TRAVERSE SURVEY
Lecture - 2
Basic Principle of Surveying
• The ruling principle of surveying is:
“To work from whole to part and not form part
to whole”.
• First; control points are established in the area to
be surveyed. This can be done through a network
of triangles or traversing.
• Control points for the „primary network‟ are
provided with the help of instruments of highest
precision and by adopting well established
methods of observation.
Basic Principle of Surveying
• If these control points are quite far apart and it is difficult to
plot details, the primary network can be further divided into a
network of „secondary triangles‟. This work is conducted by
less precise methods & instruments. In the end „survey of
details‟ is conducted by taking these established control
points as the base points. The underlying idea is to minimize
the accumulation of the error and to localize the error.
• If survey is made to expand outward from central point, the
minor errors will become so magnified as to become
uncontrollable at the end.
• But if the basic control points are established with highest
precision, minor errors, if any, are further localized between
the small networks in which the work is conducted.
Traverse Surveying
• A traverse surveying is one in which the
framework consists of connected lines whose
lengths are measured with a chain or tape and
the directions are determined with an angular
instrument.
1. Open Traverse
2. Closed Traverse
Open Traverse:
• A traverse is said to be an open traverse when it does not
form a closed polygon.
• It consists of a series of lines extending in the same general
direction and does not return to the starting point. Similarly,
it does not start and end at points whose positions on plan
are known.
• It is suitable for the survey of a long narrow strip of country
e.g the roads, canals or railways etc.
Closed Traverse:
• A traverse is said to be closed when a complete circuit is
made i.e. when it returns to the starting point forming a
closed polygon as shown in figure. Or when it begins and
ends at points whose positions on the plan are known.
• Sum of angles for a closed traverse = (2N ± 4) 900
• Where N = No. of sides of closed traverse.
• +ve sign for exterior angles and –ve sign for the interior
angles.
Bearing of a line:
• The direction of a survey may be defined by the horizontal
angle between the line and the fixed line of reference
(called the meridian) called the bearing of a line.
• “It is the horizontal angle which a line makes with some
reference direction. Reference Direction is called
meridian.”
• The reference direction employed in a survey may be
1. A true or geographic meridian
2. A magnetic meridian
3. An arbitrary or assumed meridian
1. True or Geographic Meridian:
• The true or geographic meridian is a line in which
the plane passing through the given point and the
north and south poles intersect the surface of
earth.
• The direction of a true meridian is invariable. The
true meridians through the various stations are
not parallel, but converge to the poles.
• However, for ordinary small surveys, they are
assumed to be parallel to each other.
• The horizontal angle between the true meridian
and the line is called true bearing of a line. It is
also known as Azimuth.
2. Magnetic Meridian:
• The magnetic meridian is the direction indicated
by a freely suspended and properly balanced
magnetic needle, unaffected by the local
attractive forces.
• The angle which the line make with the magnetic
meridian is called a magnetic meridian of a line or
simply bearing of the line.
3. Arbitrary or Assumed Meridian:
• The arbitrary or assumed meridian is usually the
direction from a survey station to some well
defined permanent object or the first line of a
survey.
• The angle between this meridian and a line is
known as arbitrary or assumed Bearing.
Designations of Bearings:
• The following two systems are commonly used to
express the bearings:
1. Whole Circle Bearing System (WCB)
2. Quadrantal Bearing System (QB)
Whole Circle Bearing System:
• In the whole circle bearing system (W.C.B), the
bearing of a line is always measured clockwise
from the north point of the reference meridian
towards the line right round the circle.
• The angle measured is called whole circle
bearing (W.C.B).
• It may have any values between 00 and 3600.
• The bearing observed with the prismatic compass
are the whole circle bearings.
Quadrantal Bearing System:
• In a Quadrantal bearing system, the bearing of a
line is measured clockwise or anticlockwise from
the north or the south point whichever is nearer
the line, towards the east or west. In this system,
the bearing is reckoned from 00 and 900 in each
quadrant.
• The bearings observed with the surveyor‟s
compass are the quadrantal bearing .
To find QB from WCB
N
EW
S
A
35O15’
P
Solution :
Line PA lies in 1st quadrant.
Quadrant Bearing bearing of PA = N 35o 15’ E
To find QB from WCB
130O0’
E
S
N
W
B
P
50O
Solution :
Line PB lies in 2nd quadrant.
Quadrant Bearing of PB = S 50o 00’ E
To find QB from WCB
P
210O15’
S
E
N
C 30O15’
Solution :
Line PC lies in 3rd quadrant.
Quadrant Bearing of PC = S 30o 15’ W
To find QB from WCB
P
W
N
S
E
D
69O15’
290O45’
Solution :
Line PD lies in 4th quadrant.
Quadrant Bearing bearing of PD = N 69o 15’ W
To find Whole Circle Bearing from QB
• Qn: PA
• Ans: Line PA is in the first quadrant. Its WCB is 35o15’
N
E
S
W
35o15’
P
A
To find Whole Circle Bearing from QB
• Qn: PB
• Line PB is in second quadrant. Its WCB is 180o00’-50o00’ =
130o00’
N
E
S
W P
B
130o00’
To find Whole Circle Bearing from QB
• Qn: PC
• Line PC is third quadrant. Its WCB is 180o00’+30o15’ =
210o15’
N
E
S
W P
B
210o15’
c
To find Whole Circle Bearing from QB
• Qn: PD
• Line PD is in fourth quadrant. Its WCB is 360o00’-69o15’=
291o15’
N
E
S
W P
291o45’
D
Reduced Bearings:
• When the whole circle bearing of a line exceed
900, it may be reduced to the corresponding
angle less than 900, which has the same
numerical values of the trigonometric functions.
The angle is known as the reduced bearing (R.B).
In order to obtain the reduced bearings o the
lines, the following table may be used:
Case W.C.B between Rule of R.B Quadrant
I 0o and 90o = W.C.B N-E
II 90o and 180o = 180o - W.C.B S-E
III 180o and 270o = W.C.B - 180o S-W
IV 270o and 360o = 360o - W.C.B N-W
Traverse Survey Part 1/2

