December 18th , 2010 Jubail
Master Project Schedule
Development of a Level 3
Construction Schedule
2
AMTPJ Construction Schedule Level 3
1. Safety Moment
2. Schedule History-Level 2
3. Objective-Develop a Level 3 Schedule.
4. Area Plan Layouts Issue for Reviews-Links
5. P6 Plan Statistics, Basis and Validation
6. Baselining and Schedule Implementation
7. Short Term Planning, Milestones and Look Aheads
8. Plan Quantity Tracking and Resources
9. Contractor Level 3 and 4 input, implementation
10.Project Reporting, Schedule Metrics and Clients.
1) Safety moment
• All drivers to practice a defensive driving approach to and from
work.
•See attached slide re defensive driving statistics to saving lives
4
 History
• 1300 Activities and tracking Piling, Building & Equipment Foundations, MEIP with
Contractor support.
• Monthly reporting use and CP analysis with various degrees of success.
• Skill level as a tool is limited and based on long duration estimates, limited interface and
logic connections for a large construction project.
• AMJ not on board with both schedule presentation for realistic predictions to Start Up
Milestones. Looking for a more detail experienced approach to CPM through level 3,
quantity tracking, resource and budgetry control management.
• Reasons to bring on more horsepower/experience to provide added detail schedule
development, planning and constructability to the CM team.
 Issues and Concerns
• Need to develop a believable set of conditions to the Project as a whole.
• Need to develop and execute at level 3 as a minimum objective to execution.
• Need to understand the interfacing, sequencing that will allow a safe Construction using
both Contractor and Direct Labor.
• Need to understand criticality and short term gains through day to day coordination.
• Current construction team and CM finding so much interface clash with an inordinate
amount of coordination at interfaces.
• Lack of experience with tools of choice P6 Database software.
2) Schedule History Level 2
3)Objective-Develop a Level 3 Schedule
 Objective and Outline of Development
• Must deliver a level 3 schedule that has as a minimum the constructability meets all execution
strategies for the Project and has buy in by the PM, CM team, Area Managers and Contractors.
Plan before schedule that is the best way to achieve a construction plan. That means more
constructability improvements as alternate strategies at the top down.
• A minimum WBS by Unit/Process or /Sub Area/ CWP (Contractor)/Discipline. See current wbs.
• Support the overall Major Project Objectives and through a formal Management of Change
program meet all Key Project and lower level 2/3 area Milestones.
• Development Program is 1) Develop, review and issue by 30 December 2010. 2) Revise with all
current Contractor Inputs and 3)Implement a Baseline program from Jan 1st
2011.
• Establish the Areas and detail to current planners on board. Review progress 2 x weekly. Roll
out status and development to PM,CM and Construction Area Manager by 20th
December.
• Expedite all current detail design, procurement and contract data for input to schedule.
• Participate in all current supplier workshops and update the detail level 3 & 4 data into the P6
working file.
• Establish basic duration estimates from either contractor level 2 (HSH, Sinusteel) and/or
suppliers for added value to meet sequence, logic and interfaces to the schedule development.
• Ensure that schedule integrity and basis for a quality product is met ( IPA standard audit
procedures).
• Cold Eyes review if necessary to improve the product. Add more interface and sequencing.
4) Area Plan Layouts –Issue for Constructability Reviews
 P6 Layouts by Areas
• All Construction is driving the project by Area and Process line.
• The Project is not only driven by Major Equipment but is unfortunately driven by a large process
building (Main Building) and Major Equipment Foundations.
• All AREA PLANS and Process Lines rely on all purchase or contracts committed to a vendor
design, manufacture, logistics, sea transport, storage and site transport from any port of origin over
a wide world supply chain. The history and status quo has to be managed for sequential
construction and pre-staging of the project as we see it today.
• The LEVEL 3 PLAN WBS (see pdf attached) is a simple breakdown of the AREAS as follows;
• Plan1 Main Building ( including Crane rails, cranes and electrification). All
Finished Grade Slabs and Underground Services).
• Plan2 Process Lines ( 10 specific Trains or Lines).
• Plan3 Power Distribution ( Substation, E Rooms and Power Distribution
from HV SW GR and Delivery to Main Substation).
• Plan 4 Water Treatment Plant ( Areas 100 to 700).
• Plan 5 Auxiliary Buildings (between 15-18 Masonry or structural Steel
Buildings)
• Plan 6 Utilities for Inside Battery and Outside Battery Limits
• Plan 7 Main Lab Facilities and Maintenance Facilities.
