Public procurement system –
Institutional set-up and practice
Roles and responsibilities of key institutions in
public procurement
Gheorghe Cazan, Roumania
Chisinau, 9 June 2014
Leogrand Hotel
General Approach
The following features characterise a sound and efficient public procurement
system:
• National legislation in compliance with international requirements and appropriate
procurement policies and rules on the effective, efficient and proper use of public
resources.
• Information-gathering systems that enable the public procurement system to provide
information on the state of public procurement.
• Clear strategies and policies for the allocation of responsibilities and structures for
public procurement decision making, for accountability of public expenditure, for
increasing efficiency, and for combating fraud and corruption.
General Approach
• Well-developed central structures and sufficient administrative capacity for the
effective implementation of laws and other national policies, including the
preparation and dissemination of information, and for the provision of guidance and
training for stakeholders in the system.
• Review systems capable of providing rapid and effective remedies.
• Appropriate means for monitoring the effectiveness of the policy and legal framework
of the system
• Professionalisation of the procurement function at all levels throughout the public
sector.
Key Central
Public Procurement Functions
To make the public procurement system work at all levels, a set of functions needs to be
performed at the central (or regional) level.
The Member States of the European Union generally establish central organisational
structures to carry out functions related to the public procurement system as a whole.
The practical experience of recent EU Member States and EU candidate countries proves
that a key challenge in the procurement reform process, along with the reform of the
legal component, is the issue of how to best organise the central organisational
structure for the co-ordination, implementation and monitoring of public procurement.
Key Central
Public Procurement Functions
Core functions
- regulated by national law, often in direct response to obligations connected to
membership in the European Union
• Primary policy and legislative functions
Designated bodies at the government level have the task of developing fundamental
procurement policies aimed at setting the overall legal framework for public procurement
operations.
The most important function is to prepare and draft primary public procurement
legislation.
Other tasks commonly assigned:
• to lead the working group in the drafting process;
• to organise the consultation process with the main stakeholders in the procurement
system
• to take part in other legislative activity of relevance to public procurement.
Key Central
Public Procurement Functions
• Secondary policy and regulatory functions
• International co-ordination functions (EU, WTO, PPN)
• Monitoring and compliance assessment functions
• preparation of an annual report to the Government or the Parliament on the functioning of the
national public procurement system;
• collection of statistical and other information;
• auditing, control, inspections, checking of legal compliance;
• initiation of proceedings for judicial review in courts of law for violations of public procurement
law;
• where applicable, management of an official list of certified economic operators and/or
certified procurement officers.
Key Central
Public Procurement Functions
Supplementary functions
They are not attributed as an obligation under law for EU Member States
• Advisory and operations support functions
• organisation of a help desk function to provide legal and professional support to purchasers and
economic operators on a daily basis;
• development of guidance systems and operational tools for managing all phases of the
procurement process, e.g. methodologies for tender evaluation;
• issuance of publications, commentaries and interpretative communications on various aspects of
public procurement.
• Publication and information functions
Key Central
Public Procurement Functions
• Professionalization and capacity strengthening functions
• Development and procurement co-ordination functions
• co-ordination and support of concessions and PPP projects
• introduction of systems for performance measurement of public procurement,
• development of procurement techniques, such as performance-based technical
specifications.
• establishment of electronic procurement system(s), by providing the electronic
platform to be used by contracting authorities.
• inclusion of social, environmental and innovative aspects in the public procurement
process
Review and Remedies System
• Review function must not be combined with other key central public
procurement functions
• Main objectives of the review and remedies system:
- To enforce the practical application of public procurement legislation
- To ensure that violations of the legislation and intentional or unintentional
mistakes of contracting authorities can be corrected
Review and Remedies System
• The review and remedies systems of EU Member States have to be
established and developed on the basis of the specific requirements of the:
• EU Public Procurement Remedies Directives 89/665/EEC and 92/13/EEC, amended by
