SlideShare una empresa de Scribd logo
1 de 40
National Aeronautics and Space Administration




NASA Earned Value Management (EVM) Capability Project
PM Challenge

Jerald Kerby



February 9, 2011




www.nasa.gov
                                                        1
Content

•   EVM Capability Objectives
•   Approach
•   Project Life Cycle
•   Current State/Gaps within Agency
•   Current EVM Capability Project Status
•   Lessons Learned/Issues to date
    – Actual Costs
    – Planning
•   Possible Future Issue Papers
•   Gaps Update
•   Path Forward
•   Backups
    – ANSI/EIA-748 (32 guidelines)
    – Draft NASA EVM Processes



                                            2
NASA EVM Capability Objectives

Overall Objective is to develop an Agency EVM capability that complies with the
guidelines in ANSI/EIA-748 and test through two pilots, refine and finalize EVM process
based on test results.

• Provide integrated set of processes, tools, guidance, training and
  technical support (people) to develop and demonstrate an
  Agency EVM capability.
• Apply lessons learned from previous pilot activities
• Clarify roles at program, project and Center level
• Devise a strategy for EVM software tool licensing and
  maintenance
• Provide for the planning, managing, controlling and integration of
  “in-house” work at a project’s primary and support Centers
• Integrate “in-house” with contractor data for comprehensive
  project performance assessment
• Goal is to apply ANSI/EIA 748 guidelines to enhance EVM
  capability.
     – Document anomalies if needed

                                                                                          3
EVM Capability Approach

•   Manage as a project with formulation, implementation, and
    operations/maintenance phases
     –   Approved by NASA Project Management Counclil (PMC) in Dec. 2009
•   Maximize use of existing COTS software
•   Partner with ESMD, SMD, CFO, CIO, OP, JSC, MSFC, GSFC
•   Pilot capability on one Constallation (CxP) project and one SMD project
•   Establish a steering committee with members from all Mission Directorates
    and Centers
•   Commission a peer review board to include EVM practitioners, business
    managers, project managers in project oversight.
•   Document agreements (via MOU/Project Plan) between Centers, mission
    directorates and support offices to define roles and responsibilities.
•   Present status twice annually to NASA PMC via Baseline Performance
    Review (BPR).
•   Once capability is developed and tested via pilot activities, system
    operations and maintenance, including licenses and technical support, will
    be funded by projects and by the institutions as they implement EVM

                                                                                 4
Steering Committee


                    Steering Committee                        Email                Telephone
OCE      Mike Ryschkewitsch                         mike.ryschkewitsch@nasa.gov    202.358.1823
OCFO     Beth Robinson (Chair)                     elizabeth.m.robinson@nasa.gov   202.358.0978
SMD      Mike Luther                                      mluther@nasa.gov         202.358.0260
         Roy Maizel (alternate for SMD)                 roy.a.maizel@nasa.gov      202.358.2630
ESMD
OCIO     Gary Cox                                        gary.cox-1@nasa.gov       202-358-0413
         Michael Medsker (alternate for OCIO)       michael.medsker@nasa.gov       202-358-0637
OP       Jim Balinskas                              james.a.balinskas@nasa.gov     202.358.0445
PA&E     Tom Coonce                                   tom.coonce-1@nasa.gov        202.358.4905
MSFC     Pam Cucarola                                pamela.cucarola@nasa.gov      256.544.0092
JSC      Cynthia Neal                                  cynthia.s.neal@nasa.gov     281.483.2202
GSFC     George Barth                                 george.barth-1@nasa.gov      301.286.5894
GRC      James Free                                    james.m.free@nasa.gov       216.433.3339
JPL      Dale Johnson                                dale.m.johnson@nasa.gov       818.354.5453
ARC      Carol Carroll                                carol.w.carroll@nasa.gov     650.604.0267
SSC      Jim Bevis                                     james.t.bevis@nasa.gov      228.688.3374
         Keith Brock (alternate for SSC)               keith.d.brock@nasa.gov      228.688.1311
DRFC
LaRC     Dr. David Gilman                            david.a.gilman@nasa.gov       757.864.4428
KSC      Janet Petro                                  janet.e.petro@nasa.gov       321.867.2355
Others




                                                                                                  5
Peer Review Team


                        Peer Review Team                      Email                Telephone
OCE      Sandra Smalley                                  ssmalley@nasa.gov         202.358.4731
OCFO     Kevin Buford                                  Kevin.Buford@nasa.gov       202.358.0405
SMD      Chuck Miller                                  chuck.miller@nasa.gov       202.358.0715
         Claude Freaner (alternate for SMD)           claude.freaner@nasa.gov      202.358.2522
ESMD
OCIO     Gerald Smith                                  gerald.smith@nasa.gov       202-358-1372
         Kai Moericke (alternate for OCIO)             kai.moericke@nasa.gov       202-358-4733
OP       Carl Weber                                    carl.c.weber@nasa.gov       202.358.1784
PA&E     John Fitch                                    john.fitch-1@nasa.gov       202.358.1228
MSFC     Stacy Counts                                 stacy.m.counts@nasa.gov      256.544.6004
JSC      Doug Sander                                 douglas.r.sander@nasa.gov     281.244.7391
JSC      Justin Mathurin                             justin.e.mathurin@nasa.gov    281.483.6333
GSFC     William Sluder                              william.h.sluder@nasa.gov     301.286.8976
GRC      Bob Sefcik                                   robert.j.sefcik@nasa.gov     216.433.8445
         Vince Bilardo (alternate for GRC)           vincent.j.bilardo@nasa.gov    216.433.3931
JPL      Kevin Rice                                     kevin.l.rice@nasa.gov      818.354.3622
ARC
SSC      Robert Ross                                   robert.b.ross@nasa.gov      228.688.2320
         Deborah Norton (alternate for SSC)          deborah.s.norton@nasa.gov     228.688.1168
DRFC
LaRC     Dan Tenney (Chair)                           daniel.j.tenney@nasa.gov     757.864.6095
LaRC     Dr. Barry Lazos                               barry.s.lazos@nasa.gov      757.864.5731
KSC      Franci Brice                                enid.frances.brice@nasa.gov   321.867.2381
KSC      Richard Dobbs                                richard.a.dobbs@nasa.gov     321.867.7402
KSC      Susan Waterman                              susan.j.waterman@nasa.gov     321.867.6688
Others   Richie Law                                    richard.c.law@nasa.gov      757-864-2184
Others   Roy Savage                                    roy.e.savage@nasa.gov       757-864-4886




                                                                                                  6
EVM Capability Life Cycle




Formulation                           Implementation               Operations & Maintenance
•   Planning                          • CxP pilot (EVA)            •   Consultation/ technical support
•   Requirements                      • SMD pilot (ICESat2)        •   Mentoring
•   Design & development              • Integration and test       •   Data archival
•   CxP/NEDI/Others Lessons           • Initial operations         •   IBR support
    Learned                           • Capability modifications   •   Training
•   Ops Concept/Capability              and enhancements
    Storyboard                        • Handbook and procedure
•   Capability Description (Gap         updates
    Analysis)                         • Agency-wide
•   Procedure development               communications
•   Training Requirements
•   MOU
•   Steering Committee
•   Business Rules/PPBE
    Integration




                                                                                                         7
Current State within NASA

NASA utilizes EVM data on contracts but lacks the
  capability to: (1) readily apply EVM on in-house
  development effort; and (2) integrate in-house and
  contracted EVM data for total project performance
  assessment.

   – CxP is in the process of building EVM capability but consistent
     Agency processes do not exist
   – Centers are also in process of building capability but none are
     ANSI compliant except JPL
   – Consistent roles and responsibilities between programs, projects
     and Centers do not exist to streamline EVM
   – NASA lacks an approach to coordinate necessary business
     system, policy, and process changes


                                                                    8
Current State - ANSI EIA-748 Compliance status


• All ANSI/EIA-748 Guidelines Can Be Met - Some
  Require Workarounds or Changes to NASA
  policies/procedures
   – 21 of 32 guidelines can be met with no changes required to
     current NASA policies/procedures
   – 11 guidelines currently not met due to gaps with the Agency
     business systems and processes
   – Labor intensive workarounds identified for all but 3 of the
     guidelines not currently met
Fixing the gaps require…

•   OCE, CFO and CIO solve gaps associated with Agency
    business systems
•   In parallel, MDs and Centers establish consistent processes
    and procedures
•   Charter a steering committee for oversight and strategic Agency
    decision making (Members: All Mission Directorates and
    Centers given the opportunity for membership)
    –   Decisional Direction – Approve a change or waive the requirement
•   Run two pilots (SMD/ESMD) proofing out capability for
    integrated in-house and contractor EVM that identifies business
    system solutions and creates efficiencies through streamlined
    processes and training
    – Provide template for all projects to follow
    – Validate needed business system changes
    – Develop workarounds for interim solution
    – Identify optimal solution (what’s good enough?)
                                                                           10
Current EVM Capability Project Status

•   Completed Formulation Activities
     – Drafted EVM Capability processes, system description, and project plan
     – Peer Review conducted the week of April 12th, 2010
        • Responded with Action plan to closeout Request for Actions
        • No major issues
        • Any disagreements will come before the Steering Committee for Resolution

•   Entered implementation phase
     – 1st Pilot kicked-off at JSC week of April 5th, 2010 and initial gap analysis
       complete
     – EVA pilot cancelled in June 2010 because of changes/uncertainty within the
       CxP and the project office
         • Documented Results/ Lessons Learned/Issues Papers (end of July)
               – Two Issue Papers Submitted for Consideration
                     • Inconsistency between Plan and Performance
                     • Business Rules and Actual Cost
     – 2nd Pilot has started with review of data and setup support
         • Started in Sept. at GSFC
         • Pilot delayed in Nov. for re-planning until early Jan. 2011

                                                                                      11
Issue Paper: Business Rules and Actual Costs
Effects: NASA business rules and cost distribution methodologies impact NASA’s effective use of
    the Earned Value approach to project management. The following are three effects.

    1. Artificial Variances
    2. Distorts EVM data
    3. Significantly impairs predictive ability of EVM

Possible Solutions: The goal is for projects to obtain reliable and timely actual cost data from
   NASA’s accounting system for all elements of cost and provide meaningful cost and schedule
   data for management insight and control. There are several solutions, described below.

Alternatives/Recommendation:
    1. Maintain Current State

    2. Modify System/Processes: Continue the Contractor Performance and Cost Tracking
       (C-Initiative) or similar initiative with emphasis to resolve these issues.

