SlideShare una empresa de Scribd logo
1 de 60
Earned Value Analysis:
    Making it Work

                            February 22-23, 2012

   Joe Lukas, PMP, PM, CCE
           Vice-President



            609-575-9306 (c)
            888-762-3683 (w)
     joe.lukas@pmcentersusa.com
Traditional Project Cost Curve
What can you tell about the health of this project based on this graph?

                               Status Date
                                                         Budget – Planned Work
        $‟s or
        Hours
                                         Actual Cost



                                                Time

           1. Completing work for less than the budgeted amount
           2. Behind the project schedule
           3. Spending less than planned
           4. Behind schedule & completing work for less than the budget amount


                                                                                   2
                                    ©Joe Lukas, February 22-23, 2012
Traditional Project Cost Curve
The only information you know from this graph is that spending is
less than planned!
                          Status Date
                                                               Budget – Planned Work
       $‟s or
       Hours
                                              Actual Cost



                                                     Time

          1. Completing work for less than the budgeted amount

          2. Behind the project schedule

        3. Spending less than planned
          4. Behind schedule & completing work for less than the budget amount



                                                                                       3
                                        ©Joe Lukas, February 22-23, 2012
Earned Value Analysis Curve
What can you tell about the health of this project based on this graph?

                                      Status Date                       Budget

             $‟s or       Earned Value
             Hours

                                                  Actual Cost



                                                                Time
           1. Completing work for less than the budgeted amount
           2. Ahead of the project schedule
           3. Spending less than planned
           4. Ahead of schedule & completing work for less than the budget amount

                                                                                     4
                                     ©Joe Lukas, February 22-23, 2012
Earned Value Analysis Curve
You have completed more work than planned, but you can’t tell if
you are ahead of schedule! Why not?
                                        Status Date                              Budget

           $‟s or         Earned Value
           Hours

                                                      Actual Cost



                                                                    Time
        1. Completing work for less than the budgeted amount
          2. Ahead of the project schedule

        3. Spending less than planned
          4. Ahead of schedule & completing work for less than the budget amount

                                                                                          5
                                              ©Joe Lukas, February 22-23, 2012
What Will Be Covered?
• TOPIC 1: Quick review of
  Earned Value Analysis (EVA)
  terminology, calculations, and
  best practices


• TOPIC 2: Top ten pitfalls that
  can make EVA unsuccessful
  and corrective actions that can
  be applied to your project to
  counter these hazards
                                                          6
                       ©Joe Lukas, February 22-23, 2012
Topic 1
EVA Terminology & Calculations

                                       PV
                CV                                     EV
                                                  AC
                         SPI                                SV
                                           CPI
            ACWP                                       BAC
                                     BCWP
              EAC
                                                       BCWS
                                             ETC
                                                                 7
               ©Joe Lukas, February 22-23, 2012
Earned Value Terms
• Earned Value Analysis (EVA): Quantitative calculations
  that use the progress of authorized work and the budget
  for that work (called the earned value) for the purpose of
  monitoring performance and predicting the final required
  costs (and time) necessary to finish the project

• Earned Value Management (EVM): a method for
  measuring the performance of work packages, control
  accounts and the project; includes the integrated
  schedule and budget based on the project
• Earned Value Management System (EVMS): the
  integrated policies practices, procedures, tools and
  templates used to do EVM
                                                               8
                           ©Joe Lukas, February 22-23, 2012
Earned Value Terms: PV

            Planned Value (PV)
 • Also called Budgeted Cost of Work
   Scheduled (BCWS)
 • Portion of the approved cost estimate
   (budget) scheduled to be spent on the
   task during a given time period
 • This is the budget cost of what was
   scheduled to be done

                                                         9
                      ©Joe Lukas, February 22-23, 2012
Planned Value (PV)
                                  Time Now
                   75
Dollars or Hours




                   50                                 planned or
                                                PV = scheduled work

                   25



                    0
                        6                 12                   18
                               Time
                                                                      10
                            ©Joe Lukas, February 22-23, 2012
Earned Value Terms: AC

       Actual Cost (AC)
 • Also called Actual Cost of Work
   Performed (ACWP)
 • Costs incurred in accomplishing
   work on the task
 • This is what the work actually cost




                                                           11
                        ©Joe Lukas, February 22-23, 2012
Actual Cost (AC)
                    Time Now
                                                               planned or
          75                                           PV =   scheduled work



          50
                                       what the work
Dollars




                                  AC = actually cost

          25



           0
               6            12                          18
                   Time
                                                                           12
                    ©Joe Lukas, February 22-23, 2012
Earned Value Terms: EV

           Earned Value (EV)
 • Also called Budgeted Cost of Work
   Performed (BCWP)
 • The value of completed work calculated by
   multiplying the work budget by the percent
   of the work completed
 • This is what was actually done (earned)



                                                         13
                      ©Joe Lukas, February 22-23, 2012
Earned Value (EV)

                    Time Now
                                                              planned or
          75                                          PV -   scheduled work



          50
Dollars




                                               what the work
                                AC -           actually cost

          25                           actual work
                                  EV = accomplished

           0
               6            12                         18
                   Time
                                                                          14
                   ©Joe Lukas, February 22-23, 2012
Earned Value Relationships
The work with the schedule
and budget is the PLAN                                     Costs
                                             Budget Actual
                   Scheduled                        PV
         Work
                   Performed                        EV          AC


Earned Value looks at the budget                  The work performed
amount for the work performed                     (done) and the costs for
                                                  that work are ACTUAL
                                                  results
                                                                             15
                             ©Joe Lukas, February 22-23, 2012
Calculating Earned Value (EV)

 EV = % Complete x budget $ for that activity

• Percent complete is the physical progress of the
  task:
   A task is 0% complete if not started
   A task is 100% complete when finished
   Different techniques can be used to evaluate progress
    while a task is being done