the Remedies Directive 2007/66/EC,
• Treaty on the functioning of the European Union, and
• Case law of the Court of Justice of the European Union (CJEU).
Such a system has to provide aggrieved tenderers and candidates with remedies, which
must be:
• Rapid;
• Effective;
• Transparent;
• Non-discriminatory.
Review and Remedies System
Options:
• Regular courts
• Specialised administrative bodies
• A combination of the two (e.g. complaints involving damages can be
reviewed in the regular courts, while a specialised procurement review
body may review complaints that do not involve damages)
Judicial Character of a Review Body
Conditions:
1. The body is established by law
The legal provisions should regulate various aspects ensuring the functionality of
the body, including for example provisions concerning the:
- review body’s competences,
- appointment and dismissal of its members
- qualifications required of the review body’s members
- conflict-of-interest
- predetermined system for the distribution of cases
- procedural requirements
Judicial Character of a Review Body
2. The body is permanent
The body is not established on an ad hoc basis. Its members remain in their position for a
determined number of years.
This requirement does not exclude the possibility of having several panels within the review
body dealing with cases according to a predetermined distribution system.
3. The body’s jurisdiction is compulsory
Any decision made by the review body has to be enforceable.
- Impose interim measures, with the aim of correcting the infringement or preventing further
damage, including measures to suspend or ensure the suspension of the tender procedure or the
implementation of any decision taken by the contracting authority;
- Set aside or ensure the setting aside of any decision taken unlawfully, including the removal of
discriminatory technical, economic or financial specifications in the tender notice or in tender
documentation.
Judicial Character of a Review Body
4. The procedure before the review body is between the parties (inter partes)
- All interested parties are given an adequate opportunity to present the facts and evidence, and
each party should have the right to respond or to challenge all evidence and arguments
presented by the other party
- Oral hearings (an acceptable alternative is to allow the parties to submit written statements
during the review procedure)
- Both parties must have access to the review proceedings file, with the exception of confidential
information
5. The body applies the rules of law
6. The body is independent
The main principle is that the review body carries out its task independently and under its own
responsibility, and that its members are subject only to observance of the law
Practical Issues
 The capacities of the review body have to be adequate
Staff size
• Range of tasks assigned to the review body
• Number of contracting authorities in the country
• Review culture, including local mentality and propensity of economic operators to file
complaints against the decisions of contracting authorities
• Time limits provided in the law for deciding on the dispute
• Number of members of the review body that, according to the law, have to deal with
each case
• Support that can be offered to the members of the review body by the technical and
administrative staff of the institution
Practical Issues
Educational background of the staff
Members must not only have a good knowledge of public procurement matters but
must also be capable of assessing evidence and drafting substantiated decisions
Training is a must !
 The independence of the review body have to be ensured
Practical Issues
 Clear and detailed norms should be established in the legislation
- Procedural requirements and rules for the review process
- The way of allocating cases among the members of the review body (random distribution is
probably the best choice)
- The means of avoiding conflicts of interest
- The qualifications required to become a member (studies, experience, knowledge and other
specific skills)
- Maximum deadlines for the decisions of the review body
- Panels or not?
- The review body shall exclusively investigate the pleas presented by the economic operators or it
should be better to investigate the entire file?
Practical Issues
 Access to remedies should be open to all economic operators without
discrimination
- On grounds of nationality
- Fees to be paid
- Time limits for submission of complaints
- Evidence to be presented
All the above mentioned aspects must not render the exercise of rights conferred by law
impossible or excessively difficult!
Practical Issues
 Transparency of the decisions
- clear and transparent procedures in order to ensure the coherent application of
the law
- each party should have the right to be informed of the development of the
proceedings, so as to enable them to adequately prepare their arguments
- the parties should be informed of the reasons for the review body’s decision,
including the arguments that determined the evaluation of the evidence and the
considerations of legal issues that were relevant to the decision
Also:
- Publication of the review body’s decisions on its website
- Database of decisions, including search facilities
Thank you
for your attention

