Control Costs: Tools and Techniques
1
Earned value management is a methodology that combines scope, schedule, and resource
measurements to assess project performance and progress. Using earned value management helps
the team understand whether they are on target for costs or schedule per the project plan. It compares
planned vs. actuals. It uses the cost, scope and schedule baselines to form the performance baseline,
which helps the project management team assess and measure project performance and progress.
Let’s go into more detail about each of the earned value formulas and what each one is used for and how
to remember them. Consider starting to practice a “brain dump sheet,” where you write down all the
formulas and other information you need to remember for the exam. Make sure you practice writing down
each formula name and the actual formula, until it becomes rote memory.
Here are some definitions in earned value management:
1
Budget at completion (BAC): The total budget for the project or the sum of all budgets established
for the work to be performed.
1
Planned value (PV): The value of the work you plan on completing during a specific period of time in
the project schedule. Or it’s the authorized budget assigned to scheduled work.
1
Earned value (EV): The value of work that’s actually been performed or completed. Or it’s a measure
of work performed expressed in terms of the budget authorized for work.
1
Actual cost (AC): The actual money spent on the project at a given point in time. Or it’s the realized
cost incurred for the work performed on an activity during a specific time period.
Tip: In order to calculate the earned value formulas, you only need to get values for each of the items
above. Once you have the four values above, you can calculate any of the EV formulas. It’s just a matter of
plugging in the values and solving the formula.
Variances from the approved baseline are measured with the following:
1
Schedule variance (SV): The difference between the work you planned to do and what you actually
did (planned vs. actuals) at a specific point in time. It’s a measure of schedule performance expressed
as the difference between the earned value and the planned value. It is the amount by which the
project is ahead or behind the planned delivery date, at a given point in time.
1
Cost variance (CV): The difference between the costs you planned to spend and what you actually
spent (planned vs. actuals) at a specific point in time. It’s the amount of budget deficit or surplus at a
given point in time, expressed as the difference between earned value and actual cost.
1
Schedule performance index (SPI): Measures the efficiency of the work put into the project at a
specific point in time. It’s a measure of schedule efficiency expressed as a ratio of earned value to
planned value. It measures how well the project team is using its time.
Cert Prep: Project Management Professional (PMP)® (2018)
with Sandra Mitchell
PMP® Certification Exam Preparation with Sandra Mitchell
2 of 7
1
Cost performance index (CPI): Measures the efficiency of the money spent on the project at a
specific point in time. It’s a measure of cost efficiency of budgeted resources, expressed as a ratio
of earned value to actual cost. It’s considered the most critical EVM metric and measures the cost
efficiency of the work completed.
There are a few values used for forecasting:
1
Estimate at completion (EAC): Based on project performance, the cost at the end of the project may
be more or less than what was budgeted (BAC). EAC will tell you the cost estimate based on how the
team is performing now. The expected total cost of completing all work expressed as the sum of the
actual cost to date and the estimate to complete.
1
Estimate to completion (ETC): Takes into consideration what you’ve spent to date, then evaluates
team performance, and then provides a cost of how much the remaining work will cost to complete.
The expected cost to finish all the remaining project work.
1
Variance at completion (VAC): Calculates the difference between the BAC and what you expect
to spend (EAC). A projection of the amount of budget deficit or surplus, expressed as the difference