    3. Implement Work-Around:
         Workaround Alternative 3.a.: Use cost/schedule integration commercial-off-the-shelf
         (COTS) tools to capture lower level costs using estimated actuals outside of SAP.
          Workaround Alternative 3.b: Use Total Calculated Cost from SAP.

    4. Interim Workarounds and Modify System/Processes: This is an integrated alternative that
    leverages Workaround alternatives 3.a. and 3.b. in the near term, while Alternative 2, Modifying
    system/Processes, is evaluated for implementation in the longer term.
                                                                                                   12
Issue Paper: Inconsistency Plan and Performance

Effects: NASA inconsistency between plan and performance impacts NASA’s effective use of the Earned Value approach to project
Management. The following are two effects.
       1. Artificial variances are created which dilute the value of EVM metrics in providing meaningful performance data for the
       responsible manager, monthly project reviews, and external senior management reviews of project performance.

       2. The predictive value of EVM performance metrics that enables developing creditable Estimates at Complete (EAC) for work remaining is compromised.

 Possible Solutions: The goal is to realize and record cost in the period the work is planned and performed. There are several
solutions described below.

Alternatives/Recommendations:

1. Maintain Current State

2. Modify System/Processes: Develop a consistent methodology for accumulating and distributing non-direct costs to cover support organizations’ indirect budgets. These
      costs would be allocated to projects that use these services utilizing indirect cost
      pools similar to industry practices today.

3. Implement Workarounds:
       Workaround Alternative 3.a Refine the planning/work authorization process that documents the agreement between the project and performing support organizations for
       the technical scope of work, along with the associated schedule and budget, to require time-phasing all elements of costs to be consistent with the planned timing of
       allocating these                 costs.

       Workaround Alternative 3.b: Develop a process using estimate actuals where indirect costs are incurred in the same manner and in the same time period in which they
       are planned in the EVM PMB.

       Workaround Alternative 3.c: Plan indirect costs in a separate work package (WP) within the control account. This would require a method to distinguish the costs so they
       can be associated with the correct WPs.

       Workaround Alternative 3.d: Plan indirect costs in a separate, higher-level control account at the project level that could be managed and reported separately.

       Workaround Alternative 3.e: Increase Center CM&O budgets to meet the needs of the support organizations’ indirects or ODCs.

4. Interim Workarounds and Modify System/Processes: This is an integrated alternative that leverages Workaround Alternatives 3.a. and 3.d. in the near term while
        Alternative 2, Modifying System/Processes, is evaluated for implementation. The approach would be to refine the planning/work authorization process that documents
        the scope, schedule, and budget (all elements of cost) between organizations (Workaround 3.a); in conjunction with requiring the establishment of a separate, higher-
        level control account at the project level for indirect costs to be planned in the same manner in which costs are expected to be recognized and services rendered
        (Workaround 3.d). In the far term, develop a consistent methodology for accumulating and distributing non-direct costs to cover support organizations’ indirect budgets
        (Alternative 2).
Recommendations/Approval on Issues
• Issue Paper #1 - Planning
     − Continue to access the impact of EVA pilot during ICESat-2 pilot
         − Test the two recommended alternatives
         − Document ICESat 2 results and either make a process/business
           change or address in training

• Issue Paper #2 - Business rules and actual costs
     − Maintain recommendations made by project team
         −Test workarounds during ICESat 2 pilot and document results
         – OCFO develops a detail plan for the Initiative C to help address
         the issues
              • Delivery date to coincide with end of pilot or before
                  • EVM Capability will support by providing EVM
                  requirements
              • Agency makes a decision on long-term solution based on pilot
              results and OCFO plan.

• Next Steps…
    • Resume the ICESat2 pilot and update Steering Committee early
       spring 2011.
                                                                               14
Possible Future Issue - Implement EVM early/Transition

Lesson Learned: Implement EVM as early as possible in Project Life
    – Setting up EVM in the planning phase is easier than trying to retrofit once the
       project is nearing maturity

•   Issue: EVM from Phase B to Phase C. Currently the Agency’s requirement is to
    report EVM 60 days after entering into phase C. The actuals have not caught up
    with the EVM data when the first month of EVM is required

•   Causes: The same project number is used for each phase of a project. Actuals
    are slow to catch up from one phase to another

•   Effect: The EVM data will be distorted until the actuals for the EV and cost for all
    phases except C are subtracted from the totals.

•   Possible Solutions:
     – Change the project code after each phase to distinguish costs/work for each
       phase
     – Make the 1st month’s reporting due 90 days after entering into phase C for
       actuals to catch up
     – Develop a recommended approach and document in EVM Capability
     – Develop training to illustrate the problem and solution

                                                                                           15
Phase B to C Transition Comparison
     Why the timing is relevant
                             EVM PROJECT PHASE COMPARISON


EARNED VALUE COMPONENTS                         Total with Phase B           PHASE C/D Only


          BUDGET                                         $    1,137,606.00          $   475,000.00

       EARNED VALUE                                      $    1,088,606.00          $   426,000.00

         ACTUALS                                        $       845,406.00          $   384,000.00




       COST VARIANCE                                    $       292,200.00          $    91,000.00


  COST PERFORMANCE INDEX                                              1.29                    1.11


     SCHEDULE VARIANCE                                  $      (49,000.00)         $    (49,000.00)


SCHEDULE PERFORMANCE INDEX                                            0.96                    0.90




                                                                                                      16
Gaps Impacting NASA’s Ability to be Compliant with
                   ANSI/EIA-748
                                    * All priorities within a group are of equal importance
Gap # Priority* Gap Description                                                                                   Guideline(s) Status
                                                                                                                   Impacted
  1        1                        *   All priorities within a group are of equal
                NASA business practice requires that obligations and costs occur at the same level of the           16, 17       Workaround/
                WBS in SAP, sometimes resulting in costs being posted where obligations are available and
                                                         importance                                                              Change
                not necessarily where the work is performed (off charging).                                                      Required
  2        1    Costing old money first (off charging)                                                                16         Workaround/
                                                                                                                                 Change
                                                                                                                                 Required
  3        1    Algorithm being used to distribute 533 cost (off charging)                                            16         Workaround/
                                                                                                                                 Change
                                                                                                                                 Required
  4        1    Inability to collect support contractor hours and elements of cost at the appropriate WBS             16         Workaround/
                element where the work is performed.                                                                             Change
                                                                                                                                 Required
  5        2    Leave (annual, sick, or comp) is charged to the project when taken not earned (off charging)          16         Change
                                                                                                                                 Required
  6        2    Projects sometimes need to break down the WBS below level 7 to obtain a manageable                  17, 22       Change
                piece of work                                                                                                    Required
                                                                                                                                 /Workaround
  7        3    The Project Manager will not be able to control the configuration of the WBS until he/she is           1         Change
                given approval authority of WBS elements being added to SAP.                                                     Required

  8        3    NASA does not have a Work Authorization system for work across the Agency.                             9         Change
                                                                                                                                 Required

  9        4    Indirect cost policies continue to change and are not handled like normal, full cost are in an     4, 19, 24     Workaround/
                EVM System.                                                                                                      Change
                                                                                                                                 Required
  10       4    Projects are not able to get timely and reliable grant, Internal Partner, and Reimbursable cost   6, 7, 16, 27   Workaround/
                data from the system.                                                                                            Change
                                                                                                                                 Required
  11       4    NASA does not have a Material Management System or policies across the Agency to                    3,9,21       Workaround/
                support the EVM guidelines for material.                                                                         Change
                                                                                                                                 Required
                                                                                                                                          17
  Issue papers addressed solutions for the circled gaps.
Path Forward

•   Continue ICESat2 Pilot and document lessons learned, update
    documentation as needed
•   Develop transition strategy for long-term implementation
•   Continue to provide Steering Committee with information to make decisions
    for Agency
•   Enter into O&M upon successful Operational Readiness Review (ORR)
•   Project Close (EVM Capability Team will not do the implementation)




                                                                            18
Backup



         19
Issue Paper: Business Rules and Actual Costs
Issue: NASA’s business rules and the accounting system’s recording of actual cost present challenges for generating meaningful
data for EVM performance measurement and analysis. Useful EVM performance measurement and analysis is dependent upon
comparing actual costs, value of accomplished work, and budget values. During the Extravehicular Activity (EVA) Pilot, there were
numerous examples of unreliable EVM performance measurement indicators and analysis based on data created by following NASA
business rules that influence the manner in which contractor budgets are developed and actual costs reported. Additionally, the
manner in which SAP records obligations and actual costs further destabilized the EVM performance measurement and analysis
process on the EVA Project.
Causes: During the EVA EVM pilot there were two causes that contributed to the misalignment of actual costs with budgeted work.
The first is the methods used to establish and allocate contractor costs. The second cause is the manner in which NASA records
obligations and actual costs in SAP.

     1. Contractor Costs The manners in which contract reporting requirements are established and costs recorded contribute to a
     misalignment of plans and actual costs.
              Establishment Finalized contracts do not consistently contain Data Requirements Documents (DRD) with detailed
              requirements for individual Work Year Equivalents (WYE), hours, tasks, cost, etc. to support project-level EVM
              reporting.
              Allocated Cost The algorithm that is sometimes used to distribute contractor costs does not necessarily reflect the
              manner in which work is being performed on the project. This algorithm is often used in cases where multiple
              organizations fund a task agreement. While there are several methods for distributing actual cost, the primary cost
              distribution business rule is to cost the oldest money first, irrespective of where the work was performed. Costing old
              money first means that actual costs are recorded against the fund with the earliest expiration date.

     2. Recording of Obligations and Actual Costs in SAP The methods used by NASA to record obligations and actual costs in
     SAP contribute to a misalignment of plans and actual costs.
             SAP business rules do not allow cost to exceed obligations for a WBS, and the SAP Cost category contains only
             those actual costs that do not exceed the obligation amount for that WBS element. This can cause significant
             understatement of a WBS element.
             SAP business rules require that obligations occur at the same level of the WBS where costs are collected. SAP
             currently allows actual costs to be collected at a maximum of seven levels. The EVA Project costs are often collected
             at the lowest WBS level which from a total contract perspective, some WBS codes may have excess obligations while
             others have obligations insufficient to accommodate the actual costs incurred. Hence, costs not getting recorded to the
             proper WBS element. This is further complicated by the laborious process required to move obligations to where they
             are required. When additional funds are obligated a spike in the cost for the month can occur.
                                                                                                                                        20
Issue Paper: Inconsistency Plan and Performance

Issue: In evaluating the EVA Project’s planning and performance data, there are instances where Center support organizations’
budget plans were not time phased consistent with how certain elements of cost were realized. The problem is primarily with
other support costs (e.g., material; equipment, ODCs) that are attributable to that organization’s support to project offices. The
result is artificial cost variances caused by budget planning methodology that isn’t synchronized with how performance and actual
costs are incurred.
Causes: The systemic cause can be isolated to the practice of Center support organizations including in their monthly, time phased
plan a factor that represents other support costs that are attributable to the support organization’s support.

