SlideShare una empresa de Scribd logo
1 de 41
Descargar para leer sin conexión
Belagavi - 590018
Technical Seminar On
BANDRABANDRA--WORLI SEAWORLI SEA
LINKLINK
Visvesvaraya Technological University
LINKLINK
By:
KAVYA HULLUR
(USN : 2VX19CSE05)
Under the Guidance
Prof. KIRAN MALIPATIL
DEPARTMENT OF CIVIL ENGINEERING
VTU BELAGAVI. 2
CONTENTS
 Introduction
 Location
 Objectives
 Sequence of the project
 Characteristics
 Main components Main components
 Foundation and substructure construction
 Superstructure construction
 Cable stayed bridge
 Loading
 Conclusion
 References
INTRODUCTION
 The Bandra-Worli Sea Link, officially called Rajiv
Gandhi Sea Link, is a cable-stayed bridge with pre-
stressed concrete-steel viaducts on either side that
links Bandra in the Western Suburbs of Mumbai with
Worli in South Mumbai across the Mahim Bay.
 Bandra-Worli Sea Link is the longest sea bridge of
india.
 Designed By : Sheshadri Srinivasan(Structural
engineer ).
 Commissioned By : Maharashtra State Road
Development Corporation.
Cont..
 Constructed By : Hindustan Construction company,
India ( HCC)
 The foundation stone was laid in 1999,Construction
started on 2000, opened to the public on 30 June
2009, all eight lanes were opened on 24 March 2010.2009, all eight lanes were opened on 24 March 2010.
 The original plan estimated the cost at ₹6.6 billion to
be completed in five years but the project was
subjected to numerous public interest litigations, with
the 5 year delay resulting in the cost escalating to ₹16
billion .
LOCATION
Side view of main cable stayed Front view of main cable stayed
OBJECTIVES
 To reduce the traffic flow along the corridor of Mumbai.
 The sea link reduces travel time between Bandra and
Worli during peak hours from 20-30 minutes to 10
minutes.
 Estimated savings in fuel and vehicle operating cost is
around $ 16.2 million .
 Reduced accidents, noise pollution and air pollution .
Official Name Rajiv Gandhi Sea Link
Carries 8 lane of traffic
Design cable-stayed , concrete-steel
precast viaducts
Total length 5.6 kilometers (3.5 miles)
CHARACTERISTICS
Total length 5.6 kilometers (3.5 miles)
Width 2x20 meters (66 ft)
Height 126 meters (413 ft)
Longest span 2x250 meters (820ft)
Toll System Automated 16-Lane Toll Plaza
CONSTRUCTION
Foundation and Substructure
 The foundations being the most important elements of the
bridge, it’s also one of the most challenging activities at
the project due to geological conditions.
 All the Piles in the Project are vertical and cast-in-situ All the Piles in the Project are vertical and cast-in-situ
permanent steel liners and are friction and end-bearing
type of Piles.
 The foundations were designed by Lachel Felice. The
drilled shaft method construction was used to for the
shafts.
Process of driving piles
 The piles are driven with RCD Rigs mounted on the
Jack up Platforms.Construction of cofferdam followed
by the placement of tremie seal after the dewatering is
Process
required for the erection of a pile.
 Concrete produced at the Batching Plant under
controlled conditions is transported by agitator drums
on concrete barges and is placed at the required
location using Concrete Pumps.
 Number of Piles from P1 to P18
and P20 to P60 are 4and each are of
diameter 1500mm except for P17,
P18, P20 and P21 which has Piles
of diameter 2000mm.
 The number of Piles for P19 is 52
including both north and south
Constructed piers
including both north and south
carriageways, and the diameter for
each Pile is 2000mm.
 Lastly, P27 and P30 have 6 Piles
each of diameter 2000mm, this
includes both carriageways. The
depth of each Pile varies from
5.15m to 663.4m at P19.
Construction of foundation below the
cable stayed portion
RCD Drill Bit used in RCD Rigs for
foundation construction
 The Piers for the bridge are hollow but the Piercaps
are solid mass of concrete.Prefabricated reinforcement
cages are brought at site for the construction of the
piers and sacrificial concrete lines are installed with a
Pile cap and Pier
SUB STRUCTURE CONSTRUCTION
piers and sacrificial concrete lines are installed with a
top cover so as to create the hollow part inside them.
 Once inner liners are installed the cage is aligned in
the position and placed as requisite and concreting is
done after installing the outer form. The recess for
bearing installation is cast with Pier cap.
Pile Cap Reinforcement
Cross section of pier
The formwork for the Sub structure Completion of pierThe formwork for the Sub structure
construction
Completion of pier
Constructed piers
SUPER STRUCTURE CONSTRUCTION
Segments
 The segments are cast at a centralized pre-casting
yard using short line method of casting, which means
once a segment is casted its conjugate segment isonce a segment is casted its conjugate segment is
casted right after it so as the two of them matches.
 A typical 50m span comprises of 15 numbers of
precast segments.
 The segment weights vary from 110 tons to 140 tons