between the budget at completion and the estimate at completion.
The final earned value forecast looks at how the project needs to handle cost performance to meet
original goals:
1
To-complete performance index (TCPI) Measure of the cost performance that is required to be achieved
with the remaining resources in order to meet a specified management goal, expressed as a ratio of the
cost to finish the outstanding work to the remaining budget.
1These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
PMP® Certification Exam Preparation with Sandra Mitchell
3 of 7
In this table, you’ll see each earned value term, abbreviation, formula, and description.
Term Abbrev Formula Description
Budgeted at
Completion
BAC The sum of all budgets established
for the work to be performed
The total budget originally
allocated for this project
Actual Cost AC The realized cost incurred for the
work performed on an activity
during a specific period of time
The total costs spent during a
specific period of time
Earned Value EV EV=Actual % Complete x BAC The planned value of all the work
completed (earned) to a point in
time
Planned
Value
PV PV=Planned % Complete x BAC The value of the work planned to
be completed to a point in time
Cost Variance CV CV=EV-AC The difference between the value
of work completed to a point in
time, and the actual costs to the
same point in time
Schedule
Variance
SV SV=EV-PV The difference between the work
completed to a point in time, and
the work planned to be completed
at the same point in time
Cost
Performance
Index
CPI CPI=EV/AC Measures the cost efficiency of
budgeted resources at a specific
point in time
Schedule
Performance
Index
SPI SPI=EV/PV Measures the schedule efficiency
at a specific point in time
Estimate at
Completion
EAC EAC=BAC/CPIC
The expected total cost of
completing all work
Estimate to
Completion
ETC ETC=EAC-AC The expected cost to finish all the
remaining project work
Variance at
Completion
VAC VAC=BAC-EAC The estimated difference in cost at
the completion of the project
<1=bad
1=on track
>1=good
<1=bad
1=on track
>1=good
PMP® Certification Exam Preparation with Sandra Mitchell
4 of 7
Term Abbrev Formula Description
To-Complete
Performance
Index
TCPIc
TCPIc
=(BAC-EV)/(BAC-AC)
or
(BAC-EV)/remaining funding
<1 is good is this case because you
have the space to spend more
The efficiency that must be
maintained in order to complete
on plan
Next, I’ve provided an example that you can use to practice applying these formulas. The first thing you
want to do is calculate the first four values: BAC, AC, EV, and PV.
Example: You have a project to install 10 hair dryers in a salon. The cost per hair dryer is $2,750 and the
project will last 10 weeks. At week 5, six hair dryers were installed and you’ve spent $15,500.
Budgeted at Completion $27,500
Actual Cost $15,500
Earned Value Actual % Complete x BAC $16,500
Planned Value Planned % Complete x BAC $13,750
Cost Variance EV-AC $1,000
Schedule Variance EV-PV $2,750
Cost Performance Index EV/AC 1.06
Schedule Performance Index EV/PV 1.2
Estimate at Completion EAC=BAC/CPI $25,943.39
Estimate to Completion ETC=EAC-AC $10,443.39
Variance at Completion VAC=BAC-EAC $1,556.61
To-Complete Performance Index (BAC-EV)/(BAC-AC) 0.91666
PMP® Certification Exam Preparation with Sandra Mitchell
5 of 7
BAC: To calculate BAC, just take 10 dryers times the cost per hair dryer ($2,750): 10(2,750)=$27,500.
AC: The next value to get is the AC, which is stated as “you’ve spent $15,500.”
EV: Now let’s calculate EV. You do this by taking Actual % Complete x BAC. To calculate the actual %
complete, take the number of hair dryers installed (6) and divide by the total number of hair dryers to
install (10): 6/10=.60. Then apply the formula: .60 x $27,500=$16,500. This is the value you’ve earned at
this point in the project.
PV: Now let’s calculate PV. You do this by taking Planned % Complete x BAC. To calculate the planned %
complete, take the number of hair dryers that were supposed to be installed by week 5 (5) and divide by
the total number of hair dryers to install (10): 5/10=.50. Then apply the formula: .50 x $27,500=$13,750.
