Nabil Nassar has over 25 years of experience in municipal engineering projects related to water and wastewater treatment infrastructure. He has worked extensively in project management and construction management roles on large wastewater treatment plants and other civil engineering projects across the Middle East and Canada. Nassar holds professional engineering qualifications in Ontario, as well as certifications in project management and construction management. He is currently working as an Assistant Resident Engineer on a wastewater treatment plant and effluent pipeline project in Abu Dhabi.
1. NABIL NASSAR
21 Holiday Avenue London, Ontario N6E 1M9 050-1445170 nabil.nassar@parsons .com
OBJECTIVE
Municipal Environmental
SUMMARY OF QUALIFICATIONS
Proficient in Municipal Engineering over 25 years experiences in water and waste water treatment
and infrastructures projects (Passed PEO technical examinations in Municipal Engineers, water and
Waste treatment plants
Project management experience combined with many courses in project management passed all PMP
on line courses through Parsons University / SKILLSOFT (see courses result attached herewith )
Construction Management Experience , in the process to be a member of The Construction
Management Association of America CMAA (See courses result attached herewith )
EIT, Professional Engineers Ontario
ENGINEERING EXPERIENCE
Project Planning
Studied contract documents: tenders, contract terms, drawings, bills of quantity, quotations, suppliers’
prices, and project requirements including labor, material, equipment and site mobilization
Prepared project schedule according to relevant documents using Primavera Project Planner
Planned site mobilization including personnel, equipment, supplies and temporary offices
Reviewed project design criteria factoring in actual conditions and experience as contractor and
submitted report to consultant
Prepared materials submittal for executive manager, consultant and client approval
Prepared material take off list according to approved materials and delivery schedule for one month,
three months, six months as well as entire project
Prepared shop drawing for consultant approval with AutoCAD operator and quantity surveyor
Construction Management
Led team for site development, road work, construction of structures: secondary settlement tanks,
degassing distribution structure, aeration tanks, storm water storage tanks, aerobic digestion storage
tanks, dewatered sludge storage, inlet works building, ferric chloride storage, odor control building,
activated sludge recirculation pumping station, aeration air blower building, electrical building, piping
Oversaw all civil works; led civil works team and technical site office to solve on-site technical issues;
forwarded to engineering for approval; filed change request or request for information
Supervised all aspects of construction: surveying, excavation, pipe laying, water testing, backfilling,
asphalt restoration, site grading, soil stabilization for embankments, compaction tests
Monitored subcontractors’ activities, material submission and reviewed statement of work method
Managed handover of site and oversaw demolition, site clearance, site mobilization and surveying
Coordinated communication among all subcontractors: civil, mechanical, electrical and instruments
Monitored construction progress; followed up daily work progress, prepared daily, weekly, monthly
reports, took proactive action to prevent delays and implemented strategies to deal with delays
Implemented Quality Control and Health and Safety policies ensuring compliance to standards
Checked shop drawings, prepared as built drawings, provided records and other related documents
Prepared monthly payment certificates for client with quantity surveyor
Followed up on project progress through daily checks and weekly meetings with consultant and client
2. Nabil Nassar 519-208-0625
Page 2 of 5
HISTORY OF EXPERIENCE
Assistant Residences Engineer / Civil 2014 - to date
Parsons International Limited MEA(Middle East Africa ) /UAE
Client ADSSC/Abu Dhabi Sewerage Service Company /UAE
Project ; Construction Management for the project of Design and Build Alruwais Waste water
Treatment Plant with Capacity of 15000 m/day and associated Treated water Effluent Line ( 600mm
Dia & 10 km length )
Project scope of works Construction Management & Consultant Engineering .
Construction Manager 2011 – 2014
Kharafi National, Ismalia, Egypt
Client: Ministry of Electricity (East Delta Electricity Production Company); Consultant: PGESCO
Project: Al-Shabab Power Plant – 1000 MW simple cycle gas turbine units; part of emergency plan for
Ministry of Electricity to add 3500 megawatts into power grid
Engineering, procurement and construction project consisted of eight gas turbines, 1000 megawatts, 125
mw each. Completed in six months, setting world record
Construction work – electromechanical, instrument and civil works; approximately 40,000m3 reinforced
concrete; works included GT pedestal and auxiliary foundations, RO plant, sewage treatment plant,
industrial water treatment plant, two solar tanks - 10,000 m3 each, service water tank - 23,800m3 ,
RO tank – 7400 m3, and demineralization tank – 6400m3, GIS (control-switch), gantry yard, administration
and warehouse buildings, MV & LV sub stations, underground utilities, landscaping and roads
Site Manager 2008 – 2011
Khadafy National, Abu Dhabi, UAE
Client: Abu Dhabi Sewage Services Company
Project: ISTP-1 Sewage Treatment BOOT Project, Al-Saad (capacity: 80,000 m3 per day) and Al Wathba
(capacity: 300,000 m3 per day) Sewage Treatment Plants, Abu Dhabi
Project involved financing, designing, constructing, operating and maintaining sewage treatment plants.