                                                             16
                          ©Joe Lukas, February 22-23, 2012
Progressing Techniques

• Units Completed
• Incremental Milestones
• Start – Finish
• Apportioned Relationship
• Level of Effort
• Individual Judgment
• Combination Methods

                                                           17
                        ©Joe Lukas, February 22-23, 2012
Quantitative Progressing
• Units Completed - work with repeated production of easily
  measured pieces of work

• Incremental Milestones - work broken down in
  multiple measurable milestones, with specific budget
  values

• Start–Finish - some progress
  may be assigned at start;
  100% at completion



                                                               18
                            ©Joe Lukas, February 22-23, 2012
Qualitative Progressing
• Level of Effort - assumes the progress of the activity is
  equal to the amount spent


                       • Individual Judgment -
                         Important to get multiple
                         opinions of progress, this
                         provides a „checks and balance‟
                         on the progress accuracy




                                                               19
                            ©Joe Lukas, February 22-23, 2012
Misc. Progressing Techniques

• Apportioned Relationship - has a direct intrinsic
  performance relationship to another discrete Work Package
  & progress is same


• Combination Methods - Use two or
  more of the other progressing
  techniques


   These techniques can be either
   qualitative or quantitative

                                                              20
                           ©Joe Lukas, February 22-23, 2012
What Progressing Technique?
New carpet installation in company cafeteria
  1. Units Completed
  2. Incremental Milestones
  3. Start – Finish
  4. Apportioned Relationship
  5. Level of Effort
  6. Individual Judgment
  7. Combination Methods



                                                              21
                           ©Joe Lukas, February 22-23, 2012
What Progressing Technique?
Rock Excavation for new foundation

  1. Units Completed
  2. Incremental Milestones
  3. Start – Finish
  4. Apportioned Relationship
  5. Level of Effort
  6. Individual Judgment
  7. Combination Methods


                                                              22
                           ©Joe Lukas, February 22-23, 2012
What Progressing Technique?
New pill press machine purchase

  1. Units Completed
  2. Incremental Milestones
  3. Start – Finish
  4. Apportioned Relationship
  5. Level of Effort
  6. Individual Judgment
  7. Combination Methods


                                                              23
                           ©Joe Lukas, February 22-23, 2012
What Progressing Technique?
Factory inspector for equipment fabrication
  1. Units Completed
  2. Incremental Milestones
  3. Start – Finish
  4. Apportioned Relationship
  5. Level of Effort
  6. Individual Judgment
  7. Combination Methods


                                                              24
                           ©Joe Lukas, February 22-23, 2012
Schedule & Cost: Variance & Index
• Schedule Variance
 measures schedule performance                            SV = EV - PV
 at a point in time:
• Schedule Performance Index
 ratio of work performed to work                          SPI = EV  PV
 scheduled (earned / plan):
• Cost Variance
 measures cost performance                                CV = EV - AC
 at a point in time:
• Cost performance index
 ratio of budget costs for work                           CPI = EV  AC
 performed to actual costs:
                                                                          25
                            ©Joe Lukas, February 22-23, 2012
SV & CV – Bad Project
                                    Time Now
          75                                                                   Planned
                                                                 Budget -
                                                                             (Scheduled) Work



          50
Dollars




                                                  Actual Cost
               SV = -25
                                                     CV = -12
          25

                                    Earned Value -                   Budget of Work
                                                                     Accomplished
           0
                          6   9             12                          18
                                  Time
                                                                                            26
                                  ©Joe Lukas, February 22-23, 2012
SV & CV – „Good‟ Project

                                  Time Now
                                                                     Budget
          75


               SV = +5
          50
                                                         CV = +18
Dollars




                  Earned Value

          25                       Actual Cost



           0
                         6   9            12                        18
                                 Time
                                                                              27
                                 ©Joe Lukas, February 22-23, 2012
SPI Warning!!!
• Caution! The Schedule Performance
 Index may or may not accurately reflect the
 true schedule condition of the project!
 • Total Float must also be considered!
 • SPI > 1.0 may occur by “earning”
   progress on non-critical activities




                                                              28
                           ©Joe Lukas, February 22-23, 2012
Key Cost Forecasting Terms

• Budget at Completion (BAC) - sum of all
  authorized budgets allocated to a project - the
  “Performance Measurement Baseline”

• Estimate to Complete (ETC) - the expected
  additional cost to complete the project

• Estimate at Completion (EAC) - the expected total
  cost of the project when the defined scope of work
  is completed

                                                            29
                         ©Joe Lukas, February 22-23, 2012
Key Cost Forecasting Terms
                                                                             EAC
               BAC
                           TIME
                           NOW
                                                                     Project
                                                            ETC   Contingencies
DOLLARS




          PV         AC   EV
                                    NOTE: Most ETC & EAC formulas
                                    include an adjustment based on
                                    project performance (CPI, SPI)



                                                   TIME
                                                                                   30
                               ©Joe Lukas, February 22-23, 2012
EAC Formulas: CPI = 1
• „Mathematical‟ or „Overrun-to-Date‟ EAC

• EAC = AC + (BAC - EV) - assumes the plan will
 be met for the remaining work (CPI = 1.0)

• Yields the most optimistic EAC when CPI < 1.0

                               Time Now

     CPI                                   „Good Project‟

        1.0
                                               Project #1 & #2 CPI
              Actual CPI                   „Bad Project‟
        0.0
                                                 Time
                                                                     31
                           ©Joe Lukas, February 22-23, 2012
EAC Formulas: „Most Likely‟
• „Cumulative CPI‟ EAC
• EAC = AC + (BAC - EV)/CPI = BAC/CPI
• Assumes the performance (CPI) will remain unchanged
  for the rest of the project