This is the planned value at this point in the project.
Now you have all the values needed to complete the rest of the equations! Let’s move on to the rest of
the formulas.
CV: Calculated by taking EV-AC: 16,500-15,500=$1,000. Notice that this is a positive number. This is
good because you’ve spent less money than what you planned to spend at this point in the project.
SV: Calculated by taking EV-PV: 16,500-13,750=$2,750. Notice that this is a positive number. This is good
because you’ve installed more hair dryers than what you planned at this point in the project.
Tip: For any CV or SV value:
•	 >$1 is good as you’re getting more value out of your money or time.
•	 <$1 is bad as you’re getting less value out of your money or time.
•	 =$1 you’re right on target with costs and time.
CPI: Calculated by taking EV/AC: 16,500/15,500=1.06. This is good. What this means is that for every
$1.00 spent, you are getting $1.06 worth of value. You are getting more for your dollar.
SPI: Calculated by taking EV/PV: 16,500/13,750=1.2. This is good. What this means is that for every 1 hour
worked, you are getting 1.2 hours worth of work done. You are getting more for your time.
Tip: For any CPI or SPI index value:
•	 >1 is good as you’re getting more value out of your money or time.
•	 <1 is bad as you’re getting less value out of your money or time.
•	 =1 you’re right on target with costs and time.
The following formulas are used for forecasting:
EAC: Calculated by BAC/CPI: 27,500/1.06=$25,943.39. This means if the project continues performing, as
it is now, that the total cost of the project at completion will be $25,943.39. This is great news because the
BAC was set at $27,500. The sponsor will pay less than planned for the project.
ETC: Calculated by EAC-AC: 25,943.39-15,500=$10,443.39. What this does is looks at what you’ve
already spent (AC) and what you estimate to spend at completion (EAC) and, subtracts them so you end
up with an amount you’ll spend from now until the end of the project.
PMP® Certification Exam Preparation with Sandra Mitchell
6 of 7
VAC: Calculated by BAC-EAC: 27,500-25,943.39=$1,556.61. This tells you the difference between what
was budgeted (BAC) and what you’ll actually spend on the project (EAC).
TCPI: Calculated by (BAC-EV)/(BAC-AC) (original budget) or (BAC-EV)/(EAC-AC) (current forecast).
(27,500-16,500)/(27,500-15,500)=11,000/12,000=0.91666. This is good. The amount of effort to complete
the project on plan is less than 1. The project team doesn’t have to work as hard to complete the project
per plan. They may even finish early if they choose to.
Tip: This calculation is the exception when it comes to the indices. You want this number to be =/-1
because this measures the amount of effort needed to achieve the schedule or financial goals. Let’s say
the value was 2. This means the project team would have to put in twice the effort to complete the project
on plan.
•	 >1 is bad.
•	 <1 is good.
•	 =1 you’re right on target.
Tip: Here’s a way that might help you remember these four formulas. First, put them in alphabetical order
by pairs: CV, SV, CPI, SPI.
CV=EV-AC
SV=EV-PV
CPI=EV/AC
SPI=EV/PV
•	 Notice that they each start with EV.
•	 The first two are minus, minus.
•	 The second two are divide, divide.
•	 In alphabetical order, AC (costs) comes before PV (schedule). So it’s AC, PV, AC, PV. When you
practice writing these, do it in order vertically:
Formula 1st step 2nd step 3rd step 4th step 5th step
CV=EV-AC CV EV - AC
SV=EV-PV SV EV - PV
CPI=EV/AC CPI EV / AC
SPI=EV/PV SPI EV / PV
Tip: Also, there’s somewhat of a pattern with these three formulas that might help you remember them
when you practice for your dump sheet. First, put them in alphabetical order.
PMP® Certification Exam Preparation with Sandra Mitchell
7 of 6
EAC=BAC/CPI
ETC=EAC-AC
VAC=BAC-EAC
Next, if you look at them like it’s a tic-tac-toe board, notice how EAC starts in the upper-left corner, then
goes to the middle and then to the bottom-right corner.
Then BAC is on the top and the bottom. Remember to divide, then minus, minus. The last two you just
need to remember, no tricks: CPI and then AC. This helped me; maybe it’ll help you too!

