2. Reduced time and cost of scheme
delivery
20mph zones
• Sign illumination can be relaxed throughout a 20mph
limit/zone – subject to risk analysis
• Remove the requirement for terminal signs to be placed
on both sides of the road
• Repeater signs can be used as a physical feature
• Remove the requirement for a speed roundel to be
accompanied by an upright sign
• Provided new signs for 20mph part-time limits
10. Traffic management costs
• Average speed hump = £2000
• Illuminated traffic sign =£600
• Energy costs and maintenance = £100 pa
• Cost to place an unilluminated sign = £200
• Cost to place pair of unilluminated signs (back to
back) = £300
• Cost to mark a parking bay = £500
11. Scheme costs
Total cost = £36,200
• 8 x speed hump = £2000 x 8 = £16000
• Illuminated traffic sign = £600 x 16 = £9600
• Energy costs and maintenance = £100 pa =
£1600 x 5 = £8000
• 4 back-to-back signs for zone = £4 x £300 =
£1200
• 2 x unilluminated parking signs = 2 x £200 =
£400
• Mark 2 x parking bay = £500 x 2 = £1000