                       Time Now
                                          Project #2 CPI    „Good Project‟
 CPI
    1.0
                                         Project #1 CPI
          Actual CPI                                         „Bad Project‟
    0.0
                                      Time
                                                                             32
                         ©Joe Lukas, February 22-23, 2012
EAC Formulas: CPI times SPI
• „Cumulative CPI times SPI‟ EAC
• EAC = AC + ((BAC - EV) / (CPI x SPI)) or
      = BAC / (CPI x SPI) [Not quite the same calculation]

• Yields the most pessimistic EAC when both SPI & CPI < 1.0

                         Time Now           Project #2 CPI
                                                              „Good Project‟
 CPI
     1.0
                                            Project #1 CPI
           Actual CPI                                          „Bad Project‟
     0.0
                                       Time
                                                                               33
                           ©Joe Lukas, February 22-23, 2012
Comments on Cumulative CPI

• Cumulative CPI has been shown to stabilize
  as early as the 20% completion point of the
  project
• “…researchers found the cumulative CPI
  does not change by more than 10% once a
  contract is 20% complete; in most cases,
  the cumulative CPI one worsens as a contract
  proceeds to completion”1

1Dr. David S. Christensen, “Using Performance Indices to Evaluate the Estimate at Completion,” The Journal of
Cost Analysis of the Society of Cost Estimating and Analysis, Spring 1994, page 19.

                                                                                                                34
                                                   ©Joe Lukas, February 22-23, 2012
To-Complete Performance Index
• TCPI – provides a forecast of the required performance
  level, expressed as a CPI, which must be achieved on the
  remaining work in order to meet the project financial goal,
  which can be:
    Current authorized budget
    Project Manager‟s current EAC

• TCPI – provides a sanity check for the Project Manager on
  whether the required CPI for the rest of the project is
  obtainable

• Remember: “…cumulative CPI does not change by more
  than 10% once a contract is 20% complete…”

                                                                    35
                                 ©Joe Lukas, February 22-23, 2012
TCPI Formulas
               Work Remaining                                   (BAC – EV)
TCPI (BAC) =                                            =
               Funds Remaining                                  (BAC – AC)

                Work Remaining                                   (BAC – EV)
TCPI (EAC) =                                              =
                Funds Remaining                                  (EAC – AC)
                                Time Now
                                                               TCPI (BAC)
     CPI
                                                                            Baseline
        1.0                                                                   Plan

               Actual CPI
        0.0
                                                  Time
                                                                                       36
                            ©Joe Lukas, February 22-23, 2012
Topic 2

Top Ten List on what‟s needed to make
EVA successful


                &

Actions that should be done on projects
to help ensure successful use of EVA



                                                          37
                       ©Joe Lukas, February 22-23, 2012
Making EVA Work

What‟s needed to make EVA Successful:

 6. Integrated Project Plan (WBS-Schedule-Budget)

 7. Correct Schedule & Budget

 8. Effective Cost collection system

 9. Accurate Reported Progress

10. No Management influence on progress

                                                          38
                       ©Joe Lukas, February 22-23, 2012
Making EVA Work

What‟s needed to make EVA Successful:

 1. Defined Requirements

 2. Complete Requirements

 3. WBS Used and Accepted

 4. Complete WBS

 5. Change Management Process

                                                       39
                    ©Joe Lukas, February 22-23, 2012
#1: Defined Requirements

Business
Objectives
                 Problem or
                 Opportunity
                      “Why”              Business
                                       Requirements
                                              “What”
                                                                  Functional &
                                                                    Technical
                                                                  Requirements
                                  WBS                               “What”
        Solution
     Architecture &                “How”
     Specifications
                                               Project Scope documented
         “How”                                 by the WBS


                                                                                 40
                               ©Joe Lukas, February 22-23, 2012
#2: Complete Requirements

          Schedule
                                                          Quality
                                                Communications
  Scope          Staffing
                                                        Procurement
          Cost                                             Risk



Requirements                                              Project
                                                           Plan
                                                                      41
                     ©Joe Lukas, February 22-23, 2012
#3: WBS Used & Accepted

• WBS lists the project deliverables, which is the
  input to the project schedule & budget
• Consequence if not used: Control Accounts and
  Work Packages not identified – making EVA
  calculations difficult and time consuming
• Correct Action:
    Prepare a WBS on your project!




                                                            42
                         ©Joe Lukas, February 22-23, 2012
#3: Use of a WBS

   Proper Naming of Deliverables & Activities


                    Major Deliverables
    WBS Elements




                                                              May not be needed for small
                        Deliverables                         or medium projects, probably
                                                              >1 level for large projects
                          Work Package                                Lowest level for control
                           Deliverables

                                                                  Steps needed to create the
                            Activities                           WBS deliverable


                                                                                                  43
                                    ©Joe Lukas, February 22-23, 2012
#3: Naming WBS Deliverables

• Data Flow Diagram
• Risk Management Plan
• Training Manual Outline
• Test Plan

• Conduct unit test for program 21A
• Review requirements document
• Prepare report specification draft
• Write script for interface module
                                                          44
                       ©Joe Lukas, February 22-23, 2012
#4: Complete WBS

                                   Project Product




               Major                    Major                                    Major
           Deliverable 1            Deliverable 2                            Deliverable 3


                                                        Deliverable 3.1                  Deliverable 3.2
Deliverable 1.1       Deliverable 1.2



          = Control Accounts

          = Work Packages           Sub-Deliverable 3.1.1                   Sub-Deliverable 3.1.2




   Need to verify WBS covers all project requirements!
                                                                                                           45
                                         ©Joe Lukas, February 22-23, 2012
#5: Change Management Process

• Consequence if not used:
   Cost / schedule deviations for Work Packages not
    documented
   Scope changes not captured – baseline not updated

• Correct Action:
   Implement a change management process on your
    project for both deviations and scope changes




                                                            46
                         ©Joe Lukas, February 22-23, 2012
#6: Integrated Project Plan

• WBS, Schedule and Budget are not integrated
• Consequence if not used: Makes doing EVA
  calculations difficult
• Correct Action: Use WBS as the starting point in
  preparing project schedule and budget