Más contenido relacionado

La actualidad más candente

Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
constructioninside
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
Paul King
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
Fahad Ali
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 

La actualidad más candente (19)

PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value
Earned valueEarned value
Earned value
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 

Similar a 09 05 control costs tools and techniques

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
Nita Cristian
 

Similar a 09 05 control costs tools and techniques (20)

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Earned value management
Earned value managementEarned value management
Earned value management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 

Último

Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 

Último (20)

Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 

09 05 control costs tools and techniques

  • 1. PMP® Certification Exam Preparation with Sandra Mitchell 1 of 6 Control Costs: Tools and Techniques 1 Earned value management is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. Using earned value management helps the team understand whether they are on target for costs or schedule per the project plan. It compares planned vs. actuals. It uses the cost, scope and schedule baselines to form the performance baseline, which helps the project management team assess and measure project performance and progress. Let’s go into more detail about each of the earned value formulas and what each one is used for and how to remember them. Consider starting to practice a “brain dump sheet,” where you write down all the formulas and other information you need to remember for the exam. Make sure you practice writing down each formula name and the actual formula, until it becomes rote memory. Here are some definitions in earned value management: 1 Budget at completion (BAC): The total budget for the project or the sum of all budgets established for the work to be performed. 1 Planned value (PV): The value of the work you plan on completing during a specific period of time in the project schedule. Or it’s the authorized budget assigned to scheduled work. 1 Earned value (EV): The value of work that’s actually been performed or completed. Or it’s a measure of work performed expressed in terms of the budget authorized for work. 1 Actual cost (AC): The actual money spent on the project at a given point in time. Or it’s the realized cost incurred for the work performed on an activity during a specific time period. Tip: In order to calculate the earned value formulas, you only need to get values for each of the items above. Once you have the four values above, you can calculate any of the EV formulas. It’s just a matter of plugging in the values and solving the formula. Variances from the approved baseline are measured with the following: 1 Schedule variance (SV): The difference between the work you planned to do and what you actually did (planned vs. actuals) at a specific point in time. It’s a measure of schedule performance expressed as the difference between the earned value and the planned value. It is the amount by which the project is ahead or behind the planned delivery date, at a given point in time. 1 Cost variance (CV): The difference between the costs you planned to spend and what you actually spent (planned vs. actuals) at a specific point in time. It’s the amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and actual cost. 1 Schedule performance index (SPI): Measures the efficiency of the work put into the project at a specific point in time. It’s a measure of schedule efficiency expressed as a ratio of earned value to planned value. It measures how well the project team is using its time. Cert Prep: Project Management Professional (PMP)® (2018) with Sandra Mitchell
  • 2. PMP® Certification Exam Preparation with Sandra Mitchell 2 of 7 1 Cost performance index (CPI): Measures the efficiency of the money spent on the project at a specific point in time. It’s a measure of cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost. It’s considered the most critical EVM metric and measures the cost efficiency of the work completed. There are a few values used for forecasting: 1 Estimate at completion (EAC): Based on project performance, the cost at the end of the project may be more or less than what was budgeted (BAC). EAC will tell you the cost estimate based on how the team is performing now. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete. 1 Estimate to completion (ETC): Takes into consideration what you’ve spent to date, then evaluates team performance, and then provides a cost of how much the remaining work will cost to complete. The expected cost to finish all the remaining project work. 1 Variance at completion (VAC): Calculates the difference between the BAC and what you expect to spend (EAC). A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion. The final earned value forecast looks at how the project needs to handle cost performance to meet original goals: 1 To-complete performance index (TCPI) Measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as a ratio of the cost to finish the outstanding work to the remaining budget. 1These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
  • 3. PMP® Certification Exam Preparation with Sandra Mitchell 3 of 7 In this table, you’ll see each earned value term, abbreviation, formula, and description. Term Abbrev Formula Description Budgeted at Completion BAC The sum of all budgets established for the work to be performed The total budget originally allocated for this project Actual Cost AC The realized cost incurred for the work performed on an activity during a specific period of time The total costs spent during a specific period of time Earned Value EV EV=Actual % Complete x BAC The planned value of all the work completed (earned) to a point in time Planned Value PV PV=Planned % Complete x BAC The value of the work planned to be completed to a point in time Cost Variance CV CV=EV-AC The difference between the value of work completed to a point in time, and the actual costs to the same point in time Schedule Variance SV SV=EV-PV The difference between the work completed to a point in time, and the work planned to be completed at the same point in time Cost Performance Index CPI CPI=EV/AC Measures the cost efficiency of budgeted resources at a specific point in time Schedule Performance Index SPI SPI=EV/PV Measures the schedule efficiency at a specific point in time Estimate at Completion EAC EAC=BAC/CPIC The expected total cost of completing all work Estimate to Completion ETC ETC=EAC-AC The expected cost to finish all the remaining project work Variance at Completion VAC VAC=BAC-EAC The estimated difference in cost at the completion of the project <1=bad 1=on track >1=good <1=bad 1=on track >1=good