     1. While their direct support (labor) is performed and actual costs recorded monthly consistent with the plan, these other costs
     are allocated direct on a non-recurring basis.

     2. Hence, the budget for these costs is spread over each month, while the actual costs are recorded in lump sums only a few
     months during the year.

     3. The pervasive view of the support organizations’ is these (indirect) costs will all equal at the end of the year so there is no
     emphasis on improving the monthly time phasing.

Effects: NASA inconsistency between plan and performance impacts NASA’s effective use of the Earned Value approach to project
Management. The following are two effects.

     1. Artificial variances are created which dilute the value of EVM metrics in providing meaningful performance data for the
     responsible manager, monthly project reviews, and external senior management reviews of project performance.

     2. The predictive value of EVM performance metrics that enables developing creditable Estimates at Complete (EAC) for work
     remaining is compromised.

 Possible Solutions: The goal is to realize and record cost in the period the work is planned and performed. There are several
solutions described below.




                                                                                                                                          21
ANSI EIA 748 Guidelines (Level 1 Requirements)

1.   Define the authorized work elements for the program. A work breakdown structure (WBS),
     tailored for effective internal management control, is commonly used in this process.
2.   Identify the program organizational structure including the major subcontractors responsible
     for accomplishing the authorized work, and define the organizational elements in which work
     will be planned and controlled.
3.   Provide for the integration of the company’s planning, scheduling, budgeting, work
     authorization and cost accumulation processes with each other, and as appropriate, the
     program work breakdown structure and the program organizational structure.
4.   Identify the company organization or function responsible for controlling overhead (indirect
     costs).
5.   Provide for integration of the program work breakdown structure and the program
     organizational structure in a manner that permits cost and schedule performance
     measurement by elements of either or both structures as needed.
6.   Schedule the authorized work in a manner which describes the sequence of work and
     identifies significant task interdependencies required to meet the requirements of the program.
7.   Identify physical products, milestones, technical performance goals, or other indicators that will
     be used to measure progress.




                                                                                                          22
ANSI EIA 748 Guidelines (Level 1 requirements)

8.    Establish and maintain a time-phased budget baseline, at the Cost Account level, against
      which program performance can be measured. Budget for far-term efforts may be held in
      higher level accounts until an appropriate time for allocation to the CA level. Initial budgets
      established for performance measurement will be based on either internal management goals
      or the external customer negotiated target cost, including estimate for authorized but
      undefinitized work. On Government contracts, if an over target baseline is used for
      performance measurement reporting purposes, prior notification must be provided to the
      customer.
9.    Establish budgets for authorized work with identification of significant cost elements (labor,
      material, etc.) as needed for internal management and for control of subcontractors.
10.   To the extent it is practical to identify the authorized work in discrete work packages,
      establish budgets for this work in terms of dollars, hours, or other measurable units. Where
      the entire control account is not subdivided into work packages, identify the far term effort in
      larger planning packages for budget and scheduling purposes.
11.   Provide that the sum of all work package budgets plus planning package budgets within a
      control account equals the control account budget.
12.   Identify and control level of effort activity by time-phased budgets established for this
      purpose. Only that effort which is immeasurable or for which measurement is impractical
      may be classified as level of effort.




                                                                                                         23
ANSI EIA 748 Guidelines (Level 1 requirements)

13.   Establish overhead budgets for each significant organizational component of the company for
      expenses which will become indirect costs. Reflect in the program budgets, at the
      appropriate level, the amounts in overhead pools that are planned to be allocated to the
      program as indirect costs.
14.   Identify management reserves and undistributed budget.
15.   Provide that the program target cost goal is reconciled with the sum of all internal program
      budgets and management reserves.
16.   Record direct costs in a manner consistent with the budgets in a formal system controlled by
      the general books of account.
17.   When a work breakdown structure is used, summarize direct costs from control accounts into
      the work breakdown structure without allocation of a single control account to two or more
      work breakdown structure elements.
18.   Summarize direct costs from the control accounts into the contractor’s organizational
      elements without allocation of a single control account to two or more organizational
      elements.
19.   Record all indirect costs which will be allocated to the contract.
20.   Identify unit costs, equivalent units costs, or lot costs when needed.




                                                                                                     24
ANSI EIA 748 Guidelines (Level 1 requirements)

21.   For EVMS, the material accounting system will provide for:
      1)   Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the
           budgets using recognized, acceptable, costing techniques.
      2)   Cost performance measurement at the point in time most suitable for the category of material involved,
           but no earlier than the time of progress payments or actual receipt of material.
      3)   Full accountability of all material purchased for the program including the residual inventory.
22.   At least on a monthly basis, generate the following information at the control account and other
      levels as necessary for management control using actual cost data from, or reconcilable with,
      the accounting system:
      1)   Comparison of the amount of planned budget and the amount of budget earned for work accomplished.
           This comparison provides the schedule variance.
      2)   Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for
           the same work. This comparison provides the cost variance.
23.   Identify, at least monthly, the significant differences between both planned and actual schedule
      performance and planned and actual cost performance, and provide the reasons for the
      variances in the detail needed by program management.
24.   Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by
      management for effective control, along with the reasons for any significant variances.




                                                                                                                    25
ANSI EIA 748 Guidelines (Level 1 requirements)

25.   Summarize the data elements and associated variances through the program organization
      and/or work breakdown structure to support management needs and any customer reporting
      specified in the contract.
26.   Implement managerial actions taken as the result of earned value information.
27.   Develop revised estimates of cost at completion based on performance to date, commitment
      values for material, and estimates of future conditions. Compare this information with the
      performance measurement baseline to identify variances at completion important to company
      management any applicable customer reporting requirements including statements of funding
      requirements.
28.   Incorporate authorized changes in a timely manner, recording the effects of such changes in
      budgets and schedules. In the directed effort prior to negotiation of a change, base such
      revisions on the amount estimated and budgeted to the program organizations.
29.   Reconcile current budgets to prior budgets in terms of changes to the authorized work and
      internal replanning in the detail needed by management for effective control.
30.   Control retroactive changes to records pertaining to work performed that would change
      previously reported amounts for actual costs, earned value, or budgets. Adjustments should
      be made only for correction of errors, routine accounting adjustments, effects of customer or
      management directed changes, or to improve the baseline integrity and accuracy of
      performance measurement data.
31.   Prevent revisions to the program budget except for authorized changes.
32.   Document changes to the performance measurement baseline.




                                                                                                      26
Storyboard – Pre KDP B
                                                                                          (latest revision August 2010)



  0.0 Pre KDP B

                                                     No                                                                  No
     MDAA / HQ




                          0.01
                      Acquisition                              0.03                                                                0.06
                   Strategy Planning                         Approve                                                          Program Plan &
                        Process                            Program FAD                                      0.05               PCA approval
                                           0.02                                                         Develop Draft                                      0.08
                                         Prepare                                                     Program Plan (PM)                                 Project FAD
                                       Program FAD                                                     & PCA (MDAA)                                     Approval
                                                                                                                                          Yes
Program Mgr /




                                                                                               Yes                                                                         Yes
Program Mgt




                                                                                0.04
                                                              Yes
    Office




                                                                             Acquisition
                                                                          Strategy Meeting
                                                                         (Work Distribution/
                                                                             Make/Buy)                                                     0.07
                                                                                                                                         Prepare
                                                                                                                                        Project FAD
                                                                                                                                                                                                      0.10
Project Office




                                                                                                                                                                                                 Approval for
 Manager /




                                                                                                                                                                                              Preliminary Project
   Project




                                                      No                                                                                                                                      Plan, WBS, Budget,             1.01
                                                                                                                                                      No                                                            Yes
                                                                                                                                                                                              Schedules, etc. for         Organization
                                                                                                                                                                             0.09                all phases as
                                                                                                                                                                        Preliminary                applicable
                                                                                                                                                                       Project Plan,
                                                                                                                                                                      WBS, Budget,
                                                                                                                                                                      Schedules, etc.
                                                                                                                                                                     for all phases as
Element Mgr /
 Subproject /




                                                                                                                                                                         applicable
   Team
  Institutional/
   Functional




                                                                                                                                                                                         No




                                                                                                                                                                                                                                  27
Storyboard – Organization

  1.0 Organization
     MDAA / HQ




                    1.01
                   KDP B
                                    No
Program Mgr /
Program Mgt
    Office




                                                                                                                                                    3.04
                                                                                                                                              Prepare & Issue
                                                                                                                                                Preliminary
                                                                                                                                                 Planning
                                                                                                                                             Guidance / WAD /
                                                                                                                                              Dollarized RAM
Project Office
 Manager /




                                   1.02
   Project




                           Finalize Project Plan
                            for Phase C (EVM
                                Approach)
                                                                                                                                                   2.01
                                                                                                                                             Extend and Refine
                                                       1.03
                                                                                                                                              Master Schedule
                                                     Approve
                                                                                                                                                  (Draft)
                                                   Project Plan
Element Mgr /
 Subproject /




                                                                             1.04
                                                                                              1.05                              1.07
   Team




                                                                  Yes     Extend &                            1.06
                                                                                         Prepare WBS                         Extend &
                                                                        Refine Project                      Extend &
                                                                                           Dictionary                         Refine
                                                                            WBS                              Refine        Responsibility
                                                                                                        Organizational      Assignment             8.01
                                                                                                          Breakdown       Matrix (RAM) &     Estimate Material
                                                                                                        Structure (OBS)   Identify Control   Needs and Cost
                                                                                                                             Accounts
     P-CAM
  Institutional/
   Functional




                                                                                                                                                                 28
Storyboard – Scheduling

   2.0 Scheduling

                                        Developing IMS                                                                                                        IMS Status & Update                                                  7-1.11
                                                                                                                                                                                                                             Input CAPs/update
                                                                                                                                                                                                                              IMS, WBS, RAM,
                                                                                                                                                                                                                              WAD, etc. Update
                                                                                                                                                                                             10.08                            budget logs (PBB,
     Project Manager / Project Office