Más contenido relacionado

La actualidad más candente

RegulatoryScreening_short_guide
RegulatoryScreening_short_guideRegulatoryScreening_short_guide
RegulatoryScreening_short_guideViola Peter
 
Manual on Market Examinations
Manual on Market ExaminationsManual on Market Examinations
Manual on Market ExaminationsOECD Governance
 
Administrative burdens created by the national transposition of EU legislation
Administrative burdens created by the national transposition of EU legislationAdministrative burdens created by the national transposition of EU legislation
Administrative burdens created by the national transposition of EU legislationOECD Governance
 
Advance ruling by nbr needs to be well defined
Advance ruling by nbr needs to be well definedAdvance ruling by nbr needs to be well defined
Advance ruling by nbr needs to be well definedM S Siddiqui
 

La actualidad más candente (20)

PPT, M Lemke, SIGMA, Third ENP East public procurement conference, Tbilisi, 6...
PPT, M Lemke, SIGMA, Third ENP East public procurement conference, Tbilisi, 6...PPT, M Lemke, SIGMA, Third ENP East public procurement conference, Tbilisi, 6...
PPT, M Lemke, SIGMA, Third ENP East public procurement conference, Tbilisi, 6...
 
6 The Croatian Experience of Building a Remedies System_English
6 The Croatian Experience of Building a Remedies System_English6 The Croatian Experience of Building a Remedies System_English
6 The Croatian Experience of Building a Remedies System_English
 
RegulatoryScreening_short_guide
RegulatoryScreening_short_guideRegulatoryScreening_short_guide
RegulatoryScreening_short_guide
 
Presentation by Maria Stylianidou, Hellenic Open University, Greece (ENG) Sec...
Presentation by Maria Stylianidou, Hellenic Open University, Greece (ENG) Sec...Presentation by Maria Stylianidou, Hellenic Open University, Greece (ENG) Sec...
Presentation by Maria Stylianidou, Hellenic Open University, Greece (ENG) Sec...
 
Manual on Market Examinations
Manual on Market ExaminationsManual on Market Examinations
Manual on Market Examinations
 
Quentin Reed CoE
Quentin Reed CoEQuentin Reed CoE
Quentin Reed CoE
 
PPT, CR Ipate, EC, Third ENP East public procurement conference, Tbilisi, 6 N...
PPT, CR Ipate, EC, Third ENP East public procurement conference, Tbilisi, 6 N...PPT, CR Ipate, EC, Third ENP East public procurement conference, Tbilisi, 6 N...
PPT, CR Ipate, EC, Third ENP East public procurement conference, Tbilisi, 6 N...
 
Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...
Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...
Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...
 
Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...
Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...
Corruption risk assessment of public procurement in Jordan, SIGMA, Amman 30 J...
 
Paulo Magina, OECD Public Governance Directorate, third regional conference o...
Paulo Magina, OECD Public Governance Directorate, third regional conference o...Paulo Magina, OECD Public Governance Directorate, third regional conference o...
Paulo Magina, OECD Public Governance Directorate, third regional conference o...
 
5 Central Public Procurement Functions Identification, Combination, Separatio...
5 Central Public Procurement Functions Identification, Combination, Separatio...5 Central Public Procurement Functions Identification, Combination, Separatio...
5 Central Public Procurement Functions Identification, Combination, Separatio...
 
Administrative burdens created by the national transposition of EU legislation
Administrative burdens created by the national transposition of EU legislationAdministrative burdens created by the national transposition of EU legislation
Administrative burdens created by the national transposition of EU legislation
 
Presentation by Teja Kolar, SIGMA Expert, Croatia
Presentation by Teja Kolar, SIGMA Expert, CroatiaPresentation by Teja Kolar, SIGMA Expert, Croatia
Presentation by Teja Kolar, SIGMA Expert, Croatia
 
Advance ruling by nbr needs to be well defined
Advance ruling by nbr needs to be well definedAdvance ruling by nbr needs to be well defined
Advance ruling by nbr needs to be well defined
 
Ileana Martinez
Ileana MartinezIleana Martinez
Ileana Martinez
 
Presentation by D. Vilytė, Lithuania (ENG), Eighth SIGMA Regional IPA Confere...
Presentation by D. Vilytė, Lithuania (ENG), Eighth SIGMA Regional IPA Confere...Presentation by D. Vilytė, Lithuania (ENG), Eighth SIGMA Regional IPA Confere...
Presentation by D. Vilytė, Lithuania (ENG), Eighth SIGMA Regional IPA Confere...
 