per segment. The segment length varies from 3000 mm
to 3200 mm.
Segment being cast and its conjugate
Segment being taken from the casting yard
to jetty
Top View of the Casting Yard Erection gantry
The details of the Erection Gantry
CABLE STAYED BRIDGE
Complete cable stayed bridge at Bandra-side of the Sea Link
Cable stayed bridge construction can be divided
among following components:
 Construction of foundation
 Construction of Tower or Pylon below deck
 Construction of Diaphragm
 Construction of Pier Table
 Construction of Tower or Pylon above deck
 Erection of Deck and Stay Cables
 Stressing of Stay Cables
 Wet Joint Construction
 Continuity PT and Grouting of Cables
 Force adjustment and fine tuning.
 Construction of foundation
The P19 Pylon of Bandra Worli Sea Link stands on a
foundation comprising of 52 nos. M50 Piles, each of 2m
diameters.
 Construction of Tower or Pylon below deck
The construction of Pylon below includes 6 lifts of M60 grade
concrete each of 3.0m and 1 lift of 3.260m. The rebar layout for
every leg is predesigned and the steel bars are being cut and bent as
per the requirements of the prefabricated reinforcement cages at the
rebar fabrication yard.
Construction process of pylon
 Construction of Pier Table
The Pire Table constitutes the cast-in-situ diaphragms,
adjacent segments and segments between and outside Tower
Legs.
Construction of Tower or Pylon above deck
The following wind speeds are
binding according to the static
calculations:
 During working and
climbing process:
Max wind speed = 70kmph
Bandra cable stayed
Max wind speed = 70kmph
 Wind speed-exceeding
70kmph:
All working and climbing
process to be stopped
 Wind speed-exceeding
100kmph:
Close formwork
 Erection of Deck and Stay Cables
 The deck or road bed is the roadway surface of a cable-stayed
bridge.
 Dead loads are taken to be just the weight of the precast deck
section; any reinforcing steel is assumed to be accounted for by the
increased density of the concrete.
 Density of reinforced concrete = 2400 kg/m3=24 KN/m3
 Cross-sectional deck area =7.2m2 Cross-sectional deck area =7.2m2
 Force per unit length on deck=Density × Area=24 × 7.2=172.8
KN/m
Deck Cross Section
Cables
 Each cable consists a group of steel wires ( 6 wires ) has a diameter
7mm with a breaking limit of 6.28 Tonnes.
 Group of these wires was packed in two layers of HDPE (High
Density Poly Ethylene) material, Six different sizes of cables were
used in the cable stayed portion. The difference between them was
only on the basis of number of steel wires in each cable. Six different
types used were of 61, 73, 85,91, 109 and 121 steel wires.
.
C/S of Worli cable stayed tower
 The cable-stayed portion of the Bandra channel is 600 meters in
overall length between expansion joints and consists of two 250-meter
cable supported main spans flanked by 50 meters conventional
approach spans. A centre tower, with an overall height of 128 meters
above pile cap level with inverted Y shape.
Worli cable stayed tower
Bandra cable stayed tower
 The cable-stayed portion of the Worli channel is 350 meters in
overall length between expansion joints and consists of one 150
meters cable supported main span flanked by two 50 meters
conventional approach spans. A centre tower, with an overall height
of 55 meters, supports the superstructure above the pile cap level
with inverted I shape.
Worli cable stayed tower
Loading
 Dead Loads
 Super-imposed Dead Load
 Live Traffic Loading
1. HA : HA is the combination of the effects of a
UDL over a notional lane and a knife-edge load place
at the most critical point within this lane.at the most critical point within this lane.
2. HB : HB loading takes account of a particularly
large truck placed at the most critical point along the
bridge.
 Wind Loading
 Seismic Loading
 Natural Frequency
Loading Calculations
Loads Factors Value
Dead 1.05 177.9kN/m
Super-imposed
Dead
1.75 178.5kN/m
HA 1.5 13.5kN/m
HB 1.3 45 units,
nominally
146.3kN per
wheel
CONCLUSION
 Having studied the Bandra Worli Sea Link in depth
we can appreciate that it is a worthy representation of
current bridge engineering technology and a good
example of what is possible in the current climate.
 The optimised execution of the inverted Y design of The optimised execution of the inverted Y design of
the pylon is a solution that is both aesthetically and
technically successful.
 The use of tensioning mechanisms has provided an
efficient compromise between deck sizing and costly
strengthening methods.
REFERENCES
 Bandra–Worli Sea Link – Wikipedia.
 Modal Analysis of Cable Stayed Bridge (Bandra-Worli Sea
Link) using ANSYS IJSRD - International Journal for
Scientific Research & Development Vol. 4, Issue 03, 2016.
 Case Study of Bandra-Worli Sea Link by K.K.Wagh Case Study of Bandra-Worli Sea Link by K.K.Wagh
Polytechnic Nashik.
 https://www.flickr.com/groups/bandra-worli-sealink/pool/
Bandra Worli sea link

