ALEXANDER HAMILTON BRIDGEALEXANDER HAMILTON BRIDGE
RECONSTRUCTION PROJECTRECONSTRUCTION PROJECTD260888 - X72681
Rehabilitation of the I-95 Corridor and
Interchange with I-87 between
Amsterdam Avenue and Undercliff Avenue
New York State Department of Transportation
Region 11
Joan McDonald, Commissioner
Phillip Eng P.E., Regional Director
State of New York
Governor Andrew Cuomo
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Meeting AgendaMeeting Agenda
I. Background/ Project History
II. Scope/ Elements of Work
III. Current Work
IV. Future Work
V. Modifications to Original Designs
VI. Project Management Tools
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
The Project TeamThe Project Team
• Area Construction Supervisor
– Manny Silva, NYSDOT
• Engineer in Charge
– Mike McCotter, NYSDOT
• Resident Engineer
– Albert Pozotrigo, M&J Eng. Ammann & Whitney Group
• Contractor
– CCA Civil/Halmar International LLC
• Community Liaison
– Kaitlyn Pezik, Zetlin Strategic Communications
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton BridgeAlexander Hamilton Bridge
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Background/Project HistoryBackground/Project History
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
I-87
Alexander Hamilton
Bridge
George Washington Bridge
181st
Street Bridge
LocationLocation
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge HistoryAlexander Hamilton Bridge History
A new eight-lane arch span was
proposed - the Alexander Hamilton
Bridge – to connect the Trans-
Manhattan and Cross-Bronx
Expressways.
Currently, estimated traffic
over the Hamilton Bridge
is over 188,000 vehicles
per day.
The Alexander Hamilton
Bridge has not undergone
major repair since it opened
on January 15, 1963.
In 1955, Robert Moses determined that
the 181st
Street Bridge would not be able
handle the anticipated traffic demands
from the proposed lower level of the
George Washington Bridge.
Information source: NYCRoads.com
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Final Design began: Winter 2002
• Original Letting: March 29, 2007 (No Bidders)
• NYSDOT redesigned temporary structures and
repackaged contract documents
• 2nd
Letting Date: January 22, 2009
Lowest Bidder- CCA Civil/ Halmar International
$407 Million
• Construction Began: Spring 2009
• Substantial Completion of Construction Work:
Winter 2013/2014
– Approximately 55% completed
History of the ProjectHistory of the Project
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Alexander Hamilton Bridge (I-95)– Maintain All
Through Lanes
(other than night-time 12:01 am to 5:30 am)
• Highbridge Interchange - Ramps “A” & “D”- Maintain
all lanes other than for lane shifts
• Weekend closures at nighttime only for lane shifts
• Undercliff Avenue Bridge – No long term closure
(staged construction)
• Ramp TE- Full Detour for Ramp Closure
Work Zone Traffic Control (MPT)Work Zone Traffic Control (MPT)
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Scope/Elements of WorkScope/Elements of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Remove and replace existing deck
• Fill in median framing
• Widen deck by 11’ each side
• Continuity splices in approach spans – make 2 span
continuous
• Some floorbeam and stringer replacement
• Eliminate some deck joints – reduce number of deck joints by
50%
• Construct new cap beams at piers
• Replace bearings
• Repair substructure concrete
• Retrofit substructure to meet current seismic requirements
• Paint steel superstructure
• Replace drainage, overhead sign structures & lighting
Alexander Hamilton BridgeAlexander Hamilton Bridge
Reconstruction Scope of WorkReconstruction Scope of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Existing Width: 115
ft.
Proposed Width: 137 ft.
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Construction Stages on theConstruction Stages on the
DeckDeck
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Arch reinforcement
Spandrel
Column
reinforcement
Expansion Joint
Elimination
Alexander Hamilton BridgeAlexander Hamilton Bridge
Structural Modifications-ArchStructural Modifications-Arch
SpanSpan
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
2 span
continuous
2 span
continuous
2 span
continuous
Alexander Hamilton BridgeAlexander Hamilton Bridge
Structural Modifications-EastStructural Modifications-East
ApproachApproach
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
2 span
continuous
Alexander Hamilton BridgeAlexander Hamilton Bridge
Structural Modifications-WestStructural Modifications-West
ApproachApproach
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Highbridge InterchangeHighbridge Interchange
RampsRamps
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp
B
(R.H.
Side)
RampRamp
DD
Ramp
F
Ramp
A
Ramp
L
(L.H.
Side)
Highbridge Interchange RampsHighbridge Interchange Ramps
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Provide temporary bridges adjacent to existing
ramps to take traffic during construction
• Remove existing deck
• Replace deck with new Cast-in-Place deck
• Widen deck by 1’-9” each side – 2 sections of ramp
• Replace deck in-kind – other sections of ramp
• Replace bearings
• Repair substructure concrete
• Retrofit substructure to meet current seismic
requirements
• Replace drainage, overhead sign structures &
lighting
• Paint superstructure steel
Highbridge Ramps Scope ofHighbridge Ramps Scope of
WorkWork
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp F: Red
Ramp A: Blue
Ramp D: Yellow
Highbridge Ramps TemporaryHighbridge Ramps Temporary
StructuresStructures
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Undercliff Avenue BridgeUndercliff Avenue Bridge
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Demolish existing 2 span concrete arch
• Complete bridge replacement with single
span multi-stringer bridge
• Relocate existing utilities
• Water Main
• Electric
• Gas
• Replace drainage & lighting
Undercliff Avenue BridgeUndercliff Avenue Bridge
Scope of WorkScope of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Undercliff Avenue BridgeUndercliff Avenue Bridge
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp TE
Alexander Hamilton Bridge
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Demolish existing concrete box superstructure
• Complete bridge replacement except abutments
• New steel box girder superstructure
• Rehabilitate existing abutments to accommodate
new superstructure
• Eliminate 5 piers and increase span lengths
• Relocate 2 piers to accommodate Alexander
Hamilton Bridge widening
• Rehabilitate 2 piers to accommodate new
superstructure
• Replace drainage & lighting
• Re-opened May 2011
Ramp TE Scope of WorkRamp TE Scope of Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Existing Ramp TEExisting Ramp TE
Demolition of TEDemolition of TE
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp TERamp TE
Tub GirdersTub Girders
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp TERamp TE
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Prepared Alexander Hamilton Bridge Median
• Provided temporary support to all of West and East Approach
Spans
• Constructed cap beams and foundation strengthening
• Reconstructed Ramp ‘TE’
• Constructed temporary structures
Stage IStage I
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage IStage I
Existing Median SidewalkExisting Median Sidewalk
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage IStage I
Median WorkMedian Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage IStage I
Median WorkMedian Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Widened Alexander Hamilton Bridge (WB)
• Completed cap beams and foundations
• Continued with temporary structures
• Completed reconstruction of Ramp ‘TE’
Stage IIStage II
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage II WideningStage II Widening
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage IIStage II
Ramp ARamp A
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage IIStage II
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage IIStage II
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage II & IIIStage II & III
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Current WorkCurrent Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Widening of Alexander Hamilton Bridge (EB)
• Continue with temporary structures
• To be completed June 2012
Stage IIIStage III
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Current Work- Stage IIICurrent Work- Stage III
MDE Temporary Ramp DMDE Temporary Ramp D
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage III MainlineStage III Mainline
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Stage III WideningStage III Widening
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Future WorkFuture Work
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Rehabilitate remaining portion of EB side of Alexander
Hamilton Bridge
• AHB EB lanes split around work-zone
• Rehabilitation of Highbridge Ramps Ongoing
• Duration 6 months
• Incentive/Disincentive Clause of $55,000 per day is
applicable to the completion of Stage IV
Stage IVStage IV
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Rehabilitate remaining portion of WB side of Alexander Hamilton