Presentation on public procurement review system in EU member states
Presentation on public procurement review system in EU member statesPresentation on public procurement review system in EU member states
Presentation on public procurement review system in EU member states
 
Paulo Magina, OECD Public Governance Directorate, third regional conference o...
Paulo Magina, OECD Public Governance Directorate, third regional conference o...Paulo Magina, OECD Public Governance Directorate, third regional conference o...
Paulo Magina, OECD Public Governance Directorate, third regional conference o...
 
Presentation on Importance of independent review system
Presentation on Importance of independent review system Presentation on Importance of independent review system
Presentation on Importance of independent review system
 
CAREC Presentation (Melvin Spreij) - REVISED2
CAREC Presentation (Melvin Spreij) - REVISED2CAREC Presentation (Melvin Spreij) - REVISED2
CAREC Presentation (Melvin Spreij) - REVISED2
 

Similar a Presentation on public procurement system institutional set up and practice

PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...
PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...
PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...ssuser9d93ae
 
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...UbongAkpekong1
 
OECD Regulatory Policy Review of Korea 2017 - Key Findings
OECD Regulatory Policy Review of Korea 2017 - Key FindingsOECD Regulatory Policy Review of Korea 2017 - Key Findings
OECD Regulatory Policy Review of Korea 2017 - Key FindingsOECD Governance
 
OECD Regulatory Policy Review of Korea - Key Findings
OECD Regulatory Policy Review of Korea - Key FindingsOECD Regulatory Policy Review of Korea - Key Findings
OECD Regulatory Policy Review of Korea - Key FindingsJustin Kavanagh
 
Alternatives to Regulation, Mohammad Zayyad
Alternatives to Regulation, Mohammad ZayyadAlternatives to Regulation, Mohammad Zayyad
Alternatives to Regulation, Mohammad ZayyadOECD Governance
 
Infrastructure Regulatory System
Infrastructure Regulatory SystemInfrastructure Regulatory System
Infrastructure Regulatory SystemTseringodrub Gurung
 
Presentation on theme.docx
Presentation on theme.docxPresentation on theme.docx
Presentation on theme.docxkayerencaole1
 

Similar a Presentation on public procurement system institutional set up and practice (20)

Presentation on how to set up independent review body
Presentation on how to set up independent review bodyPresentation on how to set up independent review body
Presentation on how to set up independent review body
 
Georghes Cazan, SIGMA Public procurement review bodies conference, Ohrid 9-10...
Georghes Cazan, SIGMA Public procurement review bodies conference, Ohrid 9-10...Georghes Cazan, SIGMA Public procurement review bodies conference, Ohrid 9-10...
Georghes Cazan, SIGMA Public procurement review bodies conference, Ohrid 9-10...
 
The resolution of competition cases by specialised and generalist courts: Sto...
The resolution of competition cases by specialised and generalist courts: Sto...The resolution of competition cases by specialised and generalist courts: Sto...
The resolution of competition cases by specialised and generalist courts: Sto...
 
Ippc6 bpp
Ippc6 bppIppc6 bpp
Ippc6 bpp
 
PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...
PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...
PROCUREMENT OVERSIGHT AND MONITORING – A MEANS FOR EFFECTIVE PROJECT IMPLEMEN...
 
Presentation by Ruslan Malai, Moldova (ENG) Second SIGMA Regional ENP East Co...
Presentation by Ruslan Malai, Moldova (ENG) Second SIGMA Regional ENP East Co...Presentation by Ruslan Malai, Moldova (ENG) Second SIGMA Regional ENP East Co...
Presentation by Ruslan Malai, Moldova (ENG) Second SIGMA Regional ENP East Co...
 
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
 
Legal protection in public procurement, Erika Bozzay, SIGMA regional conferen...
Legal protection in public procurement, Erika Bozzay, SIGMA regional conferen...Legal protection in public procurement, Erika Bozzay, SIGMA regional conferen...
Legal protection in public procurement, Erika Bozzay, SIGMA regional conferen...
 
