SlideShare una empresa de Scribd logo
1 de 16
COSTING
“The technique and
process of
ascertaining costs.”
Contract
Costing
Batch
Costing
Single
Costing
Process
Costing
Job Costing
Operating
Costing
Multiple
Costing
 Contract Costing is defined by the ICMA
Terminology as
 Each contract is treated as a cost unit.
 A separate account for each contract.
 Work is done at site, away from contractor’s own
premises.
 The contract has a long duration usually extending more
than one accounting year.
 All items of cost which are directly related to the contract
are chargeable to respective contract accounts.
 Payment is made by contractee on the basis of work
certified by surveyor or architect.
 Penalties or extra money may be imposed.
 Though contract costing is a part of Cost Accounting, but
it is purely based on the principles of Financial
Accounting. Such as Dual Aspect, Prudence and
Conservatism. And AS9 (Revenue Recognition)
• Fixed Price is agreed
• Deductions are made for Defectives and Penalties
• Extra money for additional work
Fixed Price Contract
• compensates for costs actually incurred by contractor.
• a percentage of cost or any lump sum amount.
Cost Plus Contract
• Mixture of both of the above.
• A fixed price will increase with increase in cost of material,
labour.
Contract with Escalation Cost
 Land Cost
 Site labour Cost
 Cost of material
 Depreciation on plant and equipments used at site
 Sub Contract Cost
 Cost of moving plant
 Cost of hiring Plant & Machinery
 Cost of design
 Maintenance Cost
 Guarantee & Warrantee Cost
 Penalties, etc.
× General Administrative Cost
× Selling Cost
× Research & Development Cost
× Depreciation on ideal plant & equipment
× Cost of unconsumed material
× Advance payment to sub contractor
× Cost of material which is delivered to site for
future
× Profit/Loss on sale of any material/plant
Can you Say how
much work
has been
completed ???
Can you Say how
much work
has been
completed ???
New Building of
Central Bank,
Europe
 “Work Certified is that
proportion of the work
completed which has
been certified or and
valued by the architect
or surveyor.”
 Payment is made on the
basis of Work Certified.
 “Work Uncertified is
that part of the work
completed which has not
been certified/approved
by the contractee’s
architect or surveyor.”
 There is no role of Work
Uncertified in payment.
Accounting Treatment is same for both:
Work-in-Progress A/c Dr.
To Contract A/c
01/04/2015 – 31/03/2016
(ONE FINANCIAL YEAR)
01/04/2015
1.Starting of year
2. Starting
/continuation
of contract
31/10/2015
Assessment done
by Architect or
Surveyor and
certified the
work done, i.e.
work certified
31/03/2015
1.Ending of year
2. Date of
payment
3. Closing of
account of
incomplete
contract
Work Done and certified
Work Done but not
certified
WORK
CERTIFIED
WORK
UNCERTIFIED
 A Contractor does not receive full payment of the
Work Certified by the surveyor.
 Contractee retains some amount to be paid, after
sometime, when it is ensured that there is no fault in
the work carried out by contractor.
 This retained money is called as Retention Money.
Retention Money= Value of work Certified
(-) Payment actually made
Particulars Amount Particulars Amount
To Material Purchased XXX By Work-in-progress:
Work Certified
Work Uncertified
XXX
XXX
To Material received from
stores XXX
By Material Return to
Stores XXX
To Material from other
contract XXX
By Material sent to other
contract XXX
To Wages XXX By COST of Material Sold XXX
To Indirect Expenses XXX By Material on Hand XXX
To Plant & Machinery XXX By Plant on Hand XXX
To Accrued Wages XXX
To Accrued Expenses XXX
To Notional Profit c/d XXX
XXX XXX
If Profit,
Transferred to Credit
side of P&LAccount
If Loss,
Transferred to Debit
side of P&LAccount
If Profit,
1 Part Transferred to
Credit side of P&L
Account as per the
work Completed
Another to WIPA/c
If Loss,
Transferred to Debit
side of P&LAccount
As per the % of Work Completion, 3 stages of work completed
is made which helps in transferring the amount to P&L Account.
Stage Name
% of Work
Completion
Formulae
Initial Stage 0% to 24% No Profit will be transferred to P&L
Work done but
not Substantial
25% to 49%
Substantial
Work Done
50% to 100%
LIABILITIES Amount ASSETS Amount
Work in Progress:
XXX
Work Certified XXX
Costing P&L Account
XXX
(+)Work
Uncertified XXX
Contractee A/c XXX (-) Cash Received (XXX)
Unpaid Expenses XXX (-) WIP Reserve (XXX)
Unpaid Wages
XXX
Plant in Hand
(Less Depreciation) XXX
Material on Hand XXX
Cash XXX
Shubham Verma
varma.shubham0365@gmail.com

