2. Agenda
• Introduction
• Flow of Deliverables Mapping Tools
• What is a Deliverables Map?
• Definitions
• Deliverables Map Process Overview
• Benefits
• Summary
• Foundations of Project Success
3. Introduction
A real-time management process for product development using visuals for improved
communications and control through:
• Continually decreasing waste, cost and cycle time
• Continually demonstrates if the Critical Path cannot be achieved
• Continually increasing quality
• Allows the Team to conduct What-if Analysis
• Process applies “backward pass” planning
• Establishing the deliverable paths
• High levels of worker involvement, ownership and commitment
Deliverables Mapping creates the opportunity
to develop Higher Fidelity Schedules.
4. Flow of Deliverables Mapping Tools
in Initiating and Planning Processes
Clarifying remark
to initial
verbatim
response.
Clarifying remark
to initial
verbatim
response.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
Customer's
response to
probing by team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
Clarifying remark
to initial
verbatim
response.
Customer's
response to
probing by team.
Clarifying remark
to initial
verbatim
response.
Clarifying remark
to initial
verbatim
response.
Clarifying remark
to initial
verbatim
response.
Clarifying remark
to initial
verbatim
response.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
Customer's
response to
probing by team.
Customer's
response to
probing by team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
VerbatimVerbatim
response to nonresponse to non
leading question.leading question.
from team.from team.
Clarifying remark
to initial
verbatim
response.
Clarifying remark
to initial
verbatim
response.
Customer's
response to
probing by team.
Customer's
response to
probing by team.
X Y
Stage 1 FAI
required on all
hardware
Rapid turnaround of
prototype hardware
on fuel injector
The development
programme will run
better with co-
ordinated use of all
availabletest faciities
Current funding
may only provision
for 4 - 5 builds
The last build will
be an indurance run
High cost / weigt
must be justified on
builds 1 & 2 with
audit team
understanding and
control of tolerance
stack up through fuel
system will produce a
better system
Design and
manufacture drop
offs would threaten
the programme
RR need to do a risk
assessment before
they can define safety
critical and despatch
critical areas
High risk
technology can be
included if it does
not hazard the
whole programme
Defined levels of
risk at each build
are needed to
define inovation
level
Risk levels will
reduce over the life
of the programme
Risk may be reduced
via rig tests as well
as engine tests
A simple overall
final system that
meets
performance
objectives
+ + + + +
Deliver a TRL6
system + + + + +
Programme and
schedule + +
ACTIONS
Define what stage
1 FAI
requirements are
Design for quick
prototype
Continue to work
with funding
agencies
Goodrich to be
partner in audit
team
Late change of
requirements need to
be managed
RR to schedule and
early whole engine risk
assessment to define
safety and despatch
critical features
Ensure innovative
solutions are
explored for builds
1 & 2
Joint risk
management plan
Joint risk
management plan
Document Review
Voice Of the Customer
Impact Matrix
Output:
Actions to resolve higher fidelity
requirements and increased
confidence of compliance
Deliverables Map
LWW Project Planning
Output:
Risk Mitigation and
Contingency Plans
Output:
LWWPP with active
risk management built
inRisk Management
This is an Iterative process that
continues into the Executing and
Monitoring and Control Processes
You are
Here
5. What is a Deliverables Map?
A Top Level Network Diagram that:
• Establishes the key project milestones
• Identifies the key project deliverables (those items delivered to the customer for their
approval or acceptance)
• Identifies the project deliverables - those work-products created by you in order to
accomplish the project deliverables
• Identifies customer and regulatory deliverables
• Establishes schedule constraints with linkage and flow among deliverables
• Start / start, Start / finish, Finish / finish, Finish / start
6. Definitions
• Milestone
• A point in time; no duration; a state has been achieved
• Deliverable
• A thing, an artifact, something you can hold or email
• Completing deliverables leads to achieving milestones
• Actions
• Tasks, work, things you do
• Completing actions leads to having deliverables
• Schedule Constraint
• Anything that limits your scheduling options
• A “drop-dead” completion date imposed by the customer
• Restricted access to certain facilities
• Timing of conference calls with team members in other time zones
• Includes: Start on, Start no earlier than, Start no later than, Finish on, Finish no earlier
than, Finish no later than
7. Deliverables Map Process Overview
Project
Team
Establish
flow and linkage
between
all
Deliverables
Delete Waste
VoC
Data
+
Impact
Matrix
Identify
Customer
Input
Requirements
Identify
Milestones
and
Customer
deliverables
Identify
Company
and
Regulatory
deliverables
8. Benefits
Tangible
• Key to breaking down every activity into enough detail to identify waste and opportunity
• Challenge processes to remove waste and increase productivity
• Identify deliverables from the document / requirements review and VoC
• Key to establishing the deliverable paths
• Key to forming a disciplined approach that mandates / drives small continuous
improvements
• Key to identifying any external regulatory deliverable requirements
• Key to identifying any customer input dependencies
• The primary key to building a “team” feeling
Intangible
• Improved communication within entire team
• Promotes teamwork
• Increases organizational ownership
9. Summary
• Deliverable Mapping is an important continuous improvement tool
• Deliverable Mapping fosters employee involvement
• Deliverable Mapping considers techniques such as: fast-tracking, crashing and
establishing Linkage and Flow of Deliverables
• Every employee has the opportunity to contribute to the Deliverables Map
• Deliverable Mapping is a powerful communication forum
• Deliverable Mapping helps develop ways to reduce schedule without changing the project
scope
• Deliverable Mapping works….let’s make it work at your company!
Future State: To
incorporate Deliverable Mapping in all
project scopes of work.
10. Foundations of Project Success
Scope and Requirements
Schedule
Project Success
Quality
Cost
Integrity and Safety