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdf
 
Bandra worli sealink pdf
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdf
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Construction challenge of bridge in hilly areas
 Construction challenge of bridge in hilly areas Construction challenge of bridge in hilly areas
Construction challenge of bridge in hilly areas
 
Underground construction
Underground constructionUnderground construction
Underground construction
 
Foot bridge presentation
Foot bridge presentationFoot bridge presentation
Foot bridge presentation
 
Different types of bridges or innovative bridges in india
Different types of bridges or innovative bridges in indiaDifferent types of bridges or innovative bridges in india
Different types of bridges or innovative bridges in india
 
Chenab Railway Bridge
Chenab Railway BridgeChenab Railway Bridge
Chenab Railway Bridge
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminar
 
Bridges lecture 101
Bridges lecture 101Bridges lecture 101
Bridges lecture 101
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
Namaste tower final ppt
Namaste tower final pptNamaste tower final ppt
Namaste tower final ppt
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
 
Golden gate bridge
Golden gate bridgeGolden gate bridge
Golden gate bridge
 
Peb ss
Peb ssPeb ss
Peb ss
 
Susppension bridges
Susppension bridges Susppension bridges
Susppension bridges
 
Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acp
 
Long Span Building Construction
Long Span Building ConstructionLong Span Building Construction
Long Span Building Construction
 
Metro ppt - copy
Metro ppt - copyMetro ppt - copy
Metro ppt - copy
 

Similar a Bandra Worli sea link

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracturekhushal tadas
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge Taseem mir
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note FinalMohamed Elfike
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxRajeshKumar25548
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPANfaishalniet
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridgejaiveer singh
 
Bhupen hazarika setu
Bhupen hazarika setuBhupen hazarika setu
Bhupen hazarika setuRatulDas36
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Rajesh Prasad
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...IEI GSC
 

Similar a Bandra Worli sea link (20)

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
report
reportreport
report
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge
 
Chenab bridge ppt
Chenab bridge pptChenab bridge ppt
Chenab bridge ppt
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note Final
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridge
 
Bhupen hazarika setu
Bhupen hazarika setuBhupen hazarika setu
Bhupen hazarika setu
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
 

Último

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Último (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Bandra Worli sea link