                                                          47
                       ©Joe Lukas, February 22-23, 2012
#7: Correct Schedule/Budget

• Schedule logic incorrect, work package estimates
  incorrect
• Consequence if happens: Incorrect EVA
  calculations
• Correct Action:
   Follow good scheduling practices
   Estimate at Work Package activities level
   Use a contingency fund to handle cost & schedule
    deviations


                                                            48
                         ©Joe Lukas, February 22-23, 2012
#7: Use of Contingency

 WP #     WP Title/Description                  WP Estimate
  ~




                         ~




                                                                    ~
  15       Package Implementation                       $           50,000
  -        Sub-total                                    $1,545,000
  -        Contingency                                  $ 155,000

  -           Project Total                             $1,700,000

           Task           Schedule
      ~




                                                             Project
            P            Contingency                        Complete
                           11 days

                  Task
          ~




                   Q

                                                                             49
                                 ©Joe Lukas, February 22-23, 2012
#7: Contingency Management
            Sample Contingency Drawdown Graph
     Dollars                                  Status                                                                    Days
                                               Date
     $40k                                                                                                                20
                  001                                             Cost Contingency Start = $38k
                        002

                              003

     $30k                           004
                                                                    Schedule Contingency Start = 15 days                15
                                      $29.4k
                  001



                        002
     $20k                                                                                                               10
                              003

                                           004                                                             EAC = $15k

                                          6 days
     $10k                                                                                                               5

       $0
            Oct   Nov               Dec                Jan             Feb           Mar       Apr           May
                                                 Project Timeline                          EAC = -9 days

50                                                     ©Joe Lukas, February 22-23, 2012
                                                                                                                             50
#8: Effective Cost System

• Internal labor hours not captured, costs not
  captured at Work Package level, multiple cost
  systems in place
• Consequence: Difficult or impossible to report
  actual costs
• Correct Action: Use SV and SPI only for internal
  work if costs not available, have contractors report
  EVA information for their work


                                                            51
                         ©Joe Lukas, February 22-23, 2012
#8: Adequate Cost System

Divide the project into internal and external work:

   Use SV, SPI, CV, CPI                                                     Use SV, SPI

                                     Project



         External Work                                                   Internal Work



 Deliverable A      Deliverable B                      Deliverable 1                 Deliverable 2




                                    Work Package 1.1                     Work Package 2.1

                                                                                                     52
                                      ©Joe Lukas, February 22-23, 2012
#9: Accurate Reported Progress

• Reported progress must be accurate – can be
  team bias (usually too optimistic)
• Consequence if not accurate: Incorrect EVA
  results
• Correct Action: Minimize subjective progress
  techniques - if use of Individual Judgment and
  Level of Effort >10%, EVA results probably not
  valid


                                                          53
                       ©Joe Lukas, February 22-23, 2012
#10: Management Influence

• Management pressures teams to show only good
  results
• Consequence if happens: Reported progress
  too optimistic - results in incorrect EAC
• Correct Action: Resist management influence




                                                        54
                     ©Joe Lukas, February 22-23, 2012
Back to the Earned Value Curve
                               Time Now
                                                                   Budget
          75



          50
Dollars




                                           Actual Cost
               Earned Value

          25                                 This was the graph for a
                                             real project…

           0
                    6     9           12                          18
                              Time
                                                                            55
                               ©Joe Lukas, February 22-23, 2012
The Results?
• Final Costs = 4x
• Final Schedule = + 1 year
• The good news – the software worked!



        So What Happened?


                                                        56
                     ©Joe Lukas, February 22-23, 2012
EVMS Standard

• In 1995, National Defense Industrial Association
  (NDIA) started work to rewrite Cost/Schedule
  Control System Criteria (C/SCSC) to make it
  more compatible with the needs of private
  industry
• Result was American National Standard Institute-
  Electronic Industries Association ANSI/EIA 748
  standard



                                                          57
                       ©Joe Lukas, February 22-23, 2012
EVMS Standard

• New version is called Earned Value
  Management System (EVMS) Criteria and
  contains 32 criteria in five groups:
     Organization
     Planning, Scheduling and Budgeting
     Accounting Considerations
     Analysis and Management Reports
     Revisions and Data Maintenance




                                                           58
                        ©Joe Lukas, February 22-23, 2012
Conclusion

• Earned Value is a methodology that, if used
  properly, provides project performance
  measurement
• EV requires complete requirements, scope
  definition and a Project Plan!
• Properly used, Earned Value is a flexible
  process that provides timely information on the
  project health


                                                          59
                       ©Joe Lukas, February 22-23, 2012
Questions?


  Joe Lukas, PMP, PM, CCE
                       Vice-President



               609-575-9306 (c)
               888-762-3683 (w)
        joe.lukas@pmcentersusa.com




                                      February 22-23, 2012
                                                             60
   ©Joe Lukas, February 22-23, 2012

Más contenido relacionado

La actualidad más candente

Esker.linda
Esker.lindaEsker.linda
Esker.linda
NASAPMC
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbier
NASAPMC
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
NASAPMC
 
John.baniszewski
John.baniszewskiJohn.baniszewski
John.baniszewski
NASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richard
NASAPMC
 
Glenn.counts
Glenn.countsGlenn.counts
Glenn.counts
NASAPMC
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
NASAPMC
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
NASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
NASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
NASAPMC
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
NASAPMC
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
NASAPMC
 
Mc nally
Mc nallyMc nally
Mc nally
NASAPMC
 
Price.rick
Price.rickPrice.rick
Price.rick
NASAPMC
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
NASAPMC
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerby
NASAPMC
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
NASAPMC
 

La actualidad más candente (20)

Esker.linda
Esker.lindaEsker.linda
Esker.linda
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbier
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
 
John.baniszewski
John.baniszewskiJohn.baniszewski
John.baniszewski
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Glenn.counts
Glenn.countsGlenn.counts
Glenn.counts
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Mc nally
Mc nallyMc nally
Mc nally
 
Symons
SymonsSymons
Symons
 
Price.rick
Price.rickPrice.rick
Price.rick
 
Harvey elliott
Harvey elliottHarvey elliott
Harvey elliott
 
Jerald kerby
Jerald kerbyJerald kerby
Jerald kerby
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
 

Destacado

Destacado (17)

Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
The importance of properly describing risks, presented by Peter Simon, 10th O...
The importance of properly describing risks, presented by Peter Simon, 10th O...The importance of properly describing risks, presented by Peter Simon, 10th O...
The importance of properly describing risks, presented by Peter Simon, 10th O...
 