Bridge
• AHB WB lanes split around work-zone
• Rehabilitation of Highbridge Ramps Ongoing
• Duration 6 months
• Incentive/Disincentive Clause of $25,000 per day is applicable to
the completion of Stage V
Stage VStage V
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Rehabilitate median of Alexander Hamilton Bridge
• Replace on-grade pavement – Manhattan; Only off-peak lane
closures
• Replace on-grade pavement – Highbridge Ramps; Closures for
lane shifts only
• Duration 7 months
Stage VIStage VI
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Park Mitigation & ImprovementsPark Mitigation & Improvements
Renovation of Quisqueya
and CPF Playgrounds
Coordination with NYC
Parks Department
Highbridge Park Project on
Bronx Side
New Park Elements Include:
New Skateboard Feature
New Overlook Terrace/Area
Rehabilitation of Stairs, Brick
Walls, Walk Paths & Access Road
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Park Mitigation & ImprovementsPark Mitigation & Improvements
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Modifications to OriginalModifications to Original
DesignsDesigns
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp A & D WallsRamp A & D Walls
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp
A
Ramp D
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
MDE CrossoversMDE Crossovers
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Retrofit GirdersRetrofit Girders
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Support TowersSupport Towers
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Ramp TE FootingsRamp TE Footings
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Manny Silva, PE –Manny Silva, PE –
NYSDOT Region 11 ConstructionNYSDOT Region 11 Construction
Area Construction SupervisorArea Construction Supervisor
• NYSDOT R-11 Construction 1999 - Present
 Area Construction Supervisor
 CPM Coordinator for Construction (2007 – 2009)
 AGC/NYSDOT Emerging Technologies Subcommittee
• Task Force Meeting on CPM (2008 – 2009)
• NYSDOT R-8 Construction 1984 - 1999
 Engineer in Charge 1991 - 1999
 Inspector 1984 - 1991
• Major Projects
 Alexander Hamilton Bridge and Highbridge Ramps - Present
• Largest NYSDOT Construction Contract - $407 million
 West Side Highway Rehabilitation (Battery Place to W. 59th
Street) –
1999 - 2003
• 5 Construction Contracts - $500 million
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Project Management - AHBProject Management - AHB
• Project Management Tools:
– Field Automated Communications System -
FACS
• Inspection Reports
• Diaries
• Material Certifications
• Estimates (CEES Export)
• Contract Documents
• Cost control
– Oracle Primavera
• Contract Manager – Document Control
• P6 – Schedule Control (CPM)
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Contract Manager – Document ControlContract Manager – Document Control
• Project Team Collaboration
• Ball-In-Court (BIC) Feature
– Contractor has direct input
– Field Office has direct access and control
– Region management has access
– Albany support groups have direct access
and input
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Project Team CollaborationProject Team Collaboration
• Prime Contractor’s staff
– Subcontractors
– Fabricators
• NYSDOT staff
– Office of Construction
Field Office (includes consultant for Construction Support
Services)
Regional Office
Main Office
– Office of Structures - Structural Engineering Services Bureau
Metals Engineering Unit
Construction Support/Foundations Engineering Unit
Concrete Engineering Unit
– Office of Technical Services
Geotechnical Engineering Bureau
Materials Bureau
• Federal Highway Administration (FHWA)
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Contract Manager – Document ControlContract Manager – Document Control
• Manages submission & tracking of:
– Contractor Submittals
• Shop Drawings
• Erection Drawings
• Design Calculations
• Design Drawings
• FCS Drawings
• Demolition Drawings
• Catalog Cuts
– Requests For information (RFI)
– Progress Meeting Minutes
– Correspondence
– Contract Plan Sheet revisions
– Issues
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
BenefitsBenefits
– Reduces RFI turnaround times
– Shortens submittal (Shop Drawing) approval times
– Improves Field Office tracking of document
submittals
– Reduces costs - No mailing costs, reduced printing
costs.
– Increases productivity - Data is easily accessed.
– Improves team collaboration.
– Reduces disputes due to improved communication
– Easy access to contract records and documents
long after contract completion
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Primavera P6Primavera P6
CPM Scheduling SpecificationCPM Scheduling Specification
• P6 enterprise web based system
• No import and export issues
• Weekly schedule updates
• Maintain schedule
• Weekly schedule meetings
• Constantly talk about schedule
• Monthly schedule submissions
• Record all weekly data
• Report on issues and impacts
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Important Project AidsImportant Project Aids
• Winter concrete specification and Bid Item
– No winter calendars used on Bridge Deck
concrete activities
– Pay winter concrete with bid item
• Inspectors prepare electronic inspection
reports in FACS
– Each inspection report includes the schedule
activity related to the operation
– Inspectors choose schedule activity related to
their operation
– Scheduler can follow progress by reviewing
inspection reports remotely
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Schedule AnalysisSchedule Analysis
• Goal – Maintain Integrity of the Schedule
– Keeping schedule relevant
– Able to use schedule
– Tracking schedule impacts
– Modeling mitigation
– Modeling acceleration
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Weekly Update ProcessWeekly Update Process
• Contractor physically updates
schedule with progress and prepares
PDF prints for schedule meeting:
– Weekly Update Critical Path
– Weekly Update Look Ahead (3-4 months)
– PDF of any proposed changes
• Also discuss additional changes that
need to be made to schedule for
monthly update
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Weekly Update ScheduleWeekly Update Schedule
MeetingMeeting
• Status of schedule for the week
• Why did milestone dates move?
• Who is responsible?
• Key issues
– Important submittals and how they are or
can affect schedule
– Construction Issues and how they are or
can affect schedule
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Weekly Update ScheduleWeekly Update Schedule
MeetingMeeting
• Driving Critical Path activities
– Do they make sense?
– Are we working on them every day?
• Look ahead
– Review low float or negative float activities
• Why?
• Can the schedule be adjusted to fix float?
• Review upcoming changes
– Direct Contractor to adjust schedule based on
approved changes
– Allow Contractor to input changes – subject to
review with monthly submission
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Weekly Update ScheduleWeekly Update Schedule
MeetingMeeting
• Who attends?
– NYSDOT Scheduler
– Resident Engineer
– Engineer in Charge
– Area Supervisor*
– Submittal Coordinator*
– On-site Design Coordinator*
– Contractor’s Scheduler
– Contractor’s Engineering Management*
* Available on an as-need basis
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Issue- Floorbeam DeteriorationIssue- Floorbeam Deterioration
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Update 22 – July 2, 2011 Data Date
286- CCD behind schedule
• Update 27- December 3, 2011 Data Date
134- CCD behind schedule
Substantial Completion: February 14, 2014
• Projections from arch floorbeam issue
driving schedule
– Schedule Plan
• Model impact in schedule immediately
• Adjust frequently as more information comes available
• Develop & model mitigation options
• Make decisions
2011 Schedule Status2011 Schedule Status
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
AHB – Contractor Baseline TimelineAHB – Contractor Baseline Timeline
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Split up Stage 2 – start Stage 3 early
• Start Stage 6 west approach work early
• Speedy review of critical submittals
• Early opening of Temporary Bridge 7
Mitigation EffortsMitigation Efforts
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
• Eliminate Stage 3 Phase 2
• Acceleration program
• Used schedule to show how acceleration could
mitigate impacts and move bridge decks for
remaining stages into preferred construction season
Additional Mitigation EffortsAdditional Mitigation Efforts
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Lessons LearnedLessons Learned
• Buy-in by Project Team and Management is
key
• Provide Design Schedule/Template to
Contractor in enterprise system
• Schedule Specification
• Minimum bid price for scheduling
• If you maintain the integrity of the schedule
you can actually use it to manage the project
Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation
Region 11
Contact InfoContact Info
• Field Office Address:
– 26 Bruckner Blvd. Suite #32B Bronx, NY
10454
• Office Phone:
– (718) 402-9001
• Community Liaison:
Kaitlyn Pezik (718) 402-9008