Presentation- Seminar Standard Cost Model - Turkey, 5-6 April 2018 - English
Presentation- Seminar Standard Cost Model - Turkey, 5-6 April 2018 - EnglishPresentation- Seminar Standard Cost Model - Turkey, 5-6 April 2018 - English
Presentation- Seminar Standard Cost Model - Turkey, 5-6 April 2018 - English
 
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
 
7.1 m&e[1]acm
7.1 m&e[1]acm7.1 m&e[1]acm
7.1 m&e[1]acm
 
2011 july 28 bre tre consultation slides
2011 july 28  bre tre consultation slides2011 july 28  bre tre consultation slides
2011 july 28 bre tre consultation slides
 
OECD Regulatory Policy Review of Korea 2017 - Key Findings
OECD Regulatory Policy Review of Korea 2017 - Key FindingsOECD Regulatory Policy Review of Korea 2017 - Key Findings
OECD Regulatory Policy Review of Korea 2017 - Key Findings
 
OECD Regulatory Policy Review of Korea - Key Findings
OECD Regulatory Policy Review of Korea - Key FindingsOECD Regulatory Policy Review of Korea - Key Findings
OECD Regulatory Policy Review of Korea - Key Findings
 
Alternatives to Regulation, Mohammad Zayyad
Alternatives to Regulation, Mohammad ZayyadAlternatives to Regulation, Mohammad Zayyad
Alternatives to Regulation, Mohammad Zayyad
 
Infrastructure Regulatory System
Infrastructure Regulatory SystemInfrastructure Regulatory System
Infrastructure Regulatory System
 
Presentation on theme.docx
Presentation on theme.docxPresentation on theme.docx
Presentation on theme.docx
 
Profile of the Court of Accounts of Algeria, SIGMA conference 16 December 2014
Profile of the Court of Accounts of Algeria, SIGMA conference 16 December 2014Profile of the Court of Accounts of Algeria, SIGMA conference 16 December 2014
Profile of the Court of Accounts of Algeria, SIGMA conference 16 December 2014
 
4 Principles and Policies for Good Policy Making and Legislative Drafting: OE...
4 Principles and Policies for Good Policy Making and Legislative Drafting: OE...4 Principles and Policies for Good Policy Making and Legislative Drafting: OE...
4 Principles and Policies for Good Policy Making and Legislative Drafting: OE...
 
Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...
Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...
Presentation by Malgorzata Stachowiak, Poland (ENG) Second SIGMA Regional ENP...
 

Más de Support for Improvement in Governance and Management SIGMA

Más de Support for Improvement in Governance and Management SIGMA (20)

PPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Ukraine roadmap.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Moldova roadmap.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdfPPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -CAF Armenia roadmap.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....
PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....
PPT - SIGMA-GIZ Academies - Stage 1 - Financial support tu PAR in Montenegro....
 
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdfPPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
 
Photo gallery - SIGMA-GIZ Academies on QM - Stage 1.pdf
Photo gallery - SIGMA-GIZ Academies on QM - Stage 1.pdfPhoto gallery - SIGMA-GIZ Academies on QM - Stage 1.pdf
Photo gallery - SIGMA-GIZ Academies on QM - Stage 1.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdfPPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - prezentacija gsb podgorica.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF-MONTENEGRO-29-FEB.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF Georgia.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2 and 3.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2  and 3.pdfPPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2  and 3.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - QM Roadmapping Day 2 and 3.pdf
 
Academies-QM_Stage1_Ministry of Higher Education CAF.pdf
Academies-QM_Stage1_Ministry of Higher Education CAF.pdfAcademies-QM_Stage1_Ministry of Higher Education CAF.pdf
Academies-QM_Stage1_Ministry of Higher Education CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - ReSPA and CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Bosnia Herzegovina CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Montenegro CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - North Macedonia CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdfPPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - CAF in Ukraine.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdfPPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdf
PPT - SIGMA-GIZ Academies - Stage 1 -Serbia CAF.pdf
 
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdfPPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
PPT - SIGMA-GIZ Academies - Stage 1 - SIGMA opening.pdf
 
Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...
Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...
Omnichannel management, by Willem Pieterson - SIGMA Webinars on service desig...
 
eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...
eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...
eZdravlje, by Vladimir Raickovic - SIGMA Webinars on service design and deliv...
 