                                                                                                                                                                                       Integrate Supplier                    AUW, Contingency/
                                                                                                                                                                                         Cost/ Schedule                           MR, UB)
                                                                                                                                                                                        Data into Cost &
                                                                                                                                                                                      Schedule Tools and
                                                                                                                                                                                                                                   7-2.08
                                                                                                                                                                                            Reports
                                                                                                                                                                                                                             Input CAPs/update
                                                                                                                                                                                                                              IMS, WBS, RAM,
                                                                                                                                                                                                                              WAD, etc. Update
                                               1.07                                                                                                                                                                           budget logs (PBB,
                                         Extend & Refine                                                                                                                                      8.21                           AUW, Contingency/
                                                                                  2.04
                                          Responsibility                                                                                                                               Received Material                          MR, UB)
                                                                               Integrate
                                           Assignment                           detailed                                                                                              Item / Claim BCWP
                                         Matrix (RAM) &                       schedules                                                           3.11
                                         Identify Control                                                                                     Establish the
                                            Accounts                                                                                             PMB



                                                                                                                                                                                                                                            2.13
                                                                                                                                                                       2.08                                                                 Input
                                                                 2.02                                              2.05                                            Generate a                                                            workaround
                                              2.01
                                                             Extend and                                        Health Check                                    form to gather IMS                                                          plans.         2.14
                                          Extend and
                                                                Refine            2.03                                                                          status updates or                                                                     Publish and       2.15
                                         Refine Master                                                                                                                                              2.10                2.11
                                                            Intermediate-     Extend and                       Verify vertical                                   electronic file to                                                         Health     Distribute   Export data
                                           Schedule                                                                                              2.07                                          Input P-CAM       Calculate a new
                                                                Level        Refine logic-                      traceability                                     collect P-CAM’s                                                          Check and       final     to cost tool
                                             (Draft)                                                                                          Baseline and                                    updates into the   critical path and
  Element Mgr




                                                              Schedule           linked            3.07                                                         schedule updates                                                           Analysis    schedules
  Subproject/




                                                                                                                                                Publish                                      detailed schedule    new forecast
                                                                             detailed CAP       Reconcile         Verify                                         and EVM status
                                                                                                                                                  IMS                                         and or cost tool         dates
                                                                              schedule or     schedule with     significant                                                                                                                Iterate
                                                                            source of CAP      budget data        project                                                                                                                as needed.
                                                                                                                                                   (top,
                                                                                schedule         until fully    milestones                    intermediate,
                                                                               (draft), and     integrated                                      and detail
                                                                             if applicable                      Determine           2.06          level)
                                                                              assign EV                         critical path    Review and
                                                                            measurement                                                                                                                                                                                6-1.02
                                                                                                                                  Approve                                                                                                               6-1.01
                                                                              techniques                        Schedule                                                                                                                                              Monthly
                                                                                                                                    IMS                                                                                                                Schedule
                                                                                                                  Risk                                                                                                                                              Performance
                                                                                                                                                                                                                                                       Analysis
     P-CAM




                                                                                                               Assessment                                              2.09                                                                                           Analysis
                                                                                                                                                                  Provide status                                       2.12
                                                                                                                                                                including AS/AF,                                 Review results of
                                                                                                                                                                forecasted dates,                                     status.
                                                                                                                                                                Milestones, & EV
                                                                                                                                                                                                                     Develop
                                                                                3.05
                                                                                                                                                                                                                 workaround plans
                                                                              P-CAMs
                                                                                                                                                                                                                   as needed to
                                                                            Develop CAPs
                                                                                                                                                                                                                      correct
  Institutional/




                                                                            (Budget only)
   Functional




                                                                                                                                                                                                  9.14              forecasted
                                                                                                                                                                                               Integrate          schedule slips
                                                                                                                                                                                            Contractor Cost/
                                                                                                                                                                                           Schedule Data into
                                                                                                                                                                                            Cost & Schedule
                                                                                                                                                                                           Tools and Reports


Agency EVM Capability Project / Jerald Kerby, PM / (256) 544-3243                                                                                                                                                                                                          08/02/2010




                                                                                                                                                                                                                                                                                   29
Storyboard – Work/Budget Authorization

  3.0 Work/Budget Authorization
      MDAA / HQ




                                                                                                                                                                                                                       3.15
                                                                                                                                                                                                                      KDP C
                                                                                                                            2.05
                           3.01
                                                                                                                        Health Check
                       Update/Issue
                         WAD or
                                                                                                                        Verify vertical
                      Equivalent (e.g.,
Program Mgr /




                                                                                                                         traceability
Program Mgt




                           PAD)
                                                                                                                       Verify significant
    Office




                                                                                         1.07                         project milestones
                                                                                    Extend & Refine
                                                                                     Responsibility                      Determine                                                                       3.13
                                                                                  Assignment Matrix                      critical path                                                               Perform IBR
                                                                                   (RAM) & Identify
                                                                                                                                                                                                 (Verify SOW, WBS
                                                                                  Control Accounts                     Schedule Risk                                                              Dictionary, PMB,
                                                                                                                        Assessment                                                                 IMS, Risk, etc.)
  Project Manager /
    Project Office




                                                                                                                                                                                 3.11
                                                                                                                                                          3.10                 Determine
                                                                                                                                                                     Yes
                                                                                                                                                        Approved               Reserves
                                                                                                                                                                                Rqmnts

                                                                                         3.03
                                                 3.02
                                                                                   Prepare & Issue
                                           Establish Project
                                                                                 Preliminary Planning
                                             Budget Log
                                                                                  Guidance / WAD /
                                                                                   Dollarized RAM
                                                                                                                                                                                  3.12
Element Mgr /




                                                                                                                             3.07
 Subproject /




                                                                                                                                                                              Establish the
                                                                                                                          Reconcile                                              PMB
   Team




                                                                                                                        schedule with
                                                                                                                         budget data
                                                                                                                           until fully
                                    2.03                                                                     3.06         integrated
                           Extend and Refine                                            3.04            Extend and                                         3.09
                                                                     5.03                                                                     3.08      Finalize &
                                logic-linked                                     Develop Tech, Cost,       Refine
                                                                 Time-phase                                                                 Negotiate   Issue CA
                               detailed CAP                                       & Schedule Risk          Charge                                                               2.07
                                                               indirect budget                                                               CAPs         WAD
                           schedule or source                                       Assessment           Numbers                                                             Baseline and
                             of CAP schedule                                                            (If needed)                                                            Publish
      P-CAM




                                 (draft), and                                                                                                                                                          3.14
                                                                                                                                                                                 IMS
                           if applicable assign                                                                                                                                                     Incorporate
                             EV measurement                                                                                                                                                         Changes if
                                                                                                                                                                           (top, intermediate,
                                techniques                                                                                                                                                           Required
                                                                                                                                                                             and detail level)
                                                                                        3.05
                                                                                  P-CAMs Develop
                                                                                       CAPs
  Institutional/




                                                                                    (Budget only)
   Functional




                                                                                                                              2.04
                                                                                                                           Integrate
                                                                                                                            detailed
                                                                                                                          schedules




Agency EVM Capability Project / Jerald Kerby, PM / (256) 544-3243                                                                                                                                                         08/02/2010




                                                                                                                                                                                                                              30
Storyboard – Accounting

  4.0 Accounting
Program Mgr /
Program Mgt
    Office




                                                                                                                                 Yes
     Project Manager / Project Office




                                                                                                                                                                                             6-1.02
                                                                                                                                                       4.07                  4.08
                                                                                                                                                                                            Monthly
                                                                                                                                                Incorporate verified   Verify Load into
                                                                                                                                                                                          Performance
                                                                                                                                                ACWP into Cost tool      Cost Tool
                                                                                      4.03                                                                                                  Analysis
                                                                                                           4.04
                                                                                Download data from
                                                                                                     Verify/Distribute
                                                                                  Core Financial
                                                                                                     ACWP data to P-
                                                                                   System into
                                                                                                          CAMs
                                                                                  spreadsheets

                                                                                                                                                                            4.09
                                                                                                                                                                        Reconcile to
                                                                                                                                                                       general book of
                                                                                                                                                                          accounts
Element Mgr /
 Subproject /




                                                                                                                                  4.05
   Team




                                                                                                                         Verify labor charges
                                                                                                                         and other charges as
                                                                                                                              applicable


                                               8.13                                                                                                    4.06
                                        Enter acceptance                                                                                         Correct errors as
                                        into SAP (Actuals                                                                                           applicable
                                            Recorded)
     P-CAM
  Institutional/
   Functional




                                             4.01
                                         Record Cost in           4.02
                                         Core Financial     Month end closing                                                          No
                                            System




Agency EVM Capability Project / Jerald Kerby, PM / (256) 544-3243                                                                                                                                       08/02/2010




                                                                                                                                                                                                            31
Storyboard – Indirect Management

  5.0 Indirect Management
     MDAA / HQ
Program Mgr /
Program Mgt




                                                        3.05
    Office




                                                  P-CAMs Develop
                                                       CAPs
                                                    (Budget only)
Project Office
 Manager /
   Project
Element Mgr /
 Subproject /




                                                                              5.05                  5.08
                                                                                                                         6-2.02
   Team




                          5.02                           5.03             Analyze and       Establish EAC with
                                                                                                                   Develop ETC Plan
                   Establish budgets                 Time-phase        evaluate variances      ETC rates for
                                                                                                                    for the Control
                    for indirect cost              indirect budget     caused by indirect   indirect cost at CA/
                                                                                                                   Account and BoE
                                                                             costs                WP level
     P-CAM
  Institutional/
   Functional




                         5.01                                                 5.06
                                                         5.04                                     5.07
                    IM Center CFO                                         Analyze and
                                                  Collect and record                         Develop EAC &
                    provide indirect                                   evaluate base and
                                                     indirect cost                             ETC rates
                       Guidance                                          rate variances




                                                                                                                                      32
Storyboard – Managerial Analysis

  6-1.0 Managerial Analysis
     MDAA / HQ




                                 9.14                                  10.08
                              Integrate                           Integrate Intra-
                                                                                                                                                                6-1.12
                             Contractor                            Agency (other
                                                                                                                                                               Review
                           Cost/Schedule                          Centers) Cost/
                                                                                                                                                          Performance Data
                          Data into Cost &                      Schedule Data into
                                                                                                                                                          Assess Impact on
Program Mgr /
Program Mgt




                          Schedule Tools                         Cost & Schedule
                                                                                                                                                           Reserves (UFE)
                            and Reports                         Tools and Reports
    Office




                       2.14
                   Publish and
Project Office




                    Distribute
                                                                                                                                                               6-1.11
 Manager /




                       final                                                                                           6-1.05                             Prepare and Issue
   Project




                    schedules                                                                     6-1.04                                   6-1.08
                                                                                                                 Identify accounts                            Monthly              6-1.10
                                                                                 6-1.03        Analyze Data                           Review Metrics,
                                                                                                                    that exceed                             Performance          Review and
                                                                             Run preliminary    Metrics and                          Variance Analysis,
                                                                                                                    established                               Reports         Approve Changes
                                                                               CPR and           Trends                              Corrective Actions
                                                                                                                     thresholds                                                and incorporate
                                                                                Variance
                                                                             Analysis Report                                                                                   revised ETC, if
                                                                                 forms                                                                                           necessary
Element Mgr /
 Subproject /




