ABSTRACT



The main aim of this project is to study
the various types of electrical and
mechanical equipment involved in the
process of generation of Electrical
power.
INTRODUCTION


KTPS-V Station was commissioned in 1996.



It was the first major thermal power station
in AP.



KTPS V Stage had achieved 94.5% plant load
factor.
WORKING PRINCIPLE


The thermal power station is a power plant in
which the prime mover is steam driven.



Water is heated, turns into steam and spins a
steam turbine which drives an electrical
generator.



The coal is used as a major source of fuel.



The thermal power plant works on the principle
PARTS OF THERMAL POWER
PLANT
TYPES OF CIRCUITS
For simplicity let us divide the whole
arrangement into four circuits.
1. Steam and water circuit
2. Air and gas circuit
3. Coal and ash circuit
4. Cooling water circuit.


1.STEAM AND WATER
CIRCUIT
boiler

Drum

Super
heater

IP Turbine

Re Heater

Hp turbine

LP Turbine

Condenser
BOILER


A boiler is a device for generating steam for
power, processing or heating purposes.



The boiler used here is a two pass, tower type,
reheat natural circulation single drum,
balanced draft and dry bottom (open hopper
type) boiler and is designed for burning coal as
principal fuel.
SCHMETIC DIAGRAM OF
BOILER
CLASSFICATION OF
BOILERS


Boilers are mainly classified into two types.
They are
1. Fire tube boiler
2.Water tube boiler
CONDENSER


Condenser is a
Surface heat
exchanger.



Exhaust steam from
LP turbine enters
into the condenser,
where it
condensates into
water by exchanging
its heat energy to
cooling water.
FEED WATER FLOW FROM
CONDENSER
Condenser

CEPs

LPH

HP heaters

BFPs

Deaerator

Economiser

Drum

boiler
ECONOMISER


An economiser
extracts apart of this
heat from the flue
gases.



It uses extracted
heat for heating the
feed water before it
enters into the
steam drum.
2.AIR AND GAS CIRCUIT
PRIMARY AIR FAN(PA FAN)
 The primary air has got two functions.
1.Pre heating the coal.
2. Transportation of fuel into furnace.
PA fan

Air
Heater

Mills

Boiler
FORCED DRAFT FAN(FD
FAN)


The function of FD FAN is to supply sufficient
quantity of air required for complete
combustion.



The air flow is as shown below
FD Fan

Air
Heater

Furnace
AIR PRE HEATERS


Air pre heater function is to heat the air with
the help of flue gases.



The air heater used in KTPS-V is a
Regenerative Tri-sector air heater.
The flue gases flow is as shown :



Boiler

Air
preheater

ESP

ID Fan

Chimney
INDUCED DRAFT FAN (ID
FAN)


The function of Induced Draft fan is to suck the
gases out of furnaces and throw them into the
stack.



Boiler is provided with two no. of Induced Draft
Fans.
ELECTROSTATIC
PRECIPITATOR


The main function of ESP is to clean the gases
which are being released into atmosphere.
COAL AND ASH CIRCUIT


The coal flow is as shown below:

Coal
storage
plant

Crushers

Bunkers

Mills

Boiler
COAL HANDLING PLANT
ASH HANDLING PLANT






At the bottom of the furnace, there is a hopper
for collection of bottom ash.
Fly ash is captured and removed from the flue
gas by electrostatic precipitators.
The flow of ash is as shown below
Boiler

Air pre
Heater

ESP

Ash
handling
plant

Ash
pond
COOLING WATER CIRCUIT
WATER SUPPLY




Water requirement for the KTPS is provided
from Kinnerasani Project.
The total water required for the station is 1,
50,000 tons per day.
Primary Fuel Supply:



KTPS is linked to Singareni Collieries
Company limited (S.C.C.L.) for supply of coal
from Manuguru, Yellandu and Rudrampur
mines.
STEAM TURBINE


Steam turbine is a
rotating machine
which converts the
heat energy of
steam into
mechanical
energy.
Description of Steam
Turbines
•

HP Turbine

•

IP Turbine

•

LP Turbine

HIGH PRESSURE TURBINE:
 In high pressure turbine steam is expanded to do
work.
 High pressure turbine having 25 reaction stages.
o
 Steam admitted at 540 c and pressure 150
kg/sq.cm.
TYPES OF TURBINES
IP TURBINE:
 Exhaust steam from hp turbine, after passing
through re heater is admitted for second phase of
expansion of steam.
 IP turbine having 17 reaction stages.
LOW PRESSURE TURBINE:
 Exhaust steam from IP turbine admitted to lp
turbine for the last phase of expansion of steam.
 LP turbine having 8 reaction stages
Excitation system


The excitation system comprises of an exciter
and automatic voltage regulator.