Último

Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...Hemant Purohit
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escortssonatiwari757
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.Christina Parmionova
 

Último (20)

Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl Service Ludhiana 7001035870 Enjoy Call Girls With Our Escorts
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 

Presentation on public procurement system institutional set up and practice

  • 1. © OECD AjointinitiativeoftheOECDandtheEuropeanUnion, principallyfinancedbytheEU Public procurement system – Institutional set-up and practice Roles and responsibilities of key institutions in public procurement Gheorghe Cazan, Roumania Chisinau, 9 June 2014 Leogrand Hotel
  • 2. General Approach The following features characterise a sound and efficient public procurement system: • National legislation in compliance with international requirements and appropriate procurement policies and rules on the effective, efficient and proper use of public resources. • Information-gathering systems that enable the public procurement system to provide information on the state of public procurement. • Clear strategies and policies for the allocation of responsibilities and structures for public procurement decision making, for accountability of public expenditure, for increasing efficiency, and for combating fraud and corruption.
  • 3. General Approach • Well-developed central structures and sufficient administrative capacity for the effective implementation of laws and other national policies, including the preparation and dissemination of information, and for the provision of guidance and training for stakeholders in the system. • Review systems capable of providing rapid and effective remedies. • Appropriate means for monitoring the effectiveness of the policy and legal framework of the system • Professionalisation of the procurement function at all levels throughout the public sector.
  • 4. Key Central Public Procurement Functions To make the public procurement system work at all levels, a set of functions needs to be performed at the central (or regional) level. The Member States of the European Union generally establish central organisational structures to carry out functions related to the public procurement system as a whole. The practical experience of recent EU Member States and EU candidate countries proves that a key challenge in the procurement reform process, along with the reform of the legal component, is the issue of how to best organise the central organisational structure for the co-ordination, implementation and monitoring of public procurement.
  • 5. Key Central Public Procurement Functions Core functions - regulated by national law, often in direct response to obligations connected to membership in the European Union • Primary policy and legislative functions Designated bodies at the government level have the task of developing fundamental procurement policies aimed at setting the overall legal framework for public procurement operations. The most important function is to prepare and draft primary public procurement legislation. Other tasks commonly assigned: • to lead the working group in the drafting process; • to organise the consultation process with the main stakeholders in the procurement system • to take part in other legislative activity of relevance to public procurement.
  • 6. Key Central Public Procurement Functions • Secondary policy and regulatory functions • International co-ordination functions (EU, WTO, PPN) • Monitoring and compliance assessment functions • preparation of an annual report to the Government or the Parliament on the functioning of the national public procurement system; • collection of statistical and other information; • auditing, control, inspections, checking of legal compliance; • initiation of proceedings for judicial review in courts of law for violations of public procurement law; • where applicable, management of an official list of certified economic operators and/or certified procurement officers.
  • 7. Key Central Public Procurement Functions Supplementary functions They are not attributed as an obligation under law for EU Member States • Advisory and operations support functions • organisation of a help desk function to provide legal and professional support to purchasers and economic operators on a daily basis; • development of guidance systems and operational tools for managing all phases of the procurement process, e.g. methodologies for tender evaluation; • issuance of publications, commentaries and interpretative communications on various aspects of public procurement. • Publication and information functions
  • 8. Key Central Public Procurement Functions • Professionalization and capacity strengthening functions • Development and procurement co-ordination functions • co-ordination and support of concessions and PPP projects • introduction of systems for performance measurement of public procurement, • development of procurement techniques, such as performance-based technical specifications. • establishment of electronic procurement system(s), by providing the electronic platform to be used by contracting authorities. • inclusion of social, environmental and innovative aspects in the public procurement process
  • 9. Review and Remedies System • Review function must not be combined with other key central public procurement functions • Main objectives of the review and remedies system: - To enforce the practical application of public procurement legislation - To ensure that violations of the legislation and intentional or unintentional mistakes of contracting authorities can be corrected