Más contenido relacionado

La actualidad más candente

east_london_line_reborn (2)
east_london_line_reborn (2)east_london_line_reborn (2)
east_london_line_reborn (2)Robert Sharpe
 
Infrastructure Projects - Yanbu Industrial City
Infrastructure Projects - Yanbu Industrial CityInfrastructure Projects - Yanbu Industrial City
Infrastructure Projects - Yanbu Industrial CityNadeem Bakhsh
 
Energy Corridor - Residual Elevation and Flood Risk
Energy Corridor - Residual Elevation and Flood RiskEnergy Corridor - Residual Elevation and Flood Risk
Energy Corridor - Residual Elevation and Flood RiskDavis Tolman
 
Panama all in one ...
Panama all in one                                                            ...Panama all in one                                                            ...
Panama all in one ...jainagawat
 
Tunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_Forum
Tunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_ForumTunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_Forum
Tunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_ForumKevin Lovell, PMP
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen PowerpointMay Begum
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen PowerpointHayley Sharp
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingVDOT Northern Virginia
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Pont Samuel-De Champlain Bridge
 
pt 8: The Quickway Proposal: North County
pt 8: The Quickway Proposal: North Countypt 8: The Quickway Proposal: North County
pt 8: The Quickway Proposal: North CountyAlan Hoffman
 
Bay bridge second cr vassil final
Bay bridge second cr  vassil finalBay bridge second cr  vassil final
Bay bridge second cr vassil finalVassil Mladjov
 
Yeager Skanska - Temple Avenue Train Diversion
Yeager Skanska - Temple Avenue Train DiversionYeager Skanska - Temple Avenue Train Diversion
Yeager Skanska - Temple Avenue Train DiversionHanh N. Hong
 
JKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail PresentationJKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail PresentationJoe Krajewski
 
Bridges Middle East - Rick Haggett - Qatar Bahrain Causeway Management
Bridges Middle East - Rick Haggett - Qatar Bahrain Causeway ManagementBridges Middle East - Rick Haggett - Qatar Bahrain Causeway Management
Bridges Middle East - Rick Haggett - Qatar Bahrain Causeway ManagementOliviaModisakeng
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover damJasmine Tung
 
Norfolk Southern Presentation; Rail Night
Norfolk Southern Presentation; Rail NightNorfolk Southern Presentation; Rail Night
Norfolk Southern Presentation; Rail NightColumbus Chamber
 

La actualidad más candente (19)

east_london_line_reborn (2)
east_london_line_reborn (2)east_london_line_reborn (2)
east_london_line_reborn (2)
 
Senior Project PSR
Senior Project PSRSenior Project PSR
Senior Project PSR
 
Infrastructure Projects - Yanbu Industrial City
Infrastructure Projects - Yanbu Industrial CityInfrastructure Projects - Yanbu Industrial City
Infrastructure Projects - Yanbu Industrial City
 
Energy Corridor - Residual Elevation and Flood Risk
Energy Corridor - Residual Elevation and Flood RiskEnergy Corridor - Residual Elevation and Flood Risk
Energy Corridor - Residual Elevation and Flood Risk
 
Panama all in one ...
Panama all in one                                                            ...Panama all in one                                                            ...
Panama all in one ...
 
Tunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_Forum
Tunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_ForumTunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_Forum
Tunnel_and_Reservoir_Plan_Great_Lakes_Infrastructure_Forum
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
Jones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meetingJones Branch Connector "Pardon Our Dust" meeting
Jones Branch Connector "Pardon Our Dust" meeting
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016
 
News 3
News 3News 3
News 3
 
pt 8: The Quickway Proposal: North County
pt 8: The Quickway Proposal: North Countypt 8: The Quickway Proposal: North County
pt 8: The Quickway Proposal: North County
 
Bay bridge second cr vassil final
Bay bridge second cr  vassil finalBay bridge second cr  vassil final
Bay bridge second cr vassil final
 
Yeager Skanska - Temple Avenue Train Diversion
Yeager Skanska - Temple Avenue Train DiversionYeager Skanska - Temple Avenue Train Diversion
Yeager Skanska - Temple Avenue Train Diversion
 
Panama canal expansion delay
Panama canal expansion delayPanama canal expansion delay
Panama canal expansion delay
 
JKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail PresentationJKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail Presentation
 
Bridges Middle East - Rick Haggett - Qatar Bahrain Causeway Management
Bridges Middle East - Rick Haggett - Qatar Bahrain Causeway ManagementBridges Middle East - Rick Haggett - Qatar Bahrain Causeway Management
Bridges Middle East - Rick Haggett - Qatar Bahrain Causeway Management
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover dam
 
Norfolk Southern Presentation; Rail Night
Norfolk Southern Presentation; Rail NightNorfolk Southern Presentation; Rail Night
Norfolk Southern Presentation; Rail Night
 

Similar a AGC Presentation_Final_12.6.11(2)

Jan_2016_US27-SR29-jef.pdf
Jan_2016_US27-SR29-jef.pdfJan_2016_US27-SR29-jef.pdf
Jan_2016_US27-SR29-jef.pdfssuser87d0a41
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road RealignmentFairfax County
 
Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020Fairfax County
 
APWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line StationAPWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line StationT.Y. Lin International
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown UpdateCrosstown TO
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingFairfax County
 
Tempe Town Lake Pedestrian Bridge Construction 5 19 11
Tempe Town Lake Pedestrian Bridge Construction 5 19 11Tempe Town Lake Pedestrian Bridge Construction 5 19 11
Tempe Town Lake Pedestrian Bridge Construction 5 19 11City of Tempe, Arizona
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018Crosstown TO
 
The 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelThe 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelChris Goodman
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park NorthFairfax County
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
 

Similar a AGC Presentation_Final_12.6.11(2) (20)

Jan_2016_US27-SR29-jef.pdf
Jan_2016_US27-SR29-jef.pdfJan_2016_US27-SR29-jef.pdf
Jan_2016_US27-SR29-jef.pdf
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
 
Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020Fairfax County Little River Turnpike Walkway August 2020
Fairfax County Little River Turnpike Walkway August 2020
 
APWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line StationAPWA Reporter - Cermak-McCormick Place Elevated Green Line Station
APWA Reporter - Cermak-McCormick Place Elevated Green Line Station
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
 
After the Storm
After the StormAfter the Storm
After the Storm
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
C.V.
C.V.C.V.
C.V.
 
Tempe Town Lake Pedestrian Bridge Construction 5 19 11
Tempe Town Lake Pedestrian Bridge Construction 5 19 11Tempe Town Lake Pedestrian Bridge Construction 5 19 11
Tempe Town Lake Pedestrian Bridge Construction 5 19 11
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
The 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelThe 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment Panel
 
Poster
PosterPoster
Poster
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park North
 
Golden gate bridge
Golden gate bridgeGolden gate bridge
Golden gate bridge
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Huntington Levee
Huntington LeveeHuntington Levee
Huntington Levee
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Four Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force PresentationFour Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force Presentation
 

AGC Presentation_Final_12.6.11(2)