The duty of an exciter is to provide the
necessary field current to the rotor winding of
the alternator.



Brush less excitation is used in KTPS Vth
stage.
BRUSHLESS EXCITATION
SYSTEM:
Excitation system


The excitation system comprises of an exciter
and automatic voltage regulator.



The duty of an exciter is to provide the
necessary field current to the rotor winding of
the alternator.



Brush less excitation is used in KTPS Vth
stage.
SALIENT FEATUREs OF K.T.P.S


TOTAL INSTALLED CAPACITY:

1)

KTPS-A Station

: 4*60 = 240 MW

2)

KTPS-B Station

: 2*120 = 240 MW

3)

KTPS-C Station

: 2*120 = 240 MW

4)

KTPS-V Stage

: 2*250 = 500 MW

5)

KTPS-VI Stage

: 1*500=500 MW

Total installed capacity = 1720 MW
CONCLUSION






In a modern thermal power plant the Rankine
Cycle is modified to include superheating of
steam, regenerative feed water heating and
reheating of the steam.
Reheating the steam after it has partially
expanded, improves the thermal cycle efficiency
by 4 to 5%.Regenerative feed water heating by
using Low pressure and High pressure heaters
also improves the thermal cycle efficiency by 6 to
7%.
So the overall efficiency of a modern thermal
power plant is about 42%.
An Overview of Thermal Power Plant
An Overview of Thermal Power Plant

Más contenido relacionado

La actualidad más candente

C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-report
Anil Saharan
 
Boilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant OverviewBoilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant Overview
seshu seelamsetti
 

La actualidad más candente (20)

SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso KadamSUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
SUPER-CRITICAL THERMAL POWER PLANT by Tatyaso Kadam
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Steam turbine power plant
Steam turbine power plantSteam turbine power plant
Steam turbine power plant
 
Best ppt on thermal power station working
Best ppt on thermal power station workingBest ppt on thermal power station working
Best ppt on thermal power station working
 
Feedwater heaters by Himanshu Vaid
Feedwater heaters by Himanshu VaidFeedwater heaters by Himanshu Vaid
Feedwater heaters by Himanshu Vaid
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
 
Boilers and its types & components
Boilers and its types & componentsBoilers and its types & components
Boilers and its types & components
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)
 
CFBC boiler operation
CFBC boiler operationCFBC boiler operation
CFBC boiler operation
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-report
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
steam turbines presentation
steam turbines presentationsteam turbines presentation
steam turbines presentation
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
steam power plant
steam power plantsteam power plant
steam power plant
 
High pressure boiler
High pressure boilerHigh pressure boiler
High pressure boiler
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Boilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant OverviewBoilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant Overview
 

Similar a An Overview of Thermal Power Plant

presentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptxpresentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptx
rajam575648
 

Similar a An Overview of Thermal Power Plant (20)

training report
training reporttraining report
training report
 
kstps training report
kstps training reportkstps training report
kstps training report
 
National thermal power corporation
National thermal power corporationNational thermal power corporation
National thermal power corporation
 
thermal power plant suratgarh ppt
thermal power plant suratgarh ppt thermal power plant suratgarh ppt
thermal power plant suratgarh ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Ppt
PptPpt
Ppt
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
 
Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyard
 
boiler and cogeneration training material
boiler and cogeneration training materialboiler and cogeneration training material
boiler and cogeneration training material
 
Ntpc ppt complete
Ntpc ppt completeNtpc ppt complete
Ntpc ppt complete
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 
Pintu raj
Pintu rajPintu raj
Pintu raj
 
hindalco power
hindalco powerhindalco power
hindalco power
 
POWER PLANT.pdf
POWER PLANT.pdfPOWER PLANT.pdf
POWER PLANT.pdf
 
Mini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesMini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliaries
 
Harsh ntpc
Harsh ntpcHarsh ntpc
Harsh ntpc
 
presentation_thermal_power.pptx
presentation_thermal_power.pptxpresentation_thermal_power.pptx
presentation_thermal_power.pptx
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
presentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptxpresentation_thermal_power_plant_1447503788_165600.pptx
presentation_thermal_power_plant_1447503788_165600.pptx
 
Coal Base Thermal Power Plant
Coal Base Thermal Power PlantCoal Base Thermal Power Plant
Coal Base Thermal Power Plant
 

Último

Breaking Down the Flutterwave Scandal What You Need to Know.pdf
Breaking Down the Flutterwave Scandal What You Need to Know.pdfBreaking Down the Flutterwave Scandal What You Need to Know.pdf
Breaking Down the Flutterwave Scandal What You Need to Know.pdf
UK Journal
 
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
panagenda
 

Último (20)

