Power Line Carrier
CommunicationTO FROM:
PROF.RAVI SONI PREETESH KUMAR ARYA
(PROF.,EE DEPARTMENT) (IV YR,EE)
Contant
 Training overview
 Company profile
 Introduction
 General modulation principle
 Basic principle of PLCC
 Specification
 Basic arrangement
 Wave trap
 Tuning capacitor
 Battery charger
 Technical specification
 Maintanance and fault traction
 Maintanance and fault traction procedure
 applications
 Advantages
 disadvantages
 Key learning
 Conclusion
Training overview
 Name of industry : Rajasthan Rajya vidyut prasaran nigam limited
 Location : 220KV BASNI GSS , Jaipur
 Duration of training : 20 may to 11 july
 Department of training : electrical engineering
About company
 RRVPNL started working from july 1957
 Sh.shailendra Agarwal,IAS is the chairman & MD of RRVPNL
 RVPN provides the pathway for power within whole rajasthan
 This is the body of big organization ACT, like public limited
companies
 It works as electric power distribution regulation within the state.
Introduction
 PLCC, Power Line Carrier Communication, is an approach to utilize
the existing power lines for the transmission of information.
 This technology has been in wide use since 1950 and was mainly
used by the grid stations to transmit information at high speed.
 Can use existing infrastructure for data traffic
 Involves a lot of technicalities.
General modulation principle
 Single side band transmission
 Carrier frequency is spaced on a 4KHz
 I.F. fixed at 16KHz
 Full duplex mode is used
 Lower side band is used throught all communication
Basic principle of PLCC
 The communication system cannot be directly
connected to the high voltage lines suitably designed
coupling devices.
 These usually consist of high voltage capacitor with
polaritical devices used in conjucation with suitable line
matching unit (LMU) for matching the impedence of line
to that of the coaxial cable connecting the unit of the
PLC transmit-receive equipment.
Specifications of PLCC
1) GENERAL:-
 Carrier frequency range:-40 to 512KHz
 Useful AF band:-300 to 3700Hz
2) TRANSMITTER:-
 Peak envelope power:-25W
 Side band power:-15W
Basic arrangement
 The basic arrangement of connecting the WT and coupling
capacitor in PLCC communication is shown in figure
Types of coupling
 A) phase to ground coupling
 Phase to phase coupling
 Phase to phase coupling
 INTERLINE OR INTER CIRCUIT COUPLING
Wave traps
 Wave traps – (WT’s) are used between the transmission line and the
power stations to avoid carrier power dislocation in the power plant
and cross talk with other power line carrier circuits connected to the
same power station
Tuning capacitor
 For lower voltage class of tuning units with impulse test voltage
rating upto 40 KV polystyrene capacitors are used
 For higher voltage class of tuning units with impulse test voltage
rating upto 150 KV, capacitors with mineral oil impregnated paper
dielectric are used
 Used are high voltage, high stability mica capacitors with low losses
Battery charger
 PLCC (Power Line Carrier Communication) works on rectified AC or
main power supply. When supply goes off, we use BATTERY CHARGER
for proper functioning of PLCC, which provides supply to the PLCC
equipment for uninterrupted working. It provides DC to the panel by
battery of 48V. In this type 24 batteries are connected in series and
individually per battery has approximately 2V capacity.
 Battery charger mainly consists of 4 sections –