  • 1. ALEXANDER HAMILTON BRIDGEALEXANDER HAMILTON BRIDGE RECONSTRUCTION PROJECTRECONSTRUCTION PROJECTD260888 - X72681 Rehabilitation of the I-95 Corridor and Interchange with I-87 between Amsterdam Avenue and Undercliff Avenue New York State Department of Transportation Region 11 Joan McDonald, Commissioner Phillip Eng P.E., Regional Director State of New York Governor Andrew Cuomo
  • 2. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Meeting AgendaMeeting Agenda I. Background/ Project History II. Scope/ Elements of Work III. Current Work IV. Future Work V. Modifications to Original Designs VI. Project Management Tools
  • 3. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 The Project TeamThe Project Team • Area Construction Supervisor – Manny Silva, NYSDOT • Engineer in Charge – Mike McCotter, NYSDOT • Resident Engineer – Albert Pozotrigo, M&J Eng. Ammann & Whitney Group • Contractor – CCA Civil/Halmar International LLC • Community Liaison – Kaitlyn Pezik, Zetlin Strategic Communications
  • 4. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Alexander Hamilton BridgeAlexander Hamilton Bridge
  • 5. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline
  • 6. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Alexander Hamilton Bridge MainlineAlexander Hamilton Bridge Mainline
  • 7. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Background/Project HistoryBackground/Project History
  • 8. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 I-87 Alexander Hamilton Bridge George Washington Bridge 181st Street Bridge LocationLocation
  • 9. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Alexander Hamilton Bridge HistoryAlexander Hamilton Bridge History A new eight-lane arch span was proposed - the Alexander Hamilton Bridge – to connect the Trans- Manhattan and Cross-Bronx Expressways. Currently, estimated traffic over the Hamilton Bridge is over 188,000 vehicles per day. The Alexander Hamilton Bridge has not undergone major repair since it opened on January 15, 1963. In 1955, Robert Moses determined that the 181st Street Bridge would not be able handle the anticipated traffic demands from the proposed lower level of the George Washington Bridge. Information source: NYCRoads.com
  • 10. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Final Design began: Winter 2002 • Original Letting: March 29, 2007 (No Bidders) • NYSDOT redesigned temporary structures and repackaged contract documents • 2nd Letting Date: January 22, 2009 Lowest Bidder- CCA Civil/ Halmar International $407 Million • Construction Began: Spring 2009 • Substantial Completion of Construction Work: Winter 2013/2014 – Approximately 55% completed History of the ProjectHistory of the Project
  • 11. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Alexander Hamilton Bridge (I-95)– Maintain All Through Lanes (other than night-time 12:01 am to 5:30 am) • Highbridge Interchange - Ramps “A” & “D”- Maintain all lanes other than for lane shifts • Weekend closures at nighttime only for lane shifts • Undercliff Avenue Bridge – No long term closure (staged construction) • Ramp TE- Full Detour for Ramp Closure Work Zone Traffic Control (MPT)Work Zone Traffic Control (MPT)
  • 12. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Scope/Elements of WorkScope/Elements of Work
  • 13. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Remove and replace existing deck • Fill in median framing • Widen deck by 11’ each side • Continuity splices in approach spans – make 2 span continuous • Some floorbeam and stringer replacement • Eliminate some deck joints – reduce number of deck joints by 50% • Construct new cap beams at piers • Replace bearings • Repair substructure concrete • Retrofit substructure to meet current seismic requirements • Paint steel superstructure • Replace drainage, overhead sign structures & lighting Alexander Hamilton BridgeAlexander Hamilton Bridge Reconstruction Scope of WorkReconstruction Scope of Work
  • 14. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Existing Width: 115 ft. Proposed Width: 137 ft.
  • 15. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Construction Stages on theConstruction Stages on the DeckDeck
  • 16. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Arch reinforcement Spandrel Column reinforcement Expansion Joint Elimination Alexander Hamilton BridgeAlexander Hamilton Bridge Structural Modifications-ArchStructural Modifications-Arch SpanSpan
  • 17. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 2 span continuous 2 span continuous 2 span continuous Alexander Hamilton BridgeAlexander Hamilton Bridge Structural Modifications-EastStructural Modifications-East ApproachApproach
  • 18. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 2 span continuous Alexander Hamilton BridgeAlexander Hamilton Bridge Structural Modifications-WestStructural Modifications-West ApproachApproach
  • 19. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Highbridge InterchangeHighbridge Interchange RampsRamps
  • 20. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp B (R.H. Side) RampRamp DD Ramp F Ramp A Ramp L (L.H. Side) Highbridge Interchange RampsHighbridge Interchange Ramps
  • 21. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Provide temporary bridges adjacent to existing ramps to take traffic during construction • Remove existing deck • Replace deck with new Cast-in-Place deck • Widen deck by 1’-9” each side – 2 sections of ramp • Replace deck in-kind – other sections of ramp • Replace bearings • Repair substructure concrete • Retrofit substructure to meet current seismic requirements • Replace drainage, overhead sign structures & lighting • Paint superstructure steel Highbridge Ramps Scope ofHighbridge Ramps Scope of WorkWork
  • 22. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp F: Red Ramp A: Blue Ramp D: Yellow Highbridge Ramps TemporaryHighbridge Ramps Temporary StructuresStructures
  • 23. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Undercliff Avenue BridgeUndercliff Avenue Bridge
  • 24. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Demolish existing 2 span concrete arch • Complete bridge replacement with single span multi-stringer bridge • Relocate existing utilities • Water Main • Electric • Gas • Replace drainage & lighting Undercliff Avenue BridgeUndercliff Avenue Bridge Scope of WorkScope of Work
  • 25. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Undercliff Avenue BridgeUndercliff Avenue Bridge
  • 26. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp TE Alexander Hamilton Bridge Ramp TERamp TE