Más contenido relacionado

La actualidad más candente

Current trends in cost & management accounting
Current trends in cost  & management accountingCurrent trends in cost  & management accounting
Current trends in cost & management accountingTushar Sadhye
 
Reconciliation of cost and financial accounts
Reconciliation of cost and financial accountsReconciliation of cost and financial accounts
Reconciliation of cost and financial accountsMahesh Chandra Sharma
 
process costing ppt
process  costing pptprocess  costing ppt
process costing pptstudent
 
AS-26 intangible assets.pptx
AS-26 intangible assets.pptxAS-26 intangible assets.pptx
AS-26 intangible assets.pptxGokilavaniS3
 
Foreign currency transilition
Foreign currency transilitionForeign currency transilition
Foreign currency transilitionPiyush Gaur
 
Valuation of goodwill
Valuation of goodwillValuation of goodwill
Valuation of goodwillItisha Sharma
 
Branch Accounting PPT
Branch Accounting PPTBranch Accounting PPT
Branch Accounting PPTRahulnegi135
 
Price level Accounting
Price level AccountingPrice level Accounting
Price level AccountingAijaz Aryan
 
Sebi and regulations
Sebi and regulationsSebi and regulations
Sebi and regulationsvishnu1204
 
Process costing
Process costingProcess costing
Process costinggrvthakkar
 
Merchant bank underwriting
Merchant bank underwritingMerchant bank underwriting
Merchant bank underwritingParamkusa K
 

La actualidad más candente (20)

As 13
As 13As 13
As 13
 
Current trends in cost & management accounting
Current trends in cost  & management accountingCurrent trends in cost  & management accounting
Current trends in cost & management accounting
 
Reconciliation of cost and financial accounts
Reconciliation of cost and financial accountsReconciliation of cost and financial accounts
Reconciliation of cost and financial accounts
 
Contract costing
Contract costingContract costing
Contract costing
 
process costing ppt
process  costing pptprocess  costing ppt
process costing ppt
 
IAS 11 Construction Contracts
IAS 11 Construction ContractsIAS 11 Construction Contracts
IAS 11 Construction Contracts
 
AS-26 intangible assets.pptx
AS-26 intangible assets.pptxAS-26 intangible assets.pptx
AS-26 intangible assets.pptx
 
Cost accounting
Cost accountingCost accounting
Cost accounting
 
Foreign currency transilition
Foreign currency transilitionForeign currency transilition
Foreign currency transilition
 
Valuation of goodwill
Valuation of goodwillValuation of goodwill
Valuation of goodwill
 
Branch Accounting PPT
Branch Accounting PPTBranch Accounting PPT
Branch Accounting PPT
 
Cost sheet
Cost sheetCost sheet
Cost sheet
 
Price level Accounting
Price level AccountingPrice level Accounting
Price level Accounting
 
Marginal Costing
Marginal CostingMarginal Costing
Marginal Costing
 
Sebi and regulations
Sebi and regulationsSebi and regulations
Sebi and regulations
 
Customs duty ppt
Customs duty ppt Customs duty ppt
Customs duty ppt
 
Process costing
Process costingProcess costing
Process costing
 
Customs duty
Customs dutyCustoms duty
Customs duty
 
Merchant bank underwriting
Merchant bank underwritingMerchant bank underwriting
Merchant bank underwriting
 
Batch costing
Batch costingBatch costing
Batch costing
 

Destacado

Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingRai University
 
Batch Costing System
Batch Costing SystemBatch Costing System
Batch Costing SystemSvtuition
 
Deduction under chapter VI-A (section 80C- 80U) income tax, 1961
Deduction under chapter VI-A (section 80C- 80U) income tax, 1961Deduction under chapter VI-A (section 80C- 80U) income tax, 1961
Deduction under chapter VI-A (section 80C- 80U) income tax, 1961Shubham Verma
 
Job costing Tutorial
Job costing TutorialJob costing Tutorial
Job costing TutorialSvtuition
 
Sources of business finance
Sources of business financeSources of business finance
Sources of business financeShubham Verma
 
Job order costing and Process costing
Job order costing and Process costingJob order costing and Process costing
Job order costing and Process costingHurriya Saeed rana
 
Chapter4 job costing
Chapter4 job costingChapter4 job costing
Chapter4 job costingkamran
 
Method of costing
Method of costingMethod of costing
Method of costingskillssoft
 
Wine making business plan
Wine making business planWine making business plan
Wine making business plansanal suraj
 
Job Costing, Job Costing System, Normal costing, ABC Costing
Job Costing, Job Costing System, Normal costing, ABC CostingJob Costing, Job Costing System, Normal costing, ABC Costing
Job Costing, Job Costing System, Normal costing, ABC CostingAdvance Business Consulting
 