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
Where do risks (threats and opportunities) arise from?, presented by Lynn Sta...
 
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
Risk analysis for project decision-making, presented by Keith Gray, 10th Oct ...
 
Building business continuity through risk management, presented by Kimberley ...
Building business continuity through risk management, presented by Kimberley ...Building business continuity through risk management, presented by Kimberley ...
Building business continuity through risk management, presented by Kimberley ...
 
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
A simple approach to contingency drawdown, presented by Ben Fry, 10th Oct 201...
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
 
MyPM Project Management Formulas
MyPM Project Management Formulas MyPM Project Management Formulas
MyPM Project Management Formulas
 
5 Easy Steps of Contingency Planning
5 Easy Steps of Contingency Planning5 Easy Steps of Contingency Planning
5 Easy Steps of Contingency Planning
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Quality in software industry
Quality in software industryQuality in software industry
Quality in software industry
 
Risk contingency and management reserve
Risk contingency and management reserveRisk contingency and management reserve
Risk contingency and management reserve
 
Risk contingency survey
Risk contingency surveyRisk contingency survey
Risk contingency survey
 
Fujitsu’s management of contingency
Fujitsu’s management of contingencyFujitsu’s management of contingency
Fujitsu’s management of contingency
 
Contingency and management reserve
Contingency and management reserveContingency and management reserve
Contingency and management reserve
 
Calculating contingency for management reserve
Calculating contingency for management reserveCalculating contingency for management reserve
Calculating contingency for management reserve
 

Similar a Lukas

Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...
Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...
Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...
Jacob Feldman
 
Planificación del proyecto estimación
Planificación del proyecto   estimaciónPlanificación del proyecto   estimación
Planificación del proyecto estimación
ProColombia
 
What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...
commonsenseLT
 
Project m&e & logframe
Project m&e & logframeProject m&e & logframe
Project m&e & logframe
Wesley Opaki
 
Cierre del proyecto
Cierre del proyectoCierre del proyecto
Cierre del proyecto
ProColombia
 
Cost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 janCost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 jan
Skript
 
At bruxelles scaling agile - v1.5 slideshare
At bruxelles   scaling agile - v1.5 slideshareAt bruxelles   scaling agile - v1.5 slideshare
At bruxelles scaling agile - v1.5 slideshare
Herve Lourdin
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 

Similar a Lukas (20)

Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...
Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...
Using Decision Tables to Model and Solve Scheduling and Resource Allocation P...
 
Planificación del proyecto estimación
Planificación del proyecto   estimaciónPlanificación del proyecto   estimación
Planificación del proyecto estimación
 
What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...
 
Basics of Project Planning
Basics of Project PlanningBasics of Project Planning
Basics of Project Planning
 
Project m&e & logframe
Project m&e & logframeProject m&e & logframe
Project m&e & logframe
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
project-management-1.pptx
project-management-1.pptxproject-management-1.pptx
project-management-1.pptx
 
Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)
 
Cierre del proyecto
Cierre del proyectoCierre del proyecto
Cierre del proyecto
 
Cost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 janCost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 jan
 
At bruxelles scaling agile - v1.5 slideshare
At bruxelles   scaling agile - v1.5 slideshareAt bruxelles   scaling agile - v1.5 slideshare
At bruxelles scaling agile - v1.5 slideshare
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
Prince2 Project Management With Web 2.0
Prince2 Project Management With Web 2.0Prince2 Project Management With Web 2.0
Prince2 Project Management With Web 2.0
 
Agile at Large Scale - Conference at Agile Tour Brussels
Agile at Large Scale - Conference at Agile Tour BrusselsAgile at Large Scale - Conference at Agile Tour Brussels
Agile at Large Scale - Conference at Agile Tour Brussels
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 

Más de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
NASAPMC
 

Más de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Último

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
giselly40
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 

Último (20)

