SlideShare una empresa de Scribd logo
1 de 5
Descargar para leer sin conexión
Cost Controlling in Project Management
1. Planned Value (PV) is the authorized budget assigned for the completion of an activity or component of WBS.
2. Earned Value (EV) measured the completed work of project in percentage with Project Budget
EV = % of Completed Work * BAC
3. Actual Cost (AC) is the amount of money that you have spent so far.
4. Schedule variance (SV) indicates whether a project schedule is ahead or behind and is typically used within Earned Value.
Schedule variance (SV) = Earned Value(EV) - Planned Value (PV)
SV = EV – PV
5. Schedule Performance Index (SPI) concludes that: The completed work is equal to the planned work
Schedule variance (SV) = Earned Value(EV) / Planned Value (PV)
SPI= EV / PV
 SPI is greater than one; the project is ahead of schedule.
 SPI is less than one. The project is behind schedule.
 SPI is equal to one; the project is on schedule.
6. Cost Performance Index (CPI) is a measure of the financial effectiveness and efficiency of a project.
Cost Performance Index (CPI) = Earned Value(EV) / Actual Cost(AC)
CPI = EV / AC
 CPI is greater than one. The project is under budget.
 CPI is less than one. The project is over budget.
 CPI is equal to one. Project is proceeding as per the Estimated Cost.
7. Budget At Completion (BAC) refers to the sum of all budget values that have been previously established for the work to be performed
on a project, or on components within a project such as a schedule activity or work breakdown structure component.
8. Estimate At Completion (EAC) is The expected total cost of completing all work of project it is shows sum of the Actual Cost (AC)
spent so far.
 If future performance will be the same as past performance.
Estimate At Completion (EAC) = Budget At Completion (BAC) / Cost Performance Index (CPI)
EAC = BAC / CPI
 If we have deviated from our budget estimate, but from now on we can complete the remaining work as planned.
Estimate At Completion (EAC) = Actual Cost(AC) + [Budget At Completion (BAC) – Earned Value (EV)]
EAC = AC + (BAC – EV)
 If we are over budget, behind schedule, and the client is insisting us complete the project on time.
Estimate At Completion (EAC) = Actual Cost(AC) + [Budget At Completion (BAC) – Earned Value (EV) /
[Cost performance index (CPI) * Schedule performance index (SPI)]
EAC = AC + [(BAC – EV) / (CPI * SPI)]
 If we find out that your cost estimate was imperfect and we must calculate the new cost estimate for the remaining
project work.
Estimate At Completion (EAC) = Actual Cost(AC) + Bottom-up Estimate to Complete
EAC = AC + Bottom-up Estimate to Complete
9. Estimation to Completion (ETC) gives the approximate cost required to complete the remaining work of project.
There are two methods.
1. Bottom-up Cost Estimation
2. ETC = Estimation to Completion (ETC) – Actual Cost (AC)
10. Variance at Completion (VAC) gives the difference of the Budget at Completion (BAC) to the Estimate At Completion (EAC).
Variance at Completion (VAC) = Budget at Completion (BAC) - Estimate At Completion (EAC)
VAC = BAC – EAC
11. TO-COMPLETE PERFORMANCE INDEX (TCPI) gives the future cost performance that we may need to complete the project within
the approved budget.
 If we Maintain efficiency for Budget
TCPI = (BAC – EV) / (BAC – AC)
 If Maintain efficiency for Earned Value
TCPI = (BAC – EV) / (EAC – AC)
Scenario
