are required should be reduced. Capable: • Can each step be performed the same way with the same result every time? • Is the result satisfactory from the standpoint of the customer? • Can the steps be executed in similar locations with the same output every time? Adequate: • Can each step be performed every time it needs to be performed? • Can each step be performed in the cycle time required? • Is there enough capacity to perform each step without waiting? • Is there too much capacity due to the need to add capacity in large increments? • Can the process accommodate changes to operating conditions and still meet customer requirements? • Can the process produce similar quality outputs across a range of operating conditions? 23
  • 25. Step 3 – Process Redesign C. Identify Current Problems & Issues Human Method Machine Im proper N preventive o No Standard loading M aintenance W ork Lack of Training Lack of O M ld odel docum entation N Training o M anual Poor Design Interuption of Job Paper Jams in the Paper fill Copier level not Poor quality Copier clearly Paper overheats m arked Paper gets Num of ber Paper wet jam per day s wrinkled in R not air oom not captured shipm ent conditioned Supplier not R leaks oof aw of are problem Measurement Materials Environment Fishbone or Cause & Effect diagrams are used to brainstorm potential root causes to a problem. The “5 Why’s” is method developed by Toyota for analyzing and solving problems by asking “Why?” five times or until no other reasons can be brainstormed. These “root” causes are what need to be addressed to eliminate failure. The first few brainstormed causes were likely just symptoms of the more underlying root issues. 24
  • 26. Steps 3 & 4 – Process Redesign & Improve D. Identify Waste for Elimination The team and key stakeholders then develop a “waste free” Future State vision for the process. Once you have as waste free of a picture or vision as possible (given your time, resources and buy-in by the team), it is time to start developing an action plan and implement it. An example Future State Map is below. Again, it is recommended that you use your original post-it note process steps (with green stickers for value added) to do this step. Make sure that you do NOT move any red-stickered (non value added) steps over to the Future State unless there is no other solution. 25
  • 27. Step 4 –Improve During this step, the team will plan out then implement the solutions selected in the previous step. The team should communicate all potential changes to the people in the affected area before, during and after the RIE. After implementing each item, the team will then evaluate solutions against targeted goals to determine effectiveness. New process cycle times and Standard Work will be updated as well. The team will verify their results from the previous step and measure the impact of their changes against the goals. Results should be documented. Note: always take a “before” picture before you move some major objects. A good example of these steps through Future State Map and Action Plan is included on the next page. A good way to prioritize the Action Items that were brainstormed in the prior steps is to rank them based on Difficulty (how easy and cheap it would be to implement this step) and Impact (progress toward the goals of the RIE). An example of this follows. The cutoffs for these factors should be defined before prioritizing the tasks. For more examples, see the Air Force Smart Ops for the 21st Century -- AFSO21 CoP at link. 26
  • 28. Potential Action Items are placed in one of the four quadrants. Those items that can be implemented with minimal effort but have a large impact should become “just do its”. Others may be future RIEs or projects which require more investment – but may be just as worthwhile to pursue. Impact Difficulty 27
  • 29. Step 5 – Measure, Assess, & Sustain The team will do a practice debriefing within the group before presenting to leaders. During this meeting the group will: • Document areas where further examination (and follow-up – may be another RIE) may be necessary • Identify who will monitor (and audit) changes, and who will update the action register with future results • Identify areas for future RIE events • The team should also recognize the efforts of those in the area being improved It is important to present your RIE results to leaders and stakeholders on the final day of your RIE. Do not wait until a fancy briefing can be drawn up and approved. Present what you have, even if it is just hand-drawn flip charts. These sometimes make the most effective communication devices for busy leaders. Note: make sure you discuss the importance of thanking the team with your leaders in advance. Nightly outbriefs to these leaders can prevent a negative reaction in front of your team. The Team Leaders, Champions & Sponsors need to check on all major improvements in the days, weeks, and months following the RIE (especially Monday after)! The final briefing action plan should be used to prevent backsliding. Follow-up must continue until the plan has been implemented, stability has been achieved on the new process, and/or the next improvement effort on the process has begun. 28