  • 27. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Demolish existing concrete box superstructure • Complete bridge replacement except abutments • New steel box girder superstructure • Rehabilitate existing abutments to accommodate new superstructure • Eliminate 5 piers and increase span lengths • Relocate 2 piers to accommodate Alexander Hamilton Bridge widening • Rehabilitate 2 piers to accommodate new superstructure • Replace drainage & lighting • Re-opened May 2011 Ramp TE Scope of WorkRamp TE Scope of Work
  • 28. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Existing Ramp TEExisting Ramp TE Demolition of TEDemolition of TE
  • 29. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp TERamp TE Tub GirdersTub Girders
  • 30. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp TERamp TE
  • 31. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp TERamp TE
  • 32. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp TERamp TE
  • 33. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Prepared Alexander Hamilton Bridge Median • Provided temporary support to all of West and East Approach Spans • Constructed cap beams and foundation strengthening • Reconstructed Ramp ‘TE’ • Constructed temporary structures Stage IStage I
  • 34. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage IStage I Existing Median SidewalkExisting Median Sidewalk
  • 35. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage IStage I Median WorkMedian Work
  • 36. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage IStage I Median WorkMedian Work
  • 37. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Widened Alexander Hamilton Bridge (WB) • Completed cap beams and foundations • Continued with temporary structures • Completed reconstruction of Ramp ‘TE’ Stage IIStage II
  • 38. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage II WideningStage II Widening
  • 39. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage IIStage II Ramp ARamp A
  • 40. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage IIStage II
  • 41. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage IIStage II
  • 42. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage II & IIIStage II & III
  • 43. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Current WorkCurrent Work
  • 44. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Widening of Alexander Hamilton Bridge (EB) • Continue with temporary structures • To be completed June 2012 Stage IIIStage III
  • 45. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Current Work- Stage IIICurrent Work- Stage III MDE Temporary Ramp DMDE Temporary Ramp D
  • 46. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage III MainlineStage III Mainline
  • 47. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Stage III WideningStage III Widening
  • 48. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Future WorkFuture Work
  • 49. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Rehabilitate remaining portion of EB side of Alexander Hamilton Bridge • AHB EB lanes split around work-zone • Rehabilitation of Highbridge Ramps Ongoing • Duration 6 months • Incentive/Disincentive Clause of $55,000 per day is applicable to the completion of Stage IV Stage IVStage IV
  • 50. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 51. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Rehabilitate remaining portion of WB side of Alexander Hamilton Bridge • AHB WB lanes split around work-zone • Rehabilitation of Highbridge Ramps Ongoing • Duration 6 months • Incentive/Disincentive Clause of $25,000 per day is applicable to the completion of Stage V Stage VStage V
  • 52. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 53. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Rehabilitate median of Alexander Hamilton Bridge • Replace on-grade pavement – Manhattan; Only off-peak lane closures • Replace on-grade pavement – Highbridge Ramps; Closures for lane shifts only • Duration 7 months Stage VIStage VI
  • 54. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Park Mitigation & ImprovementsPark Mitigation & Improvements Renovation of Quisqueya and CPF Playgrounds Coordination with NYC Parks Department Highbridge Park Project on Bronx Side New Park Elements Include: New Skateboard Feature New Overlook Terrace/Area Rehabilitation of Stairs, Brick Walls, Walk Paths & Access Road
  • 55. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Park Mitigation & ImprovementsPark Mitigation & Improvements
  • 56. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Modifications to OriginalModifications to Original DesignsDesigns
  • 57. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp A & D WallsRamp A & D Walls
  • 58. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 59. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 60. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp A Ramp D
  • 61. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 62. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 MDE CrossoversMDE Crossovers
  • 63. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 64. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 65. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Retrofit GirdersRetrofit Girders
  • 66. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 67. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 68. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 69. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Support TowersSupport Towers
  • 70. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 71. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 72. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Ramp TE FootingsRamp TE Footings
  • 73. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 74. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 75. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 76. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Manny Silva, PE –Manny Silva, PE – NYSDOT Region 11 ConstructionNYSDOT Region 11 Construction Area Construction SupervisorArea Construction Supervisor • NYSDOT R-11 Construction 1999 - Present  Area Construction Supervisor  CPM Coordinator for Construction (2007 – 2009)  AGC/NYSDOT Emerging Technologies Subcommittee • Task Force Meeting on CPM (2008 – 2009) • NYSDOT R-8 Construction 1984 - 1999  Engineer in Charge 1991 - 1999  Inspector 1984 - 1991 • Major Projects  Alexander Hamilton Bridge and Highbridge Ramps - Present • Largest NYSDOT Construction Contract - $407 million  West Side Highway Rehabilitation (Battery Place to W. 59th Street) – 1999 - 2003 • 5 Construction Contracts - $500 million
  • 77. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Project Management - AHBProject Management - AHB • Project Management Tools: – Field Automated Communications System - FACS • Inspection Reports • Diaries • Material Certifications • Estimates (CEES Export) • Contract Documents • Cost control – Oracle Primavera • Contract Manager – Document Control • P6 – Schedule Control (CPM)