Suppose we have 4 equal sites where we need to install equipment of Base Station for Telecom and budget
8000$ per side, schedule for completion is 1 side per day. Finish 4 days & cost 32000$.
Total Sites = 4 Same Equal Work
Budget per Site = 8000 USD
Scheduled Plan = Compilation of 1 side per day.
Total Days in Scope baseline = 4
Total Budget = 32000 USD
Total Days Actual
Cost
Per Day
Incurred cost
(Yes/No)
Work Performance on
Site
Remaining
work in %age
Completed Work in
%age
After Day 1 Site 1 8000 USD No 100 % Work
Completed on Site 1
75% 25%
After Day 2 Site 2 8500 USD Yes Work Started But 85%
completed
65 % 35%
After Day 3 Site 3 6500 USD No Site 2 Work Completed
But Site 3 completed
90%
35% 65%
Day 4 Site 4
Below are Cost Controlling Calculations
Earned Value (EV) = %age of Remaining Work * Budget At Completion (BAC)
Earned Value (EV) = 65 % * 32000 = 20,800 USD
Planned value (PV) = 8000 + 8000 + 8000 + 8000 = 32,000 USD
Actual Cost (AC) = 8000 + 8500 + 6500 = 23,000 USD
Find Cost Variance (CV), Schedule Variance (CV), Schedule performance index (SPI) and Cost performance index (CPI)?
Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC)
CV = 23000 -20800 =22, 00 USD
Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)
SV = 23000 – 32000 = 10000 USD
Schedule performance index (SPI) = Earned Value (EV) / Planned Value (PV)
SPI = 23000 / 32000 = 0.72 ( < 1 So, Less Work Than Plan because it is less than 1)
Cost performance index (CPI) = Earned Value (EV) - Actual Cost (AC)
CPI = 23000 / 20800 = 1.10 (CPI >1 So, Cost Under Run)
Estimation Value At Complete (EAC) = Budget At Completion (BAC) / Cost performance index (CPI)
EAC = 32000 / 1.10 = 2,909 USD
Estimation to Completion (ETC) = Estimation at Completion (EAC) - Actual cost (AC)
ETC = 2909 – 23000 = -20,091 USD
Variance At Completion (VAC) = Budget At Completion (BAC) - Estimation Value At Complete (EAC)
VAC = 32000 – 2909 = 29,091 USD
TO-COMPLETE PERFORMANCE INDEX (TCPI)
 If we Maintain efficiency for Budget
TCPI = (BAC – EV) / (BAC – AC) = (32000-20800) / (32000-23000) =1.24 (>1 So, Easier to Complete)
 If Maintain efficiency for Earned Value =
TCPI = (BAC – EV) / (EAC – AC) = ( 32000-20800) / (2909-23000)=0.055 (< 1 Hard To Complete Because less work than pan)
Planned value (PV)
Earned value (EV)
Actual cost (AC)
PV = EV – AC
Earned Value (EV) EV = % of Completed Work * BAC
Schedule variance (SV) SV = EV – PV Value CPI SPI TPI
Schedule performance index (SPI) SPI = EV / PV < 1 Cost Over
run
Less Work
than Plan
Hard to
Complete
Cost performance index (CPI) CPI = EV / AC >1 Cost Under
run
More Work
than Plan
Easier to
Complete
Estimation At Completion (EAC) EAC = BAC /CPI = 1 Equal to
Cost
As per Plan Same to
Complete
Estimation to Completion (ETC) ETC = EAC – AC
Variance At Completion (VAC) VAC = BAC – EAC
Forecasting for Earned Value
if CPI are same for remaining project EAC = BAC / CPI
if in future the work completed @
planned rate
EAC = AC + BAC – EV
if the initial plan is no longer valued EAC = AC + Bottom-up ETC
if both SPI and CPI effect the
remaining Work
EAC = AC + [ (BAC – EV) / (CPI x
SPI) ]
TO-COMPLETE PERFORMANCE INDEX (Measure the cost performance that
must be Achieved)
Maintain efficiency for Budget TCPI = (BAC – EV)/(BAC – AC)
Maintain efficiency for Earned Value TCPI = (BAC – EV)/(EAC – AC)
After Completion of Project Cost Variance
Variance At Completion (VAC)
Budget At Completion (BAC)
Earned Value At Completion (EAC)
VAC = BAC – EAC