  • 1.
  • 2. Belagavi - 590018 Technical Seminar On BANDRABANDRA--WORLI SEAWORLI SEA LINKLINK Visvesvaraya Technological University LINKLINK By: KAVYA HULLUR (USN : 2VX19CSE05) Under the Guidance Prof. KIRAN MALIPATIL DEPARTMENT OF CIVIL ENGINEERING VTU BELAGAVI. 2
  • 3.
  • 4. CONTENTS  Introduction  Location  Objectives  Sequence of the project  Characteristics  Main components Main components  Foundation and substructure construction  Superstructure construction  Cable stayed bridge  Loading  Conclusion  References
  • 5. INTRODUCTION  The Bandra-Worli Sea Link, officially called Rajiv Gandhi Sea Link, is a cable-stayed bridge with pre- stressed concrete-steel viaducts on either side that links Bandra in the Western Suburbs of Mumbai with Worli in South Mumbai across the Mahim Bay.  Bandra-Worli Sea Link is the longest sea bridge of india.  Designed By : Sheshadri Srinivasan(Structural engineer ).  Commissioned By : Maharashtra State Road Development Corporation.
  • 6. Cont..  Constructed By : Hindustan Construction company, India ( HCC)  The foundation stone was laid in 1999,Construction started on 2000, opened to the public on 30 June 2009, all eight lanes were opened on 24 March 2010.2009, all eight lanes were opened on 24 March 2010.  The original plan estimated the cost at ₹6.6 billion to be completed in five years but the project was subjected to numerous public interest litigations, with the 5 year delay resulting in the cost escalating to ₹16 billion .
  • 8. Side view of main cable stayed Front view of main cable stayed
  • 9. OBJECTIVES  To reduce the traffic flow along the corridor of Mumbai.  The sea link reduces travel time between Bandra and Worli during peak hours from 20-30 minutes to 10 minutes.  Estimated savings in fuel and vehicle operating cost is around $ 16.2 million .  Reduced accidents, noise pollution and air pollution .
  • 10.
  • 11. Official Name Rajiv Gandhi Sea Link Carries 8 lane of traffic Design cable-stayed , concrete-steel precast viaducts Total length 5.6 kilometers (3.5 miles) CHARACTERISTICS Total length 5.6 kilometers (3.5 miles) Width 2x20 meters (66 ft) Height 126 meters (413 ft) Longest span 2x250 meters (820ft) Toll System Automated 16-Lane Toll Plaza
  • 12.
  • 13. CONSTRUCTION Foundation and Substructure  The foundations being the most important elements of the bridge, it’s also one of the most challenging activities at the project due to geological conditions.  All the Piles in the Project are vertical and cast-in-situ All the Piles in the Project are vertical and cast-in-situ permanent steel liners and are friction and end-bearing type of Piles.  The foundations were designed by Lachel Felice. The drilled shaft method construction was used to for the shafts.
  • 15.  The piles are driven with RCD Rigs mounted on the Jack up Platforms.Construction of cofferdam followed by the placement of tremie seal after the dewatering is Process required for the erection of a pile.  Concrete produced at the Batching Plant under controlled conditions is transported by agitator drums on concrete barges and is placed at the required location using Concrete Pumps.
  • 16.  Number of Piles from P1 to P18 and P20 to P60 are 4and each are of diameter 1500mm except for P17, P18, P20 and P21 which has Piles of diameter 2000mm.  The number of Piles for P19 is 52 including both north and south Constructed piers including both north and south carriageways, and the diameter for each Pile is 2000mm.  Lastly, P27 and P30 have 6 Piles each of diameter 2000mm, this includes both carriageways. The depth of each Pile varies from 5.15m to 663.4m at P19.
  • 17. Construction of foundation below the cable stayed portion RCD Drill Bit used in RCD Rigs for foundation construction
  • 18.  The Piers for the bridge are hollow but the Piercaps are solid mass of concrete.Prefabricated reinforcement cages are brought at site for the construction of the piers and sacrificial concrete lines are installed with a Pile cap and Pier SUB STRUCTURE CONSTRUCTION piers and sacrificial concrete lines are installed with a top cover so as to create the hollow part inside them.  Once inner liners are installed the cage is aligned in the position and placed as requisite and concreting is done after installing the outer form. The recess for bearing installation is cast with Pier cap.
  • 21. The formwork for the Sub structure Completion of pierThe formwork for the Sub structure construction Completion of pier Constructed piers
  • 22. SUPER STRUCTURE CONSTRUCTION Segments  The segments are cast at a centralized pre-casting yard using short line method of casting, which means once a segment is casted its conjugate segment isonce a segment is casted its conjugate segment is casted right after it so as the two of them matches.  A typical 50m span comprises of 15 numbers of precast segments.  The segment weights vary from 110 tons to 140 tons per segment. The segment length varies from 3000 mm to 3200 mm.