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Control surveying
Control surveyingControl surveying
Control surveying
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in Survey
 
Plane Table Survey
Plane Table SurveyPlane Table Survey
Plane Table Survey
 
Introduction to surveying, ranging and chaining
Introduction to surveying, ranging and chainingIntroduction to surveying, ranging and chaining
Introduction to surveying, ranging and chaining
 
Triangulation survey
Triangulation surveyTriangulation survey
Triangulation survey
 
surveying contouring
surveying contouring surveying contouring
surveying contouring
 
Two points problem of plane table
Two points problem of plane table Two points problem of plane table
Two points problem of plane table
 
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptx
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Electronic distance measurement (EDM)
Electronic distance measurement (EDM)Electronic distance measurement (EDM)
Electronic distance measurement (EDM)
 
Introduction to Surveying
Introduction to SurveyingIntroduction to Surveying
Introduction to Surveying
 
Plane Table Surveying PPt
Plane Table Surveying PPtPlane Table Surveying PPt
Plane Table Surveying PPt
 
Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
 
Levelling
LevellingLevelling
Levelling
 
Angular measurement for surveying
Angular measurement for surveyingAngular measurement for surveying
Angular measurement for surveying
 
chain surveying
chain surveyingchain surveying
chain surveying
 
Theodolite angle measurement
Theodolite angle measurementTheodolite angle measurement
Theodolite angle measurement
 

Destacado

Vampire Electricity-Standby Power
Vampire Electricity-Standby PowerVampire Electricity-Standby Power
Vampire Electricity-Standby PowerGAURAV. H .TANDON
 
1392741020 traverse survey
1392741020 traverse survey1392741020 traverse survey
1392741020 traverse surveyanjali adabala
 
Trigonometric levelling jithin
Trigonometric levelling   jithinTrigonometric levelling   jithin
Trigonometric levelling jithinJithin Jose
 
Chap.6 traverse surveys
Chap.6 traverse surveysChap.6 traverse surveys
Chap.6 traverse surveysstudent
 
Trigonometric leveling
Trigonometric leveling Trigonometric leveling
Trigonometric leveling Siddhant Patel
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouringAbdul Majid
 
Tacheometric survey
Tacheometric surveyTacheometric survey
Tacheometric surveyStudent
 

Destacado (10)

Vampire Electricity-Standby Power
Vampire Electricity-Standby PowerVampire Electricity-Standby Power
Vampire Electricity-Standby Power
 
1392741020 traverse survey
1392741020 traverse survey1392741020 traverse survey
1392741020 traverse survey
 