                                                                                                                                            No
                                                                                                   6-2.01
   Team




                     6-1.01                      6-1.02                                             Issue
                    Schedule                    Monthly                                        Comprehensive
                    Analysis                  Performance                                       project EAC                                                                       6-1.09
                                                Analysis                                          planning            6-1.06              6-1.07                                Review and
                                                                                                 guidelines         Analysis and       Routine ETC /
                                                                                                                                                                      Yes      Submit revised
                                                                                                                 response to VARs      EAC Revision                           WAD, If Required
                                                                                                                                        Required?
     P-CAM




                                                                                                      Optional




                                                                                                                                                                                   7-2.01
                                                                                                                                                                               Identify Internal
  Institutional/




                                                   4.08                                                                                                                           Change
   Functional




                                             Verify Load into
                                               Cost tool




                                                                                                                                                                                                   33
Storyboard – Comprehensive EAC

  6-2.0 Comprehensive Estimate-at-Completion (EAC)
     MDAA / HQ
Program Mgr /
Program Mgt
    Office




                      6-1.04                                                                                                                                               6-2.12
                   Analyze Data                                                                                                                                         Performance
                    Metrics and                                                                                                                                           Reports
                     Trends
                                                                                              6-2.05
                                                                                                                               Yes
Project Office




                                                                                           Approve EAC?
 Manager /
   Project




                                                                                                                                        6-2.09             6-2.10            6-2.11
                                                                                                                                     Update Project   Contingency/MR   Update Reported
                                      6-2.01                                                                                           Lien List         Analysis             EAC
                                       Issue                                                                                                                            (If Necessary)
                                                       6-2.03                6-2.04                                Yes
                                  Comprehensive
                                                  Analyze EACs and       Review Project
                                   project EAC
                                                        BoEs              ETC / EAC
                                     planning
                                                                                                 No
Element Mgr /




                                    guidelines
 Subproject /

   Team




                                                                                               6-2.06
                                                        6-2.02                                Document
                                                  Develop ETC Plan                        Disagreement (re-
                                                   for the Control                         negotiate/iterate
                                                  Account and BoE                            as needed)
     P-CAM




                                                                                                                                         6-2.08
                                                                                                                  6-2.07              Revised EAC:
                                                                                                               Update EAC on         Approved WAD
                                                                                                                   WAD


                                                          5.08
                                                  Establish EAC with
                                                     ETC rates for
  Institutional/
   Functional




                                                  indirect cost at CA/
                                                        WP level




                                                                                                                                                                                      34
Storyboard – Change Mgmt (External)

  7-1.0 Change Management (External Changes)
     MDAA / HQ




                                                                                                            7-1.06
                                                            No
                        7-1.01                                                                            Approved?
                   Identify External
Program Mgr /
Program Mgt




                      Changes
    Office




                                                                                                                                 Yes




                                                                                7-1.04                       7-1.05
                                                                           Revise Program/              Revise Program/
Project Office




                                                                                             Yes          Project Plan
                                                                               Project
 Manager /




                                                                                Plan?
   Project




                                                                                                                                7-1.07
                                                                                                                          Publish Guidance                                                   7-1.11               7-1.12
                                                                                                   No                      for Authorized                                              Input CAPs/update     Issue approved
                                                                                                                                                                     7-1.10                                   WADs/CAPS/
                                                                                                                               Change                                                   IMS, WBS, RAM,
                                                                                                                                                                    Review &                                IMS/WBS/Publish
                                                                                                                                                                                 Yes    WAD, etc. Update
Element Mgr /




                                                             7-1.03                                                                                               Approve CAPs
 Subproject /




                                           7-1.02                                                                                                                                       budget logs (PBB,     Project Budget
                                          Prepare      Assess change,                                                                                               & EACs?                                        Logs
                                                                                                                                                                                       AUW, Contingency/
   Team




                                          Change           develop                                                                                                                          MR, UB)
                                         Request       technical, cost &
                                       Documentation       schedule
                                                            impacts                                                                               7-1.09
                                                                                                                                               Review CAPs
                                                                                                                                                 & EACs

                                                                                                                                7-1.08
                                                                                                                          Develop new and/                                                                       7-1.13
     P-CAM




                                                                                                                          or revise existing                                                                Receive approved
                                                                                                                           Control Account                                                                   WAD, CAPs &
                                                                                                                           Plans (CAPs) &                                                                         EAC
                                                                                                                                 EAC
  Institutional/
   Functional




                                                                                                                                                             No




                                                                                                                                                                                                                               35
Kerby.jerald
Kerby.jerald
Kerby.jerald
Kerby.jerald
Kerby.jerald

Más contenido relacionado

Destacado

Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngbloodNASAPMC
 
Krasa.lee
Krasa.leeKrasa.lee
Krasa.leeNASAPMC
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012NASAPMC
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbieNASAPMC
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robertNASAPMC
 
Carol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalCarol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalNASAPMC
 
Garrett.skrobot
Garrett.skrobotGarrett.skrobot
Garrett.skrobotNASAPMC
 
Emma.antunes
Emma.antunesEmma.antunes
Emma.antunesNASAPMC
 
Michael.bay
Michael.bayMichael.bay
Michael.bayNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012NASAPMC
 
Doug.sander
Doug.sanderDoug.sander
Doug.sanderNASAPMC
 
Darryl.mitchell
Darryl.mitchellDarryl.mitchell
Darryl.mitchellNASAPMC
 
Maura.fujieh
Maura.fujiehMaura.fujieh
Maura.fujiehNASAPMC
 
Baldwin.kristen
Baldwin.kristenBaldwin.kristen
Baldwin.kristenNASAPMC
 
Hoffman.ed
Hoffman.edHoffman.ed
Hoffman.edNASAPMC
 
Estlin aegissoyajpl 2012
Estlin aegissoyajpl 2012Estlin aegissoyajpl 2012
Estlin aegissoyajpl 2012NASAPMC
 
David.fuller
David.fullerDavid.fuller
David.fullerNASAPMC
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinhNASAPMC
 

Destacado (20)

Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngblood
 
Krasa.lee
Krasa.leeKrasa.lee
Krasa.lee
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
 
Augustin.debbie
Augustin.debbieAugustin.debbie
Augustin.debbie
 
Kelso.robert
Kelso.robertKelso.robert
Kelso.robert
 
Carol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinalCarol scottcowartmcphillipspm challengefinal
Carol scottcowartmcphillipspm challengefinal
 
Symons
SymonsSymons
Symons
 
Garrett.skrobot
Garrett.skrobotGarrett.skrobot
Garrett.skrobot
 
Emma.antunes
Emma.antunesEmma.antunes
Emma.antunes
 
Michael.bay
Michael.bayMichael.bay
Michael.bay
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012
 
Doug.sander
Doug.sanderDoug.sander
Doug.sander
 
Darryl.mitchell
Darryl.mitchellDarryl.mitchell
Darryl.mitchell
 
Maura.fujieh
Maura.fujiehMaura.fujieh
Maura.fujieh
 
Baldwin.kristen
Baldwin.kristenBaldwin.kristen
Baldwin.kristen
 
Hoffman.ed
Hoffman.edHoffman.ed
Hoffman.ed
 
Estlin aegissoyajpl 2012
Estlin aegissoyajpl 2012Estlin aegissoyajpl 2012
Estlin aegissoyajpl 2012
 
David.fuller
David.fullerDavid.fuller
David.fuller
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinh
 

Más de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

Más de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Último

My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 

Último (20)