  • 23. Segment being cast and its conjugate Segment being taken from the casting yard to jetty
  • 24. Top View of the Casting Yard Erection gantry
  • 25. The details of the Erection Gantry
  • 26. CABLE STAYED BRIDGE Complete cable stayed bridge at Bandra-side of the Sea Link
  • 27. Cable stayed bridge construction can be divided among following components:  Construction of foundation  Construction of Tower or Pylon below deck  Construction of Diaphragm  Construction of Pier Table  Construction of Tower or Pylon above deck  Erection of Deck and Stay Cables  Stressing of Stay Cables  Wet Joint Construction  Continuity PT and Grouting of Cables  Force adjustment and fine tuning.
  • 28.  Construction of foundation The P19 Pylon of Bandra Worli Sea Link stands on a foundation comprising of 52 nos. M50 Piles, each of 2m diameters.
  • 29.  Construction of Tower or Pylon below deck The construction of Pylon below includes 6 lifts of M60 grade concrete each of 3.0m and 1 lift of 3.260m. The rebar layout for every leg is predesigned and the steel bars are being cut and bent as per the requirements of the prefabricated reinforcement cages at the rebar fabrication yard. Construction process of pylon
  • 30.  Construction of Pier Table The Pire Table constitutes the cast-in-situ diaphragms, adjacent segments and segments between and outside Tower Legs.
  • 31. Construction of Tower or Pylon above deck The following wind speeds are binding according to the static calculations:  During working and climbing process: Max wind speed = 70kmph Bandra cable stayed Max wind speed = 70kmph  Wind speed-exceeding 70kmph: All working and climbing process to be stopped  Wind speed-exceeding 100kmph: Close formwork
  • 32.  Erection of Deck and Stay Cables  The deck or road bed is the roadway surface of a cable-stayed bridge.  Dead loads are taken to be just the weight of the precast deck section; any reinforcing steel is assumed to be accounted for by the increased density of the concrete.  Density of reinforced concrete = 2400 kg/m3=24 KN/m3  Cross-sectional deck area =7.2m2 Cross-sectional deck area =7.2m2  Force per unit length on deck=Density × Area=24 × 7.2=172.8 KN/m Deck Cross Section
  • 33. Cables  Each cable consists a group of steel wires ( 6 wires ) has a diameter 7mm with a breaking limit of 6.28 Tonnes.  Group of these wires was packed in two layers of HDPE (High Density Poly Ethylene) material, Six different sizes of cables were used in the cable stayed portion. The difference between them was only on the basis of number of steel wires in each cable. Six different types used were of 61, 73, 85,91, 109 and 121 steel wires. .
  • 34.
  • 35. C/S of Worli cable stayed tower
  • 36.  The cable-stayed portion of the Bandra channel is 600 meters in overall length between expansion joints and consists of two 250-meter cable supported main spans flanked by 50 meters conventional approach spans. A centre tower, with an overall height of 128 meters above pile cap level with inverted Y shape. Worli cable stayed tower Bandra cable stayed tower  The cable-stayed portion of the Worli channel is 350 meters in overall length between expansion joints and consists of one 150 meters cable supported main span flanked by two 50 meters conventional approach spans. A centre tower, with an overall height of 55 meters, supports the superstructure above the pile cap level with inverted I shape. Worli cable stayed tower
  • 37. Loading  Dead Loads  Super-imposed Dead Load  Live Traffic Loading 1. HA : HA is the combination of the effects of a UDL over a notional lane and a knife-edge load place at the most critical point within this lane.at the most critical point within this lane. 2. HB : HB loading takes account of a particularly large truck placed at the most critical point along the bridge.  Wind Loading  Seismic Loading  Natural Frequency
  • 38. Loading Calculations Loads Factors Value Dead 1.05 177.9kN/m Super-imposed Dead 1.75 178.5kN/m HA 1.5 13.5kN/m HB 1.3 45 units, nominally 146.3kN per wheel
  • 39. CONCLUSION  Having studied the Bandra Worli Sea Link in depth we can appreciate that it is a worthy representation of current bridge engineering technology and a good example of what is possible in the current climate.  The optimised execution of the inverted Y design of The optimised execution of the inverted Y design of the pylon is a solution that is both aesthetically and technically successful.  The use of tensioning mechanisms has provided an efficient compromise between deck sizing and costly strengthening methods.
  • 40. REFERENCES  Bandra–Worli Sea Link – Wikipedia.  Modal Analysis of Cable Stayed Bridge (Bandra-Worli Sea Link) using ANSYS IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 03, 2016.  Case Study of Bandra-Worli Sea Link by K.K.Wagh Case Study of Bandra-Worli Sea Link by K.K.Wagh Polytechnic Nashik.  https://www.flickr.com/groups/bandra-worli-sealink/pool/