  • 78. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 79. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Contract Manager – Document ControlContract Manager – Document Control • Project Team Collaboration • Ball-In-Court (BIC) Feature – Contractor has direct input – Field Office has direct access and control – Region management has access – Albany support groups have direct access and input
  • 80. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Project Team CollaborationProject Team Collaboration • Prime Contractor’s staff – Subcontractors – Fabricators • NYSDOT staff – Office of Construction Field Office (includes consultant for Construction Support Services) Regional Office Main Office – Office of Structures - Structural Engineering Services Bureau Metals Engineering Unit Construction Support/Foundations Engineering Unit Concrete Engineering Unit – Office of Technical Services Geotechnical Engineering Bureau Materials Bureau • Federal Highway Administration (FHWA)
  • 81. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Contract Manager – Document ControlContract Manager – Document Control • Manages submission & tracking of: – Contractor Submittals • Shop Drawings • Erection Drawings • Design Calculations • Design Drawings • FCS Drawings • Demolition Drawings • Catalog Cuts – Requests For information (RFI) – Progress Meeting Minutes – Correspondence – Contract Plan Sheet revisions – Issues
  • 82. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11
  • 83. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 BenefitsBenefits – Reduces RFI turnaround times – Shortens submittal (Shop Drawing) approval times – Improves Field Office tracking of document submittals – Reduces costs - No mailing costs, reduced printing costs. – Increases productivity - Data is easily accessed. – Improves team collaboration. – Reduces disputes due to improved communication – Easy access to contract records and documents long after contract completion
  • 84. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Primavera P6Primavera P6 CPM Scheduling SpecificationCPM Scheduling Specification • P6 enterprise web based system • No import and export issues • Weekly schedule updates • Maintain schedule • Weekly schedule meetings • Constantly talk about schedule • Monthly schedule submissions • Record all weekly data • Report on issues and impacts
  • 85. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Important Project AidsImportant Project Aids • Winter concrete specification and Bid Item – No winter calendars used on Bridge Deck concrete activities – Pay winter concrete with bid item • Inspectors prepare electronic inspection reports in FACS – Each inspection report includes the schedule activity related to the operation – Inspectors choose schedule activity related to their operation – Scheduler can follow progress by reviewing inspection reports remotely
  • 86. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Schedule AnalysisSchedule Analysis • Goal – Maintain Integrity of the Schedule – Keeping schedule relevant – Able to use schedule – Tracking schedule impacts – Modeling mitigation – Modeling acceleration
  • 87. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Weekly Update ProcessWeekly Update Process • Contractor physically updates schedule with progress and prepares PDF prints for schedule meeting: – Weekly Update Critical Path – Weekly Update Look Ahead (3-4 months) – PDF of any proposed changes • Also discuss additional changes that need to be made to schedule for monthly update
  • 88. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Weekly Update ScheduleWeekly Update Schedule MeetingMeeting • Status of schedule for the week • Why did milestone dates move? • Who is responsible? • Key issues – Important submittals and how they are or can affect schedule – Construction Issues and how they are or can affect schedule
  • 89. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Weekly Update ScheduleWeekly Update Schedule MeetingMeeting • Driving Critical Path activities – Do they make sense? – Are we working on them every day? • Look ahead – Review low float or negative float activities • Why? • Can the schedule be adjusted to fix float? • Review upcoming changes – Direct Contractor to adjust schedule based on approved changes – Allow Contractor to input changes – subject to review with monthly submission
  • 90. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Weekly Update ScheduleWeekly Update Schedule MeetingMeeting • Who attends? – NYSDOT Scheduler – Resident Engineer – Engineer in Charge – Area Supervisor* – Submittal Coordinator* – On-site Design Coordinator* – Contractor’s Scheduler – Contractor’s Engineering Management* * Available on an as-need basis
  • 91. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Issue- Floorbeam DeteriorationIssue- Floorbeam Deterioration
  • 92. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Update 22 – July 2, 2011 Data Date 286- CCD behind schedule • Update 27- December 3, 2011 Data Date 134- CCD behind schedule Substantial Completion: February 14, 2014 • Projections from arch floorbeam issue driving schedule – Schedule Plan • Model impact in schedule immediately • Adjust frequently as more information comes available • Develop & model mitigation options • Make decisions 2011 Schedule Status2011 Schedule Status
  • 93. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 AHB – Contractor Baseline TimelineAHB – Contractor Baseline Timeline
  • 94. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Split up Stage 2 – start Stage 3 early • Start Stage 6 west approach work early • Speedy review of critical submittals • Early opening of Temporary Bridge 7 Mitigation EffortsMitigation Efforts
  • 95. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 • Eliminate Stage 3 Phase 2 • Acceleration program • Used schedule to show how acceleration could mitigate impacts and move bridge decks for remaining stages into preferred construction season Additional Mitigation EffortsAdditional Mitigation Efforts
  • 96. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Lessons LearnedLessons Learned • Buy-in by Project Team and Management is key • Provide Design Schedule/Template to Contractor in enterprise system • Schedule Specification • Minimum bid price for scheduling • If you maintain the integrity of the schedule you can actually use it to manage the project
  • 97. Alexander Hamilton Bridge ReconstructionNew York State Department of Transportation Region 11 Contact InfoContact Info • Field Office Address: – 26 Bruckner Blvd. Suite #32B Bronx, NY 10454 • Office Phone: – (718) 402-9001 • Community Liaison: Kaitlyn Pezik (718) 402-9008