Both plants use combined treatment processes, including biological and advanced treatment units with
primary, secondary and tertiary treatments. Sludge treatment utilizes anaerobic digestion and bio gas
cogeneration facilities. Both plants produce effluent to maximum level of 2.0 nephelometric turbidity units.
Engineer-in-Training 2007
LAW Engineering London, Inc., London, Ontario
Client: Ministry of Transportation Ontario and City of London
Project: Asphalt and concrete study, Highway 8, 14 km, Waterloo; Highland Subdivision, London
Project Manager 2002 – 2006
Mohamed Abdul - Moshsin Al Kharfi Sons Co., Saudi Arabia
Client: Ministry of Industry and Electricity
Project: Development of 4th stage of industrial city, Riyadh; approximately 1,000,000 m2 including sanitary
sewer network, storm sewer network, medium voltage cables, lightning poles, lighting cables, telephone
cables, road work (cut and fill), curb stones, sidewalks (tile) and asphalt laying. Replacement of drinking
water network, 24,000 m in length and existing asphalt, 200,000 m2
3. Nabil Nassar 519-208-0625
Page 3 of 5
HISTORY OF EXPERIENCE
Project Manager 1998 – 2002
Mohamed Abdul Moshsin Al Kharfi Sons Co., Saudi Arabia
Client: Ministry of Industry and Electricity
Project: Expansion of industrial wastewater treatment plant. Increased capacity from 14000 m3 / day to
54000 m3 / day; improved treated water result to comply with international standard BOD 10 mm / L and
TSS 10 mm / L. Project included civil and electromechanical works for new aeration tank, four primary
clarifiers, two secondary clarifiers, two aerobic digesters, restoration of two existing aeration tanks, four
sludge lagoons and existing pump stations
Project Manager 1996 – 1998
Misfer Bin Kademes Construction, Saudi Arabia
Client: Ministry of Defense and Aviation
Project: Replacement of wastewater and drinking water network of King Faisal Air Academy, restoration of
asphalt for roadways and addition of wastewater pump station and storm sewer system with storage bond
for storm water. Project included sewer pipeline, diameter, 200 mm to 600 mm, length, 10000m; drinking
water pipeline, diameter, 50 mm to 200 mm, length, 12000 m; pump station with concrete and
electromechanical work; storm water pipeline, diameter, 300 mm to 600 mm, length, 6000m; storm water
storage bond, 150000 m3
Site Engineer 1993 – 1996
Misfer Bin Kademes, Construction, Saudi Arabia
Client: Ministry of Municipalities
Project: Construction of main pipelines for sewer system to Al Aziza, diameter, 500 mm to 900 mm, length,
15000m and two pump stations as well as asphalt restoration
Project Manager 1990 – 1993
Misfer Bin Kademes Construction, Saudi Arabia
Client: Ministry of Defense and Aviation
Project: Construction of firing range including earth works, artificial targets, asphalt work for entrance road
of two km and small storage building
4. Nabil Nassar 519-208-0625
Page 4 of 5
EDUCATION
PMI (Project Management institute /PMP ) . 2015
Project Management professional certifications courses / Parsons university .
CMAA (THE Construction Management Association of America ) 2015
Construction Management certifications Courses /Parsons university
Professional Engineeing Ontario 2007
(Technical &Law and Ethics Exams )
Project Management Courses 2007
Fanshawe College, London, Ontario
Certificate of Qualifications, Construction Craft Worker 2007
Ministry of Colleges, Training and Universities, Ontario
Bachelor’s Degree in Civil Engineering 1986
Mansoura University, Mansoura, Egypt
MEMBERSHIPS
Egyptian Engineering Council Member of Egyptian of Engineers Syndicate.
Member of Arab Canadian Engineers Association
Professional Engineers Ontario (EIT)