 1. Float charger
 2. Boost charger section
 3. Control section
 4. Alarm section
Technical specifications
 NORMAL INPUT :415 V AC 3-PHASE
 INPUT VARIATION : +/- 20%
FLOAT CHARGER :
DC OUTPUT :50 V
OUTPUT CURRENT :20 TO 40 AMP
EFFICIENCY : >70%
 BOOST CHARGER
 DC output - 43.2 to 67.2 V
 Output current - 25-70 Amps.
 Efficiency - >80%
Maintanace & fault traction
 Fault analysis:
in fault analysis the faulty devices are checked in this
serial or manner:
1. Telephone or tele operation signal
2. Cabling low frequency circuit or DC power supply
3. PLC equipment
4. HF transmission path
Maintainance and fault traction
procedure
 The control circuit boards should be inserted far firmly.
 The charger should be switch off once in every month.
 The battery terminal should be connected first and AC input after
that.
 All mounting bolts should be checked before energizing.
Applications
 PLCC Unit Provide Five type of operation:
1:TELEPHONE FACILITES
2:COMPRESSOR & EXPANDER
3:EMERGENCY CALL
4:SIGNAL BOOSTING
5:SUPERVISION & ALARMS
Advantages
 No separate wires are needed for communication purpose.
 Both communication and power transfer can be possible on same
circuit
 Power lines provides the shortest route between the power station
 Increase reliability
 Lower attenuation over long distance
 Implementation cost is reduced
Disadvantages
 Reflection are produced on spur lines connected to high voltage
line this increased attenuation and create other problem.
 High voltage lines have transformer connections,which attenuate
carrier currents.
 Noise introduced by power lines is far more than in case of
telephonic lines.
 Proper care has to be taken to guard carrier equipment and
persons using them against high voltages and currents on the lines.
Key learning
 PLCC is mainly used for telecommunication,tele-protection and
tele-monitoring,between electrical substation through power lines.
 In a PLCC system the communication is established through the
power line.
 The carrier frequency range is allocated to include the audio signal,
protection and the pilot frequency.
conclusion
 Power line carrier communication has been found to be the most
economical and reliable method for communication in a medium
and over long distance in a power system.
Questions?
Thank you

Más contenido relacionado

La actualidad más candente

BSNL Industrial Training ppt 2014.
BSNL Industrial Training ppt 2014.BSNL Industrial Training ppt 2014.
BSNL Industrial Training ppt 2014.Shubham Singh
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presentionRazu Khan
 
Power Line Carrier Communication
Power Line Carrier CommunicationPower Line Carrier Communication
Power Line Carrier CommunicationNeha Gethe
 
Power Line Carrier Communication seminar
Power Line Carrier Communication seminarPower Line Carrier Communication seminar
Power Line Carrier Communication seminarAishwary Verma
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scadaHemendra Kumar Rajput
 
Electro magnetic interference and compatibility(ECM,ECI)
Electro magnetic interference and compatibility(ECM,ECI)Electro magnetic interference and compatibility(ECM,ECI)
Electro magnetic interference and compatibility(ECM,ECI)Palani murugan
 
Power Line Communication
Power Line CommunicationPower Line Communication
Power Line CommunicationPiyush Chand
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclVISHAL VERMA
 
BSNL Training Report file
BSNL Training Report fileBSNL Training Report file
BSNL Training Report fileOjas Maheshwari
 
Bts installation & commisioning.ppt
Bts installation & commisioning.pptBts installation & commisioning.ppt
Bts installation & commisioning.pptAIRTEL
 
Fault Location Of Transmission Line
Fault Location Of Transmission LineFault Location Of Transmission Line
Fault Location Of Transmission LineCHIRANJEEB DASH
 
Fundamentals of electromagnetic compatibility (EMC)
Fundamentals of electromagnetic compatibility (EMC)Fundamentals of electromagnetic compatibility (EMC)
Fundamentals of electromagnetic compatibility (EMC)Bruno De Wachter
 
Pole mounted substaion in kerala
Pole mounted substaion in keralaPole mounted substaion in kerala
Pole mounted substaion in keralasebinkb
 
Optical Fiber Introduction
Optical Fiber IntroductionOptical Fiber Introduction
Optical Fiber Introductionjunaidmandviwala
 
Testing and Troubleshooting Fiber Optic Cables
Testing and Troubleshooting Fiber Optic CablesTesting and Troubleshooting Fiber Optic Cables
Testing and Troubleshooting Fiber Optic CablesLiving Online
 
Web based power quality monitoring system
Web based power quality monitoring systemWeb based power quality monitoring system
Web based power quality monitoring systemVikram Purohit
 

La actualidad más candente (20)

Report on PLCC
Report on PLCCReport on PLCC
Report on PLCC
 
BSNL Industrial Training ppt 2014.
BSNL Industrial Training ppt 2014.BSNL Industrial Training ppt 2014.
BSNL Industrial Training ppt 2014.
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presention
 