  • 10. Review and Remedies System • The review and remedies systems of EU Member States have to be established and developed on the basis of the specific requirements of the: • EU Public Procurement Remedies Directives 89/665/EEC and 92/13/EEC, amended by the Remedies Directive 2007/66/EC, • Treaty on the functioning of the European Union, and • Case law of the Court of Justice of the European Union (CJEU). Such a system has to provide aggrieved tenderers and candidates with remedies, which must be: • Rapid; • Effective; • Transparent; • Non-discriminatory.
  • 11. Review and Remedies System Options: • Regular courts • Specialised administrative bodies • A combination of the two (e.g. complaints involving damages can be reviewed in the regular courts, while a specialised procurement review body may review complaints that do not involve damages)
  • 12. Judicial Character of a Review Body Conditions: 1. The body is established by law The legal provisions should regulate various aspects ensuring the functionality of the body, including for example provisions concerning the: - review body’s competences, - appointment and dismissal of its members - qualifications required of the review body’s members - conflict-of-interest - predetermined system for the distribution of cases - procedural requirements
  • 13. Judicial Character of a Review Body 2. The body is permanent The body is not established on an ad hoc basis. Its members remain in their position for a determined number of years. This requirement does not exclude the possibility of having several panels within the review body dealing with cases according to a predetermined distribution system. 3. The body’s jurisdiction is compulsory Any decision made by the review body has to be enforceable. - Impose interim measures, with the aim of correcting the infringement or preventing further damage, including measures to suspend or ensure the suspension of the tender procedure or the implementation of any decision taken by the contracting authority; - Set aside or ensure the setting aside of any decision taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the tender notice or in tender documentation.
  • 14. Judicial Character of a Review Body 4. The procedure before the review body is between the parties (inter partes) - All interested parties are given an adequate opportunity to present the facts and evidence, and each party should have the right to respond or to challenge all evidence and arguments presented by the other party - Oral hearings (an acceptable alternative is to allow the parties to submit written statements during the review procedure) - Both parties must have access to the review proceedings file, with the exception of confidential information 5. The body applies the rules of law 6. The body is independent The main principle is that the review body carries out its task independently and under its own responsibility, and that its members are subject only to observance of the law
  • 15. Practical Issues  The capacities of the review body have to be adequate Staff size • Range of tasks assigned to the review body • Number of contracting authorities in the country • Review culture, including local mentality and propensity of economic operators to file complaints against the decisions of contracting authorities • Time limits provided in the law for deciding on the dispute • Number of members of the review body that, according to the law, have to deal with each case • Support that can be offered to the members of the review body by the technical and administrative staff of the institution
  • 16. Practical Issues Educational background of the staff Members must not only have a good knowledge of public procurement matters but must also be capable of assessing evidence and drafting substantiated decisions Training is a must !  The independence of the review body have to be ensured
  • 17. Practical Issues  Clear and detailed norms should be established in the legislation - Procedural requirements and rules for the review process - The way of allocating cases among the members of the review body (random distribution is probably the best choice) - The means of avoiding conflicts of interest - The qualifications required to become a member (studies, experience, knowledge and other specific skills) - Maximum deadlines for the decisions of the review body - Panels or not? - The review body shall exclusively investigate the pleas presented by the economic operators or it should be better to investigate the entire file?
  • 18. Practical Issues  Access to remedies should be open to all economic operators without discrimination - On grounds of nationality - Fees to be paid - Time limits for submission of complaints - Evidence to be presented All the above mentioned aspects must not render the exercise of rights conferred by law impossible or excessively difficult!
  • 19. Practical Issues  Transparency of the decisions - clear and transparent procedures in order to ensure the coherent application of the law - each party should have the right to be informed of the development of the proceedings, so as to enable them to adequately prepare their arguments - the parties should be informed of the reasons for the review body’s decision, including the arguments that determined the evaluation of the evidence and the considerations of legal issues that were relevant to the decision Also: - Publication of the review body’s decisions on its website - Database of decisions, including search facilities
  • 20. Thank you for your attention