Breaking Down the Flutterwave Scandal What You Need to Know.pdf
Breaking Down the Flutterwave Scandal What You Need to Know.pdfBreaking Down the Flutterwave Scandal What You Need to Know.pdf
Breaking Down the Flutterwave Scandal What You Need to Know.pdf
 
Extensible Python: Robustness through Addition - PyCon 2024
Extensible Python: Robustness through Addition - PyCon 2024Extensible Python: Robustness through Addition - PyCon 2024
Extensible Python: Robustness through Addition - PyCon 2024
 
Syngulon - Selection technology May 2024.pdf
Syngulon - Selection technology May 2024.pdfSyngulon - Selection technology May 2024.pdf
Syngulon - Selection technology May 2024.pdf
 
The Metaverse: Are We There Yet?
The  Metaverse:    Are   We  There  Yet?The  Metaverse:    Are   We  There  Yet?
The Metaverse: Are We There Yet?
 
WSO2CONMay2024OpenSourceConferenceDebrief.pptx
WSO2CONMay2024OpenSourceConferenceDebrief.pptxWSO2CONMay2024OpenSourceConferenceDebrief.pptx
WSO2CONMay2024OpenSourceConferenceDebrief.pptx
 
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
 
WebRTC and SIP not just audio and video @ OpenSIPS 2024
WebRTC and SIP not just audio and video @ OpenSIPS 2024WebRTC and SIP not just audio and video @ OpenSIPS 2024
WebRTC and SIP not just audio and video @ OpenSIPS 2024
 
1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT
1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT
1111 ChatGPT Prompts PDF Free Download - Prompts for ChatGPT
 
Using IESVE for Room Loads Analysis - UK & Ireland
Using IESVE for Room Loads Analysis - UK & IrelandUsing IESVE for Room Loads Analysis - UK & Ireland
Using IESVE for Room Loads Analysis - UK & Ireland
 
TopCryptoSupers 12thReport OrionX May2024
TopCryptoSupers 12thReport OrionX May2024TopCryptoSupers 12thReport OrionX May2024
TopCryptoSupers 12thReport OrionX May2024
 
Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...
Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...
Secure Zero Touch enabled Edge compute with Dell NativeEdge via FDO _ Brad at...
 
Linux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdf
Linux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdfLinux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdf
Linux Foundation Edge _ Overview of FDO Software Components _ Randy at Intel.pdf
 
AI presentation and introduction - Retrieval Augmented Generation RAG 101
AI presentation and introduction - Retrieval Augmented Generation RAG 101AI presentation and introduction - Retrieval Augmented Generation RAG 101
AI presentation and introduction - Retrieval Augmented Generation RAG 101
 
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
 
Long journey of Ruby Standard library at RubyKaigi 2024
Long journey of Ruby Standard library at RubyKaigi 2024Long journey of Ruby Standard library at RubyKaigi 2024
Long journey of Ruby Standard library at RubyKaigi 2024
 
Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...
Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...
Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...
 
A Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System StrategyA Business-Centric Approach to Design System Strategy
A Business-Centric Approach to Design System Strategy
 
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
Easier, Faster, and More Powerful – Alles Neu macht der Mai -Wir durchleuchte...
 
Overview of Hyperledger Foundation
Overview of Hyperledger FoundationOverview of Hyperledger Foundation
Overview of Hyperledger Foundation
 
BT & Neo4j _ How Knowledge Graphs help BT deliver Digital Transformation.pptx
BT & Neo4j _ How Knowledge Graphs help BT deliver Digital Transformation.pptxBT & Neo4j _ How Knowledge Graphs help BT deliver Digital Transformation.pptx
BT & Neo4j _ How Knowledge Graphs help BT deliver Digital Transformation.pptx
 