Power Line Carrier Communication
Power Line Carrier CommunicationPower Line Carrier Communication
Power Line Carrier Communication
 
Power Line Carrier Communication seminar
Power Line Carrier Communication seminarPower Line Carrier Communication seminar
Power Line Carrier Communication seminar
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scada
 
Power line communication
Power line communicationPower line communication
Power line communication
 
Hs Emc
Hs EmcHs Emc
Hs Emc
 
Electro magnetic interference and compatibility(ECM,ECI)
Electro magnetic interference and compatibility(ECM,ECI)Electro magnetic interference and compatibility(ECM,ECI)
Electro magnetic interference and compatibility(ECM,ECI)
 
Power Line Communication
Power Line CommunicationPower Line Communication
Power Line Communication
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
BSNL Training Report file
BSNL Training Report fileBSNL Training Report file
BSNL Training Report file
 
Bts installation & commisioning.ppt
Bts installation & commisioning.pptBts installation & commisioning.ppt
Bts installation & commisioning.ppt
 
Fault Location Of Transmission Line
Fault Location Of Transmission LineFault Location Of Transmission Line
Fault Location Of Transmission Line
 
Fundamentals of electromagnetic compatibility (EMC)
Fundamentals of electromagnetic compatibility (EMC)Fundamentals of electromagnetic compatibility (EMC)
Fundamentals of electromagnetic compatibility (EMC)
 
Pole mounted substaion in kerala
Pole mounted substaion in keralaPole mounted substaion in kerala
Pole mounted substaion in kerala
 
Optical Fiber Introduction
Optical Fiber IntroductionOptical Fiber Introduction
Optical Fiber Introduction
 
Testing and Troubleshooting Fiber Optic Cables
Testing and Troubleshooting Fiber Optic CablesTesting and Troubleshooting Fiber Optic Cables
Testing and Troubleshooting Fiber Optic Cables
 
Web based power quality monitoring system
Web based power quality monitoring systemWeb based power quality monitoring system
Web based power quality monitoring system
 
Ppt
PptPpt
Ppt
 

Destacado

Destacado (7)

Presentation on power line career communication by ramanand sagar
Presentation on power line career communication by ramanand sagarPresentation on power line career communication by ramanand sagar
Presentation on power line career communication by ramanand sagar
 
17 capability curve
17 capability curve17 capability curve
17 capability curve
 
Pong dam ppt
Pong dam pptPong dam ppt
Pong dam ppt
 
Bbmb
BbmbBbmb
Bbmb
 
Plcc
PlccPlcc
Plcc
 
Furan Testing of Transformers Oil
Furan Testing of Transformers OilFuran Testing of Transformers Oil
Furan Testing of Transformers Oil
 
SlideShare 101
SlideShare 101SlideShare 101
SlideShare 101
 

Similar a Plcc presentation

POWER LINE CARRIER COMMUNICATION
POWER LINE CARRIER COMMUNICATIONPOWER LINE CARRIER COMMUNICATION
POWER LINE CARRIER COMMUNICATIONAtul Kumar Sharma
 
Rrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communication
Rrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communicationRrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communication
Rrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communicationDushyant Singh Chouhan
 
Power_Line_Carrier_Communication.pptx
Power_Line_Carrier_Communication.pptxPower_Line_Carrier_Communication.pptx
Power_Line_Carrier_Communication.pptxVara Prasad
 
Power line carrier communication
Power  line  carrier  communicationPower  line  carrier  communication
Power line carrier communicationRahul Mehta
 
A new approach to motor condition monitoring
A new approach to motor condition monitoringA new approach to motor condition monitoring
A new approach to motor condition monitoringUFRN
 
industrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunindustrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunsurendra rawat
 
Power line carrier communication
Power line carrier communicationPower line carrier communication
Power line carrier communicationuttarakhatik
 
Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2Zulfiqar Mangrio
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )AnandMohan271812
 
INDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDYINDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDYtarun1504
 
