The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
Watershed planning in texas ling
1. Ward Ling
Texas A&M AgriLife Extension
July 25, 2016
WATERSHED PLANNING IN TEXAS:
LESSONS LEARNED
2. AGRILIFE’S WPP EXPERIENCE
Plum Creek WPP – 2009
Geronimo Creek WPP - 2012
Mill Creek WPP – 2016
All received EPA acceptance
3. PLUM CREEK WPP PROCESS
Pre-emptive Work
Met with local media, County Extension Agents
Identified potential steering committee members
Watershed characterization and set up model
Data collection
WPP Development
public meetings and sought input on development
presented chapters multiple times, presented complete draft
plan twice at the end of period
1 ½ year delay to achieve EPA acceptance
Some implementation started during the long interim
period between development and acceptance
EPA accepted in June 2009
4. PLUM CREEK WPP PROCESS
Pre-emptive work – 5 months
WPP development – 25 months
Some implementation started before EPA acceptance
EPA review – 17 months
Time = 3.8 yrs
Pre-emptive
Development
EPA Review
5. GERONIMO CREEK WPP PROCESS
Pre-emptive work
Met with local media, County Extension Agents
Identified potential steering committee members
Watershed characterization and set up model
Data collection (drought started)
WPP Development
Used report model from Plum WPP
presented draft sections to public as developed
Delays – Was put on hold by funding entity over
modeling issues
EPA approval September 2012
6. GERONIMO CREEK WPP PROCESS
Pre-emptive work – 4 months
Development – 16 months
Delays – 16 months
EPA review – 2 weeks
Time = 3 yrs
Pre-emptive
Development
Delay
EPA Review
7. MILL CREEK PROCESS
Pre-emptive Work
Met with local media, County Extension Agents
Identified potential steering committee members
Watershed characterization and set up model
Data collection
WPP Development
Public meetings and sought input on development
Ran model and presented outputs
Submitted sections to public as developed
EPA approval delay– took longer due to internal
restructuring
8. MILL CREEK WPP PROCESS
Pre-emptive work – 4 months
Development – 6 months
EPA review – 8 months
Time = 1.5 yrs
Pre-emptive
WPP
Development
EPA Review
9. THINGS TO DO
Preemptive work
Set up the model—have it ready—easy to
understand
Meet with potential Steering Committee members
Have a document template ready
Value your stakeholders
Communicate with them
Value them - Name them in press releases,
websites, and keep them informed
Engage approving agencies starting at day 1
10. THINGS TO AVOID
Long development phase— no re-running the
model or recalibration, please…
Time lags between development and
implementation
Long approval or acceptance process
These can all lead to:
Turnover of elected officials and city management
Stakeholder “fatigue”
11. SUGGESTED POLICY CHANGES
Match Flexibility - allow steering committee member
time to count towards match
Refreshments – allowance for meetings—“if you
feed them, they will come…”
Travel funds – increase funding to allow federal and
state personnel to attend stakeholder meetings
Reduce “us and them” feelings by stakeholders
Would help to keep them engaged in the development and
reviewing the document as it is developed