The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 

Lukas

  • 1. Earned Value Analysis: Making it Work February 22-23, 2012 Joe Lukas, PMP, PM, CCE Vice-President 609-575-9306 (c) 888-762-3683 (w) joe.lukas@pmcentersusa.com
  • 2. Traditional Project Cost Curve What can you tell about the health of this project based on this graph? Status Date Budget – Planned Work $‟s or Hours Actual Cost Time  1. Completing work for less than the budgeted amount  2. Behind the project schedule  3. Spending less than planned  4. Behind schedule & completing work for less than the budget amount 2 ©Joe Lukas, February 22-23, 2012
  • 3. Traditional Project Cost Curve The only information you know from this graph is that spending is less than planned! Status Date Budget – Planned Work $‟s or Hours Actual Cost Time  1. Completing work for less than the budgeted amount  2. Behind the project schedule  3. Spending less than planned  4. Behind schedule & completing work for less than the budget amount 3 ©Joe Lukas, February 22-23, 2012
  • 4. Earned Value Analysis Curve What can you tell about the health of this project based on this graph? Status Date Budget $‟s or Earned Value Hours Actual Cost Time  1. Completing work for less than the budgeted amount  2. Ahead of the project schedule  3. Spending less than planned  4. Ahead of schedule & completing work for less than the budget amount 4 ©Joe Lukas, February 22-23, 2012
  • 5. Earned Value Analysis Curve You have completed more work than planned, but you can’t tell if you are ahead of schedule! Why not? Status Date Budget $‟s or Earned Value Hours Actual Cost Time  1. Completing work for less than the budgeted amount  2. Ahead of the project schedule  3. Spending less than planned  4. Ahead of schedule & completing work for less than the budget amount 5 ©Joe Lukas, February 22-23, 2012
  • 6. What Will Be Covered? • TOPIC 1: Quick review of Earned Value Analysis (EVA) terminology, calculations, and best practices • TOPIC 2: Top ten pitfalls that can make EVA unsuccessful and corrective actions that can be applied to your project to counter these hazards 6 ©Joe Lukas, February 22-23, 2012
  • 7. Topic 1 EVA Terminology & Calculations PV CV EV AC SPI SV CPI ACWP BAC BCWP EAC BCWS ETC 7 ©Joe Lukas, February 22-23, 2012
  • 8. Earned Value Terms • Earned Value Analysis (EVA): Quantitative calculations that use the progress of authorized work and the budget for that work (called the earned value) for the purpose of monitoring performance and predicting the final required costs (and time) necessary to finish the project • Earned Value Management (EVM): a method for measuring the performance of work packages, control accounts and the project; includes the integrated schedule and budget based on the project • Earned Value Management System (EVMS): the integrated policies practices, procedures, tools and templates used to do EVM 8 ©Joe Lukas, February 22-23, 2012
  • 9. Earned Value Terms: PV Planned Value (PV) • Also called Budgeted Cost of Work Scheduled (BCWS) • Portion of the approved cost estimate (budget) scheduled to be spent on the task during a given time period • This is the budget cost of what was scheduled to be done 9 ©Joe Lukas, February 22-23, 2012
  • 10. Planned Value (PV) Time Now 75 Dollars or Hours 50 planned or PV = scheduled work 25 0 6 12 18 Time 10 ©Joe Lukas, February 22-23, 2012
  • 11. Earned Value Terms: AC Actual Cost (AC) • Also called Actual Cost of Work Performed (ACWP) • Costs incurred in accomplishing work on the task • This is what the work actually cost 11 ©Joe Lukas, February 22-23, 2012
  • 12. Actual Cost (AC) Time Now planned or 75 PV = scheduled work 50 what the work Dollars AC = actually cost 25 0 6 12 18 Time 12 ©Joe Lukas, February 22-23, 2012
  • 13. Earned Value Terms: EV Earned Value (EV) • Also called Budgeted Cost of Work Performed (BCWP) • The value of completed work calculated by multiplying the work budget by the percent of the work completed • This is what was actually done (earned) 13 ©Joe Lukas, February 22-23, 2012
  • 14. Earned Value (EV) Time Now planned or 75 PV - scheduled work 50 Dollars what the work AC - actually cost 25 actual work EV = accomplished 0 6 12 18 Time 14 ©Joe Lukas, February 22-23, 2012
  • 15. Earned Value Relationships The work with the schedule and budget is the PLAN Costs Budget Actual Scheduled PV Work Performed EV AC Earned Value looks at the budget The work performed amount for the work performed (done) and the costs for that work are ACTUAL results 15 ©Joe Lukas, February 22-23, 2012
  • 16. Calculating Earned Value (EV) EV = % Complete x budget $ for that activity • Percent complete is the physical progress of the task:  A task is 0% complete if not started  A task is 100% complete when finished  Different techniques can be used to evaluate progress while a task is being done 16 ©Joe Lukas, February 22-23, 2012
  • 17. Progressing Techniques • Units Completed • Incremental Milestones • Start – Finish • Apportioned Relationship • Level of Effort • Individual Judgment • Combination Methods 17 ©Joe Lukas, February 22-23, 2012
  • 18. Quantitative Progressing • Units Completed - work with repeated production of easily measured pieces of work • Incremental Milestones - work broken down in multiple measurable milestones, with specific budget values • Start–Finish - some progress may be assigned at start; 100% at completion 18 ©Joe Lukas, February 22-23, 2012
  • 19. Qualitative Progressing • Level of Effort - assumes the progress of the activity is equal to the amount spent • Individual Judgment - Important to get multiple opinions of progress, this provides a „checks and balance‟ on the progress accuracy 19 ©Joe Lukas, February 22-23, 2012
  • 20. Misc. Progressing Techniques • Apportioned Relationship - has a direct intrinsic performance relationship to another discrete Work Package & progress is same • Combination Methods - Use two or more of the other progressing techniques These techniques can be either qualitative or quantitative 20 ©Joe Lukas, February 22-23, 2012