Generally accepted accounting principal
Generally accepted accounting principalGenerally accepted accounting principal
Generally accepted accounting principalXädiquę Xhäfiquę
 
Assumptions underlying accounting measurement
Assumptions underlying accounting measurementAssumptions underlying accounting measurement
Assumptions underlying accounting measurementpraveensureshpai
 
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmugrcaldwell002
 
Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha ShahMegha Shah
 

Destacado (20)

Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
Batch Costing System
Batch Costing SystemBatch Costing System
Batch Costing System
 
JOB BATCH COSTING
JOB BATCH COSTINGJOB BATCH COSTING
JOB BATCH COSTING
 
Deduction under chapter VI-A (section 80C- 80U) income tax, 1961
Deduction under chapter VI-A (section 80C- 80U) income tax, 1961Deduction under chapter VI-A (section 80C- 80U) income tax, 1961
Deduction under chapter VI-A (section 80C- 80U) income tax, 1961
 
Job and batch costing
Job and batch costingJob and batch costing
Job and batch costing
 
Job costing Tutorial
Job costing TutorialJob costing Tutorial
Job costing Tutorial
 
Sources of business finance
Sources of business financeSources of business finance
Sources of business finance
 
Job order costing
Job order costingJob order costing
Job order costing
 
Job order costing and Process costing
Job order costing and Process costingJob order costing and Process costing
Job order costing and Process costing
 
Job costing
Job costingJob costing
Job costing
 
Chapter4 job costing
Chapter4 job costingChapter4 job costing
Chapter4 job costing
 
Method of costing
Method of costingMethod of costing
Method of costing
 
Wine making business plan
Wine making business planWine making business plan
Wine making business plan
 
Job Costing, Job Costing System, Normal costing, ABC Costing
Job Costing, Job Costing System, Normal costing, ABC CostingJob Costing, Job Costing System, Normal costing, ABC Costing
Job Costing, Job Costing System, Normal costing, ABC Costing
 
Generally accepted accounting principal
Generally accepted accounting principalGenerally accepted accounting principal
Generally accepted accounting principal
 
Assumptions underlying accounting measurement
Assumptions underlying accounting measurementAssumptions underlying accounting measurement
Assumptions underlying accounting measurement
 
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmug
 
Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha Shah
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 
Fma10
Fma10Fma10
Fma10
 

Similar a Contract costing

Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptxVasuV18
 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docxSreedeviPMenon
 
Chapter 06 Costing Methods
Chapter 06   Costing MethodsChapter 06   Costing Methods
Chapter 06 Costing Methodsayanthimadhumali
 
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdfafar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdfGiovanniperez59
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)AmarnathRana1
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3Project Controls Expo
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.pptmayuray
 
Complex Procurement.doc
Complex Procurement.docComplex Procurement.doc
Complex Procurement.docTarigTaha3
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011Irma_Miller_11344
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02hlksd
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 
7_C's_OF_COMMUNIOCATION[1].pptx
7_C's_OF_COMMUNIOCATION[1].pptx7_C's_OF_COMMUNIOCATION[1].pptx
7_C's_OF_COMMUNIOCATION[1].pptxchandansahoo82
 
Cost Accounting unit 5.pptx
Cost Accounting unit 5.pptxCost Accounting unit 5.pptx
Cost Accounting unit 5.pptxJOSEPHINELENTAF
 
Govology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & ProceduresGovology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & ProceduresRobert E Jones
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimatesnagashree123
 
Managerial Economics- Cost analysis and BEP Analysis notes
Managerial Economics- Cost analysis and BEP Analysis notesManagerial Economics- Cost analysis and BEP Analysis notes
Managerial Economics- Cost analysis and BEP Analysis notesDr. Durgaprasad Navulla
 

Similar a Contract costing (20)

Contract account
Contract accountContract account
Contract account
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptx
 
Contract costing
Contract costingContract costing
Contract costing
 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docx
 
Chapter 06 Costing Methods
Chapter 06   Costing MethodsChapter 06   Costing Methods
Chapter 06 Costing Methods
 
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdfafar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
 
Complex Procurement.doc
Complex Procurement.docComplex Procurement.doc
Complex Procurement.doc
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Pmc hitesh
Pmc hiteshPmc hitesh
Pmc hitesh
 
Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
7_C's_OF_COMMUNIOCATION[1].pptx
7_C's_OF_COMMUNIOCATION[1].pptx7_C's_OF_COMMUNIOCATION[1].pptx
7_C's_OF_COMMUNIOCATION[1].pptx
 
Cost Accounting unit 5.pptx
Cost Accounting unit 5.pptxCost Accounting unit 5.pptx
Cost Accounting unit 5.pptx
 
Govology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & ProceduresGovology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & Procedures
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
Managerial Economics- Cost analysis and BEP Analysis notes
Managerial Economics- Cost analysis and BEP Analysis notesManagerial Economics- Cost analysis and BEP Analysis notes
Managerial Economics- Cost analysis and BEP Analysis notes
 

