SlideShare una empresa de Scribd logo
1 de 33
Descargar para leer sin conexión
Philadelphia
Electric Transmission &
Distribution System
Investments

  Behind the scenes at the facilities
  that keep the lights on in the city
  Summer 2009
Meeting the electric needs of
Philadelphia with new, rebuilt and larger
electric substations

  $160 million in the city’s electric infrastructure to ensure
  reliability for current and future energy demand
  Tuna Substation in Northern Liberties (2005)
  Waverly substation in Center City (2007)
  Southwark substation in South Philadelphia/Navy Yard
  (2008)
  Tunnel substation in University City (Spring 2009)
  Schuylkill & Grays Ferry tr substations in South
  Philadelphia (Summer/Fall 2009)
  These are part of a network of 20 electric substations that
  make up the Center City transmission system
  Near future: Penrose (2011) and Peltz (2013) substations
  planned in near future
                                                                 2
New Southwark distribution
Substation
 $18 million capital investment
 Install new 69/13kV duplex substation adjacent to
 existing substation
 •   New control house
 •   Two 62MVA 69/13kV transformers
 •   13kV switchgear for 3 distribution busses
 •   5 new distribution circuits




                                                     3
Transformer Foundation Piles




                               4
New Transformer w/ Firewall




                              5
New Switchgear




                 6
Tunnel Substation
  $25 million capital investment
  New 220/13kV - 62MVA substation
  Located along Schuylkill River on University of
  Pennsylvania campus
  • Meet substantial new electric demand in University City
  • Two (2) 62MVA 220/13kV transformers
  • Eight (8) 13kV distribution circuits
      − Ultimate capacity of 12 circuits
  • Nine (9) MVAR capacitor bank
  • Taps the 220-27 line between Parrish & Grays Ferry
  • Benefits
      −   Relieves 40MVA load on facilities east of Schuylkill River
      −   Improved reliability in West Philadelphia
      −   Provides additional capacity to University City area
      −   Begins the retirement of Schuylkill 13kV substation



                                                                       7
Tunnel Substation – April 2008




                                 8
Tunnel Substation – Dec 2008




                               9
Tunnel Substation – Boring Operation




                                       10
Tunnel Substation – North Bore Ducts




                                       11
12
13
14
15
16
17
18
19
Schuylkill & Grays Ferry
Transmission substations
 $18 million upgrades to Schuylkill substation
  • Major transmission supply for Center City
  • Modernizes existing facilities
  • Rebuilding electrical facilities on same site as existing sub
  • Replace 12 69kV breakers, disconnects, insulators, and bus work at the
    North and Center rings
  • Install 4 new 69kV breakers to tie in with Grays Ferry
  • Relocate controls from the neighboring generating station to newly
    installed control houses (North and East yards)
 $22 million Grays Ferry expansion
  • Increased electric transmission capacity for improved reliability and
    operational flexibility
  • Install 230-kv/69-kv transformer
  • Install new 69kV transmission line from Grays Ferry to Schuylkill Center
    ring
  • Install new 230kV breakers, upgrade existing breakers, and reconfigure
    Grays Ferry bus into ring bus
 Connect fiber optic rings
  • Schuylkill and Grays Ferry & Waverly, Lombard, and Penn
                                                                               20
Schuylkill’s 69kV Circuit Breaker




                                    21
Disconnect Switch, Insulators & Bus




                                      22
New Breaker &Associated Bus Work




                                   23
Schuylkill Station Controls
Old and New




                              24
25
26
27
Grays Ferry




              28
29
30
31
32
Additional City Investments
  $1.5 million replacement of automated switches for three
  Center City distribution networks
  Replacement of vacuum circuit breakers
  • Multi-year commitment to replace outdated VCBs and install fiber
    for enhanced communications and operations in Center City
  $2 million for relocation of utility facilities for city’s South
  Street Bridge replacement
  • Relocation of manholes & ducts for construction
  • Installation of ducts in new bridge
  Aerial and underground distribution improvements in
  Germantown, Overbrook, Mt. Airy, Chestnut Hill, Walnut
  Street, Hunting Park
  Planned retirement of Southwark, Delaware and Schuylkill
  13-kv substations in near future (within five year plan)
                                                                       33

Más contenido relacionado

La actualidad más candente

Off-shore dynamic cable and wet mate connector
Off-shore dynamic cable and wet mate connectorOff-shore dynamic cable and wet mate connector
Off-shore dynamic cable and wet mate connector
Carles Escofet
 
404 presentation
404 presentation404 presentation
404 presentation
aricsma
 
Agreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe DevelopmentAgreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe Development
City of College Station
 