  • 21. What Progressing Technique? New carpet installation in company cafeteria 1. Units Completed 2. Incremental Milestones 3. Start – Finish 4. Apportioned Relationship 5. Level of Effort 6. Individual Judgment 7. Combination Methods 21 ©Joe Lukas, February 22-23, 2012
  • 22. What Progressing Technique? Rock Excavation for new foundation 1. Units Completed 2. Incremental Milestones 3. Start – Finish 4. Apportioned Relationship 5. Level of Effort 6. Individual Judgment 7. Combination Methods 22 ©Joe Lukas, February 22-23, 2012
  • 23. What Progressing Technique? New pill press machine purchase 1. Units Completed 2. Incremental Milestones 3. Start – Finish 4. Apportioned Relationship 5. Level of Effort 6. Individual Judgment 7. Combination Methods 23 ©Joe Lukas, February 22-23, 2012
  • 24. What Progressing Technique? Factory inspector for equipment fabrication 1. Units Completed 2. Incremental Milestones 3. Start – Finish 4. Apportioned Relationship 5. Level of Effort 6. Individual Judgment 7. Combination Methods 24 ©Joe Lukas, February 22-23, 2012
  • 25. Schedule & Cost: Variance & Index • Schedule Variance measures schedule performance SV = EV - PV at a point in time: • Schedule Performance Index ratio of work performed to work SPI = EV PV scheduled (earned / plan): • Cost Variance measures cost performance CV = EV - AC at a point in time: • Cost performance index ratio of budget costs for work CPI = EV AC performed to actual costs: 25 ©Joe Lukas, February 22-23, 2012
  • 26. SV & CV – Bad Project Time Now 75 Planned Budget - (Scheduled) Work 50 Dollars Actual Cost SV = -25 CV = -12 25 Earned Value - Budget of Work Accomplished 0 6 9 12 18 Time 26 ©Joe Lukas, February 22-23, 2012
  • 27. SV & CV – „Good‟ Project Time Now Budget 75 SV = +5 50 CV = +18 Dollars Earned Value 25 Actual Cost 0 6 9 12 18 Time 27 ©Joe Lukas, February 22-23, 2012
  • 28. SPI Warning!!! • Caution! The Schedule Performance Index may or may not accurately reflect the true schedule condition of the project! • Total Float must also be considered! • SPI > 1.0 may occur by “earning” progress on non-critical activities 28 ©Joe Lukas, February 22-23, 2012
  • 29. Key Cost Forecasting Terms • Budget at Completion (BAC) - sum of all authorized budgets allocated to a project - the “Performance Measurement Baseline” • Estimate to Complete (ETC) - the expected additional cost to complete the project • Estimate at Completion (EAC) - the expected total cost of the project when the defined scope of work is completed 29 ©Joe Lukas, February 22-23, 2012
  • 30. Key Cost Forecasting Terms EAC BAC TIME NOW Project ETC Contingencies DOLLARS PV AC EV NOTE: Most ETC & EAC formulas include an adjustment based on project performance (CPI, SPI) TIME 30 ©Joe Lukas, February 22-23, 2012
  • 31. EAC Formulas: CPI = 1 • „Mathematical‟ or „Overrun-to-Date‟ EAC • EAC = AC + (BAC - EV) - assumes the plan will be met for the remaining work (CPI = 1.0) • Yields the most optimistic EAC when CPI < 1.0 Time Now CPI „Good Project‟ 1.0 Project #1 & #2 CPI Actual CPI „Bad Project‟ 0.0 Time 31 ©Joe Lukas, February 22-23, 2012
  • 32. EAC Formulas: „Most Likely‟ • „Cumulative CPI‟ EAC • EAC = AC + (BAC - EV)/CPI = BAC/CPI • Assumes the performance (CPI) will remain unchanged for the rest of the project Time Now Project #2 CPI „Good Project‟ CPI 1.0 Project #1 CPI Actual CPI „Bad Project‟ 0.0 Time 32 ©Joe Lukas, February 22-23, 2012
  • 33. EAC Formulas: CPI times SPI • „Cumulative CPI times SPI‟ EAC • EAC = AC + ((BAC - EV) / (CPI x SPI)) or = BAC / (CPI x SPI) [Not quite the same calculation] • Yields the most pessimistic EAC when both SPI & CPI < 1.0 Time Now Project #2 CPI „Good Project‟ CPI 1.0 Project #1 CPI Actual CPI „Bad Project‟ 0.0 Time 33 ©Joe Lukas, February 22-23, 2012
  • 34. Comments on Cumulative CPI • Cumulative CPI has been shown to stabilize as early as the 20% completion point of the project • “…researchers found the cumulative CPI does not change by more than 10% once a contract is 20% complete; in most cases, the cumulative CPI one worsens as a contract proceeds to completion”1 1Dr. David S. Christensen, “Using Performance Indices to Evaluate the Estimate at Completion,” The Journal of Cost Analysis of the Society of Cost Estimating and Analysis, Spring 1994, page 19. 34 ©Joe Lukas, February 22-23, 2012
  • 35. To-Complete Performance Index • TCPI – provides a forecast of the required performance level, expressed as a CPI, which must be achieved on the remaining work in order to meet the project financial goal, which can be:  Current authorized budget  Project Manager‟s current EAC • TCPI – provides a sanity check for the Project Manager on whether the required CPI for the rest of the project is obtainable • Remember: “…cumulative CPI does not change by more than 10% once a contract is 20% complete…” 35 ©Joe Lukas, February 22-23, 2012
  • 36. TCPI Formulas Work Remaining (BAC – EV) TCPI (BAC) = = Funds Remaining (BAC – AC) Work Remaining (BAC – EV) TCPI (EAC) = = Funds Remaining (EAC – AC) Time Now TCPI (BAC) CPI Baseline 1.0 Plan Actual CPI 0.0 Time 36 ©Joe Lukas, February 22-23, 2012
  • 37. Topic 2 Top Ten List on what‟s needed to make EVA successful & Actions that should be done on projects to help ensure successful use of EVA 37 ©Joe Lukas, February 22-23, 2012
  • 38. Making EVA Work What‟s needed to make EVA Successful: 6. Integrated Project Plan (WBS-Schedule-Budget) 7. Correct Schedule & Budget 8. Effective Cost collection system 9. Accurate Reported Progress 10. No Management influence on progress 38 ©Joe Lukas, February 22-23, 2012
  • 39. Making EVA Work What‟s needed to make EVA Successful: 1. Defined Requirements 2. Complete Requirements 3. WBS Used and Accepted 4. Complete WBS 5. Change Management Process 39 ©Joe Lukas, February 22-23, 2012