Advancements in inverter technology
Advancements  in inverter technologyAdvancements  in inverter technology
Advancements in inverter technologyBhanu Teja
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
THASLEEM RESUME ELECTRONICS
THASLEEM RESUME ELECTRONICSTHASLEEM RESUME ELECTRONICS
THASLEEM RESUME ELECTRONICSthasleem v
 
Impact of APFC Panel at LT Side of Transformer
Impact of APFC Panel at LT Side of TransformerImpact of APFC Panel at LT Side of Transformer
Impact of APFC Panel at LT Side of TransformerIJERA Editor
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid designsusanta das
 

Similar a Plcc presentation (20)

Ppt
PptPpt
Ppt
 
POWER LINE CARRIER COMMUNICATION
POWER LINE CARRIER COMMUNICATIONPOWER LINE CARRIER COMMUNICATION
POWER LINE CARRIER COMMUNICATION
 
Rrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communication
Rrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communicationRrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communication
Rrvpnl summer-industrial-training-ajmer-in-power-line-carrier-communication
 
Power_Line_Carrier_Communication.pptx
Power_Line_Carrier_Communication.pptxPower_Line_Carrier_Communication.pptx
Power_Line_Carrier_Communication.pptx
 
Power line carrier communication
Power  line  carrier  communicationPower  line  carrier  communication
Power line carrier communication
 
Ppt.aslam
Ppt.aslamPpt.aslam
Ppt.aslam
 
A new approach to motor condition monitoring
A new approach to motor condition monitoringA new approach to motor condition monitoring
A new approach to motor condition monitoring
 
Power Line carrier communication
Power Line carrier communicationPower Line carrier communication
Power Line carrier communication
 
industrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunindustrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradun
 
Power line carrier communication
Power line carrier communicationPower line carrier communication
Power line carrier communication
 
Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
 
wireless power transfer
wireless power transferwireless power transfer
wireless power transfer
 
INDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDYINDUSTRIAL TRAINING:SWITCHYARD STUDY
INDUSTRIAL TRAINING:SWITCHYARD STUDY
 
Advancements in inverter technology
Advancements  in inverter technologyAdvancements  in inverter technology
Advancements in inverter technology
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
THASLEEM RESUME ELECTRONICS
THASLEEM RESUME ELECTRONICSTHASLEEM RESUME ELECTRONICS
THASLEEM RESUME ELECTRONICS
 
Impact of APFC Panel at LT Side of Transformer
Impact of APFC Panel at LT Side of TransformerImpact of APFC Panel at LT Side of Transformer
Impact of APFC Panel at LT Side of Transformer
 
Ppt power grid design
Ppt power grid designPpt power grid design
Ppt power grid design
 
Advances in power systems
Advances in power systemsAdvances in power systems
Advances in power systems
 

Último

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Último (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Plcc presentation