• Plan 8 Other Buildings and Structures and assets that meet the scope of
the Project.
• Plan 9 Turnover, Commissioning and Start Up Systems support.
• Schedule Basis, Validation and General Integrity of the Project file. ( Includes Backup and Admin).
5) P6 Plan Statistics, Basis and Validation
 P6 Working Project File.
• Approximately 6-7000 activities at level 3 or lower to meet the execution strategy.
• Currently, no plans to develop a System Schedule for Turnover to Operations.The latter
required at or about the 50 % progress milestone.
• See statistics as a pdf copy to support the development.
• See Basis of Schedule and Validation Reports. No Risk Analysis and Schedule Reserve is
added. The latter performed by the PM for the AMJ Change Management Process.
• Frequent working file analysis to meet the integrity of the project schedule development. (Once
a month along with all Baseline procedures.)
• Critical Path Analysis to meet the optimum execution strategies.
 Concerns
• Proper data analysis and review prior to development.
• Project set up and a level 3 schedule needed all current development to be performed in
previous phase of project.
6) Baselines and Schedule Implementation
• If the Project Execution Team can approve all the current schedule development with all its
changes in strategy then a Baseline Program will be implemented.
• The current plan will then be progressed on a biweekly basis and take on a maintenance and
change management process. Baselines are made when current plan logic delays and task
durations are in error.
• Reporting on a large project is performed on a monthly basis with a internal review at mid month
to effect all changes in the Areas based on new recovery strategies.
• Planners will run biweekly update sessions with the Construction Area Managers.
• A procedure must be adhered to manage all changes and updates.
7) Short Term Planning, Milestones and Look Aheads
• Short Term Planning starts with having a short window to meet the specific objectives. This
means Construction breaking down the overall schedule ( ie Baseline1).
• Planning produces a 3 week look-ahead for each Area Manager and Construction Team,
Progress is marked up at bi-weekly sessions by the responsible Lead/ planner and returned for
update and maintenance.
• Inputs from Procurement and Engineering are also required for logical interfaces and
Equipment status.
• As a short term objective a workfront or package milestone may be set and targeted for all
teams to achieve. This is a normal practice for checks and balances if the current plan is
believable for both durations, logic and sequences. Adjustments are always necessary and
normal on out of sequence work, parallel work fronts and interface difficulties. Other concerns
are lack of resources.
 Look Aheads
• The effective short, medium and long term planning needs a 30/60/90 day look ahead in order
to progress a large project. After a constructability review process the current P6 plans will set
the respective plans and issue to all members of the project.
• The project schedule will be cut into short term periods to manage the project effectively. The
data date will be moved forward every month after all progress is maintained from Contractor
and other departments ( Engineering and Procurement being mandatory under the current
crisis).
8) Plan Quantity Tracking and Resources
• A second priority but part of the planning work to the project is to develop a resource based
plan to meet several project objectives.
• The physical progress is imperative to check a suite of schedule initiatives. S curve
management is just one metric and tool to determine both accuracy and quality to any plan.
• Quantity survey departments are required to support both contract and direct work packages.
The progressing is a benefit to the project as a whole and supports any risk or alternative action
plans.
• To resource the project requires a basis. This basis is normally in estimated quantities and/or
equivalent direct labor /craft hours. To produce a Baseline and Project Progress curve (‘S’) the
planners need to resource the level 2 activity with manhours.To be reviewed by the PM.
9) Contractor Level 3 and 4 schedules/Inputs
to the Project Master Plan
 Inputs by Contractors and Vendors
• All Contractor schedules should be managed on a MP,P6,P3 format and the current
live files issued to the Project Master plan on or before the month end cycle drop dead
dates. A monthly calendar set of 2011 dates will be issued in January. All updates
completed.
• A request to support the Master Plan will be formally issued by the Project Manager.
11
10) Project Reporting, Schedule Metrics and Clients
• Standard Project reporting are necessary to meet the projects commitments to both
Construction team and Clients.
• These will be developed over the next month with the Project Manager.