My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 

Kerby.jerald

  • 1. National Aeronautics and Space Administration NASA Earned Value Management (EVM) Capability Project PM Challenge Jerald Kerby February 9, 2011 www.nasa.gov 1
  • 2. Content • EVM Capability Objectives • Approach • Project Life Cycle • Current State/Gaps within Agency • Current EVM Capability Project Status • Lessons Learned/Issues to date – Actual Costs – Planning • Possible Future Issue Papers • Gaps Update • Path Forward • Backups – ANSI/EIA-748 (32 guidelines) – Draft NASA EVM Processes 2
  • 3. NASA EVM Capability Objectives Overall Objective is to develop an Agency EVM capability that complies with the guidelines in ANSI/EIA-748 and test through two pilots, refine and finalize EVM process based on test results. • Provide integrated set of processes, tools, guidance, training and technical support (people) to develop and demonstrate an Agency EVM capability. • Apply lessons learned from previous pilot activities • Clarify roles at program, project and Center level • Devise a strategy for EVM software tool licensing and maintenance • Provide for the planning, managing, controlling and integration of “in-house” work at a project’s primary and support Centers • Integrate “in-house” with contractor data for comprehensive project performance assessment • Goal is to apply ANSI/EIA 748 guidelines to enhance EVM capability. – Document anomalies if needed 3
  • 4. EVM Capability Approach • Manage as a project with formulation, implementation, and operations/maintenance phases – Approved by NASA Project Management Counclil (PMC) in Dec. 2009 • Maximize use of existing COTS software • Partner with ESMD, SMD, CFO, CIO, OP, JSC, MSFC, GSFC • Pilot capability on one Constallation (CxP) project and one SMD project • Establish a steering committee with members from all Mission Directorates and Centers • Commission a peer review board to include EVM practitioners, business managers, project managers in project oversight. • Document agreements (via MOU/Project Plan) between Centers, mission directorates and support offices to define roles and responsibilities. • Present status twice annually to NASA PMC via Baseline Performance Review (BPR). • Once capability is developed and tested via pilot activities, system operations and maintenance, including licenses and technical support, will be funded by projects and by the institutions as they implement EVM 4
  • 5. Steering Committee Steering Committee Email Telephone OCE Mike Ryschkewitsch mike.ryschkewitsch@nasa.gov 202.358.1823 OCFO Beth Robinson (Chair) elizabeth.m.robinson@nasa.gov 202.358.0978 SMD Mike Luther mluther@nasa.gov 202.358.0260 Roy Maizel (alternate for SMD) roy.a.maizel@nasa.gov 202.358.2630 ESMD OCIO Gary Cox gary.cox-1@nasa.gov 202-358-0413 Michael Medsker (alternate for OCIO) michael.medsker@nasa.gov 202-358-0637 OP Jim Balinskas james.a.balinskas@nasa.gov 202.358.0445 PA&E Tom Coonce tom.coonce-1@nasa.gov 202.358.4905 MSFC Pam Cucarola pamela.cucarola@nasa.gov 256.544.0092 JSC Cynthia Neal cynthia.s.neal@nasa.gov 281.483.2202 GSFC George Barth george.barth-1@nasa.gov 301.286.5894 GRC James Free james.m.free@nasa.gov 216.433.3339 JPL Dale Johnson dale.m.johnson@nasa.gov 818.354.5453 ARC Carol Carroll carol.w.carroll@nasa.gov 650.604.0267 SSC Jim Bevis james.t.bevis@nasa.gov 228.688.3374 Keith Brock (alternate for SSC) keith.d.brock@nasa.gov 228.688.1311 DRFC LaRC Dr. David Gilman david.a.gilman@nasa.gov 757.864.4428 KSC Janet Petro janet.e.petro@nasa.gov 321.867.2355 Others 5
  • 6. Peer Review Team Peer Review Team Email Telephone OCE Sandra Smalley ssmalley@nasa.gov 202.358.4731 OCFO Kevin Buford Kevin.Buford@nasa.gov 202.358.0405 SMD Chuck Miller chuck.miller@nasa.gov 202.358.0715 Claude Freaner (alternate for SMD) claude.freaner@nasa.gov 202.358.2522 ESMD OCIO Gerald Smith gerald.smith@nasa.gov 202-358-1372 Kai Moericke (alternate for OCIO) kai.moericke@nasa.gov 202-358-4733 OP Carl Weber carl.c.weber@nasa.gov 202.358.1784 PA&E John Fitch john.fitch-1@nasa.gov 202.358.1228 MSFC Stacy Counts stacy.m.counts@nasa.gov 256.544.6004 JSC Doug Sander douglas.r.sander@nasa.gov 281.244.7391 JSC Justin Mathurin justin.e.mathurin@nasa.gov 281.483.6333 GSFC William Sluder william.h.sluder@nasa.gov 301.286.8976 GRC Bob Sefcik robert.j.sefcik@nasa.gov 216.433.8445 Vince Bilardo (alternate for GRC) vincent.j.bilardo@nasa.gov 216.433.3931 JPL Kevin Rice kevin.l.rice@nasa.gov 818.354.3622 ARC SSC Robert Ross robert.b.ross@nasa.gov 228.688.2320 Deborah Norton (alternate for SSC) deborah.s.norton@nasa.gov 228.688.1168 DRFC LaRC Dan Tenney (Chair) daniel.j.tenney@nasa.gov 757.864.6095 LaRC Dr. Barry Lazos barry.s.lazos@nasa.gov 757.864.5731 KSC Franci Brice enid.frances.brice@nasa.gov 321.867.2381 KSC Richard Dobbs richard.a.dobbs@nasa.gov 321.867.7402 KSC Susan Waterman susan.j.waterman@nasa.gov 321.867.6688 Others Richie Law richard.c.law@nasa.gov 757-864-2184 Others Roy Savage roy.e.savage@nasa.gov 757-864-4886 6
  • 7. EVM Capability Life Cycle Formulation Implementation Operations & Maintenance • Planning • CxP pilot (EVA) • Consultation/ technical support • Requirements • SMD pilot (ICESat2) • Mentoring • Design & development • Integration and test • Data archival • CxP/NEDI/Others Lessons • Initial operations • IBR support Learned • Capability modifications • Training • Ops Concept/Capability and enhancements Storyboard • Handbook and procedure • Capability Description (Gap updates Analysis) • Agency-wide • Procedure development communications • Training Requirements • MOU • Steering Committee • Business Rules/PPBE Integration 7
  • 8. Current State within NASA NASA utilizes EVM data on contracts but lacks the capability to: (1) readily apply EVM on in-house development effort; and (2) integrate in-house and contracted EVM data for total project performance assessment. – CxP is in the process of building EVM capability but consistent Agency processes do not exist – Centers are also in process of building capability but none are ANSI compliant except JPL – Consistent roles and responsibilities between programs, projects and Centers do not exist to streamline EVM – NASA lacks an approach to coordinate necessary business system, policy, and process changes 8
  • 9. Current State - ANSI EIA-748 Compliance status • All ANSI/EIA-748 Guidelines Can Be Met - Some Require Workarounds or Changes to NASA policies/procedures – 21 of 32 guidelines can be met with no changes required to current NASA policies/procedures – 11 guidelines currently not met due to gaps with the Agency business systems and processes – Labor intensive workarounds identified for all but 3 of the guidelines not currently met
  • 10. Fixing the gaps require… • OCE, CFO and CIO solve gaps associated with Agency business systems • In parallel, MDs and Centers establish consistent processes and procedures • Charter a steering committee for oversight and strategic Agency decision making (Members: All Mission Directorates and Centers given the opportunity for membership) – Decisional Direction – Approve a change or waive the requirement • Run two pilots (SMD/ESMD) proofing out capability for integrated in-house and contractor EVM that identifies business system solutions and creates efficiencies through streamlined processes and training – Provide template for all projects to follow – Validate needed business system changes – Develop workarounds for interim solution – Identify optimal solution (what’s good enough?) 10
  • 11. Current EVM Capability Project Status • Completed Formulation Activities – Drafted EVM Capability processes, system description, and project plan – Peer Review conducted the week of April 12th, 2010 • Responded with Action plan to closeout Request for Actions • No major issues • Any disagreements will come before the Steering Committee for Resolution • Entered implementation phase – 1st Pilot kicked-off at JSC week of April 5th, 2010 and initial gap analysis complete – EVA pilot cancelled in June 2010 because of changes/uncertainty within the CxP and the project office • Documented Results/ Lessons Learned/Issues Papers (end of July) – Two Issue Papers Submitted for Consideration • Inconsistency between Plan and Performance • Business Rules and Actual Cost – 2nd Pilot has started with review of data and setup support • Started in Sept. at GSFC • Pilot delayed in Nov. for re-planning until early Jan. 2011 11
  • 12. Issue Paper: Business Rules and Actual Costs Effects: NASA business rules and cost distribution methodologies impact NASA’s effective use of the Earned Value approach to project management. The following are three effects. 1. Artificial Variances 2. Distorts EVM data 3. Significantly impairs predictive ability of EVM Possible Solutions: The goal is for projects to obtain reliable and timely actual cost data from NASA’s accounting system for all elements of cost and provide meaningful cost and schedule data for management insight and control. There are several solutions, described below. Alternatives/Recommendation: 1. Maintain Current State 2. Modify System/Processes: Continue the Contractor Performance and Cost Tracking (C-Initiative) or similar initiative with emphasis to resolve these issues. 3. Implement Work-Around: Workaround Alternative 3.a.: Use cost/schedule integration commercial-off-the-shelf (COTS) tools to capture lower level costs using estimated actuals outside of SAP. Workaround Alternative 3.b: Use Total Calculated Cost from SAP. 4. Interim Workarounds and Modify System/Processes: This is an integrated alternative that leverages Workaround alternatives 3.a. and 3.b. in the near term, while Alternative 2, Modifying system/Processes, is evaluated for implementation in the longer term. 12
  • 13. Issue Paper: Inconsistency Plan and Performance Effects: NASA inconsistency between plan and performance impacts NASA’s effective use of the Earned Value approach to project Management. The following are two effects. 1. Artificial variances are created which dilute the value of EVM metrics in providing meaningful performance data for the responsible manager, monthly project reviews, and external senior management reviews of project performance. 2. The predictive value of EVM performance metrics that enables developing creditable Estimates at Complete (EAC) for work remaining is compromised. Possible Solutions: The goal is to realize and record cost in the period the work is planned and performed. There are several solutions described below. Alternatives/Recommendations: 1. Maintain Current State 2. Modify System/Processes: Develop a consistent methodology for accumulating and distributing non-direct costs to cover support organizations’ indirect budgets. These costs would be allocated to projects that use these services utilizing indirect cost pools similar to industry practices today. 3. Implement Workarounds: Workaround Alternative 3.a Refine the planning/work authorization process that documents the agreement between the project and performing support organizations for the technical scope of work, along with the associated schedule and budget, to require time-phasing all elements of costs to be consistent with the planned timing of allocating these costs. Workaround Alternative 3.b: Develop a process using estimate actuals where indirect costs are incurred in the same manner and in the same time period in which they are planned in the EVM PMB. Workaround Alternative 3.c: Plan indirect costs in a separate work package (WP) within the control account. This would require a method to distinguish the costs so they can be associated with the correct WPs. Workaround Alternative 3.d: Plan indirect costs in a separate, higher-level control account at the project level that could be managed and reported separately. Workaround Alternative 3.e: Increase Center CM&O budgets to meet the needs of the support organizations’ indirects or ODCs. 4. Interim Workarounds and Modify System/Processes: This is an integrated alternative that leverages Workaround Alternatives 3.a. and 3.d. in the near term while Alternative 2, Modifying System/Processes, is evaluated for implementation. The approach would be to refine the planning/work authorization process that documents the scope, schedule, and budget (all elements of cost) between organizations (Workaround 3.a); in conjunction with requiring the establishment of a separate, higher- level control account at the project level for indirect costs to be planned in the same manner in which costs are expected to be recognized and services rendered (Workaround 3.d). In the far term, develop a consistent methodology for accumulating and distributing non-direct costs to cover support organizations’ indirect budgets (Alternative 2).