Eng. issam chehimi part 2 catenary-free solution
Eng. issam chehimi part 2  catenary-free solutionEng. issam chehimi part 2  catenary-free solution
Eng. issam chehimi part 2 catenary-free solution
imadhammoud
 
VACON NXP Grid Converter - Cleaner power for ports and ships
VACON NXP Grid Converter - Cleaner power for ports and ships VACON NXP Grid Converter - Cleaner power for ports and ships
VACON NXP Grid Converter - Cleaner power for ports and ships
Vacon Plc
 

La actualidad más candente (20)

Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilotMike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
Mike chapman-evolution-of-the-rural-network-stand-alone-power-system-pilot
 
introduction to power system
introduction to power systemintroduction to power system
introduction to power system
 
Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL Grid Station Construction (GSC) NTDCL
Grid Station Construction (GSC) NTDCL
 
Off-shore dynamic cable and wet mate connector
Off-shore dynamic cable and wet mate connectorOff-shore dynamic cable and wet mate connector
Off-shore dynamic cable and wet mate connector
 
404 presentation
404 presentation404 presentation
404 presentation
 
Tidal energy takes scotland inner sound
Tidal energy takes scotland inner soundTidal energy takes scotland inner sound
Tidal energy takes scotland inner sound
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
 
Presention ppt
Presention pptPresention ppt
Presention ppt
 
Islington council presentation on Wharfdale Road bridge
Islington council presentation on Wharfdale Road bridgeIslington council presentation on Wharfdale Road bridge
Islington council presentation on Wharfdale Road bridge
 
Tarbela Hydro Power Plant
Tarbela Hydro Power PlantTarbela Hydro Power Plant
Tarbela Hydro Power Plant
 
Reference - KEPCO FR ESS
Reference - KEPCO FR ESSReference - KEPCO FR ESS
Reference - KEPCO FR ESS
 
Agreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe DevelopmentAgreement with TAMUS on Campus Pointe Development
Agreement with TAMUS on Campus Pointe Development
 
Energy storage (why & how)
Energy storage (why & how)Energy storage (why & how)
Energy storage (why & how)
 
CV
CVCV
CV
 
News 3
News 3News 3
News 3
 
Eng. issam chehimi part 2 catenary-free solution
Eng. issam chehimi part 2  catenary-free solutionEng. issam chehimi part 2  catenary-free solution
Eng. issam chehimi part 2 catenary-free solution
 
VACON NXP Grid Converter - Cleaner power for ports and ships
VACON NXP Grid Converter - Cleaner power for ports and ships VACON NXP Grid Converter - Cleaner power for ports and ships
VACON NXP Grid Converter - Cleaner power for ports and ships
 
Angelique international limited : Substation Procurement, Underground Cable L...
Angelique international limited : Substation Procurement, Underground Cable L...Angelique international limited : Substation Procurement, Underground Cable L...
Angelique international limited : Substation Procurement, Underground Cable L...
 
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backupSelf-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
Self-recharging Fuel Cell's. Acta's fast track to Telecom Adoption for backup
 
Engage with...TPS | Driving the Electric Revolution Webinar
Engage with...TPS | Driving the Electric Revolution WebinarEngage with...TPS | Driving the Electric Revolution Webinar
Engage with...TPS | Driving the Electric Revolution Webinar
 

Similar a PECO projects in Philadelphia

Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical Enginner
Reza Shah Abadi
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical Enginner
Reza Shah Abadi
 
Lecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdfLecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdf
Nandi77
 
John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015
John Hitt
 

Similar a PECO projects in Philadelphia (20)

wathiq alanbaki
wathiq alanbakiwathiq alanbaki
wathiq alanbaki
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
 
Ultra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACUltra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVAC
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical Enginner
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical Enginner
 
Status of hvdc links
Status of hvdc linksStatus of hvdc links
Status of hvdc links
 
Engage with...Network Rail
Engage with...Network RailEngage with...Network Rail
Engage with...Network Rail
 
HVDC Transimmison Systems
HVDC Transimmison SystemsHVDC Transimmison Systems
HVDC Transimmison Systems
 
HVDC presentation
HVDC presentationHVDC presentation
HVDC presentation
 
Hesham Saafan C.V.1
Hesham Saafan C.V.1Hesham Saafan C.V.1
Hesham Saafan C.V.1
 
Mje transmission line 3 q - gp
Mje transmission line   3 q - gpMje transmission line   3 q - gp
Mje transmission line 3 q - gp
 
hendrik cv 3
hendrik cv 3hendrik cv 3
hendrik cv 3
 
Hvdc stations
Hvdc stationsHvdc stations
Hvdc stations
 
HVDC TRANSMISSION.pptx
HVDC TRANSMISSION.pptxHVDC TRANSMISSION.pptx
HVDC TRANSMISSION.pptx
 