Más contenido relacionado

La actualidad más candente

Resume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_SchedulingResume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_Scheduling
Quentin McColgin
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
Shraddha PMP
 
Wrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control SystemWrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control System
junejalok
 

La actualidad más candente (19)

Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Resume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_SchedulingResume_McColgin_Quentin_Master_Scheduling
Resume_McColgin_Quentin_Master_Scheduling
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Wrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control SystemWrench Enterprise - Online Project Control System
Wrench Enterprise - Online Project Control System
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 

Similar a AMTPJ-Presentn-Lvl3 Sched Dev-2010-11

Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
Peter White
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
Tarun Behera
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
OLA CV doc NRx (1)
OLA CV doc NRx (1)OLA CV doc NRx (1)
OLA CV doc NRx (1)
Saheed Taiwo
 

Similar a AMTPJ-Presentn-Lvl3 Sched Dev-2010-11 (20)

7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
 
Resume
ResumeResume
Resume
 
Peter White CV
Peter White CV Peter White CV
Peter White CV
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
Business Case _ PM.pptx
Business Case _ PM.pptxBusiness Case _ PM.pptx
Business Case _ PM.pptx
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Better release planning for Feature Teams
Better release planning for Feature TeamsBetter release planning for Feature Teams
Better release planning for Feature Teams
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
OLA CV doc NRx (1)
OLA CV doc NRx (1)OLA CV doc NRx (1)
OLA CV doc NRx (1)
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
 