Último

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structuredhanjurrannsibayan2
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxPooja Bhuva
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxDr. Ravikiran H M Gowda
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17Celine George
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxPooja Bhuva
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Pooja Bhuva
 

Último (20)

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 

Contract costing

  • 1.
  • 2. COSTING “The technique and process of ascertaining costs.” Contract Costing Batch Costing Single Costing Process Costing Job Costing Operating Costing Multiple Costing
  • 3.  Contract Costing is defined by the ICMA Terminology as
  • 4.  Each contract is treated as a cost unit.  A separate account for each contract.  Work is done at site, away from contractor’s own premises.  The contract has a long duration usually extending more than one accounting year.  All items of cost which are directly related to the contract are chargeable to respective contract accounts.  Payment is made by contractee on the basis of work certified by surveyor or architect.  Penalties or extra money may be imposed.  Though contract costing is a part of Cost Accounting, but it is purely based on the principles of Financial Accounting. Such as Dual Aspect, Prudence and Conservatism. And AS9 (Revenue Recognition)
  • 5. • Fixed Price is agreed • Deductions are made for Defectives and Penalties • Extra money for additional work Fixed Price Contract • compensates for costs actually incurred by contractor. • a percentage of cost or any lump sum amount. Cost Plus Contract • Mixture of both of the above. • A fixed price will increase with increase in cost of material, labour. Contract with Escalation Cost
  • 6.  Land Cost  Site labour Cost  Cost of material  Depreciation on plant and equipments used at site  Sub Contract Cost  Cost of moving plant  Cost of hiring Plant & Machinery  Cost of design  Maintenance Cost  Guarantee & Warrantee Cost  Penalties, etc.
  • 7. × General Administrative Cost × Selling Cost × Research & Development Cost × Depreciation on ideal plant & equipment × Cost of unconsumed material × Advance payment to sub contractor × Cost of material which is delivered to site for future × Profit/Loss on sale of any material/plant
  • 8. Can you Say how much work has been completed ??? Can you Say how much work has been completed ??? New Building of Central Bank, Europe
  • 9.  “Work Certified is that proportion of the work completed which has been certified or and valued by the architect or surveyor.”  Payment is made on the basis of Work Certified.  “Work Uncertified is that part of the work completed which has not been certified/approved by the contractee’s architect or surveyor.”  There is no role of Work Uncertified in payment. Accounting Treatment is same for both: Work-in-Progress A/c Dr. To Contract A/c
  • 10. 01/04/2015 – 31/03/2016 (ONE FINANCIAL YEAR) 01/04/2015 1.Starting of year 2. Starting /continuation of contract 31/10/2015 Assessment done by Architect or Surveyor and certified the work done, i.e. work certified 31/03/2015 1.Ending of year 2. Date of payment 3. Closing of account of incomplete contract Work Done and certified Work Done but not certified WORK CERTIFIED WORK UNCERTIFIED
  • 11.  A Contractor does not receive full payment of the Work Certified by the surveyor.  Contractee retains some amount to be paid, after sometime, when it is ensured that there is no fault in the work carried out by contractor.  This retained money is called as Retention Money. Retention Money= Value of work Certified (-) Payment actually made
  • 12. Particulars Amount Particulars Amount To Material Purchased XXX By Work-in-progress: Work Certified Work Uncertified XXX XXX To Material received from stores XXX By Material Return to Stores XXX To Material from other contract XXX By Material sent to other contract XXX To Wages XXX By COST of Material Sold XXX To Indirect Expenses XXX By Material on Hand XXX To Plant & Machinery XXX By Plant on Hand XXX To Accrued Wages XXX To Accrued Expenses XXX To Notional Profit c/d XXX XXX XXX
  • 13. If Profit, Transferred to Credit side of P&LAccount If Loss, Transferred to Debit side of P&LAccount If Profit, 1 Part Transferred to Credit side of P&L Account as per the work Completed Another to WIPA/c If Loss, Transferred to Debit side of P&LAccount
  • 14. As per the % of Work Completion, 3 stages of work completed is made which helps in transferring the amount to P&L Account. Stage Name % of Work Completion Formulae Initial Stage 0% to 24% No Profit will be transferred to P&L Work done but not Substantial 25% to 49% Substantial Work Done 50% to 100%
  • 15. LIABILITIES Amount ASSETS Amount Work in Progress: XXX Work Certified XXX Costing P&L Account XXX (+)Work Uncertified XXX Contractee A/c XXX (-) Cash Received (XXX) Unpaid Expenses XXX (-) WIP Reserve (XXX) Unpaid Wages XXX Plant in Hand (Less Depreciation) XXX Material on Hand XXX Cash XXX