Hydropower
HydropowerHydropower
Hydropower
 
Mankotia ankit
Mankotia ankitMankotia ankit
Mankotia ankit
 
HVDC Interconnections: Scaling-up Electricity Trade
HVDC Interconnections: Scaling-up Electricity TradeHVDC Interconnections: Scaling-up Electricity Trade
HVDC Interconnections: Scaling-up Electricity Trade
 
Lecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdfLecture Note 2_2023A Power Systems II (PWRS 201).pdf
Lecture Note 2_2023A Power Systems II (PWRS 201).pdf
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015John Paul Hitt 10-20-2015
John Paul Hitt 10-20-2015
 

Último

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 

Último (20)

Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 

PECO projects in Philadelphia

  • 1. Philadelphia Electric Transmission & Distribution System Investments Behind the scenes at the facilities that keep the lights on in the city Summer 2009
  • 2. Meeting the electric needs of Philadelphia with new, rebuilt and larger electric substations $160 million in the city’s electric infrastructure to ensure reliability for current and future energy demand Tuna Substation in Northern Liberties (2005) Waverly substation in Center City (2007) Southwark substation in South Philadelphia/Navy Yard (2008) Tunnel substation in University City (Spring 2009) Schuylkill & Grays Ferry tr substations in South Philadelphia (Summer/Fall 2009) These are part of a network of 20 electric substations that make up the Center City transmission system Near future: Penrose (2011) and Peltz (2013) substations planned in near future 2
  • 3. New Southwark distribution Substation $18 million capital investment Install new 69/13kV duplex substation adjacent to existing substation • New control house • Two 62MVA 69/13kV transformers • 13kV switchgear for 3 distribution busses • 5 new distribution circuits 3
  • 5. New Transformer w/ Firewall 5
  • 7. Tunnel Substation $25 million capital investment New 220/13kV - 62MVA substation Located along Schuylkill River on University of Pennsylvania campus • Meet substantial new electric demand in University City • Two (2) 62MVA 220/13kV transformers • Eight (8) 13kV distribution circuits − Ultimate capacity of 12 circuits • Nine (9) MVAR capacitor bank • Taps the 220-27 line between Parrish & Grays Ferry • Benefits − Relieves 40MVA load on facilities east of Schuylkill River − Improved reliability in West Philadelphia − Provides additional capacity to University City area − Begins the retirement of Schuylkill 13kV substation 7
  • 8. Tunnel Substation – April 2008 8
  • 10. Tunnel Substation – Boring Operation 10
  • 11. Tunnel Substation – North Bore Ducts 11
  • 12. 12
  • 13. 13
  • 14. 14
  • 15. 15
  • 16. 16
  • 17. 17
  • 18. 18
  • 19. 19
  • 20. Schuylkill & Grays Ferry Transmission substations $18 million upgrades to Schuylkill substation • Major transmission supply for Center City • Modernizes existing facilities • Rebuilding electrical facilities on same site as existing sub • Replace 12 69kV breakers, disconnects, insulators, and bus work at the North and Center rings • Install 4 new 69kV breakers to tie in with Grays Ferry • Relocate controls from the neighboring generating station to newly installed control houses (North and East yards) $22 million Grays Ferry expansion • Increased electric transmission capacity for improved reliability and operational flexibility • Install 230-kv/69-kv transformer • Install new 69kV transmission line from Grays Ferry to Schuylkill Center ring • Install new 230kV breakers, upgrade existing breakers, and reconfigure Grays Ferry bus into ring bus Connect fiber optic rings • Schuylkill and Grays Ferry & Waverly, Lombard, and Penn 20
  • 23. New Breaker &Associated Bus Work 23
  • 25. 25
  • 26. 26
  • 27. 27
  • 29. 29
  • 30. 30
  • 31. 31
  • 32. 32
  • 33. Additional City Investments $1.5 million replacement of automated switches for three Center City distribution networks Replacement of vacuum circuit breakers • Multi-year commitment to replace outdated VCBs and install fiber for enhanced communications and operations in Center City $2 million for relocation of utility facilities for city’s South Street Bridge replacement • Relocation of manholes & ducts for construction • Installation of ducts in new bridge Aerial and underground distribution improvements in Germantown, Overbrook, Mt. Airy, Chestnut Hill, Walnut Street, Hunting Park Planned retirement of Southwark, Delaware and Schuylkill 13-kv substations in near future (within five year plan) 33