AMTPJ-Presentn-Lvl3 Sched Dev-2010-11

  • 1. 1 December 18th , 2010 Jubail Master Project Schedule Development of a Level 3 Construction Schedule
  • 2. 2 AMTPJ Construction Schedule Level 3 1. Safety Moment 2. Schedule History-Level 2 3. Objective-Develop a Level 3 Schedule. 4. Area Plan Layouts Issue for Reviews-Links 5. P6 Plan Statistics, Basis and Validation 6. Baselining and Schedule Implementation 7. Short Term Planning, Milestones and Look Aheads 8. Plan Quantity Tracking and Resources 9. Contractor Level 3 and 4 input, implementation 10.Project Reporting, Schedule Metrics and Clients.
  • 3. 1) Safety moment • All drivers to practice a defensive driving approach to and from work. •See attached slide re defensive driving statistics to saving lives
  • 4. 4  History • 1300 Activities and tracking Piling, Building & Equipment Foundations, MEIP with Contractor support. • Monthly reporting use and CP analysis with various degrees of success. • Skill level as a tool is limited and based on long duration estimates, limited interface and logic connections for a large construction project. • AMJ not on board with both schedule presentation for realistic predictions to Start Up Milestones. Looking for a more detail experienced approach to CPM through level 3, quantity tracking, resource and budgetry control management. • Reasons to bring on more horsepower/experience to provide added detail schedule development, planning and constructability to the CM team.  Issues and Concerns • Need to develop a believable set of conditions to the Project as a whole. • Need to develop and execute at level 3 as a minimum objective to execution. • Need to understand the interfacing, sequencing that will allow a safe Construction using both Contractor and Direct Labor. • Need to understand criticality and short term gains through day to day coordination. • Current construction team and CM finding so much interface clash with an inordinate amount of coordination at interfaces. • Lack of experience with tools of choice P6 Database software. 2) Schedule History Level 2
  • 5. 3)Objective-Develop a Level 3 Schedule  Objective and Outline of Development • Must deliver a level 3 schedule that has as a minimum the constructability meets all execution strategies for the Project and has buy in by the PM, CM team, Area Managers and Contractors. Plan before schedule that is the best way to achieve a construction plan. That means more constructability improvements as alternate strategies at the top down. • A minimum WBS by Unit/Process or /Sub Area/ CWP (Contractor)/Discipline. See current wbs. • Support the overall Major Project Objectives and through a formal Management of Change program meet all Key Project and lower level 2/3 area Milestones. • Development Program is 1) Develop, review and issue by 30 December 2010. 2) Revise with all current Contractor Inputs and 3)Implement a Baseline program from Jan 1st 2011. • Establish the Areas and detail to current planners on board. Review progress 2 x weekly. Roll out status and development to PM,CM and Construction Area Manager by 20th December. • Expedite all current detail design, procurement and contract data for input to schedule. • Participate in all current supplier workshops and update the detail level 3 & 4 data into the P6 working file. • Establish basic duration estimates from either contractor level 2 (HSH, Sinusteel) and/or suppliers for added value to meet sequence, logic and interfaces to the schedule development. • Ensure that schedule integrity and basis for a quality product is met ( IPA standard audit procedures). • Cold Eyes review if necessary to improve the product. Add more interface and sequencing.
  • 6. 4) Area Plan Layouts –Issue for Constructability Reviews  P6 Layouts by Areas • All Construction is driving the project by Area and Process line. • The Project is not only driven by Major Equipment but is unfortunately driven by a large process building (Main Building) and Major Equipment Foundations. • All AREA PLANS and Process Lines rely on all purchase or contracts committed to a vendor design, manufacture, logistics, sea transport, storage and site transport from any port of origin over a wide world supply chain. The history and status quo has to be managed for sequential construction and pre-staging of the project as we see it today. • The LEVEL 3 PLAN WBS (see pdf attached) is a simple breakdown of the AREAS as follows; • Plan1 Main Building ( including Crane rails, cranes and electrification). All Finished Grade Slabs and Underground Services). • Plan2 Process Lines ( 10 specific Trains or Lines). • Plan3 Power Distribution ( Substation, E Rooms and Power Distribution from HV SW GR and Delivery to Main Substation). • Plan 4 Water Treatment Plant ( Areas 100 to 700). • Plan 5 Auxiliary Buildings (between 15-18 Masonry or structural Steel Buildings) • Plan 6 Utilities for Inside Battery and Outside Battery Limits • Plan 7 Main Lab Facilities and Maintenance Facilities. • Plan 8 Other Buildings and Structures and assets that meet the scope of the Project. • Plan 9 Turnover, Commissioning and Start Up Systems support. • Schedule Basis, Validation and General Integrity of the Project file. ( Includes Backup and Admin).
  • 7. 5) P6 Plan Statistics, Basis and Validation  P6 Working Project File. • Approximately 6-7000 activities at level 3 or lower to meet the execution strategy. • Currently, no plans to develop a System Schedule for Turnover to Operations.The latter required at or about the 50 % progress milestone. • See statistics as a pdf copy to support the development. • See Basis of Schedule and Validation Reports. No Risk Analysis and Schedule Reserve is added. The latter performed by the PM for the AMJ Change Management Process. • Frequent working file analysis to meet the integrity of the project schedule development. (Once a month along with all Baseline procedures.) • Critical Path Analysis to meet the optimum execution strategies.  Concerns • Proper data analysis and review prior to development. • Project set up and a level 3 schedule needed all current development to be performed in previous phase of project.
  • 8. 6) Baselines and Schedule Implementation • If the Project Execution Team can approve all the current schedule development with all its changes in strategy then a Baseline Program will be implemented. • The current plan will then be progressed on a biweekly basis and take on a maintenance and change management process. Baselines are made when current plan logic delays and task durations are in error. • Reporting on a large project is performed on a monthly basis with a internal review at mid month to effect all changes in the Areas based on new recovery strategies. • Planners will run biweekly update sessions with the Construction Area Managers. • A procedure must be adhered to manage all changes and updates.
  • 9. 7) Short Term Planning, Milestones and Look Aheads • Short Term Planning starts with having a short window to meet the specific objectives. This means Construction breaking down the overall schedule ( ie Baseline1). • Planning produces a 3 week look-ahead for each Area Manager and Construction Team, Progress is marked up at bi-weekly sessions by the responsible Lead/ planner and returned for update and maintenance. • Inputs from Procurement and Engineering are also required for logical interfaces and Equipment status. • As a short term objective a workfront or package milestone may be set and targeted for all teams to achieve. This is a normal practice for checks and balances if the current plan is believable for both durations, logic and sequences. Adjustments are always necessary and normal on out of sequence work, parallel work fronts and interface difficulties. Other concerns are lack of resources.  Look Aheads • The effective short, medium and long term planning needs a 30/60/90 day look ahead in order to progress a large project. After a constructability review process the current P6 plans will set the respective plans and issue to all members of the project. • The project schedule will be cut into short term periods to manage the project effectively. The data date will be moved forward every month after all progress is maintained from Contractor and other departments ( Engineering and Procurement being mandatory under the current crisis).
  • 10. 8) Plan Quantity Tracking and Resources • A second priority but part of the planning work to the project is to develop a resource based plan to meet several project objectives. • The physical progress is imperative to check a suite of schedule initiatives. S curve management is just one metric and tool to determine both accuracy and quality to any plan. • Quantity survey departments are required to support both contract and direct work packages. The progressing is a benefit to the project as a whole and supports any risk or alternative action plans. • To resource the project requires a basis. This basis is normally in estimated quantities and/or equivalent direct labor /craft hours. To produce a Baseline and Project Progress curve (‘S’) the planners need to resource the level 2 activity with manhours.To be reviewed by the PM.
  • 11. 9) Contractor Level 3 and 4 schedules/Inputs to the Project Master Plan  Inputs by Contractors and Vendors • All Contractor schedules should be managed on a MP,P6,P3 format and the current live files issued to the Project Master plan on or before the month end cycle drop dead dates. A monthly calendar set of 2011 dates will be issued in January. All updates completed. • A request to support the Master Plan will be formally issued by the Project Manager. 11
  • 12. 10) Project Reporting, Schedule Metrics and Clients • Standard Project reporting are necessary to meet the projects commitments to both Construction team and Clients. • These will be developed over the next month with the Project Manager.