  • 14. Recommendations/Approval on Issues • Issue Paper #1 - Planning − Continue to access the impact of EVA pilot during ICESat-2 pilot − Test the two recommended alternatives − Document ICESat 2 results and either make a process/business change or address in training • Issue Paper #2 - Business rules and actual costs − Maintain recommendations made by project team −Test workarounds during ICESat 2 pilot and document results – OCFO develops a detail plan for the Initiative C to help address the issues • Delivery date to coincide with end of pilot or before • EVM Capability will support by providing EVM requirements • Agency makes a decision on long-term solution based on pilot results and OCFO plan. • Next Steps… • Resume the ICESat2 pilot and update Steering Committee early spring 2011. 14
  • 15. Possible Future Issue - Implement EVM early/Transition Lesson Learned: Implement EVM as early as possible in Project Life – Setting up EVM in the planning phase is easier than trying to retrofit once the project is nearing maturity • Issue: EVM from Phase B to Phase C. Currently the Agency’s requirement is to report EVM 60 days after entering into phase C. The actuals have not caught up with the EVM data when the first month of EVM is required • Causes: The same project number is used for each phase of a project. Actuals are slow to catch up from one phase to another • Effect: The EVM data will be distorted until the actuals for the EV and cost for all phases except C are subtracted from the totals. • Possible Solutions: – Change the project code after each phase to distinguish costs/work for each phase – Make the 1st month’s reporting due 90 days after entering into phase C for actuals to catch up – Develop a recommended approach and document in EVM Capability – Develop training to illustrate the problem and solution 15
  • 16. Phase B to C Transition Comparison Why the timing is relevant EVM PROJECT PHASE COMPARISON EARNED VALUE COMPONENTS Total with Phase B PHASE C/D Only BUDGET $ 1,137,606.00 $ 475,000.00 EARNED VALUE $ 1,088,606.00 $ 426,000.00 ACTUALS $ 845,406.00 $ 384,000.00 COST VARIANCE $ 292,200.00 $ 91,000.00 COST PERFORMANCE INDEX 1.29 1.11 SCHEDULE VARIANCE $ (49,000.00) $ (49,000.00) SCHEDULE PERFORMANCE INDEX 0.96 0.90 16
  • 17. Gaps Impacting NASA’s Ability to be Compliant with ANSI/EIA-748 * All priorities within a group are of equal importance Gap # Priority* Gap Description Guideline(s) Status Impacted 1 1 * All priorities within a group are of equal NASA business practice requires that obligations and costs occur at the same level of the 16, 17 Workaround/ WBS in SAP, sometimes resulting in costs being posted where obligations are available and importance Change not necessarily where the work is performed (off charging). Required 2 1 Costing old money first (off charging) 16 Workaround/ Change Required 3 1 Algorithm being used to distribute 533 cost (off charging) 16 Workaround/ Change Required 4 1 Inability to collect support contractor hours and elements of cost at the appropriate WBS 16 Workaround/ element where the work is performed. Change Required 5 2 Leave (annual, sick, or comp) is charged to the project when taken not earned (off charging) 16 Change Required 6 2 Projects sometimes need to break down the WBS below level 7 to obtain a manageable 17, 22 Change piece of work Required /Workaround 7 3 The Project Manager will not be able to control the configuration of the WBS until he/she is 1 Change given approval authority of WBS elements being added to SAP. Required 8 3 NASA does not have a Work Authorization system for work across the Agency. 9 Change Required 9 4 Indirect cost policies continue to change and are not handled like normal, full cost are in an 4, 19, 24 Workaround/ EVM System. Change Required 10 4 Projects are not able to get timely and reliable grant, Internal Partner, and Reimbursable cost 6, 7, 16, 27 Workaround/ data from the system. Change Required 11 4 NASA does not have a Material Management System or policies across the Agency to 3,9,21 Workaround/ support the EVM guidelines for material. Change Required 17 Issue papers addressed solutions for the circled gaps.
  • 18. Path Forward • Continue ICESat2 Pilot and document lessons learned, update documentation as needed • Develop transition strategy for long-term implementation • Continue to provide Steering Committee with information to make decisions for Agency • Enter into O&M upon successful Operational Readiness Review (ORR) • Project Close (EVM Capability Team will not do the implementation) 18
  • 19. Backup 19
  • 20. Issue Paper: Business Rules and Actual Costs Issue: NASA’s business rules and the accounting system’s recording of actual cost present challenges for generating meaningful data for EVM performance measurement and analysis. Useful EVM performance measurement and analysis is dependent upon comparing actual costs, value of accomplished work, and budget values. During the Extravehicular Activity (EVA) Pilot, there were numerous examples of unreliable EVM performance measurement indicators and analysis based on data created by following NASA business rules that influence the manner in which contractor budgets are developed and actual costs reported. Additionally, the manner in which SAP records obligations and actual costs further destabilized the EVM performance measurement and analysis process on the EVA Project. Causes: During the EVA EVM pilot there were two causes that contributed to the misalignment of actual costs with budgeted work. The first is the methods used to establish and allocate contractor costs. The second cause is the manner in which NASA records obligations and actual costs in SAP. 1. Contractor Costs The manners in which contract reporting requirements are established and costs recorded contribute to a misalignment of plans and actual costs. Establishment Finalized contracts do not consistently contain Data Requirements Documents (DRD) with detailed requirements for individual Work Year Equivalents (WYE), hours, tasks, cost, etc. to support project-level EVM reporting. Allocated Cost The algorithm that is sometimes used to distribute contractor costs does not necessarily reflect the manner in which work is being performed on the project. This algorithm is often used in cases where multiple organizations fund a task agreement. While there are several methods for distributing actual cost, the primary cost distribution business rule is to cost the oldest money first, irrespective of where the work was performed. Costing old money first means that actual costs are recorded against the fund with the earliest expiration date. 2. Recording of Obligations and Actual Costs in SAP The methods used by NASA to record obligations and actual costs in SAP contribute to a misalignment of plans and actual costs. SAP business rules do not allow cost to exceed obligations for a WBS, and the SAP Cost category contains only those actual costs that do not exceed the obligation amount for that WBS element. This can cause significant understatement of a WBS element. SAP business rules require that obligations occur at the same level of the WBS where costs are collected. SAP currently allows actual costs to be collected at a maximum of seven levels. The EVA Project costs are often collected at the lowest WBS level which from a total contract perspective, some WBS codes may have excess obligations while others have obligations insufficient to accommodate the actual costs incurred. Hence, costs not getting recorded to the proper WBS element. This is further complicated by the laborious process required to move obligations to where they are required. When additional funds are obligated a spike in the cost for the month can occur. 20
  • 21. Issue Paper: Inconsistency Plan and Performance Issue: In evaluating the EVA Project’s planning and performance data, there are instances where Center support organizations’ budget plans were not time phased consistent with how certain elements of cost were realized. The problem is primarily with other support costs (e.g., material; equipment, ODCs) that are attributable to that organization’s support to project offices. The result is artificial cost variances caused by budget planning methodology that isn’t synchronized with how performance and actual costs are incurred. Causes: The systemic cause can be isolated to the practice of Center support organizations including in their monthly, time phased plan a factor that represents other support costs that are attributable to the support organization’s support. 1. While their direct support (labor) is performed and actual costs recorded monthly consistent with the plan, these other costs are allocated direct on a non-recurring basis. 2. Hence, the budget for these costs is spread over each month, while the actual costs are recorded in lump sums only a few months during the year. 3. The pervasive view of the support organizations’ is these (indirect) costs will all equal at the end of the year so there is no emphasis on improving the monthly time phasing. Effects: NASA inconsistency between plan and performance impacts NASA’s effective use of the Earned Value approach to project Management. The following are two effects. 1. Artificial variances are created which dilute the value of EVM metrics in providing meaningful performance data for the responsible manager, monthly project reviews, and external senior management reviews of project performance. 2. The predictive value of EVM performance metrics that enables developing creditable Estimates at Complete (EAC) for work remaining is compromised. Possible Solutions: The goal is to realize and record cost in the period the work is planned and performed. There are several solutions described below. 21
  • 22. ANSI EIA 748 Guidelines (Level 1 Requirements) 1. Define the authorized work elements for the program. A work breakdown structure (WBS), tailored for effective internal management control, is commonly used in this process. 2. Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work, and define the organizational elements in which work will be planned and controlled. 3. Provide for the integration of the company’s planning, scheduling, budgeting, work authorization and cost accumulation processes with each other, and as appropriate, the program work breakdown structure and the program organizational structure. 4. Identify the company organization or function responsible for controlling overhead (indirect costs). 5. Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed. 6. Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program. 7. Identify physical products, milestones, technical performance goals, or other indicators that will be used to measure progress. 22
  • 23. ANSI EIA 748 Guidelines (Level 1 requirements) 8. Establish and maintain a time-phased budget baseline, at the Cost Account level, against which program performance can be measured. Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation to the CA level. Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost, including estimate for authorized but undefinitized work. On Government contracts, if an over target baseline is used for performance measurement reporting purposes, prior notification must be provided to the customer. 9. Establish budgets for authorized work with identification of significant cost elements (labor, material, etc.) as needed for internal management and for control of subcontractors. 10. To the extent it is practical to identify the authorized work in discrete work packages, establish budgets for this work in terms of dollars, hours, or other measurable units. Where the entire control account is not subdivided into work packages, identify the far term effort in larger planning packages for budget and scheduling purposes. 11. Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget. 12. Identify and control level of effort activity by time-phased budgets established for this purpose. Only that effort which is immeasurable or for which measurement is impractical may be classified as level of effort. 23