Trigonometric levelling jithin
Trigonometric levelling   jithinTrigonometric levelling   jithin
Trigonometric levelling jithin
 
Chap.6 traverse surveys
Chap.6 traverse surveysChap.6 traverse surveys
Chap.6 traverse surveys
 
Trigonometric leveling
Trigonometric leveling Trigonometric leveling
Trigonometric leveling
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouring
 
Tacheometric survey
Tacheometric surveyTacheometric survey
Tacheometric survey
 
Levelling
LevellingLevelling
Levelling
 
Surveying
Surveying Surveying
Surveying
 
Industries
IndustriesIndustries
Industries
 

Similar a Traverse Survey Part 1/2

Similar a Traverse Survey Part 1/2 (20)

Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Angular measurement
Angular measurementAngular measurement
Angular measurement
 
types of bearing
types of bearingtypes of bearing
types of bearing
 
Compass Surveying.ppt
Compass Surveying.pptCompass Surveying.ppt
Compass Surveying.ppt
 
3.compass surveying
3.compass surveying3.compass surveying
3.compass surveying
 
chain and compass traversing.pptx
chain and compass traversing.pptxchain and compass traversing.pptx
chain and compass traversing.pptx
 
Compasssurveyin
CompasssurveyinCompasssurveyin
Compasssurveyin
 
Ch 5 levelling
Ch 5 levellingCh 5 levelling
Ch 5 levelling
 
COMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYINGCOMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYING
 
Survey Camp Manali ppt
Survey Camp Manali pptSurvey Camp Manali ppt
Survey Camp Manali ppt
 
Chain Surveying 2020.ppt
 Chain Surveying 2020.ppt Chain Surveying 2020.ppt
Chain Surveying 2020.ppt
 
compasssurveying-130918040430-phpapp01 (1).pdf
compasssurveying-130918040430-phpapp01 (1).pdfcompasssurveying-130918040430-phpapp01 (1).pdf
compasssurveying-130918040430-phpapp01 (1).pdf
 
Compass Surveying
Compass Surveying Compass Surveying
Compass Surveying
 
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptxUnit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
DEFINITIONS, PRINCIPLES AND CHAIN SURVEYING
DEFINITIONS, PRINCIPLES AND CHAIN SURVEYINGDEFINITIONS, PRINCIPLES AND CHAIN SURVEYING
DEFINITIONS, PRINCIPLES AND CHAIN SURVEYING
 
Chain surveying and offset
Chain surveying and offsetChain surveying and offset
Chain surveying and offset
 
Compass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil EngineeringCompass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil Engineering
 