Notas del editor

  1. Stage 1 : The median area will be reconstructed as a temporary travel lane Stage 2: The westbound right-hand lanes will be worked on and the bridge will be widened Stage 3: The eastbound right-hand lanes will be worked on and the bridge will be widened Stage 4: Eastbound traffic will be split, with the construction work area in between Stage 5: Westbound traffic will be split, with the construction work area in between Stage 6: Traffic will return to its original formation, and the median barrier will be reconstructed
  2. The arch rib will require stiffening only to the outer ribs, and primarily to reinforce these members for section loss due to corrosion. The only spandrel columns that require reinforcement are the longest columns at Panel Points 8 and 8’. This is because the original design used the same section for all columns, and buckling controlled the design. Load capacity increase is assisted by making the slab composite And finally it is proposed to eliminate the expansion joints in the deck at the 1/3 points. The analysis of the overall combined structure indicated that no overstresses resulted provided that the joints were locked at the full dead load condition.
  3. Referred to as “spaghetti ramps”
  4. Field Automated Communications Systems - FACS
  5. Acceleration analysis – our independent analysis verified Contractor’s analysis and also showed additional areas that could be accelerated to meet goals Submittal review analysis – if review process can be shortened what is result Fabrication review analysis – if fabrication duration can be shortened what is result Extensive analysis of mitigation options and ideas Will modifying stages actually save time? While we are working on mitigation ideas, what work should we be progressing Will moving west approach slab work earlier actually help? If we keep Temporary Bridge 7A in service longer, will it hurt us later?
  6. By-in by NYSDOT Management is key Enterprise system is working so well because NYSDOT has made it clear that this is the way they want to do business on this project NYSDOT Area Supervisor chaired schedule kick-off meeting at start of project – I want this system to work and to be used Involved in weekly schedule meetings Does not work well on other projects if senior DOT staff is not on board and Software Notebook Function is Excellent Tool Speeds development of monthly schedule narrative Excellent record of changes Have already applied this to other projects Provide Schedule Template to Contractor Speeds creation of baseline Uniform standard DOT calendars and codes Minimum bid price for scheduling Contractor hired qualified scheduler Two bidders bid more than minimum Shows that scheduling is very important Schedule Specification Immediate rejection criteria – avoids incomplete schedule submissions made just to meet deadlines or get paid Details how schedule should be calculated If you maintain the integrity of the schedule you can actually use it to manage the project What-if scenarios to model mitigation options or potential impacts Model acceleration to set expected goals Model impact of stage changes