  • 1. Power Line Carrier CommunicationTO FROM: PROF.RAVI SONI PREETESH KUMAR ARYA (PROF.,EE DEPARTMENT) (IV YR,EE)
  • 2. Contant  Training overview  Company profile  Introduction  General modulation principle  Basic principle of PLCC  Specification  Basic arrangement  Wave trap  Tuning capacitor  Battery charger
  • 3.  Technical specification  Maintanance and fault traction  Maintanance and fault traction procedure  applications  Advantages  disadvantages  Key learning  Conclusion
  • 4. Training overview  Name of industry : Rajasthan Rajya vidyut prasaran nigam limited  Location : 220KV BASNI GSS , Jaipur  Duration of training : 20 may to 11 july  Department of training : electrical engineering
  • 5. About company  RRVPNL started working from july 1957  Sh.shailendra Agarwal,IAS is the chairman & MD of RRVPNL  RVPN provides the pathway for power within whole rajasthan  This is the body of big organization ACT, like public limited companies  It works as electric power distribution regulation within the state.
  • 6. Introduction  PLCC, Power Line Carrier Communication, is an approach to utilize the existing power lines for the transmission of information.  This technology has been in wide use since 1950 and was mainly used by the grid stations to transmit information at high speed.  Can use existing infrastructure for data traffic  Involves a lot of technicalities.
  • 7. General modulation principle  Single side band transmission  Carrier frequency is spaced on a 4KHz  I.F. fixed at 16KHz  Full duplex mode is used  Lower side band is used throught all communication
  • 8. Basic principle of PLCC  The communication system cannot be directly connected to the high voltage lines suitably designed coupling devices.  These usually consist of high voltage capacitor with polaritical devices used in conjucation with suitable line matching unit (LMU) for matching the impedence of line to that of the coaxial cable connecting the unit of the PLC transmit-receive equipment.
  • 9. Specifications of PLCC 1) GENERAL:-  Carrier frequency range:-40 to 512KHz  Useful AF band:-300 to 3700Hz 2) TRANSMITTER:-  Peak envelope power:-25W  Side band power:-15W
  • 10. Basic arrangement  The basic arrangement of connecting the WT and coupling capacitor in PLCC communication is shown in figure
  • 11. Types of coupling  A) phase to ground coupling
  • 12.  Phase to phase coupling
  • 13.  Phase to phase coupling
  • 14.  INTERLINE OR INTER CIRCUIT COUPLING
  • 15. Wave traps  Wave traps – (WT’s) are used between the transmission line and the power stations to avoid carrier power dislocation in the power plant and cross talk with other power line carrier circuits connected to the same power station
  • 16. Tuning capacitor  For lower voltage class of tuning units with impulse test voltage rating upto 40 KV polystyrene capacitors are used  For higher voltage class of tuning units with impulse test voltage rating upto 150 KV, capacitors with mineral oil impregnated paper dielectric are used  Used are high voltage, high stability mica capacitors with low losses
  • 17. Battery charger  PLCC (Power Line Carrier Communication) works on rectified AC or main power supply. When supply goes off, we use BATTERY CHARGER for proper functioning of PLCC, which provides supply to the PLCC equipment for uninterrupted working. It provides DC to the panel by battery of 48V. In this type 24 batteries are connected in series and individually per battery has approximately 2V capacity.  Battery charger mainly consists of 4 sections –   1. Float charger  2. Boost charger section  3. Control section  4. Alarm section
  • 18. Technical specifications  NORMAL INPUT :415 V AC 3-PHASE  INPUT VARIATION : +/- 20% FLOAT CHARGER : DC OUTPUT :50 V OUTPUT CURRENT :20 TO 40 AMP EFFICIENCY : >70%
  • 19.  BOOST CHARGER  DC output - 43.2 to 67.2 V  Output current - 25-70 Amps.  Efficiency - >80%
  • 20. Maintanace & fault traction  Fault analysis: in fault analysis the faulty devices are checked in this serial or manner: 1. Telephone or tele operation signal 2. Cabling low frequency circuit or DC power supply 3. PLC equipment 4. HF transmission path
  • 21. Maintainance and fault traction procedure  The control circuit boards should be inserted far firmly.  The charger should be switch off once in every month.  The battery terminal should be connected first and AC input after that.  All mounting bolts should be checked before energizing.
  • 22. Applications  PLCC Unit Provide Five type of operation: 1:TELEPHONE FACILITES 2:COMPRESSOR & EXPANDER 3:EMERGENCY CALL 4:SIGNAL BOOSTING 5:SUPERVISION & ALARMS
  • 23. Advantages  No separate wires are needed for communication purpose.  Both communication and power transfer can be possible on same circuit  Power lines provides the shortest route between the power station  Increase reliability  Lower attenuation over long distance  Implementation cost is reduced
  • 24. Disadvantages  Reflection are produced on spur lines connected to high voltage line this increased attenuation and create other problem.  High voltage lines have transformer connections,which attenuate carrier currents.  Noise introduced by power lines is far more than in case of telephonic lines.  Proper care has to be taken to guard carrier equipment and persons using them against high voltages and currents on the lines.
  • 25. Key learning  PLCC is mainly used for telecommunication,tele-protection and tele-monitoring,between electrical substation through power lines.  In a PLCC system the communication is established through the power line.  The carrier frequency range is allocated to include the audio signal, protection and the pilot frequency.
  • 26. conclusion  Power line carrier communication has been found to be the most economical and reliable method for communication in a medium and over long distance in a power system.