Más contenido relacionado

Similar a Cost Controlling And Forecasting of Project.pdf

Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
Evm Basics
Evm BasicsEvm Basics
Evm Basicsgfbreaux
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...Tipsographic . com
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Dr Ezzat Mansour
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMatt Stehling
 

Similar a Cost Controlling And Forecasting of Project.pdf (20)

Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Pmp formulas pmbok6
Pmp formulas pmbok6Pmp formulas pmbok6
Pmp formulas pmbok6
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
 
Pmp formulas pmbok5
Pmp formulas pmbok5Pmp formulas pmbok5
Pmp formulas pmbok5
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 

Más de Nabeel Ahmad

What is the role of science and technology in risk related policy making
What is the role of science and technology in risk related policy makingWhat is the role of science and technology in risk related policy making
What is the role of science and technology in risk related policy makingNabeel Ahmad
 
Upload-Virtual-Hardisk-On-Azure.pdf
Upload-Virtual-Hardisk-On-Azure.pdfUpload-Virtual-Hardisk-On-Azure.pdf
Upload-Virtual-Hardisk-On-Azure.pdfNabeel Ahmad
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdfNabeel Ahmad
 
RAID-Level Configuration on BIOS of DELL Server.pdf
RAID-Level Configuration on BIOS of DELL Server.pdfRAID-Level Configuration on BIOS of DELL Server.pdf
RAID-Level Configuration on BIOS of DELL Server.pdfNabeel Ahmad
 
Very Simple way of subnetting for Class C.
Very Simple way of  subnetting for Class C.Very Simple way of  subnetting for Class C.
Very Simple way of subnetting for Class C.Nabeel Ahmad
 

Más de Nabeel Ahmad (7)

What is the role of science and technology in risk related policy making
What is the role of science and technology in risk related policy makingWhat is the role of science and technology in risk related policy making
What is the role of science and technology in risk related policy making
 
Upload-Virtual-Hardisk-On-Azure.pdf
Upload-Virtual-Hardisk-On-Azure.pdfUpload-Virtual-Hardisk-On-Azure.pdf
Upload-Virtual-Hardisk-On-Azure.pdf
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
RAID-Level Configuration on BIOS of DELL Server.pdf
RAID-Level Configuration on BIOS of DELL Server.pdfRAID-Level Configuration on BIOS of DELL Server.pdf
RAID-Level Configuration on BIOS of DELL Server.pdf
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
Risk management
Risk managementRisk management
Risk management
 
Very Simple way of subnetting for Class C.
Very Simple way of  subnetting for Class C.Very Simple way of  subnetting for Class C.
Very Simple way of subnetting for Class C.
 

Último

Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 

Último (20)

Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 

Cost Controlling And Forecasting of Project.pdf

  • 1. Cost Controlling in Project Management 1. Planned Value (PV) is the authorized budget assigned for the completion of an activity or component of WBS. 2. Earned Value (EV) measured the completed work of project in percentage with Project Budget EV = % of Completed Work * BAC 3. Actual Cost (AC) is the amount of money that you have spent so far. 4. Schedule variance (SV) indicates whether a project schedule is ahead or behind and is typically used within Earned Value. Schedule variance (SV) = Earned Value(EV) - Planned Value (PV) SV = EV – PV 5. Schedule Performance Index (SPI) concludes that: The completed work is equal to the planned work Schedule variance (SV) = Earned Value(EV) / Planned Value (PV) SPI= EV / PV  SPI is greater than one; the project is ahead of schedule.  SPI is less than one. The project is behind schedule.  SPI is equal to one; the project is on schedule. 6. Cost Performance Index (CPI) is a measure of the financial effectiveness and efficiency of a project. Cost Performance Index (CPI) = Earned Value(EV) / Actual Cost(AC) CPI = EV / AC  CPI is greater than one. The project is under budget.  CPI is less than one. The project is over budget.  CPI is equal to one. Project is proceeding as per the Estimated Cost. 7. Budget At Completion (BAC) refers to the sum of all budget values that have been previously established for the work to be performed on a project, or on components within a project such as a schedule activity or work breakdown structure component. 8. Estimate At Completion (EAC) is The expected total cost of completing all work of project it is shows sum of the Actual Cost (AC) spent so far.  If future performance will be the same as past performance. Estimate At Completion (EAC) = Budget At Completion (BAC) / Cost Performance Index (CPI) EAC = BAC / CPI  If we have deviated from our budget estimate, but from now on we can complete the remaining work as planned. Estimate At Completion (EAC) = Actual Cost(AC) + [Budget At Completion (BAC) – Earned Value (EV)]
  • 2. EAC = AC + (BAC – EV)  If we are over budget, behind schedule, and the client is insisting us complete the project on time. Estimate At Completion (EAC) = Actual Cost(AC) + [Budget At Completion (BAC) – Earned Value (EV) / [Cost performance index (CPI) * Schedule performance index (SPI)] EAC = AC + [(BAC – EV) / (CPI * SPI)]  If we find out that your cost estimate was imperfect and we must calculate the new cost estimate for the remaining project work. Estimate At Completion (EAC) = Actual Cost(AC) + Bottom-up Estimate to Complete EAC = AC + Bottom-up Estimate to Complete 9. Estimation to Completion (ETC) gives the approximate cost required to complete the remaining work of project. There are two methods. 1. Bottom-up Cost Estimation 2. ETC = Estimation to Completion (ETC) – Actual Cost (AC) 10. Variance at Completion (VAC) gives the difference of the Budget at Completion (BAC) to the Estimate At Completion (EAC). Variance at Completion (VAC) = Budget at Completion (BAC) - Estimate At Completion (EAC) VAC = BAC – EAC 11. TO-COMPLETE PERFORMANCE INDEX (TCPI) gives the future cost performance that we may need to complete the project within the approved budget.  If we Maintain efficiency for Budget TCPI = (BAC – EV) / (BAC – AC)  If Maintain efficiency for Earned Value TCPI = (BAC – EV) / (EAC – AC)
  • 3. Scenario Suppose we have 4 equal sites where we need to install equipment of Base Station for Telecom and budget 8000$ per side, schedule for completion is 1 side per day. Finish 4 days & cost 32000$. Total Sites = 4 Same Equal Work Budget per Site = 8000 USD Scheduled Plan = Compilation of 1 side per day. Total Days in Scope baseline = 4 Total Budget = 32000 USD Total Days Actual Cost Per Day Incurred cost (Yes/No) Work Performance on Site Remaining work in %age Completed Work in %age After Day 1 Site 1 8000 USD No 100 % Work Completed on Site 1 75% 25% After Day 2 Site 2 8500 USD Yes Work Started But 85% completed 65 % 35% After Day 3 Site 3 6500 USD No Site 2 Work Completed But Site 3 completed 90% 35% 65% Day 4 Site 4 Below are Cost Controlling Calculations Earned Value (EV) = %age of Remaining Work * Budget At Completion (BAC) Earned Value (EV) = 65 % * 32000 = 20,800 USD Planned value (PV) = 8000 + 8000 + 8000 + 8000 = 32,000 USD
  • 4. Actual Cost (AC) = 8000 + 8500 + 6500 = 23,000 USD Find Cost Variance (CV), Schedule Variance (CV), Schedule performance index (SPI) and Cost performance index (CPI)? Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC) CV = 23000 -20800 =22, 00 USD Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) SV = 23000 – 32000 = 10000 USD Schedule performance index (SPI) = Earned Value (EV) / Planned Value (PV) SPI = 23000 / 32000 = 0.72 ( < 1 So, Less Work Than Plan because it is less than 1) Cost performance index (CPI) = Earned Value (EV) - Actual Cost (AC) CPI = 23000 / 20800 = 1.10 (CPI >1 So, Cost Under Run) Estimation Value At Complete (EAC) = Budget At Completion (BAC) / Cost performance index (CPI) EAC = 32000 / 1.10 = 2,909 USD Estimation to Completion (ETC) = Estimation at Completion (EAC) - Actual cost (AC) ETC = 2909 – 23000 = -20,091 USD Variance At Completion (VAC) = Budget At Completion (BAC) - Estimation Value At Complete (EAC) VAC = 32000 – 2909 = 29,091 USD TO-COMPLETE PERFORMANCE INDEX (TCPI)  If we Maintain efficiency for Budget TCPI = (BAC – EV) / (BAC – AC) = (32000-20800) / (32000-23000) =1.24 (>1 So, Easier to Complete)  If Maintain efficiency for Earned Value = TCPI = (BAC – EV) / (EAC – AC) = ( 32000-20800) / (2909-23000)=0.055 (< 1 Hard To Complete Because less work than pan)
  • 5. Planned value (PV) Earned value (EV) Actual cost (AC) PV = EV – AC Earned Value (EV) EV = % of Completed Work * BAC Schedule variance (SV) SV = EV – PV Value CPI SPI TPI Schedule performance index (SPI) SPI = EV / PV < 1 Cost Over run Less Work than Plan Hard to Complete Cost performance index (CPI) CPI = EV / AC >1 Cost Under run More Work than Plan Easier to Complete Estimation At Completion (EAC) EAC = BAC /CPI = 1 Equal to Cost As per Plan Same to Complete Estimation to Completion (ETC) ETC = EAC – AC Variance At Completion (VAC) VAC = BAC – EAC Forecasting for Earned Value if CPI are same for remaining project EAC = BAC / CPI if in future the work completed @ planned rate EAC = AC + BAC – EV if the initial plan is no longer valued EAC = AC + Bottom-up ETC if both SPI and CPI effect the remaining Work EAC = AC + [ (BAC – EV) / (CPI x SPI) ] TO-COMPLETE PERFORMANCE INDEX (Measure the cost performance that must be Achieved) Maintain efficiency for Budget TCPI = (BAC – EV)/(BAC – AC) Maintain efficiency for Earned Value TCPI = (BAC – EV)/(EAC – AC) After Completion of Project Cost Variance Variance At Completion (VAC) Budget At Completion (BAC) Earned Value At Completion (EAC) VAC = BAC – EAC