An Overview of Thermal Power Plant

  • 1.
  • 2. ABSTRACT  The main aim of this project is to study the various types of electrical and mechanical equipment involved in the process of generation of Electrical power.
  • 3. INTRODUCTION  KTPS-V Station was commissioned in 1996.  It was the first major thermal power station in AP.  KTPS V Stage had achieved 94.5% plant load factor.
  • 4. WORKING PRINCIPLE  The thermal power station is a power plant in which the prime mover is steam driven.  Water is heated, turns into steam and spins a steam turbine which drives an electrical generator.  The coal is used as a major source of fuel.  The thermal power plant works on the principle
  • 5. PARTS OF THERMAL POWER PLANT
  • 6.
  • 7. TYPES OF CIRCUITS For simplicity let us divide the whole arrangement into four circuits. 1. Steam and water circuit 2. Air and gas circuit 3. Coal and ash circuit 4. Cooling water circuit. 
  • 8. 1.STEAM AND WATER CIRCUIT boiler Drum Super heater IP Turbine Re Heater Hp turbine LP Turbine Condenser
  • 9. BOILER  A boiler is a device for generating steam for power, processing or heating purposes.  The boiler used here is a two pass, tower type, reheat natural circulation single drum, balanced draft and dry bottom (open hopper type) boiler and is designed for burning coal as principal fuel.
  • 11. CLASSFICATION OF BOILERS  Boilers are mainly classified into two types. They are 1. Fire tube boiler 2.Water tube boiler
  • 12. CONDENSER  Condenser is a Surface heat exchanger.  Exhaust steam from LP turbine enters into the condenser, where it condensates into water by exchanging its heat energy to cooling water.
  • 13. FEED WATER FLOW FROM CONDENSER Condenser CEPs LPH HP heaters BFPs Deaerator Economiser Drum boiler
  • 14. ECONOMISER  An economiser extracts apart of this heat from the flue gases.  It uses extracted heat for heating the feed water before it enters into the steam drum.
  • 15. 2.AIR AND GAS CIRCUIT PRIMARY AIR FAN(PA FAN)  The primary air has got two functions. 1.Pre heating the coal. 2. Transportation of fuel into furnace. PA fan Air Heater Mills Boiler
  • 16. FORCED DRAFT FAN(FD FAN)  The function of FD FAN is to supply sufficient quantity of air required for complete combustion.  The air flow is as shown below FD Fan Air Heater Furnace
  • 17. AIR PRE HEATERS  Air pre heater function is to heat the air with the help of flue gases.  The air heater used in KTPS-V is a Regenerative Tri-sector air heater. The flue gases flow is as shown :  Boiler Air preheater ESP ID Fan Chimney
  • 18. INDUCED DRAFT FAN (ID FAN)  The function of Induced Draft fan is to suck the gases out of furnaces and throw them into the stack.  Boiler is provided with two no. of Induced Draft Fans.
  • 19. ELECTROSTATIC PRECIPITATOR  The main function of ESP is to clean the gases which are being released into atmosphere.
  • 20. COAL AND ASH CIRCUIT  The coal flow is as shown below: Coal storage plant Crushers Bunkers Mills Boiler
  • 22. ASH HANDLING PLANT    At the bottom of the furnace, there is a hopper for collection of bottom ash. Fly ash is captured and removed from the flue gas by electrostatic precipitators. The flow of ash is as shown below Boiler Air pre Heater ESP Ash handling plant Ash pond
  • 24. WATER SUPPLY   Water requirement for the KTPS is provided from Kinnerasani Project. The total water required for the station is 1, 50,000 tons per day.
  • 25. Primary Fuel Supply:  KTPS is linked to Singareni Collieries Company limited (S.C.C.L.) for supply of coal from Manuguru, Yellandu and Rudrampur mines.
  • 26. STEAM TURBINE  Steam turbine is a rotating machine which converts the heat energy of steam into mechanical energy.
  • 27. Description of Steam Turbines • HP Turbine • IP Turbine • LP Turbine HIGH PRESSURE TURBINE:  In high pressure turbine steam is expanded to do work.  High pressure turbine having 25 reaction stages. o  Steam admitted at 540 c and pressure 150 kg/sq.cm.
  • 28. TYPES OF TURBINES IP TURBINE:  Exhaust steam from hp turbine, after passing through re heater is admitted for second phase of expansion of steam.  IP turbine having 17 reaction stages. LOW PRESSURE TURBINE:  Exhaust steam from IP turbine admitted to lp turbine for the last phase of expansion of steam.  LP turbine having 8 reaction stages
  • 29. Excitation system  The excitation system comprises of an exciter and automatic voltage regulator.  The duty of an exciter is to provide the necessary field current to the rotor winding of the alternator.  Brush less excitation is used in KTPS Vth stage.
  • 31. Excitation system  The excitation system comprises of an exciter and automatic voltage regulator.  The duty of an exciter is to provide the necessary field current to the rotor winding of the alternator.  Brush less excitation is used in KTPS Vth stage.
  • 32. SALIENT FEATUREs OF K.T.P.S  TOTAL INSTALLED CAPACITY: 1) KTPS-A Station : 4*60 = 240 MW 2) KTPS-B Station : 2*120 = 240 MW 3) KTPS-C Station : 2*120 = 240 MW 4) KTPS-V Stage : 2*250 = 500 MW 5) KTPS-VI Stage : 1*500=500 MW Total installed capacity = 1720 MW
  • 33. CONCLUSION    In a modern thermal power plant the Rankine Cycle is modified to include superheating of steam, regenerative feed water heating and reheating of the steam. Reheating the steam after it has partially expanded, improves the thermal cycle efficiency by 4 to 5%.Regenerative feed water heating by using Low pressure and High pressure heaters also improves the thermal cycle efficiency by 6 to 7%. So the overall efficiency of a modern thermal power plant is about 42%.