  • 24. ANSI EIA 748 Guidelines (Level 1 requirements) 13. Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs. Reflect in the program budgets, at the appropriate level, the amounts in overhead pools that are planned to be allocated to the program as indirect costs. 14. Identify management reserves and undistributed budget. 15. Provide that the program target cost goal is reconciled with the sum of all internal program budgets and management reserves. 16. Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account. 17. When a work breakdown structure is used, summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements. 18. Summarize direct costs from the control accounts into the contractor’s organizational elements without allocation of a single control account to two or more organizational elements. 19. Record all indirect costs which will be allocated to the contract. 20. Identify unit costs, equivalent units costs, or lot costs when needed. 24
  • 25. ANSI EIA 748 Guidelines (Level 1 requirements) 21. For EVMS, the material accounting system will provide for: 1) Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized, acceptable, costing techniques. 2) Cost performance measurement at the point in time most suitable for the category of material involved, but no earlier than the time of progress payments or actual receipt of material. 3) Full accountability of all material purchased for the program including the residual inventory. 22. At least on a monthly basis, generate the following information at the control account and other levels as necessary for management control using actual cost data from, or reconcilable with, the accounting system: 1) Comparison of the amount of planned budget and the amount of budget earned for work accomplished. This comparison provides the schedule variance. 2) Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work. This comparison provides the cost variance. 23. Identify, at least monthly, the significant differences between both planned and actual schedule performance and planned and actual cost performance, and provide the reasons for the variances in the detail needed by program management. 24. Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control, along with the reasons for any significant variances. 25
  • 26. ANSI EIA 748 Guidelines (Level 1 requirements) 25. Summarize the data elements and associated variances through the program organization and/or work breakdown structure to support management needs and any customer reporting specified in the contract. 26. Implement managerial actions taken as the result of earned value information. 27. Develop revised estimates of cost at completion based on performance to date, commitment values for material, and estimates of future conditions. Compare this information with the performance measurement baseline to identify variances at completion important to company management any applicable customer reporting requirements including statements of funding requirements. 28. Incorporate authorized changes in a timely manner, recording the effects of such changes in budgets and schedules. In the directed effort prior to negotiation of a change, base such revisions on the amount estimated and budgeted to the program organizations. 29. Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control. 30. Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs, earned value, or budgets. Adjustments should be made only for correction of errors, routine accounting adjustments, effects of customer or management directed changes, or to improve the baseline integrity and accuracy of performance measurement data. 31. Prevent revisions to the program budget except for authorized changes. 32. Document changes to the performance measurement baseline. 26
  • 27. Storyboard – Pre KDP B (latest revision August 2010) 0.0 Pre KDP B No No MDAA / HQ 0.01 Acquisition 0.03 0.06 Strategy Planning Approve Program Plan & Process Program FAD 0.05 PCA approval 0.02 Develop Draft 0.08 Prepare Program Plan (PM) Project FAD Program FAD & PCA (MDAA) Approval Yes Program Mgr / Yes Yes Program Mgt 0.04 Yes Office Acquisition Strategy Meeting (Work Distribution/ Make/Buy) 0.07 Prepare Project FAD 0.10 Project Office Approval for Manager / Preliminary Project Project No Plan, WBS, Budget, 1.01 No Yes Schedules, etc. for Organization 0.09 all phases as Preliminary applicable Project Plan, WBS, Budget, Schedules, etc. for all phases as Element Mgr / Subproject / applicable Team Institutional/ Functional No 27
  • 28. Storyboard – Organization 1.0 Organization MDAA / HQ 1.01 KDP B No Program Mgr / Program Mgt Office 3.04 Prepare & Issue Preliminary Planning Guidance / WAD / Dollarized RAM Project Office Manager / 1.02 Project Finalize Project Plan for Phase C (EVM Approach) 2.01 Extend and Refine 1.03 Master Schedule Approve (Draft) Project Plan Element Mgr / Subproject / 1.04 1.05 1.07 Team Yes Extend & 1.06 Prepare WBS Extend & Refine Project Extend & Dictionary Refine WBS Refine Responsibility Organizational Assignment 8.01 Breakdown Matrix (RAM) & Estimate Material Structure (OBS) Identify Control Needs and Cost Accounts P-CAM Institutional/ Functional 28
  • 29. Storyboard – Scheduling 2.0 Scheduling Developing IMS IMS Status & Update 7-1.11 Input CAPs/update IMS, WBS, RAM, WAD, etc. Update 10.08 budget logs (PBB, Project Manager / Project Office Integrate Supplier AUW, Contingency/ Cost/ Schedule MR, UB) Data into Cost & Schedule Tools and 7-2.08 Reports Input CAPs/update IMS, WBS, RAM, WAD, etc. Update 1.07 budget logs (PBB, Extend & Refine 8.21 AUW, Contingency/ 2.04 Responsibility Received Material MR, UB) Integrate Assignment detailed Item / Claim BCWP Matrix (RAM) & schedules 3.11 Identify Control Establish the Accounts PMB 2.13 2.08 Input 2.02 2.05 Generate a workaround 2.01 Extend and Health Check form to gather IMS plans. 2.14 Extend and Refine 2.03 status updates or Publish and 2.15 Refine Master 2.10 2.11 Intermediate- Extend and Verify vertical electronic file to Health Distribute Export data Schedule 2.07 Input P-CAM Calculate a new Level Refine logic- traceability collect P-CAM’s Check and final to cost tool (Draft) Baseline and updates into the critical path and Element Mgr Schedule linked 3.07 schedule updates Analysis schedules Subproject/ Publish detailed schedule new forecast detailed CAP Reconcile Verify and EVM status IMS and or cost tool dates schedule or schedule with significant Iterate source of CAP budget data project as needed. (top, schedule until fully milestones intermediate, (draft), and integrated and detail if applicable Determine 2.06 level) assign EV critical path Review and measurement 6-1.02 Approve 6-1.01 techniques Schedule Monthly IMS Schedule Risk Performance Analysis P-CAM Assessment 2.09 Analysis Provide status 2.12 including AS/AF, Review results of forecasted dates, status. Milestones, & EV Develop 3.05 workaround plans P-CAMs as needed to Develop CAPs correct Institutional/ (Budget only) Functional 9.14 forecasted Integrate schedule slips Contractor Cost/ Schedule Data into Cost & Schedule Tools and Reports Agency EVM Capability Project / Jerald Kerby, PM / (256) 544-3243 08/02/2010 29
  • 30. Storyboard – Work/Budget Authorization 3.0 Work/Budget Authorization MDAA / HQ 3.15 KDP C 2.05 3.01 Health Check Update/Issue WAD or Verify vertical Equivalent (e.g., Program Mgr / traceability Program Mgt PAD) Verify significant Office 1.07 project milestones Extend & Refine Responsibility Determine 3.13 Assignment Matrix critical path Perform IBR (RAM) & Identify (Verify SOW, WBS Control Accounts Schedule Risk Dictionary, PMB, Assessment IMS, Risk, etc.) Project Manager / Project Office 3.11 3.10 Determine Yes Approved Reserves Rqmnts 3.03 3.02 Prepare & Issue Establish Project Preliminary Planning Budget Log Guidance / WAD / Dollarized RAM 3.12 Element Mgr / 3.07 Subproject / Establish the Reconcile PMB Team schedule with budget data until fully 2.03 3.06 integrated Extend and Refine 3.04 Extend and 3.09 5.03 3.08 Finalize & logic-linked Develop Tech, Cost, Refine Time-phase Negotiate Issue CA detailed CAP & Schedule Risk Charge 2.07 indirect budget CAPs WAD schedule or source Assessment Numbers Baseline and of CAP schedule (If needed) Publish P-CAM (draft), and 3.14 IMS if applicable assign Incorporate EV measurement Changes if (top, intermediate, techniques Required and detail level) 3.05 P-CAMs Develop CAPs Institutional/ (Budget only) Functional 2.04 Integrate detailed schedules Agency EVM Capability Project / Jerald Kerby, PM / (256) 544-3243 08/02/2010 30
  • 31. Storyboard – Accounting 4.0 Accounting Program Mgr / Program Mgt Office Yes Project Manager / Project Office 6-1.02 4.07 4.08 Monthly Incorporate verified Verify Load into Performance ACWP into Cost tool Cost Tool 4.03 Analysis 4.04 Download data from Verify/Distribute Core Financial ACWP data to P- System into CAMs spreadsheets 4.09 Reconcile to general book of accounts Element Mgr / Subproject / 4.05 Team Verify labor charges and other charges as applicable 8.13 4.06 Enter acceptance Correct errors as into SAP (Actuals applicable Recorded) P-CAM Institutional/ Functional 4.01 Record Cost in 4.02 Core Financial Month end closing No System Agency EVM Capability Project / Jerald Kerby, PM / (256) 544-3243 08/02/2010 31
  • 32. Storyboard – Indirect Management 5.0 Indirect Management MDAA / HQ Program Mgr / Program Mgt 3.05 Office P-CAMs Develop CAPs (Budget only) Project Office Manager / Project Element Mgr / Subproject / 5.05 5.08 6-2.02 Team 5.02 5.03 Analyze and Establish EAC with Develop ETC Plan Establish budgets Time-phase evaluate variances ETC rates for for the Control for indirect cost indirect budget caused by indirect indirect cost at CA/ Account and BoE costs WP level P-CAM Institutional/ Functional 5.01 5.06 5.04 5.07 IM Center CFO Analyze and Collect and record Develop EAC & provide indirect evaluate base and indirect cost ETC rates Guidance rate variances 32
  • 33. Storyboard – Managerial Analysis 6-1.0 Managerial Analysis MDAA / HQ 9.14 10.08 Integrate Integrate Intra- 6-1.12 Contractor Agency (other Review Cost/Schedule Centers) Cost/ Performance Data Data into Cost & Schedule Data into Assess Impact on Program Mgr / Program Mgt Schedule Tools Cost & Schedule Reserves (UFE) and Reports Tools and Reports Office 2.14 Publish and Project Office Distribute 6-1.11 Manager / final 6-1.05 Prepare and Issue Project schedules 6-1.04 6-1.08 Identify accounts Monthly 6-1.10 6-1.03 Analyze Data Review Metrics, that exceed Performance Review and Run preliminary Metrics and Variance Analysis, established Reports Approve Changes CPR and Trends Corrective Actions thresholds and incorporate Variance Analysis Report revised ETC, if forms necessary Element Mgr / Subproject / No 6-2.01 Team 6-1.01 6-1.02 Issue Schedule Monthly Comprehensive Analysis Performance project EAC 6-1.09 Analysis planning 6-1.06 6-1.07 Review and guidelines Analysis and Routine ETC / Yes Submit revised response to VARs EAC Revision WAD, If Required Required? P-CAM Optional 7-2.01 Identify Internal Institutional/ 4.08 Change Functional Verify Load into Cost tool 33
  • 34. Storyboard – Comprehensive EAC 6-2.0 Comprehensive Estimate-at-Completion (EAC) MDAA / HQ Program Mgr / Program Mgt Office 6-1.04 6-2.12 Analyze Data Performance Metrics and Reports Trends 6-2.05 Yes Project Office Approve EAC? Manager / Project 6-2.09 6-2.10 6-2.11 Update Project Contingency/MR Update Reported 6-2.01 Lien List Analysis EAC Issue (If Necessary) 6-2.03 6-2.04 Yes Comprehensive Analyze EACs and Review Project project EAC BoEs ETC / EAC planning No Element Mgr / guidelines Subproject / Team 6-2.06 6-2.02 Document Develop ETC Plan Disagreement (re- for the Control negotiate/iterate Account and BoE as needed) P-CAM 6-2.08 6-2.07 Revised EAC: Update EAC on Approved WAD WAD 5.08 Establish EAC with ETC rates for Institutional/ Functional indirect cost at CA/ WP level 34
  • 35. Storyboard – Change Mgmt (External) 7-1.0 Change Management (External Changes) MDAA / HQ 7-1.06 No 7-1.01 Approved? Identify External Program Mgr / Program Mgt Changes Office Yes 7-1.04 7-1.05 Revise Program/ Revise Program/ Project Office Yes Project Plan Project Manager / Plan? Project 7-1.07 Publish Guidance 7-1.11 7-1.12 No for Authorized Input CAPs/update Issue approved 7-1.10 WADs/CAPS/ Change IMS, WBS, RAM, Review & IMS/WBS/Publish Yes WAD, etc. Update Element Mgr / 7-1.03 Approve CAPs Subproject / 7-1.02 budget logs (PBB, Project Budget Prepare Assess change, & EACs? Logs AUW, Contingency/ Team Change develop MR, UB) Request technical, cost & Documentation schedule impacts 7-1.09 Review CAPs & EACs 7-1.08 Develop new and/ 7-1.13 P-CAM or revise existing Receive approved Control Account WAD, CAPs & Plans (CAPs) & EAC EAC Institutional/ Functional No 35