  • 40. #1: Defined Requirements Business Objectives Problem or Opportunity “Why” Business Requirements “What” Functional & Technical Requirements WBS “What” Solution Architecture & “How” Specifications Project Scope documented “How” by the WBS 40 ©Joe Lukas, February 22-23, 2012
  • 41. #2: Complete Requirements Schedule Quality Communications Scope Staffing Procurement Cost Risk Requirements Project Plan 41 ©Joe Lukas, February 22-23, 2012
  • 42. #3: WBS Used & Accepted • WBS lists the project deliverables, which is the input to the project schedule & budget • Consequence if not used: Control Accounts and Work Packages not identified – making EVA calculations difficult and time consuming • Correct Action:  Prepare a WBS on your project! 42 ©Joe Lukas, February 22-23, 2012
  • 43. #3: Use of a WBS Proper Naming of Deliverables & Activities  Major Deliverables WBS Elements May not be needed for small  Deliverables or medium projects, probably >1 level for large projects  Work Package Lowest level for control Deliverables Steps needed to create the  Activities WBS deliverable 43 ©Joe Lukas, February 22-23, 2012
  • 44. #3: Naming WBS Deliverables • Data Flow Diagram • Risk Management Plan • Training Manual Outline • Test Plan • Conduct unit test for program 21A • Review requirements document • Prepare report specification draft • Write script for interface module 44 ©Joe Lukas, February 22-23, 2012
  • 45. #4: Complete WBS Project Product Major Major Major Deliverable 1 Deliverable 2 Deliverable 3 Deliverable 3.1 Deliverable 3.2 Deliverable 1.1 Deliverable 1.2 = Control Accounts = Work Packages Sub-Deliverable 3.1.1 Sub-Deliverable 3.1.2 Need to verify WBS covers all project requirements! 45 ©Joe Lukas, February 22-23, 2012
  • 46. #5: Change Management Process • Consequence if not used:  Cost / schedule deviations for Work Packages not documented  Scope changes not captured – baseline not updated • Correct Action:  Implement a change management process on your project for both deviations and scope changes 46 ©Joe Lukas, February 22-23, 2012
  • 47. #6: Integrated Project Plan • WBS, Schedule and Budget are not integrated • Consequence if not used: Makes doing EVA calculations difficult • Correct Action: Use WBS as the starting point in preparing project schedule and budget 47 ©Joe Lukas, February 22-23, 2012
  • 48. #7: Correct Schedule/Budget • Schedule logic incorrect, work package estimates incorrect • Consequence if happens: Incorrect EVA calculations • Correct Action:  Follow good scheduling practices  Estimate at Work Package activities level  Use a contingency fund to handle cost & schedule deviations 48 ©Joe Lukas, February 22-23, 2012
  • 49. #7: Use of Contingency WP # WP Title/Description WP Estimate ~ ~ ~ 15 Package Implementation $ 50,000 - Sub-total $1,545,000 - Contingency $ 155,000 - Project Total $1,700,000 Task Schedule ~ Project P Contingency Complete 11 days Task ~ Q 49 ©Joe Lukas, February 22-23, 2012
  • 50. #7: Contingency Management Sample Contingency Drawdown Graph Dollars Status Days Date $40k 20 001 Cost Contingency Start = $38k 002 003 $30k 004 Schedule Contingency Start = 15 days 15 $29.4k 001 002 $20k 10 003 004 EAC = $15k 6 days $10k 5 $0 Oct Nov Dec Jan Feb Mar Apr May Project Timeline EAC = -9 days 50 ©Joe Lukas, February 22-23, 2012 50
  • 51. #8: Effective Cost System • Internal labor hours not captured, costs not captured at Work Package level, multiple cost systems in place • Consequence: Difficult or impossible to report actual costs • Correct Action: Use SV and SPI only for internal work if costs not available, have contractors report EVA information for their work 51 ©Joe Lukas, February 22-23, 2012
  • 52. #8: Adequate Cost System Divide the project into internal and external work: Use SV, SPI, CV, CPI Use SV, SPI Project External Work Internal Work Deliverable A Deliverable B Deliverable 1 Deliverable 2 Work Package 1.1 Work Package 2.1 52 ©Joe Lukas, February 22-23, 2012
  • 53. #9: Accurate Reported Progress • Reported progress must be accurate – can be team bias (usually too optimistic) • Consequence if not accurate: Incorrect EVA results • Correct Action: Minimize subjective progress techniques - if use of Individual Judgment and Level of Effort >10%, EVA results probably not valid 53 ©Joe Lukas, February 22-23, 2012
  • 54. #10: Management Influence • Management pressures teams to show only good results • Consequence if happens: Reported progress too optimistic - results in incorrect EAC • Correct Action: Resist management influence 54 ©Joe Lukas, February 22-23, 2012
  • 55. Back to the Earned Value Curve Time Now Budget 75 50 Dollars Actual Cost Earned Value 25 This was the graph for a real project… 0 6 9 12 18 Time 55 ©Joe Lukas, February 22-23, 2012
  • 56. The Results? • Final Costs = 4x • Final Schedule = + 1 year • The good news – the software worked! So What Happened? 56 ©Joe Lukas, February 22-23, 2012
  • 57. EVMS Standard • In 1995, National Defense Industrial Association (NDIA) started work to rewrite Cost/Schedule Control System Criteria (C/SCSC) to make it more compatible with the needs of private industry • Result was American National Standard Institute- Electronic Industries Association ANSI/EIA 748 standard 57 ©Joe Lukas, February 22-23, 2012
  • 58. EVMS Standard • New version is called Earned Value Management System (EVMS) Criteria and contains 32 criteria in five groups:  Organization  Planning, Scheduling and Budgeting  Accounting Considerations  Analysis and Management Reports  Revisions and Data Maintenance 58 ©Joe Lukas, February 22-23, 2012
  • 59. Conclusion • Earned Value is a methodology that, if used properly, provides project performance measurement • EV requires complete requirements, scope definition and a Project Plan! • Properly used, Earned Value is a flexible process that provides timely information on the project health 59 ©Joe Lukas, February 22-23, 2012
  • 60. Questions? Joe Lukas, PMP, PM, CCE Vice-President 609-575-9306 (c) 888-762-3683 (w) joe.lukas@pmcentersusa.com February 22-23, 2012 60 ©Joe Lukas, February 22-23, 2012