  • 4. PMP® Certification Exam Preparation with Sandra Mitchell 4 of 7 Term Abbrev Formula Description To-Complete Performance Index TCPIc TCPIc =(BAC-EV)/(BAC-AC) or (BAC-EV)/remaining funding <1 is good is this case because you have the space to spend more The efficiency that must be maintained in order to complete on plan Next, I’ve provided an example that you can use to practice applying these formulas. The first thing you want to do is calculate the first four values: BAC, AC, EV, and PV. Example: You have a project to install 10 hair dryers in a salon. The cost per hair dryer is $2,750 and the project will last 10 weeks. At week 5, six hair dryers were installed and you’ve spent $15,500. Budgeted at Completion $27,500 Actual Cost $15,500 Earned Value Actual % Complete x BAC $16,500 Planned Value Planned % Complete x BAC $13,750 Cost Variance EV-AC $1,000 Schedule Variance EV-PV $2,750 Cost Performance Index EV/AC 1.06 Schedule Performance Index EV/PV 1.2 Estimate at Completion EAC=BAC/CPI $25,943.39 Estimate to Completion ETC=EAC-AC $10,443.39 Variance at Completion VAC=BAC-EAC $1,556.61 To-Complete Performance Index (BAC-EV)/(BAC-AC) 0.91666
  • 5. PMP® Certification Exam Preparation with Sandra Mitchell 5 of 7 BAC: To calculate BAC, just take 10 dryers times the cost per hair dryer ($2,750): 10(2,750)=$27,500. AC: The next value to get is the AC, which is stated as “you’ve spent $15,500.” EV: Now let’s calculate EV. You do this by taking Actual % Complete x BAC. To calculate the actual % complete, take the number of hair dryers installed (6) and divide by the total number of hair dryers to install (10): 6/10=.60. Then apply the formula: .60 x $27,500=$16,500. This is the value you’ve earned at this point in the project. PV: Now let’s calculate PV. You do this by taking Planned % Complete x BAC. To calculate the planned % complete, take the number of hair dryers that were supposed to be installed by week 5 (5) and divide by the total number of hair dryers to install (10): 5/10=.50. Then apply the formula: .50 x $27,500=$13,750. This is the planned value at this point in the project. Now you have all the values needed to complete the rest of the equations! Let’s move on to the rest of the formulas. CV: Calculated by taking EV-AC: 16,500-15,500=$1,000. Notice that this is a positive number. This is good because you’ve spent less money than what you planned to spend at this point in the project. SV: Calculated by taking EV-PV: 16,500-13,750=$2,750. Notice that this is a positive number. This is good because you’ve installed more hair dryers than what you planned at this point in the project. Tip: For any CV or SV value: • >$1 is good as you’re getting more value out of your money or time. • <$1 is bad as you’re getting less value out of your money or time. • =$1 you’re right on target with costs and time. CPI: Calculated by taking EV/AC: 16,500/15,500=1.06. This is good. What this means is that for every $1.00 spent, you are getting $1.06 worth of value. You are getting more for your dollar. SPI: Calculated by taking EV/PV: 16,500/13,750=1.2. This is good. What this means is that for every 1 hour worked, you are getting 1.2 hours worth of work done. You are getting more for your time. Tip: For any CPI or SPI index value: • >1 is good as you’re getting more value out of your money or time. • <1 is bad as you’re getting less value out of your money or time. • =1 you’re right on target with costs and time. The following formulas are used for forecasting: EAC: Calculated by BAC/CPI: 27,500/1.06=$25,943.39. This means if the project continues performing, as it is now, that the total cost of the project at completion will be $25,943.39. This is great news because the BAC was set at $27,500. The sponsor will pay less than planned for the project. ETC: Calculated by EAC-AC: 25,943.39-15,500=$10,443.39. What this does is looks at what you’ve already spent (AC) and what you estimate to spend at completion (EAC) and, subtracts them so you end up with an amount you’ll spend from now until the end of the project.
  • 6. PMP® Certification Exam Preparation with Sandra Mitchell 6 of 7 VAC: Calculated by BAC-EAC: 27,500-25,943.39=$1,556.61. This tells you the difference between what was budgeted (BAC) and what you’ll actually spend on the project (EAC). TCPI: Calculated by (BAC-EV)/(BAC-AC) (original budget) or (BAC-EV)/(EAC-AC) (current forecast). (27,500-16,500)/(27,500-15,500)=11,000/12,000=0.91666. This is good. The amount of effort to complete the project on plan is less than 1. The project team doesn’t have to work as hard to complete the project per plan. They may even finish early if they choose to. Tip: This calculation is the exception when it comes to the indices. You want this number to be =/-1 because this measures the amount of effort needed to achieve the schedule or financial goals. Let’s say the value was 2. This means the project team would have to put in twice the effort to complete the project on plan. • >1 is bad. • <1 is good. • =1 you’re right on target. Tip: Here’s a way that might help you remember these four formulas. First, put them in alphabetical order by pairs: CV, SV, CPI, SPI. CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV • Notice that they each start with EV. • The first two are minus, minus. • The second two are divide, divide. • In alphabetical order, AC (costs) comes before PV (schedule). So it’s AC, PV, AC, PV. When you practice writing these, do it in order vertically: Formula 1st step 2nd step 3rd step 4th step 5th step CV=EV-AC CV EV - AC SV=EV-PV SV EV - PV CPI=EV/AC CPI EV / AC SPI=EV/PV SPI EV / PV Tip: Also, there’s somewhat of a pattern with these three formulas that might help you remember them when you practice for your dump sheet. First, put them in alphabetical order.
  • 7. PMP® Certification Exam Preparation with Sandra Mitchell 7 of 6 EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC Next, if you look at them like it’s a tic-tac-toe board, notice how EAC starts in the upper-left corner, then goes to the middle and then to the bottom-right corner. Then BAC is on the top and the bottom. Remember to divide, then minus, minus. The last two you just need to remember, no tricks: CPI and then AC. This helped me; maybe it’ll help you too!