Angular measurement
Angular measurementAngular measurement
Angular measurement
 

Último

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 

Último (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 

Traverse Survey Part 1/2

  • 2. Basic Principle of Surveying • The ruling principle of surveying is: “To work from whole to part and not form part to whole”. • First; control points are established in the area to be surveyed. This can be done through a network of triangles or traversing. • Control points for the „primary network‟ are provided with the help of instruments of highest precision and by adopting well established methods of observation.
  • 3. Basic Principle of Surveying • If these control points are quite far apart and it is difficult to plot details, the primary network can be further divided into a network of „secondary triangles‟. This work is conducted by less precise methods & instruments. In the end „survey of details‟ is conducted by taking these established control points as the base points. The underlying idea is to minimize the accumulation of the error and to localize the error. • If survey is made to expand outward from central point, the minor errors will become so magnified as to become uncontrollable at the end. • But if the basic control points are established with highest precision, minor errors, if any, are further localized between the small networks in which the work is conducted.
  • 4. Traverse Surveying • A traverse surveying is one in which the framework consists of connected lines whose lengths are measured with a chain or tape and the directions are determined with an angular instrument. 1. Open Traverse 2. Closed Traverse
  • 5. Open Traverse: • A traverse is said to be an open traverse when it does not form a closed polygon. • It consists of a series of lines extending in the same general direction and does not return to the starting point. Similarly, it does not start and end at points whose positions on plan are known. • It is suitable for the survey of a long narrow strip of country e.g the roads, canals or railways etc.
  • 6. Closed Traverse: • A traverse is said to be closed when a complete circuit is made i.e. when it returns to the starting point forming a closed polygon as shown in figure. Or when it begins and ends at points whose positions on the plan are known. • Sum of angles for a closed traverse = (2N ± 4) 900 • Where N = No. of sides of closed traverse. • +ve sign for exterior angles and –ve sign for the interior angles.
  • 7. Bearing of a line: • The direction of a survey may be defined by the horizontal angle between the line and the fixed line of reference (called the meridian) called the bearing of a line. • “It is the horizontal angle which a line makes with some reference direction. Reference Direction is called meridian.” • The reference direction employed in a survey may be 1. A true or geographic meridian 2. A magnetic meridian 3. An arbitrary or assumed meridian
  • 8. 1. True or Geographic Meridian: • The true or geographic meridian is a line in which the plane passing through the given point and the north and south poles intersect the surface of earth. • The direction of a true meridian is invariable. The true meridians through the various stations are not parallel, but converge to the poles. • However, for ordinary small surveys, they are assumed to be parallel to each other. • The horizontal angle between the true meridian and the line is called true bearing of a line. It is also known as Azimuth.
  • 9. 2. Magnetic Meridian: • The magnetic meridian is the direction indicated by a freely suspended and properly balanced magnetic needle, unaffected by the local attractive forces. • The angle which the line make with the magnetic meridian is called a magnetic meridian of a line or simply bearing of the line.
  • 10. 3. Arbitrary or Assumed Meridian: • The arbitrary or assumed meridian is usually the direction from a survey station to some well defined permanent object or the first line of a survey. • The angle between this meridian and a line is known as arbitrary or assumed Bearing.
  • 11. Designations of Bearings: • The following two systems are commonly used to express the bearings: 1. Whole Circle Bearing System (WCB) 2. Quadrantal Bearing System (QB)
  • 12. Whole Circle Bearing System: • In the whole circle bearing system (W.C.B), the bearing of a line is always measured clockwise from the north point of the reference meridian towards the line right round the circle. • The angle measured is called whole circle bearing (W.C.B). • It may have any values between 00 and 3600. • The bearing observed with the prismatic compass are the whole circle bearings.
  • 13. Quadrantal Bearing System: • In a Quadrantal bearing system, the bearing of a line is measured clockwise or anticlockwise from the north or the south point whichever is nearer the line, towards the east or west. In this system, the bearing is reckoned from 00 and 900 in each quadrant. • The bearings observed with the surveyor‟s compass are the quadrantal bearing .
  • 14. To find QB from WCB N EW S A 35O15’ P Solution : Line PA lies in 1st quadrant. Quadrant Bearing bearing of PA = N 35o 15’ E
  • 15. To find QB from WCB 130O0’ E S N W B P 50O Solution : Line PB lies in 2nd quadrant. Quadrant Bearing of PB = S 50o 00’ E
  • 16. To find QB from WCB P 210O15’ S E N C 30O15’ Solution : Line PC lies in 3rd quadrant. Quadrant Bearing of PC = S 30o 15’ W
  • 17. To find QB from WCB P W N S E D 69O15’ 290O45’ Solution : Line PD lies in 4th quadrant. Quadrant Bearing bearing of PD = N 69o 15’ W
  • 18. To find Whole Circle Bearing from QB • Qn: PA • Ans: Line PA is in the first quadrant. Its WCB is 35o15’ N E S W 35o15’ P A
  • 19. To find Whole Circle Bearing from QB • Qn: PB • Line PB is in second quadrant. Its WCB is 180o00’-50o00’ = 130o00’ N E S W P B 130o00’
  • 20. To find Whole Circle Bearing from QB • Qn: PC • Line PC is third quadrant. Its WCB is 180o00’+30o15’ = 210o15’ N E S W P B 210o15’ c
  • 21. To find Whole Circle Bearing from QB • Qn: PD • Line PD is in fourth quadrant. Its WCB is 360o00’-69o15’= 291o15’ N E S W P 291o45’ D
  • 22. Reduced Bearings: • When the whole circle bearing of a line exceed 900, it may be reduced to the corresponding angle less than 900, which has the same numerical values of the trigonometric functions. The angle is known as the reduced bearing (R.B). In order to obtain the reduced bearings o the lines, the following table may be used: Case W.C.B between Rule of R.B Quadrant I 0o and 90o = W.C.B N-E II 90o and 180o = 180o - W.C.B S-E III 180o and 270o = W.C.B - 180o S-W IV 270o and 360o = 360o - W.C.B N-W